Tentative plan for Water Shut -off Job In oil well
1. Subdue the well with fresh water - 2.0 hrs.
2. P/O S/Rods + Insert pump to surface - 3.0 hrs. 3. Function test of BOP - 0.3 hrs. 4. POOH tubing and Sand screen - 3.0 hrs. 5. Carry out scrapper trip and clear well bore till xxxxx mkb - 8.0 hrs. 6. Carry out tubing integrity test - 10.0 hrs. 7. R/in drill pipe with open ended till xxxx mkb - 3.5 hrs. 8. Carry out Polymer job as designed - 2.0 hrs. 9. Follow it up with Cement squeeze job in the interval xxxxx mkb - 2.0 hrs. 10. WOC - 9.0 hrs. 11. R/In with TCR bit and tag C/Top and drill cement till xxxxmkb - 4.0 hrs. 12. Check hermacity of the squeeze zone at 100 bar - 1.0 hrs. 13. POOH TCR bit and R/in tubing with junk basket and clear the well - 8.0 hrs. 14. Perforate the interval xxxx to xxxxmkb - 5.0 hrs. 15. Complete the well with tubing - 4.0 hrs. 16. Complete the well with SRP - 6.0 hrs.
50 Ton Work over rig time:
R1: 53 hrs.
R2: 19 hrs.
Services required:
S.no Services required Estimated cost Remarks
1 50 Ton Work over rig 28,00,000 Rates of 50ton rig Mob & demob:17 lacs Day rate:1.6 lacs & Standby rate: 1.45lacs 2 Polymer job 8,00,000 estimated 3 Cementing services 12,00,000 estimated 4 Wire line services 10,00,000 estimated 5 Material handling services 50,000 Crane & trailer