Professional Documents
Culture Documents
Square Pattern
Square Pattern
THIESS
Sangatta Mine Project
PROJECT
REPORT
0 Thiess Indonesia
“ We Add More Values”
Table of Contents
2
“ We Add More Values”
Overview
One of mining procedure is Overburden Removal, in order to expose and mine coal
laying under it. Overburden usually as sediment stone like sandstone and clay. Those stone
have hardness as its natural properties, as result of sedimentation buried process. So to break
and excavating the overburden, drill and blast is needed.
Drill and blast activity must be planned well so it will make more advantage to
company. In the other side, if drill and blast were not planned well, it will took effect
increasing of operational cost and technically blasting process will have bad effect to
environment like ground vibration, air blast, poisonous fumes, and fly rock. Usually, this
activity will be done in one sequence. Drilling process is required to insert the blasting
explosive into the ground by drilling the ground. After that, there will be to blast the area, so
that materials can be hauled easier.
3
“ We Add More Values”
Drill and Blast pattern is the position of drill holes that shows types and variation
distance of spacing and burden between holes in one row or column, as important part to be
good control bench blasting result. There are 3 were known of drill and blast pattern :
1. Square Pattern
Square pattern shows that position of burden and spacing in same distance
(burden = spacing). The position of next holes straight in a line with the holes before
and in front of it. Same distance each side. Figure below shows that the area of blast
effect for every hole. Square pattern have zone in the middle that the impact of
blasting couldn’t reach.
4
“ We Add More Values”
2. Rectangular Pattern
Rectangular pattern shows that spacing is bigger than burden. So the
combination of holes looks like rectangle shape. Maximal distance of spacing could be
twice of burden distance. This pattern have much bigger area that’s not in range of
blast impact. It could excalate to bad fragmentation of rocks.
3. Staggered Pattern
The position of the next drill holes right in the middle of spacing line for next
rows. The advantage of this pattern is have result of blast energy more and give
uniformity of fragmented rock. Especially for optimum good fragmented rock is
spacing at 1.15 of burden.
5
“ We Add More Values”
The effective Burden (Be) and the effective Spacing (Se) depend not only upon the
blast holes pattern, but also upon the sequence of firing. A square blast holes pattern
which is fired row by row from the face gives an effective burden equal to the
spacing between successive rows parallel to the face. On the other hand, an identical
pattern of blast holes can be fired echelon resulting in completely different burdens and
spacings.
Once the pattern has been designed, it is most important that the blastholes are
drilled in the correct place, at the correct angle and to the correct depth. There is a very
good reason to have the face surveyed and every blasthole measured out carefully.
Optimum blasting results can be achieved only where the correct burdens and spacing are
selected and then implemented.
6
“ We Add More Values”
Figure 6, Graphic of Plan and Actual PF from each Pattern and Various Depth
Drill and Blast team has defined that ideal PF is 0.321 kg/c.m. Graph above shows that PF from Staggered Pattern (red line) sometimes
get higher from planned PF. Especially at 5 to 6 meter and 8 to 10 meter of depth, could going to 0.35 kg/c.m. That’s mean more explosive will
use to blast those holes. If we look at Square Pattern PF (green line), it could get close to planned PF, especially in 12 meter of depth (PF =
0.321 kg/c.m). Square Pattern PF could get close with planned PF. When blastholes getting deeper, spent more explosive, and PF increasing
too.
8
“ We Add More Values”
Figure 7, Graphic of Productivity Ex.3009 from each Pattern (January 2012 and 2013)
9 Thiess Indonesia
“ We Add More Values”
Figure 8, Graphic of Productivity Ex.3009 from each Pattern (February 2012 and 2013)
Figure 9, Graphic of Productivity Ex.3009 from each Pattern (March 2012 and 2013)
10
“ We Add More Values”
From the graphs above could see different excavator productivity between Square and
Staggered pattern. In January, productivity of excavator 3009 from Staggered Pattern’s
productivity is getting low in the middle month.
