Professional Documents
Culture Documents
Construcción Cables JAW-2 PDF
Construcción Cables JAW-2 PDF
Construcción Cables JAW-2 PDF
REPORT MAY 19, 2011
Prepared by
Power Delivery Consultants, Inc.
Ballston Lake NY
Jay Williams
518 384‐1300
Page 0
PDC Transmission and Distribution Systems
PUBLIC SERVICE ELECTRIC & GAS COMPANY
REPORT MAY 19, 2011
TABLE OF CONTENTS
1.0 INTRODUCTION .................................................................................................................................. 2
2.0 ROUTE CONDITIONS ........................................................................................................................... 2
3.0 CABLE TYPE AND SIZE ......................................................................................................................... 3
3.1 Cable Type................................................................................................................................ 3
HPFF Cables........................................................................................................................................................... 3
Extruded-dielectric Cables...................................................................................................................................... 5
Self-contained Fluid-filled (SCFF) Cables ............................................................................................................. 6
3.2 Cable Type for North Central Reliability Project .................................................................... 7
3.3 Cable Size ................................................................................................................................ 8
4.0 INSTALLATION CONSIDERATIONS ........................................................................................... 8
4.1 Trenching ................................................................................................................................. 8
4.2 Manholes................................................................................................................................ 10
4.3 Cable Sheath Bonding............................................................................................................ 10
4.4 Terminations .......................................................................................................................... 10
5.0 CABLE INSTALLATION ............................................................................................................... 10
5.0 ENVIRONMENTAL CONCERNS ................................................................................................. 11
6.0 OPERATIONAL CONSIDERATIONS........................................................................................... 12
7.0 INSPECTION AND MAINTENANCE ........................................................................................... 12
8.0 COSTS.............................................................................................................................................. 13
Page 1
PDC Transmission and Distribution Systems
REPORT MAY 19, 2011
1.0 INTRODUCTION
Public Service Electric & Gas Company (PSE&G) is proposing the upgrading of existing 138‐kV
overhead lines to 230 kV, which involves using some existing structures, replacing other existing
structures, and adding new structures as required. PSE&G requested Power Delivery
Consultants, Inc. (PDC) to evaluate the potential cable options for this project. The length
considered for undergrounding would be approximately 24.5 miles.
The overhead lines will have steady‐state power transfer capability of 800 MVA and a cable
system would be required to meet this capacity.
PDC evaluated the cable system types that could be considered for this application, determined
the cable size that would be required to match the ratings of the overhead lines, and prepared
an analysis of the planning, construction, operation, and maintenance requirements for the a
230‐kV underground cable system.
2.0 ROUTE CONDITIONS
The cable would follow the existing overhead line right‐of‐way for the full length. A summary of
the route characteristics taken from the NCRP Siting Study Report, along with comments on
installation implications, is given below.
Portions of the route have high rock content and rock outcroppings, making excavation
very slow and costly, and perhaps requiring blasting
There would be approximately 115 road and railroad crossings, many of which may
require horizontal auger boring or other trenchless installation methods
The route has approximately 40 stream and river crossings, which can be very time
consuming and costly for a buried cable system. The Passaic River crossings would
Page 2
PDC Transmission and Distribution Systems
require large horizontal directional drills, which need large staging areas on either side of
the river, and which are very slow and costly.
3.0 CABLE TYPE AND SIZE
3.1 Cable Type
Three types of cable could be considered for 230‐kV systems:
High‐pressure fluid‐filled (HPFF) pipe‐type cable
Cross‐linked Polyethylene insulated extruded‐dielectric (ED) cable (commonly called XLPE
cable)
Self‐contained Fluid‐filled (SCFF) cable
Three other cable types exist, but are not considered suitable for this application: High‐pressure
gas‐filled cable and ethylene‐propylene rubber (EPR) cables are only available for voltages
through 138 kV. Compressed gas‐insulated cables, also called gas‐insulated lines (GIL) are
available at 230 kV and higher voltages, but these systems are large and expensive, not
amenable to burial, and are used almost exclusively for above‐ground applications on utility
property.
Descriptions of the three viable cable types are given below.
