MS of Earth Mat Installation - 12-10-2018-SVH-RS
MS of Earth Mat Installation - 12-10-2018-SVH-RS
MS of Earth Mat Installation - 12-10-2018-SVH-RS
Approval Process
Approver
Project
(Project JK-CRTG JV
Mr.HalukEmre Manager
Management)
GC Review Status
A B C D
Objection, A No Notice of Others
complete Re Objection No
submission with Objection
required comments
Revision History
Control Copy Issued Log (Applicable for Issuance to outsider Project area)
Page 1
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Table of Contents
Contents
1 Scope of Work ........................................................................................................................................ .3
2 References .............................................................................................................................................. 6
3 Site Preparation Condition………………………………………………………………………………………………………………….8
4 Methodology in Sequence………………………………………………………………………………………………………………....8
5 Construction Plant & Equipment...........................................................................................................14
6 HEALTH & SAFETY ................................................................................................................................. 15
7 PERMITS ................................................................................................................................................ 20
8 Environment.......................................................................................................................................... 21
9 Organisation Chart ................................................................................................................................ 21
10 Roles & Responsibility ........................................................................................................................... 22
11 EMERGENCY CONTACTS ........................................................................................................................ 24
12 APPENDIX...............................................................................................................................................23
Appendices
Appendix A : Drawings
Appendix A1 : Water Proofing Drawing
Appendix B : MIR & ITP
Appendix C : Data Sheet of Master Flow 918
Appendix D : Health & Safety Risk Assessment
Appendix E : Others – Checklist & Formats
Page 2
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
1 Scope of Work
Design, supply, install, connect, test and commissioning of earth mat for safety, grounding and
lightning protection in accordance with the Specifications / Contract stipulations herein for all
other contractors(Project Contractors)in the station, tunnels and terminate at respective rooms
with earth bus.
Earthing for DG Sets and lightning protection system shall be separately provided at ground level
Ancillary Building.
This document covers the details of Installation, Testing & Commissioning of Main Earth Mats and
Clean Earth Mat. The Main Earth Mats will be used to connect the all Electrical Equipment of ASS-
1, ASS-2, Electrical Panel Room, Sump Panel Room etc. and Clean Earth Mat will be used for systems
Rooms (As per Contract Document) for grounding the system. The document aims to highlight and
elaborate the various activities in brief order to ascertain a better understanding for start of work.
Page 3
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
There is a variation in measured soil resistivity of approx. 29.6% to 101.36% in any given direction. Since,
in a majority of the directions the variation of measured resistivity values was more than 30%, as per IS
3043 cl 36.6 the measured soil resistivity does not fit into uniform Soil Model and hence can be classified
as non-uniform soil.
Since the soil is non-uniform, multi-layer soil model as derived from the RESAP module of CDEGS software
for the measured values after applying moisture correction factor as per the curve given in IEEE 80 fig 17
is used to determine the multi-layer soil resistivity. Accordingly, the Earth mat is designed using CDEGS
software with Multi-Layer soil modeling.
Applicable Standards
Sl.
Description IEC BIS/IS BS/BS EN Remarks
No.
Page 4
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
For each ASS, there will be an Earth Mat. In total, there will be 2 Nos of ASS for each Underground
Station as per NONO CRD Drawings.
The earthing calculations have been done on the basis of the following standards and Soil
Resistivity Value: ( Design Calculations submitted separately)
The above mentioned sizes of the Earth Mats are on the basis of Submitted Drawings.
The Copper Rods for Earthing Grids shall be laid below the bottom of PCC (Undercroft) as per the
approved drawing . For Main Earth Mat (ASS-1 & ASS-2) 500 Sq.mm bared stranded Copper
conductor, XLPE insulated, LSZH sheathed cable riser shall be raised at the locations shown as an
Earth Mat Risers in the drawing. The height of the Earth Mat Risers will be up to 500 mm above
FFL of Undercroft. The Earth Mat Risers shall be passed through 60 mm dia Tinned copper sleeve
coated with epoxy resin. At crossing / Joint of Copper Rod in all types of Earth Mats (joint location
as detailed in drawing), Exothermic Welding shall be performed.
