Professional Documents
Culture Documents
05) Design Energy Efficient (LEL) PDF
05) Design Energy Efficient (LEL) PDF
1
Common Issues & Barriers to Energy
Efficiency
• Gross Oversizing
• Can Afford poor efficiency on grossly oversize plant,
can’t afford right sized high efficiency plant
• Lack of transparency in the system
• One person can spread hysteria thoughout
organisation, stop good ideas
• Lack of access to real operating sites and data to train
operators, engineers, management
• Lack of simple data which exists in many govt
repositories eg electrical maximum demand vs
installed transformer capacity (hospitals must now
publish their rates for common procedures)
2
Important issues for Owners
and Engineers
3
50 years of continuous operation……..
4
UWC Tampines:
An Example of Low pressure engineering
5
From report for Seattle campus…..
6
Installed Capacity vs Cooling Load
UWC
(original slide by NEA)
12,000 0.70
0.60
10,000
0.50
8,000
0.40
6,000
IHL 0.30
4,000 CBD
0.20
2,000
0.10
0 0.00
7
Installed capacity Cooling Load %
Chiller Plant
kW/t 1.02 0.82 1.34 1.27 1.58 1.52 0.85 1.45 3.86 1.30 1.34 135 1.17 1.92 0.74
100%
80%
% Energy Consumption
60%
40%
20%
0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Chillers Chilled Water Pumps Condenser Water Pumps Cooling Tower Fans
8
Plant Efficiency
3,500
0.74
3,000 3.86
2,500 1.92
1.35
2,000 1.17
kW
1.34
1,500 1.30
1.45
1.52
1,000
1.58 1.27 0.85
500 1.34
1.02
0.82
-
0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500
RT
9
Typical overkill is educational…..
11
12
13
14
15
16
Good Copy
17
ASHRAE--Chiller Plant Efficiency
Based on electrically driven centrifugal chiller plants in comfort conditioning applications with
42F (5.6C) nominal chilled water supply temperature and open cooling towers sized for 85F
(29.4C) maximum entering condenser water temperature and 20% excess capacity.
Local Climate adjustment for North American climates is +/- 0.05 kW/ton
18
Comparison of System kW (Before & After)
System kW
Savings in kW
19
Chilled Water Ton
Singapore Post Centre
System Efficiency (kW/Ton) – Daily/Weekly Analysis
35,000
For the week: 15-June-2007 to 21-June 2007 0.6000
0.5900
30,000
0.5800
25,000 0.5700
0.5600
20,000
Ton-hr
0.5500 kW-hr
kW/ton
15,000
0.5745 kW/Ton
0.5753 kW/Ton
0.5758 kW/Ton
0.5840 kW/Ton
0.5830 kW/Ton
0.5688 kW/Ton
0.5670 kW/Ton
0.5400
10,000 0.5300
0.5200
5,000
0.5100
0 0.5000
Fri Sat Sun Mon Tue Wed Thu
15-Jun-07 16-Jun-07 17-Jun-07 18-Jun-07 19-Jun-07 20-Jun-07 21-Jun-07 Average
Ton-hr 28,652 20,811 15,133 28,707 28,071 27,379 27,404 25,165
kW-hr 16,483 11,982 8,838 16,736 15,968 15,525 15,744 14,468
kW/ton 0.5753 0.5758 0.5840 0.5830 0.5688 0.5670 0.5745 0.5755
20
System kW/RT
SingPost 18~20 Feb 2008
21
600 RT Chiller at 110 % Capacity
65659 RT
77.55 C
22
System kW/RT for 1 x 600 RT
0.70
0.60
0.55 kWkW/RT
0.50
23
Heat Balance for 1 x 600 RT
+6%
+2%
-2%
-6%
24
0.450
25
26
27
Air + Water Side System
Efficiency
28
Improved Air Distribution System
Current CHWS Temperature and CHW T
oC
Better air side system performance at
low CHWST, higher CHW T
6oC Current CHWST set point: 5.5oC
10oC
8oC Normal day load: High CHW T
6oC
4oC
Night load: CHW T ~4-6oC
Block B
Block A
0.25 kW/RT
Block D
30
Improved Air Distribution System
Average System Efficiency <0.20 kW/RT
0.250
Air side system efficiency (kW/RT)
0.202
0.200
0.154
0.146
0.154
0.150
0.113
0.100
0.050
0.000
Block A Block B Block C Block D Average
31
Improved Air Distribution System
>50% Better than baseline as per GM-ENRB V3.0
BCA Green Mark for Existing Non-Residential Buildings (Version 3.0)
0.800 0.740
0.700
Additional improvement of ~70%!
0.600
W/CMH
0.500 0.470
0.400 Additional improvement of ~50%!
0.300
0.227
0.200
0.100 FULL GM SCORE FOR THIS SECTION: 8 POINTS!!
0.000
Constant volume Variable volume Average for MBC
Notes:
Baseline as per GM-ENRB v3.0 – Fan power limitation in air conditioning system
(allowable nameplate motor power); The factor of 400 CFM/RT is used for conversion of
air side system efficiency from kW/RT W/CMH 32
The Shoemaker’s children
are barefoot..
33
34
35
Performance metric : 9.58 secs/100 meters
36
MEWR HQ Retrofit
~ 800 RT centrifugal
Refrigerant R-123a
37
IDEAS SOUGHT FOR BETTER
DESALINATION – Aug 2007
Business Times, Singapore
38
Cheaper way found to make sea water
drinkable—Straits Times, 24June2008
39
Latest NEA guidelines for energy
audits in Singapore—June 2009
40
Simple Guide to retrofit success
• Ask for 1 minute trend data for chiller plant parameter eg tons,
kw/ton, flow rates, kw, pressures, temperatures, ambient temp and
wet bulbs for 3 months in spreadsheet format
• Ask for previous performance contract examples with bank
guarantees
• Ask for online internet access to previous projects
• Ask for ARI-550 accuracy of +-5% for chiller plant efficiency, using
as guides ASHRAE 14P & 22.