HPFF Cables
HPFF cables have been the dominant transmission cable type in the United States from the
1940’s through the start of this century. PSE&G has many HPFF cable circuits in urban areas. In
the last five years, the number of miles of extruded‐dielectric cables worldwide has overtaken
that of HPFF cables for new installations, primarily because of higher power transfer and the
simpler accessories (splices and terminations) and the absence of dielectric liquid and the
associated pressurizing plants. However, many miles of pipe‐type cables are still being installed
at voltages through 345 kV.
HPFF cables are insulated with helically‐wrapped Kraft paper or laminated paper‐polypropylene
(LPP) tapes impregnated with high‐viscosity synthetic dielectric liquid. Stainless steel skid wires
are wound helically around the cable to reduce friction between the cables and the pipe wall
during cable installation. Three phases are drawn simultaneously into a mild steel pipe, typically
8.625‐in. OD, which has a high‐quality corrosion coating and is provided with cathodic protection
to reduce the chance of corrosion. The space between cables and pipe is filled with a low‐
viscosity synthetic fluid (alkylbenzene or polybutene) which is pressurized to a minimum of 200
psig to improve the electric strength of the cable insulation. The use of LPP insulation in place
of Kraft paper allows a reduced insulation wall and cable pipe diameter and an improved power
Page 3
PDC Transmission and Distribution Systems
transmission capacity. LPP is used for all new 345‐kV HPFF cable, and for most new 230‐kV HPFF
cable.
A fluid pressurizing plant is required at least at one end of a HPFF cable system to accept fluid
expansion and contraction with temperature changes. The plant contains a reservoir tank that
would be sized at about 10,000 gallons for the potential NCRP cables, plus pressurizing pumps,
relief valves to maintain proper pressures, alarms, and controls. They are typically housed in an
insulated enclosure resembling a large outdoor cooler. Dimensions are typically about 12 ft
wide, 12 ft high, and 25‐40 ft long depending upon the size of the reservoir tank.
Figure 3.1 compares the sizes of 345‐kV Kraft paper and LPP insulated HPFF systems with equal
power transmission ratings. The left pipe is 10.75 in. OD, and the right pipe is the 8.625‐in. OD
(the size that would be used for the North Central Reliability Project). At 230 kV, the Kraft paper
insulation thickness would be about 0.605 inches and the LPP insulation thickness would be
about 0.500 inches. The 230‐kv cable would be installed in an 8.625‐in. OD steel pipe.
Figure 3.1 – 345‐kV Kraft paper and LPP HPFF cables (EPRI “Green Book”)
The service record of HPFF cable has been good. A common‐mode failure typically in the splice
area, thermo‐mechanical bending (TMB), has caused many outages on 230‐kv and 345‐kV
cables. Splices were rebuilt with additional mechanical supports, and many miles of cable were
replaced with a more TMB‐resistant cable, essentially eliminating this problem. TMB problems
have appeared in the cable length between splices for both 230‐kV and 345‐kV cables. PSE&G
has undertaken a major cable replacement project because of these failures.
Page 4
PDC Transmission and Distribution Systems
A few utilities in major metropolitan areas had many fluid leaks (with the number greatly
reduced after careful attention to the corrosion protection system). Most leaks have been due
to dig‐in, damage to corrosion coating when other subsurface utilities have been installed, or
burn‐through due to a cable electrical fault.
Extruded-dielectric Cables
Extruded‐dielectric cables, also known as solid‐dielectric cables, use cross‐linked polyethylene
(XLPE) insulation for 230‐kV operation. (Ethylene‐propylene rubber, EPR, is used up to 138 kV.)
Transmission‐voltage extruded‐dielectric cables have been used extensively in North America at
voltages 138 kV and higher since the mid‐1980s, and they have seen extensive use overseas
since the 1970s. The first 230‐kV installation in the United States was in 1992, and California
utilities have installed hundreds of circuit miles of 230‐kV XLPE cables in the last five years.
Individual single‐phase cables are typically installed in PVC ducts, in concrete‐encased ductbanks
for city street installation. Although direct burial might be permitted in rural installations, there
are very few directly buried systems in this country.