For connecting the S&T equipment’s at each area/rooms there will be one Clean Earth Mat at each
underground station as per NONO CRD drawing.
The earthing calculations have been done on the basis of the following standards and Soil
Resistivity Value: ( Design Calculations submitted separately)
Page 5
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Sl.
Description IEC BIS/IS BS/BS EN Remarks
No.
OCS
1 Code of Practice for Earthing 3043 BS 7430
SD4-76/193
Requirement for Electrical OCS
2 BS 7671
Installations SD4-4/193
ANSI/IEEE
IEEE Guide for Sub-station OCS
3 Standard 80-
Grounding SD4-76/193
2000
Copper & Copper Alloys.
BS EN
4 Copper Rod, bar and wire for IS 191
13601
general electrical purposes.
The above mentioned sizes of Earth Mats are on the basis of Submitted Drawings..The Copper
Rods for Earthing Grids shall be laid below the bottom of PCC (Undercroft) as per the approved
drawing by Engineer. For Clean Earth Mat (S&T System) 185 Sq.mm bared stranded Copper
conductor, XLPE insulated, LSZH sheathed cable riser shall be raised at the locations shown as an
Earth Mat Risers. The height of the Earth Mat Risers will be up to 500 mm above FFL of Undercroft.
The Earth Mat Risers shall be passing through 50 mm dia Tinned copper sleeve coated with epoxy
resin. At each crossing / Joint of Copper Rod in all types of Earth Mats (joint location as detailed
in drawing), Exothermic Welding shall be done.
References
Page 6
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Definition
(i) J.Kumar CRTG JV: J Kumar Infra Projects Limited – China Railway No. 3 Engineering Group
Company Limited Joint Venture.
(ii) GC, Maple: General Consultant ( Joint Venture of AECOM-PADECO-EGISRAIL-LOUIS BERGER
GROUP)
(iii) MMRCL: Mumbai Metro Rail Corporation Ltd.
(iv) ITP: Inspection Test Plan
(v) ODS: Outline Design Specification
(vi) OCS: Outline Construction Specifications
Page 7
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
2 Site Preparation condition :-Ensure all materials and accessories should be free from dust, scale
or oil. Surface should be cleaned thoroughly and tightness checks for each connection shall be
performed. Continuity of earth connection shall be checked for every link in the network.
Before starting the Earth mat installation, surface area to be levelled
Below mentioned factors shall be considered before installation of earth mat.
Climate condition: Dry weather will be preferable for execution of the earth mat installation work.
3. Methodology in Sequence
• Conducting of Soil Resistivity Test
• Final Design of Earth Mat on the basis of Soil Resistivity Value
• Execution of Earth Mat
• Combine Connection and Measurement of Combined Earth Resistance of Earth Mat.
Soil resistivity test will be done by Wenner4-Pin method for effective design of earth mat.
Please refer detailed methodology for Soil resistivity test.
The methodology proposed is based on information provided in contract documents (ODS &
OCS) and to the best of our knowledge. Exact work of Installation of Earth Mats shall be
formulated after approval of final drawings.
Page 8
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Exothermic Welding
Exothermic welding is a simple, efficient, high-quality metal joining process. It does not require
any other external energy and it is the best way for connecting the earth mat conductor.
1. Following accessories /tools are provided for making the exothermic welded joints
• Exothermic welding mould
• Welding powder
• Tool box.
Exothermic-welding Process.
• Clean the mould and materials to be welded. Clean the interior part of the mould carefully by
using soft brush.
• The dust, grease, oxide(rust) or other adhesive substances must be completely removed
from the surface of the objects which are to be welded (by using steel brush). The weld operation can
repeat after the welded materials are get cleaned.
• Drying: remove the moisture from the mould by using pre-heating tools (such as drying bins or
portable butane blowtorch).
• Position the materials to be welded into the mould (copper rod) and place the round plate
at the bottom of the reaction cavity.
• Pour the weld powder into the reaction cavity, then put some of the ignition powder on top of
the mould, the rest of the ignition powder will be put on the top of weld powder inside reaction
cavity.
