Accomplisment Sep
Accomplisment Sep
Prepared by:
Renzo Ray M. Olivar
Project / Resident Engineer
Km.7 Tigatto Road, Buhangin, Davao City
Period
Project ID No. :
Project Code Name :
CUMULATIVE PROGRESS
SCHEDULED
UNIT NET WT.
QUANTITY (PERT-CPM)
%
ls 1.00 0.207
cu.m. 15,130.70 8.800
cu.m. 3,345.00 1.979
cu.m. 9.60 0.020
cu.m. 10.25 0.005
cu.m. 9,616.03 12.048
cu.m. 821.50 1.070
kg 64,676.60 9.033
cu.m. 698.79 9.457
ln.m. 20.00 0.156
ln.m. 333.00 12.257
each 20.00 6.448
cu.m. 1,510.06 2.930
cu.m. 1,984.62 30.811
PORT
CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT THIS
ACCOMPLISHMENT MONTH
NET WT. NET WT. REMARKS
QUANTITY QUANTITY
% %
0.85 0.176 -
12,276.97 7.140 - On going
3,345.00 1.979 - - Completed
9.60 0.020 - - Completed
10.25 0.005 - - Completed
2,076.29 2.601 122.59 0.154 On going
- - - -
0.00 - no plan/design
14.25 0.006 - half of existing R
6 0.017 - demolished
3 0.027 -
0.00 - Afer Box Culv
61.627 2.46
Chief Engineer
JECT COST:
46,763,373.61
REMARKS
Completed
Completed
Completed
Completed
On going
Completed
Completed
Completed
On going
21 ln.m. lef
19 pcs lef
Completed
On going
On going
no plan/design yet
alf of existing RCPC
demolished
CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT TO
SCHEDULED TARGET Month of JULY
ACCOMPLISHMENT DATE
ITEM NO. ACTIVITY DESCRIPTION UNIT REMARKS
QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT.
(PERT-CPM) Week 1 Week 2 Week 3 Week 4
% % % %
PART B: Other General Requirements 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27
B.5 Project Billboard /Signboard each 4.00 0.040 4.00 0.040 - - Completed
B.7(1) Occupational Safety and Health Program mo 4.00 0.144 4.00 0.144 - - Completed
B.7(1) Traffic Management mo 4.00 0.103 4.00 0.103 - - Completed
B.9 Mobilization and Demobilization ls 1.00 0.031 0.50 0.016 - -
B.4(1) Construction Survey & Staking km 2.04 0.082 2.04 0.082 - - Completed
PART C: Earthworks
Removal of Structures and Obstructions
101(1) (including Restorations-wooden house) ls 1.00 0.207 0.85 0.176 With Revisions
510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 361.35 0.701 319.16 0.619 52.610 0.102 On going 0.155 0.155 0.155 0.155
510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 347.86 5.400 419.28 6.509 69.090 On going 1.627 1.627 1.627 1.627
1.070
TOTAL 100.00 53.940 7.62 1.22 Total 1.828 1.782 1.782 2.225
Cummulative 7.62
Prepared by:
Renzo Ray M. Olivar
Office Engineer
Verified Correct by:
Project Inspector / Assistant Chief Engineer
Approved by:
Chief Engineer