Figure 3.2 shows a typical XLPE‐insulated cable. The XLPE insulation thickness is about one inch
for 230‐kV operation. A lead or aluminum sheath, sometimes with additional copper or
aluminum neutral wires, is used to prevent moisture ingress and carry fault currents.
Page 5
PDC Transmission and Distribution Systems
Figure 3.2‐ XLPE‐insulated cable (courtesy of Silec Cable).
XLPE‐insulated cables are significantly larger and heavier than pipe‐type cables. Typical length
between splices is shorter – 1800 feet versus 2500 feet. XLPE‐insulated cables do not have the
long service history that HPFF cables do, but experience to date has been good. PSE&G has
installed only short sections of XLPE‐insulated cable in substations and other controlled areas.
Page 6
PDC Transmission and Distribution Systems
intermediate points along the line. Very long lines have large pumping plants near the
terminations at one or both ends of the line.
The insulated conductor is contained in a metallic sheath that can either be corrugated
aluminium or lead reinforced with metal tapes to resist the internal fluid pressure. The
fact that this sheath is an integral part of the cable construction rather than a separate
pipe is the origin of the term “self‐contained”.
The metal sheath is provided with a high‐grade extruded polymeric jacket as protection
against corrosion. This is most frequently a medium or high‐density polyethylene with a
2% addition of carbon black as a protection against UV deterioration.
Figure 3.3 shows a typical SCFF cable.
Figure 3.3 ‐ SCFF cable with corrugated aluminium sheath
SCFF cables are used extensively for submarine cables laid on the water bottom or trenched‐in
to the water bottom. Use for new land installations is uncommon; applications that were
historically installed using SCFF cables now use XLPE‐insulated cables. We therefore did not
evaluate SCFF cables for the North Central Reliability Project.
A detailed analysis of the advantages and disadvantages of HPFF cable versus XLPE‐insulated
cables, including relative costs, should be performed if the cable option were pursued further.
Page 7
PDC Transmission and Distribution Systems
However, based upon general characteristics and cable availability, we believe that an XLPE‐
insulated cable would be the preferred option – primarily because its electrical characteristics
are better for system operation, its power rating is higher, and its maintenance requirements
are lower. There are two suppliers of this cable in the United States, and another dozen
suppliers overseas.
PSE&G requires an 800‐MVA steady‐state power transfer on the cable system.
PDC performed ampacity calculations to size the cable for assumed installation conditions. We
determined that a 2500 kcmil, copper conductor, XLPE‐insulated cable should be adequate, with
two cables per phase required to provide the 800 MVA transfer. 2500 kcmil is a common
conductor size for these cables. For the one month or longer it would take to repair a cable
failure, the remaining circuit would be able to carry about 565 MVA. This is larger than half of
800 MVA since the out‐of‐service cable would not be generating heat that would de‐rate the in‐
service cable.
The physical size of each cable would be about 4.5 inches outside diameter. The weight would
be about 20 pounds per foot, for a single cable.
If the underground line were to proceed to detailed analysis, accurate rating studies may
determine that a larger conductor size is required – e.g. for installations through swampy areas,
to dip under existing services at street crossings, in deep horizontal directional drills, etc.
excavated. For a duct‐and‐manhole system, the cable is replaced from manhole‐to‐
manhole with no need for excavation.
Figure 4‐1. Typical trench cross‐section for 230‐kV XLPE‐insulated cable
Every foot of the transmission cable route would have to be trenched, or more complex
trenchless methods such as horizontal directional drilling would be used. A temporary
construction road would be required along the length of the cable route; this would need to be a
substantial road because it would need to carry heavy loads such as large excavation equipment,
concrete trucks, tractor‐trailers with 80,000 lb manholes and 50,000 lb cable reels, etc.
The cable lines would cross several creeks, highways, and railroads, where a trenched
installation may not be permitted. Trenchless installation, such as horizontal auger boring,
would be required. Horizontal directional drilling would be required for the crossings of the
Passaic River. All of these trenchless methods are time consuming and expensive, and they carry
a high risk.