• Close the mould, and then ignite the ignition powder. The reaction time only lasts in a few
seconds.
Page 9
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
100% welded joint shall be visual inspected only and vendor is responsible for the checking of
welded joints. The welding shall generally be done in conformity with IEC60364-5-54.
According to IEC60364-5-54, the jointing technique should be such that it prevents
degradation due to mechanical, chemical and electro-chemical effects.
Shifting and Placement of the Earth Mat Sections
The above Earth Mat sections shall be fabricated on the actual site location and shall be placed
one by one and joined together using exothermic welding as shown in the drawing. If any
precaution required shall be taken up in line with construction activity. Presently as per revised
drawing enough space is provided between earth mat and column footings & sumps as shown
in drawing. The earth mat shall be buried as per the NONO CRD Drawings of GC/MAPLE based
on the site conditions.
For installation of Earth Electrodes, 500q.mm stranded bare copper conductor in case of Main
Earth Mat (ASS) or 150 sq.mm stranded bare copper conductor in case of Clean Earth Mat of
required length as per NONO CRD Drawings is used. The same is directly buried in required
bore holes of 75 -100 mm dia., which shall be made by using Mechanical Augers. The hole will
be filled with soil after installation of vertical conductor and top 5 Meters of the bore hole shall
be filled with concrete.
Risers from Earth Mat shall be500 Sq.mm stranded Copper conductor, XLPE insulated cable in case
of Main Earth Mat & 185 Sq.mm stranded Copper conductor, XLPE insulated cable in case of
clean Earth Mat. It will run co-axially with Tinned copper sleeve. Risers shall come up along
the walls/columns of undercroft, up to 500 mm height above FFL up to the test point at
Undercroft level.
Page 10
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
All risers will be as per the ODS clause no: 5.4.3.9.2 of part-2 Sec-VII and shall be brought
from the earth mat up through the basement floor or wall to each of the substation rooms,
communication Equipment room, SCS rooms and relay room and other equipment rooms at
Undercroft level as per actual site condition. At each earth riser cable entry through the base
slab, a tinned copper water stop sleeve shall be provided to prevent the ingress of water. The
Sleeve shall be coated with epoxy resin. Earth bars shall be complete with twin disconnecting
links.
The risers shall be joined with earth mat by exothermic welding. Splicing of the riser cable is
done suitably up to length which is to be joined as given in drawing. For test link, it is spliced
to accommodate the lug of its size. Typical details of Test links with Copper Lugs and U-Clamp
are shown in the NONO CRD Drawing. The riser cable shall be taken through 60mm Dia & 50
mm Tinned copper sleeve coated with epoxy resin for Main & Clean earth mat respectively.
Sealant Compound shall be filled in Tinned copper sleeve after installation of riser cable. The
portion of cable exposed shall be protected through a conduit / bend projected along the wall
over screed the conduit bend shall be sealed with water proof material after installation of
cables.
Riser shall be fixed to the rebar by tie wire and make sure that no gap with shuttering if
shuttering is in place. Make sure that riser shall be covered by styro foam or any other material
in order to prevent the concrete in side conduit. Clean the riser after the removal of formwork.
In case any riser found cut/ theft above the base slab in future, the concrete around the riser
min 150 mm length to be broken. After exposing the riser 150mm , joint shall be made.
Page 11
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
e) Tunnels 2 nos
f) Interconnection of both earth Mats 2 nos
g) Lifts &Escaltors2 nos
h) Spare 2 nos
Total 16nos
Page 12
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
After casting of base slab & during further stage of installation, testing & commissioning,
measurement of earth mat resistance will be done between the reference electrode and the
particular riser to be measured. An official invitation shall be provided to GC/MMRC
representatives and all concerned system wide contractors and measurement values to be
recorded jointly within the Test Result Format as attached herewith.
On completion of activities listed above earth filling and compaction shall be done by civil
section to achieve the desired level and condition for casting of slab.
