Professional Documents
Culture Documents
PDF Energy Analyst 27 (1) .04.10-Presentation Final
PDF Energy Analyst 27 (1) .04.10-Presentation Final
Q4 FY 2010
Q4 FY 2010 1
AGENDA
Operational Performance
Financial Performance
Major Developments
Status of Projects
Way Forward
2
OPERATIONAL PERFORMANCE
3
Operational Performance
Net Generation ( Million Units) 5,171
152 %
71 %
2,056
1,791
246 %
68 % 61 %
518 29 %
42 % 32 % 39 %
58 %
Realization Rs. Per Unit
4
Operational Performance
5
FINANCIAL PERFORMANCE
6
Financial Highlights Standalone
Total Income* (Rs. Crores) EBITDA (Rs. Crores)
60 % 1,356
53 % 2,441
1,594 847
122 %
115 %
802 409
373 184
Q4 Annual
Q4 Annual
FY 09 FY 10
FY 09 FY 10
* Includes Other Income
PBT (Rs. Crores) PAT (Rs. Crores)
45 % 46 % 847
969
578
667 180 %
127 %
315
298
131 112
Q4 Annual Q4 Annual
FY 09 FY 10 FY 09 FY 10
7
Standalone Results
EPS (Rs )
EPS (Rs.) 0 82
0.82 1 92
1.92 4 23
4.23 5 86
5.86
8
Financial Highlights Consolidated
Total Income* (Rs. Crores) EBITDA (Rs. Crores)
31 % 1,288
2,429 135 %
1,852
74 % 302 % 549
843 389
484
97
Q4 Annual Q4 Annual
FY 09 FY 10 FY 09 FY 10
* IIncludes
l d Oth
Other IIncome PAT (Rs Crores)
PAT (Rs. Crores)
PBT (Rs. Crores)
868 745
136 %
169 %
43 24
Q4 Annual Q4 Annual
FY 09 FY 10 FY 09 FY 10
9
Consolidated Results
EPS (Rs )
EPS (Rs.) 0 17
0.17 1 89
1.89 2 02
2.02 5 17
5.17
10
Financial Highlights
Consolidated as at March 31, 2010
Rs. Crores
Net Worth 4780.20
Debt 7870.14
Net Fixed Assets * 11597.94
Weighted Average Cost of Debt (%) 11.51
*Including CWIP
11
MAJOR DEVELOPMENTS
12
Major Developments
13
Acquisition of Majority Stake in SACMH
Key Features
Umlabu & Ilanga (Wit Bank Region), South ¾ JSW Energy acquired 49.8% stake in
Location
Africa Royal Bafokeng Capital by providing a
value of ZAR 30 cents per share of
p
Umlabu: Explored 50 MT, Unexplored 10 MT
U l b E l d 50 MT U l d 10 MT SACMH
Resources*
Ilanga: 1 MT
¾ Total payout for acquiring 100%
Umlabu: Explored 14 MT, Unexplored 6 MT
Reserves* stake in SACMH ZAR 160.69
Ilanga: 1 MT million (US$ 21 14 million)
million (US$ 21.14 million)
RBCT:402 Km
¾ Richard’s Bay Coal Terminal
Distance to Port Maputo:405 Km Entitlement for ½ million tons per
Durban:520 Km annum
Coal Specifications
¾ Railway siding within the mine with a
GCV (NAR) 6000 Kcal 6200 Kcal capacity to handle upto 5 million tons
per annum
Total USD 50 Million (Total funding required over
Investment time)
*As per SRK Report 14
STATUS OF PROJECTS
15
Jaigad Power Transco Ltd. JV with MSETCL
Project Details Status Update
Double Circuit Quad Moose
D bl Ci it Q d M •Jaigad – Karad:
Technology •Tower Foundations: 71%
Conductor Line
•Tower Erection: 39%
Procurement Orders placed
Rs. 580 Crores including IDC •Land: Right of way achieved
Debt:Equity : 75 :25
Project Cost
Actual spent till Mar 31, 2010 :
Rs 290 9 Crs
Rs. 290.9 Crs
Expected
November 2010
Commissioning
16
Joint Ventures
St t U d t
Status Update
BLMCL Mine development process commenced at Kapurdi
Expected to extract lignite by first quarter of calendar 2011
MJSJ Coal Public hearing process completed
q p
Land acquisition in process
Target to commence production in 2011
Leveling & soil filling work & 100% piling work completed
JSW Toshiba Ground broken for turbine manufacturing facility
Contracts for civil works finalised
Total project completion 16%
Civil works for main plant & blade shop commenced
Blade manufacturing by Year 2011
17
GENERATION PROJECTS
18
Raj West Power Ltd. Barmer I
Project Details Status Update
gy
Technology Subcritical Captive Lignite based TPP
p g •Unit 2 Boiler Hydro
y test is completed
p
FSA with BLMCL (49% JV) for supply of • 89 % erection of Unit 2 BTG completed
Fuel Linkage lignite from captive lignite mines of
