Title: Water Pitcher Pump

A. Brief Description and/ or Rationale of the Outreach Activity/Service

Water plays important role in our daily living. All of us cannot survive without water. We
use water for our dialing living just for example of using it in cooking, washing our dishes,
cleaning our houses and many more. We do have many sources of water but specifically water
that is safe to use in cooking. In the past our source of water is coming from ground level by
using water pitcher pump. It is an old tradition of having water that can be used in cooking and
others uses. Nowadays, we are not depending on it because in one turn of faucets we can have
water coming from water districts or a water delivery. On the other hand, these are applicable
only to those people who can have an easy access on it, especially people who are in an
industrialized place or city. Those people who are far flung areas or shall we say far from the
access of road. Though they have now pipes that coming from water districts but in times of
electricity shortage they don’t have an option of where they get water sources. There are water
deliveries but it has an often delivering services because of the incremented road.

B. Target Group and Reasons for Choosing it:

C. Date/s of Implementation: January – May 2019

D. Objective, Activities, Outputs, Personnel and Budgeting:


Objective Activities Outputs Personnel Budget
 Provide water  Propose the project to  Provide  NSTP adviser P14,000
pitcher pump the Barangay Officials water  Barangay and
for Purok of Dahican in order to pitcher Purok Officials
Canada. have collaboration. pump as
 Provide  Meeting together with alternative
Alternative the Purok Chairman of source of
source of Canada water.
water  Survey location site for  Lessen the
 Lessen the before building the expenses
expenses in project. in terms of
attaining  Sending of Solicitation having a
water. letters to Government water
agencies. 
 Final Budgeting of the
project

E. Line Item Budget: (Format and Sample)


BUDGET ITEM PARTICULARS SUBTOTAL ESTIMATED COST

1. Operating P9,400
1.1 Work Fee 1.1.1 workers fee ( P5,000/4 persons) P5,000
1.2 Water Pitcher Pump 1.2.1 Water pitcher pump ( P1,200/ 1 piece) P1,200
1.3 Cement 1.3.1 Well tiles (P800/ 4 pieces) P3,200
2. Food P650
2.1 Meals 2.1.1 Meals ( 150/meal x 3 meals) P450
2.2 Snacks 2.2.1 Snack (50/snack x 2 snacks) P100
3. Travel Cost P450
3.1 Gasoline 3.1.1 5 Liters Diesel for Dump truck P250
(Materials gathering) ( P50/liter x 5 liters)
3.2 Fare 3.2.1 DOSCST to Purok Canada ( 50/trip x P200
4 days)
TOTAL BUDGET P10,500

F. Budget Sourcing: (Format)

______________________________
Outreach Group Leader
(Signature above Printed Name)