The route has extensive wetlands, which create substantial problems for an underground cable
since it is generally not permitted or technically feasible to bring heavy equipment through the
wetlands to install the cable. Horizontal directional drilling can bridge some wetlands, but the
maximum feasible length is about 3,000 feet. Longer lengths through wetlands would probably
require re‐routing the cables.
Page 9
PDC Transmission and Distribution Systems
Substantial portions of the potential cable route have high rock content and steep elevation
changes, which make trenching and cable installation difficult and very costly.
4.2 Manholes
Cable splices are placed in manholes, to provide a working space for the week or so it takes to
splice cable sections together, and to allow access for maintenance. A manhole for a 230‐kV
XLPE cable would be approximately 28 feet long, 8 feet wide, and 7 feet high and would weigh
about 100,000 pounds (they are supplied to the job site in two sections). Only one of the two
lines is permitted per manhole, to allow workers to safely repair an out‐of‐service line while the
other one remains energized. Therefore, a 25 mile line would require approximately 130 of
these large concrete structures.
The currents flowing in the cable conductor can induce high voltages in the cable sheath.
Although the cable jacket should protect the public from these voltages, utilities normally limit
the voltages to a few hundred volts to provide protection to utility workers. An elaborate
scheme to connect the cable sheaths in a method known as cross‐bonding can reduce the
voltages to tolerable levels, but each splice location must have small surge arresters to protect
the sheaths from overvoltages, and they are contained in a waterproof “link box” to allow
reconnection and testing of the arresters and the cable jackets. These link boxes can be placed
in a separate small manhole adjacent to the splicing manhole to allow easy access.
4.4 Terminations
The terminations, which connect the cables to overhead bus, resemble transformer bushings
and would be about 9.5 feet tall. They would be placed on steel structures in PSE&G substations
or switching stations. Six of these terminations would be required at each location.
The 230‐kV XLPE‐insulated cables would be provided on steel reels, with individual cables on
individual reels, weighing approximately 50,000 pounds each. Special winches would be set up
at one manhole, and the cable pulled from an adjacent manhole to the location with the winch.
Once cable installation from both sides to the manhole is completed, the cables may be spliced
together. Splicing is typically performed around the clock in the manhole, and the air is
conditioned to maintain low humidity and clean conditions. Three splices for one of the lines
would take about a week using highly trained and skilled splicers.
Page 10
PDC Transmission and Distribution Systems
Termination installation also requires extremely clean, dry conditions. Each termination would
take one to two days to complete.
There are several firms that have experience in installing these cables in the ducts and
manholes, but splicing and terminating are typically performed by technicians from the cable
supplier.
Page 11
PDC Transmission and Distribution Systems
An access road is required along the route, for maintenance and possible repair
operations. Personnel must travel to every manhole periodically for inspection of splices
and link boxes.
Woody vegetation is not permitted within ten feet of the cable trench
The temperature at the earth’s surface is elevated several degrees above that of the
surrounding area
Magnetic fields right above the cable trench can be higher than those of overhead lines,
but they attenuate more quickly with distance from the trench.
Page 12
PDC Transmission and Distribution Systems
Check of the sheath voltage limiters (the small surge arresters) in the link box, any time
there is a fault on the cable or a through‐fault on the transmission line. If the link boxes
are located in the manhole (the preferred location since leads from the splice to the link
box should be as short as possible), then the manhole must be pumped of water and a
safe atmosphere established before workers can enter.
Jacket integrity test and check of link box connection and sheath voltage limiters every
three years. These tests would require an outage for a week or longer depending upon
the number of crews available. Manhole integrity would be checked at this time.
Maintenance of the right‐of‐way to allow vehicle access along the full length and to
insure no woody vegetation grows too close to the cable trench
10.0 CONCLUSIONS
Underground cables are technically feasible for this 230‐kV application. Cross‐linked
polyethylene (XLPE) cables would be the preferred cable type.
However, route conditions would make cable installation very costly, disruptive, and time‐
consuming. Having these cables on the system would create operational difficulties for PSE&G
that would not be present with overhead lines, and power transfer could be severely curtailed
for longer than a month if there were a cable failure.
Page 13