Analysis from that matter could be causes by something else, like broken diggable
material is still hard to excavate, boulder fragment make digger’s bucket doing passing to
truck vessel much harder, or because in that month there’re a lot of rain that made
excavator’s working hours getting cut and productivity getting low (should check more
correlation with rainy days). But one thing for sure, excavator’s productivity when applying
Square Pattern shows good, could keep going with defined production target, and little
fluctuate production gap. But there’s some decreasing productivity when dig for 3rd layer
cut. According to theoretical calculation based on Digging Rate, when digger cut getting
depth, digging time getting long, broken material is getting hard, so that made productivity
for 3rd layer cut is getting down. Digging time data for the last cut (4th) haven’t picked up yet.
Figure 10, Graphic of Productivity Ex.3042 from each Pattern (January 2012 and 2013)
11
“ We Add More Values”
Figure 11, Graphic of Productivity Ex.3042 from each Pattern (February 2012 and 2013)
Figure 12, Graphic of Productivity Ex.3042 from each Pattern (March 2012 and 2013)
12
“ We Add More Values”
From those 3 months, digger productivity from Staggered Pattern relative good,
even better that Square Pattern. Staggered shows high digger productivity in January and
March (March 7th, 2012), but sometimes productivity got low till 400 bcm/hours. Many
working hours lose. But too bad in February Staggered pattern didn’t show good
productivity performance, in the other hand, Square pattern shows much better
productivity, even could reach till 1800 bcm/hours (more than target). Both of those
patterns have their own raise and down productivity. With Staggered or Square Pattern,
Hitachi EX. 3600 could keep up on production.
Figure 13, Graphic of Productivity Ex.3042 from each Pattern (September 2012 & January 2013)
In this section, Hitachi Ex.2600 is smallest diggers among Ex.5500 and Ex.3600,
that’s mean this digger have lower productivity, dig capability, and bucket capacity. From
first graph could see that digger’s productivity from Square Pattern didn’t work well,
almost below target all time. Staggered Pattern working more well, but some fall down
production in the end of month is should worried for. Because of the excavator 1769
starting use in Sanggatta Project is September 2012, so this report can’t compare &
explain it with same month like at Ex.3009 and Ex.3042. Overall, Square Pattern could
have productivity result as good as Staggered, even more sometimes, and even worse
sometimes. Another condition maybe much more taking control it.
13
“ We Add More Values”
Figure 14, Graphic of Productivity Ex.3042 from each Pattern (October 2012 & February 2013)
3) November 2012 & February 2013
Figure 15, Graphic of Productivity Ex.3042 from each Pattern (November 2012 & March 2013)
14
“ We Add More Values”
IV. Conclusion
From all explanation, describing, and comparison above, here’s some conclusions for
Square and Staggered Pattern :
1. Square Pattern is better than Staggered Pattern in Explosive Usage and Excavators
Productivity.
2. Square Pattern could decrease explosive usage. It shows up at Powder Factor table
(Figure 5 and 6). Average PF from Staggered Pattern is 0.296 kg/c.m and for Square
Pattern is 0.274 kg/c.m. Decreasing percentage is 7.44% (actual).
3. Excavators Productivity :
Staggered Square Actual Percentage of Raise Digging Rate Digging Rate Digging Rate
EX. 3009
Pattern Pattern and Down Productivity (%) 1st Cut 2nd Cut 3rd Cut
Jan 2012 - 2013 1352.1 1585.6 17.27% 1496 1533 1417
Feb 2012 - 2013 1036 1626.1 56.96% 1496 1533 1417
Mar 2012 - 2013 1581.7 1575.5 -0.39% 1496 1533 1417
EX. 3042
4. Drill and Blast Pattern aren’t the main major factor that could control productivity.
Another condition maybe much more taking control it, like weather, services
schedule of every units, working hours, utilization, mechanical availability, and
standby time.
15