9686-6130-ITP - 000-1002 - Inspection and Test Plan For General Civil Works Rev A1
9686-6130-ITP - 000-1002 - Inspection and Test Plan For General Civil Works Rev A1
Page 1 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev.A1 Doc. Class 2
Table of Contents
INSPECTION AND TEST PLAN ......................................................................................................................... 4
ATTACHMENT-1 CONSTRUCTION START UP CHECK LIST ........................................................................19
ATTACHMENT-2 SURVEY REPORT ..............................................................................................................21
ATTACHMENT-3 INSPECTION CHECK LIST-BEFORE EXCAVATION ..........................................................23
ATTACHMENT-4 INSPECTION CHECK LIST-EXCAVATION.........................................................................25
ATTACHMENT-5 CONCRETE PREPOUR INSPECTION ...............................................................................27
ATTACHMENT-6 CONCRETE POSTPOUR INSPECTION.............................................................................29
ATTACHMENT-7 INSPECTION CHECK LIST - CONCRETE PROTECTION WORK ........................................31
ATTACHMENT-8 INSPECTION CHECK LIST- STRUCTURE BACKFILLING ..................................................33
Page 2 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev.A1 Doc. Class 2
Page 3 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev.A1 Doc. Class 2
Page 4 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev.A1 Doc. Class 2
SP(9686-8320-SP-
Source approval for SP(9686-8320-SP-000-
1.5 Reinforcing steel 4501_01), MAR
000-4501),BS MAR H AR AR
4449:2005+A3:2016
SP(9686-8320-SP-
Source approval for welded SP(9686-8320-SP-000-
1.6 wire fabric 4501_01), MAR
000-4501_01), MAR H AR AR
BS4483:2005
Concrete Protection
Materials(Low viscosity
SP(9686-8320-SP-000- SP(9686-8320-SP-
1.10 bitumen primer ,1.6mm self MAR H AR AR
4501_01),MAR 000-4501_01)
-adhesive membrane and
protection board)
SP(9686-8320-SP-
SP(9686-8320-SP-000-
000-
Source approval for Water 4501_01),MAR,BS
1.16 stopper 10 mm thickness 2571,ASTM D395,ASTM
4501_01),MAR,BS MAR H AR AR
2571,ASTM
D2240
D395,ASTM D2240
Source approval for
Hydrocarbon Resistant SP(9686-8320-SP-000- SP(9686-8320-SP-
1.17 Sealant for expansion joints 4501_01),MAR 000-4501_01)
MAR H AR AR
tank
Material receiving
inspections for materials sl
SP(9686-8320-SP-000- SP(9686-8320-SP-
1.28 no 1.5 to 1.24 MAR,MIR H W R1
4501_01), MAR 000-4501_01), MAR
Review of Manufacturer
Test certificates
2 PREPARATION
3 Excavation
SP SP(9686-8310-
Survey Report
Check existing ground level MS ,SP SP(9686-8310-SP- SP-000-
3.1 RDD-PQP-6163- H H W1
prior to start excavation 000-4501_01) 4501_01),MS,
132-F/02
Survey Reports
Survey Report
Check excavated bottom SP SP(9686-8310-SP-000- MS, SP(9686-8310-
3.2 RDD-PQP-6163- H H W1
levels and compaction 4501_01),MS SP-000-4501_01)
132-F/02,T/C
4 Blinding concrete
Blinding pre-pour SP(9686-8320-SP-000-
4.1 H H W1
Inspection 4501_01)
Sampling and testing of
fresh blinding concrete SP(9686-8320-SP-000-
SP(9686-8320-SP-
4.2 during delivery 4501_01), BSEN 12350- T/C H H W1
000-4501_01), MS
(temperature , slump and 1:2009, BSEN 12350-2:2009
cubes)
Survey Report
RDD-PQP-6163-
SP(9686-8320-SP- 132-F/02,
4.3 Blinding Concrete post pour SP(9686-8320-SP-000- 000- Concrete post H H W1
inspection 4501_01) 4501_01),MS,IFC pour inspection
Drawings checklist RDD-
PQP-6163-132-
F/09
Testing of concrete cubes SP(9686-8320-SP-000- SP(9686-8320-SP-
4.4 T/C H W1 W1
for compressive strength 4501),BSEN 12390-3:2009 000-4501),MS
SP(9686-8320-SP-000- SP(9686-8320-SP-
4.5 Curing of concrete Visual Inspection H S/M S/M
4501) 000-4501),MS
Reinforcement and
5
Formwork
Check formwork
Concrete pre-pour
&reinforcement vertical and SP(9686-8320-SP-
SP(9686-8320-SP-000- Check list RDD-
5.1 horizontal levels, steel bars, 000-4501_01),IFC H H W1
4501_01),IFC Drawings PQP-6163-132-
anchor bolts, embedment Drawings
F/08
parts
Inspection
Inspection of water stopper checklist –
SP(9686-8320-SP-
construction joints, SP(9686-8320-SP-000-
6.3 000-4501_01), IFC Concrete H H W1
