PERHITUNGAN DISAIN FLEXIBLE PAVEMENT TANPA STABILISASI

TANAH
Lama Pelaksanaan Umur Rencana Tekanan Gandar

up(th) ip (%) ur(th) i (%) P (ton)

1 5 10 6 8

Koef. Dist Ekivalen beban sumbu Jenis Kendaraan LHRp LHRr LEP LEA

C E LHR LHR x (1+ip/100)up LHRp x (1+i/100)ur LHRp x C x E LHRr x C x E

1 0.0004 779 kend. 2ton 818 1465 0.327 0.586

1 0.1593 20 bus 8 ton 21 38 3.345 5.991

1 0.35 528 truk 2 as 10 ton 554 993 194.040 347.496

1 1.0648 truk 2 as 13 ton 0 0 0.000 0.000

1 1.0375 37 truk 3 as 20 ton 39 70 40.307 72.183

1 1.3195 truk 5 as 30 ton 0 0 0.000 0.000

238.019 426.256

LET = (LEP+LEA)/2 = 332.138 DDT = 1.69 + 4.313 x Log(DCBR) =

LER = LET x ur/10 = 332.138

W = LER x 10 x 360= 1195696.384 SN=

Mencari Indeks Tebal Perkerasan (ITP) Log (W)= 6.078 Gt=Log((Ipo-Ipt)/(4.2-1.5)) =

* CBR = 15 Log(W) = 9.36xLog(SN+1)-0.2+Gt/(0.4+1094/(SN+1)5.19)+Log(1/FR)+0.372x(DDT-3)=

* DDT = 1.69 + 4.313 x Log(CBR)


6.762 STABILISASI SUBGRADE

* FR = 2 (dari Tabel) 1. Ya, 2. Tidak ? 2 Disain CBR, DCBR (%) =

* IP = 1 (dari Tabel) Target CBR setelah stabilisasi CBR1 (%) =

IPo = 3,9 - 3,5 (dari Tabel) DCBR = Rata2 CBR1&3,CBR2 (%) =

dari nomogram didapat ITP10 = 6,1 (Z-20)xCBR11/3+20xCBR21/3+(100-Z)xCBR31/3 CBR tanah asli,CBR3 (%) =

100 Tebal Stabilisasi, Z (cm) =

Koef.Bahan tebal lap. Indeks Tebal Perkerasan (ITP)


a h (cm) axh

0.3 6.83 HRS 2.05


0.14 15.00 LPA A 2.10
0.13 15.00 LPA B 1.95
tebal = 36.83 ITP ada = 6.10
tebal, Hmin= 20 x (P x (1 + 0.7xLog(W))/DCBR)0.5

= 33.5 ITP perlu = SN x 2.54 = 0.00