• Ask for 0.60 kW/RT or better for chiller plant
41
The Evolution of truth…
• All truth passes through three stages.
• First, it is ridiculed.
• Second, it is violently opposed.
• Third, it is accepted as being self-evident.
Arthur Schopenhauer
German philosopher (1788 - 1860)
"There are only two mistakes one can make along the road to
truth; not going all the way, and not starting." -- Buddha
42
43
Guaranteed Energy Savings Performance (GESP) Contract
Project showcase:
Retrofit of Centralized Water-Cooled Chiller Plant
Company Confidential
44
Contents
45
Objective and Scope of GESP
46
The Environment Building
Background of the Water-cooled Chiller Plant
• Year of completion: 1984
• Primary building usage: Office
• Total GFA: 49,021 m2
• Total air-conditioned space: 30,300 m2
• Existing chiller plant room since retrofits in 2006
– 3 x 500 RT water-cooled chillers in 2005
– Primary & secondary chilled water pumping system
– Variable condenser water pumping system
– Variable speed cooling tower fans
– Chiller plant room system efficiency of 0.848 kW/RT
(based on energy audit data in 2011)
47
The Environment Building
Strategy of Achieving Efficient Chiller Plant System
• Use of high efficiency chiller
• Primary only variable chilled water pumping system
• Low pressure chilled water and condenser water
distribution system
• Deployment of high accuracy instruments for long term
measurement & verification (M&V) of energy efficiency &
energy savings
• Optimization of chiller plant control system with web-
based system integration solution Tracer XT
48
Energy Impact
Water-cooled chiller plant only
Annual Energy Consumption (kWh)
1,600,000
540 MWh savings
1,400,000
1,200,000 Additional
0.848 kW/RT 110 MWh savings
1,000,000
800,000
0.60 kW/RT
0.52 kW/RT
600,000
400,000
200,000
0
Baseline Audit Guaranteed Actual system
2011 system efficiency efficiency*
* The annual chiller plant energy consumption of actual system efficiency is
projected based on latest chiller plant data in Feb & March, 2013 49
Financial Impact
Water-cooled chiller plant only
500,000
Annual Energy Consumption (S$)
Actual:
~30% savings
Overall ~40% savings
400,000
S$115k savings
0.848 kW/RT
kW/RT
300,000 Additional S$30k savings
0.60 kW/RT
kW/RT
0.52 kW/RT
200,000
0.848
100,000
0.52
0
Baseline Audit Guaranteed system Actual system
2011 efficiency efficiency*
* Based on latest electricity tariff at S$0.2670 per kWh
50
Equivalent Impact
Water-cooled chiller plant only
250,000 kg reduction in
CO2 emission annually
June, 2012
52
June, 2012…
Before retrofit works start
3 x 500 RT water-cooled chillers
Balancing
valve -
high P
Balancing
valve -
high P
55
June, 2012…
Before retrofit works start
3 x condenser water pumps
Exhaust fan
July, 2012
59
July, 2012…
Retrofit works in progress
Delivery & hoisting of new 800 RT water-cooled chiller (Part I)
60
July, 2012…
Retrofit works in progress
61
July, 2012…
Retrofit works in progress
December, 2012
63
December, 2012…
Completion of retrofit works
New
staircase
platform for
easy site
access with
proper sign
labeling
66
December, 2012…
Completion of retrofit works
SMOOTHER CW PIPE
CONNECTION FOR NEW CWP
67
December, 2012…
Completion of retrofit works
STRAIGHT CW PIPE
CONNECTION TO CHILLER
CWS PIPE NOZZLE
68
December, 2012…
Completion of retrofit works
VSD FOR NEW CHWP
70
Measured Chilled Water Tonnage
New Chiller Operating Capacity
9000 Pre-retrofit (Baseline Audit) Post-retrofit PreNorm PostNorm 0.006
6000 0.004
5000
0.003
Lots of CAPACITY
4000
beyond nominal!
3000 0.002
2000
0.001
1000
0 0
200
250
300
350
400
450
500
550
600
650
700
750
800
850
900
950
1000
1050
1100
1150
1200
Chilled Water Tonnage (RT)
71
Improvement of System Performance
Total system efficiency
kW/RT
0.80 Pre-retrofit
(Baseline)
0.60
0.50
Post-retrofit
0.40 Average system efficiency:
0.521 kW/RT
72
System Efficiency versus CHWS Temperature
Pre-retrofit Baseline Data
kW/RT, oC
1.00 kW/RT
System kW/RT
0.70 kW/RT
10oC
8oC CHWST
6oC
4oC CHW T
RT
73
System Efficiency versus CHWS Temperature
Post-retrofit Data
kW/RT, oC
CHWST = 8.0oC
8oC
7oC
0.60 kW/RT CHWST = 6.7oC
RT
74
System Efficiency versus CHWS Temperature
Post-retrofit Data
kW/RT, oC
7oC
6oC CHW T
0.60 kW/RT
0.50 kW/RT System kW/RT
75
High Accuracy of Instruments
For Measurement & Verification (M&V)
INDIVIDUAL MAGNETIC
FLOW METER AT 4
INDIVIDUAL CW HEADER!
76
Improvement of System Heat Balance
Within ±5%
%
+5%
February, 2013
+2%
March, 2013
-2%
-5%
08:00 17:00
77
Chiller Plant Control System
Web-based system integration solution
78
Summary
79
80