Earth ground electrodes and risers shall be connected to the earth mat as per details in the NONO CRD
Drawing. Both Power Mats shall be interconnected in the undercroft level by using strips which shall
be taken from 2 separate risers from each earth mat.
(k) Safety
Risk Assessment report attached as attachment 2 shall be used. Workers will wear proper PPE
while working on site. All excess excavated materials; concrete etc. will be cleaned regularly.
(l)Quality
NOTE :Testing & measuring instruments shall have a valid calibration certificate from NABL accredited
lab.
A. Materials
The following major materials shall be used for the installation of Earth Mat:
Page 14
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
The cables shall run through slab in Tinned Copper sleeve as shown in the drawing. Detailed
data sheet of cables shall be submitted later.
Page 15
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Night Work: Area Lighting is needed for safety; productivity; security. The Construction
regulation requires that every working place, approach, dangerous opening and lifting
appliance be adequately and suitably lighted.
Lux meters are used to check levels of illumination. Illumination shall be measured at the
actual work place not at the light fitting. There are factors that can affect the efficiency of
lighting.
Pep talks (Daily Briefing): Site engineer shall be carryout the tool box talk at site explaining
the workers and staff about the risk and hazard associated with the activity.
COSHH: COSHH assessment is not required
Page 16
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Page 17
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Mr.MaheshTolanura
7738886655
(Dbm)
Mr.SarveshShukla 9324904204
Mr.ShivajiErande(Day) 8291814812
Page 18
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Page 19
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
7 PERMITS
A Permit shall be issued only by a competent person, who is completely familiar with the work and
the work area. The issuer should review the place where the work will be performed prior to issuing
the permit.
Page 20
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
The most appropriate type is determined according to the nature of the work to be performed and
the hazards to be eliminated or controlled.
Please refer Appendix H- Others –
8Environment
Not Applicable
9Organisation Chart
Page 21
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
10 Roles &Responsibility
Followings are the responsibilities of personnel involved in the scope of this procedure:
The Project Manager has the overall responsibility for implementation of work &
construction work processes.
Page 22
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Page 23
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
Responsible for implementation of OHSE procedures and plans in consultation with Station
Manager
Carrying out risk analysis and implementing accident prevention program
Monitoring all near miss incidents very closely and taking immediately necessary
preventive action to control it to not to turn in to accidents
Co-coordinating with The Engineer’s safety department Inculcating safety culture at site.
11 EMERGENCY CONTACTS
JK-CRTG JV GC MAPLE
PM Mr. HalukEmre +918291814808 CPM Mr. Michael Tang +917045692328
Mr. Dinesh Kumar
CM +918291815053 CRE Mr. R. K. Bariar +918291261422
Mishra
CSM Mr.Abhijeet Kumar +918291815027 SRE Mr.SathikBasha +918291261469
HR /Admin Mr. Vinay Tripathi +919167224915 CH&SE Mr.ParagDoshi +919867045872
PME - Head Mr.VrijeshVerma +917045958172 SSE Mr.Haresh More +917045692350
Police 100 MMRCL
FIRE 101 CPM Mr.Suyash Trivedi +919871165104
102,
JKUMAR- CRTG JV 8291959466
Mumbai Health 02238573833
Ambulance Care CSM Mr. Paras Kamble +919425823104
Siddhi Cardiac 02238538493
Ambulance
Ganesh Ambulance 02238512334
9820634143,
Hospital Nanavati Hospital 9967550070
9892679014
022-22619100/
Mumbai Electricity
Electrical 22619200/
Board
22619300
Water Supply and
Water Sewerage Board, 022-22026249
Mumbai
12Appendix
(a)Appendix A : Drawings
(b) Appendix A1: Water Proofing Drawing
(c) Appendix B : MIR & ITP
Page 24
Method Statement for Installation of Earth Mats
Issuing Issue To Discipline Area Doc. No. Revision Date
Entity
JKC GCC QAS P06 180161 A0 12.10.18
(d) Appendix C : Data sheet of Master Flow 918 & Brazing Material
(e) Appendix D : Health & Safety Risk Assessment
(f) Appendix E : Others – Checklists & Formats
Page 25