expansion and isolation 4501_01), IFC Drawings protection work
Drawings
joint and joint filling
RDD-PQP-6163-
132-F/10
Hydration temperature
SP(9686-8320-SP-000- SP(9686-8320-SP-
6.4 monitoring where T/C H W1 W1
4501_01 000-4501_01, MS
applicable
Inspection of Construction SP(9686-8320-SP-000- SP(9686-8320-SP- Concrete post
6.5 H W1 W1
Joints, Contraction joints 4501_01, General Notes for 000-4501_01, pour inspection
SP(9686-8310-SP-
Inspection of geo textile SP(9686-8310-SP-000-
10.1 000-4501_01, IFC Checklist H H W1
membrane installation 4501_01, IFC Drawings
Drawings, MS
11 Grouting
SP(9686-8320-SP-
SP(9686-8320-SP-000-
11.1 Check grouting 000-4501_01), IFC Checklist H H W1
4501_01), IFC Drawings
Drawings, MS
12 Backfilling
Back filling with suitable
engineering fill material in Survey Report
SP(9686-8310-SP-
SP(9686-8310-SP-000- RDD-PQP-6163-
12.1 layers not exceeding 150 000-4501_01, MS, H W1
4501_01),MS, IFC Drawings 132-F/02 and H
mm compacted thickness IFC Drawings
Check list
Page 19 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev.A1 Doc. Class 2
Activity
Availability
Item Description Comments Remarks
(Yes/NO/NA)
1 Approved Drawings / IFC Drawings are in place
2 Approved Project Quality plans available
3 Detailed scope of work are in place
4 Project specification are available
5 Data sheets are available
Check for Approved Material Requisition /Material approval
6
request
7 Approved Method Statement
8 Approved ITP are available with all Inspection checklists
9 Project Execution plan are available
10 Project Coordination / Communication procedure are in place
11 Approved WPS & PQR available
12 Approved welder / operator available
13 Project approved Personnel List available
Health, Safety and Environmental Plan (with HSE
14
organizational chart)
15 Task Risk Assessments
16 Approved Organization chart available
17 Check for availability of approved materials
18 Check for availability of equipment and its certificates
19 Check for QA/QC orientation for the construction crew
20 Check for work permits
21 Job Safety Analysis approved and available
RDD-PQP-6163-132-F/01 Page 20 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 21 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
SURVEY REPORT
Sub-Contract No Date
Verification Conclusion:
Name
Signature
Date
RDD-PQP-6163-132-F/02 Page 22 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 23 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Comply
Verification Items Remarks
Y/N/NA
3 ITP is approved
Verification Conclusion:
Name
Signature
Date
RDD-PQP-6163-132-F/03 Page 24 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 25 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Comply
Verification Items Remarks
Y/N/NA
3 ITP is approved
Verification Conclusion:
Name
Signature
Date
RDD-PQP-6163-132-F/05 Page 26 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 27 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Comply
Verification Items Remarks
Y/N/NA
3 ITP is approved
Name
Signature
Date
RDD-PQP-6163-132-F/08 Page 28 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
RDD-PQP-6163-132-F/09 Page 29 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Location RFI No:
Comply
Verification Items Remarks
Y/N/NA
Checked the post pour line and levels of concrete and found
1
as per drawings
2 Curing completed as per the specification requirement
Verification Conclusion:
Sub-Contractor EPC Contractor Company
Name
Signature
Date
RDD-PQP-6163-132-F/09 Page 30 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 31 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Location RFI No:
Comply
Verification Items Remarks
Y/N/NA
1 Copy of approved drawing is available at site
3 ITP is approved
RDD-PQP-6163-132-F/10 Page 32 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Page 33 of 34
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE 1)
INSPECTION AND TEST PLAN FOR GENERAL CIVIL WORKS
Doc No:9686-6130-ITP- 000-1002 Rev. A1 Doc. Class 2
Project Name: Ras Markaz Crude Oil Park Project Report No.
Sub-Contract No Date
Location RFI No:
Comply
Verification Items Remarks
Y/N/NA
3 ITP is approved
10
Verification Conclusion:
Sub-Contractor EPC Contractor Company
Name
Signature
Date
RDD-PQP-6163-132-F/11 Page 34 of 34