BLMCL Target Synchronization
Total Cost: Rs. 5000 Crs U i 6
Unit 6 J
January’11
’11
Debt / Equity: 75:25
Project Cost Unit 7 March’11
Amt spent till Mar 31, 2010:
Rs. 4,781.0 Crs Unit 8 February’11
19
JSW Energy (Ratnagiri) Ltd. 4 x 300 MW
Project Details Status Update
bi
Gross Capacity 1200 MW (4 x 300) •Boiler1 light up and chemical cleaning
completed
T h l
Technology S b iti l I
Subcritical Imported Coal based TPP
t d C l b d TPP •Boiler 2 & 3 hydro test is completed
•Boiler2
•Start up power commenced on April 16th
Long term supply arrangement for and three bays of switchyard charged
Fuel Linkage
Indonesian coal •Financial closure achieved
Water •Turbine 1 barring gear operation is in
MIDC + Sea Water
Allocation progress
TG Structural Erection 65
Total Cost: Rs. 4500 Crs
Debt / Equity: 75:25 Boiler‐1 Erection 94
Project Cost
Amt spent till Mar 31, 2010:
Boiler‐2 Erection 90
Rs. 3,526.6 Crs
Boiler‐3
Boiler 3 Erection
Erection 64
Unit I in May 2010
U it I i M 2010
Expected
Entire project by November / December Boiler‐4 erection 54
Commissioning
2010
20
Raj West Power Ltd. Barmer II 2 x 135 MW
Project Details Status Update
Gross Capacity 270 MW (2 x 135)
• Land in possession
Technology Subcritical Captive lignite based TPP
•Applied for coal linkage
Fuel Linkage Applied to Ministry of Coal
Water
Allocation from IGNP
Allocation
Short Term power purchase
Power Off take
arrangements
Project Cost Total Cost: Rs. 1350 Crs
Expected
January 2013
Commissioning
21
Kutehr Hydro Project 3 x 80 MW
Project Details Status Update
Total Cost: Rs. 1915.2 Crs.
Debt / Equity: 56:44
Project Cost Amt spent till Mar 31, 2010 :
Rs. 89.0 Crs
Expected
September 2015
Commissioning
22
Chhattisgarh Power Project 2 x 660 MW
Project Details Status Update
11% interest in coal block jointly
Fuel Linkage allocated; applied for additional coal •Land acquisition in progress
linkage
•BTG bid evaluation process commenced
35 mn cmpa water allocated from
Water Allocation
Mahanadi River
Combination of LTPPA and short term
Power Offtake agreements with JSWPTC; 35% to
State Govt.
Rs. 6,500 Crs
Project Cost Amt spent till Mar 31, 2010 :
Rs. 19.5 Crs
Expected Unit I July 2014
Commissioning Unit II November 2014 23
West Bengal Power Project 2 x 800 MW
Project Details Status Update
Rs. 7680 Crs for Power plant
Rs. 2000 Crs for Mines Development
Project Cost
Amt spent till Mar 31, 2010 :
R 8 6C
Rs. 8.6Crs
Expected Unit I : 2014
Commissioning Unit II : 2015
24
JSW Energy (Ratnagiri II) Ltd.– 3200 MW
Project Details Status Update
Gross Capacity 3 200 MW (4 x 800)
3,200 MW (4 x 800) •Substantial land in possession
Technology Supercritical imported coal based TPP
Letter of support from Government of
A h i
Authority
Maharashtra
Imported Coal from Indonesia and
Fuel Linkage
Mozambique Agreements in place
Water Allocation Sea Water
Power Offtake Participated in bids for power tieup
Project Cost Rs. 150 Bn.
Expected
April 2015
Commissioning
25
Jharkhand Power Project – 1620 MW
Project Details Status Update
Authority MoU with GoJ
Water is proposed to be sourced from
Water Allocation
the Subarnarekha river
25% to State Government; rest
Power Offtake through LTPPA and STPPA with
JSWPTC
Project Cost Rs. 79 Bn.
Expected
August 2015
g
Commissioning
26
Strategy & Way Forward
Creating world class
Ensure fuel power utility company
security
B ild ti t ith
Build generation assets with
diversified fuel
Balanced offtake
arrangements
Capture opportunity
provided by power sector
27
27
Site Photographs: Raj West Power Limited
g p j
Plant Overview
Plant Overview
28
28
Site Photographs: JSW Energy Ratnagiri Limited
Plant Overview
Line 1 Erection Completed
29
29
Forward Looking & Cautionary Statement
30