Chapter 12

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 22

Activity-Based Costing 245

CHAPTER 12
Activity-Based Costing

LEARNING OBJECTIVES
After studying this chapter, you should be able to:
1. Discuss the limitations of using only unit-based drivers to assign costs.
2. Provide a detailed description of activity-based product costing.
3. Describe how homogeneous cost pools can be used to reduce the number of activity rates.
4. Describe activity-based system concepts including an ABC relational database and ABC software.

CHAPTER SUMMARY
This chapter explains how activity-based costing systems produce more accurate product cost
information than traditional costing systems that use unit-based drivers. Potential users of ABC
systems are those companies that produce multiple products, have high degree of product
diversity, and have a significant percentage of nonunit-level overhead costs. This chapter also
outlines the essential steps in designing an ABC system in order for it to be implemented
successfully. The chapter concludes by Learning Objective
describing an ABC #1
relational database and ABC software.

CHAPTER REVIEW
I. Unit-Based Product Costing

A. Functional-based costing uses only unit-based drivers to assign overhead costs to products.
a. Functional-based costing first assigns overhead costs to a functional unit, creating plant or
departmental cost pools. Next, these pooled costs are assigned to products using only unit-
based drivers.
b. Unit-based drivers are factors that cause changes in cost as the units produced change.
 Functional-based costing uses only unit-based drivers because it assumes that overhead
consumed by products is highly correlated with the units produced.

Review textbook Exhibit 12-1, which provides a model


of the functional-based product costing system.

B. Plantwide and Departmental Rates


1. Both plantwide rates and departmental rates are used to assign overhead costs to products
using unit-based cost drivers.
2. A plantwide rate uses a single cost pool for the entire plant.
246 Chapter 12

3. Departmental rates use separate cost pools for the different departments.

Review textbook Exhibits 12-3 and 12-4, which show product unit cost
computations using plantwide rates and departmental rates, respectively.

C. The Failure of Plantwide and Departmental Rates


Using plantwide or departmental rates to assign overhead costs will produce inaccurate product
costs when:
1. The proportion of nonunit-related overhead costs to total overhead costs is large (e.g.,
reaching more than 40 or 50 percent of the total).
a. Using only unit-based activity drivers to assign nonunit-based costs can create cost
distortions.
b. Nonunit-related overhead costs refer to those costs that are unrelated to the number of
units produced but more logically relate to nonunit-based drivers.
 Nonunit-based drivers are factors, other than the number of units produced,
that measure the demands that cost objects place on activities.
c. Examples:
(1) Setup costs relate to the number of batches of products produced.
(2) Product engineering costs depend on the number of different engineering work
orders.
(3) Material-moving costs relate to the number of moves required, not to the number
of units produced.
2. The degree of product diversity is great.
a. Product diversity means that products consume overhead activities in different
proportions because of their differences in product size, product complexity, setup time,
and size of batches.
b. The consumption ratio measures the proportion of each activity consumed by a product.
D. Potential users of ABC systems can be identified when these companies:
1. Produce multiple products,
2. Have a high degree of product diversity, and
3. Have a significant percentage of nonunit-level overhead in production costs.
Activity-Based Costing 247

Review textbook Exhibit 12-5, which provides examples of


consumption ratios of various activities by different products.

Note that the special product (scented cards) usesLearning Objective #2 more
setup and material-moving activities.

II. Activity-Based Costing System

A. An activity-based costing (ABC) system first assigns costs to activities and then traces costs
from activities to products.
1. ABC assumes that activities consume resources, and products and other cost objects
consume activities.
2. ABC cost assignment is made possible through the identification of activities, their costs, and
the use of cost drivers. Thus, it better reflects the pattern of overhead consumption and is more
accurate than functional-based costing.

Review textbook Exhibit 12-8, which provides an activity-based costing model.

B. Six essential steps in designing an ABC system include:


Step 1: Identify, define, and classify activities and key attributes.
Step 2: Assign the cost of resources to activities.
Step 3: Assign the cost of secondary activities to primary activities.
Step 4: Identify cost objects and specify the amount of each activity consumed by specific
cost objects.
Step 5: Calculate primary activity rates.
Step 6: Assign activity costs to cost objects.
Step 1: Identify, define, and classify activities and key attributes.
1. To identify an activity means to describe the work performed by people or equipment.
a. Use an action verb and an object that receives the action to name the activity.
b. An activity inventory is a list of the activities that are performed within the
organization.

Review textbook Exhibit 12-10, which provides a sample


activity inventory for an electronics manufacturer.

2. To define an activity means to use activity attributes to describe it.


 Activity attributes are nonfinancial and financial information items that describe
individual activities (for example, description of the tasks that make up the activity,
resources consumed by the activity, amount or percentage of time spent on the activity, the
cost objects, and the activity driver.)
248 Chapter 12

 An activity dictionary lists the activities in an organization along with desired


attributes.
3. To classify an activity means to recognize the difference between it and other activities for
different purposes.
a. For product costing purposes, activities can be classified as primary or secondary.
(1) A primary activity is consumed by a final cost object (e.g., a product or
customer).
(2) A secondary activity is consumed by intermediate cost objects (e.g., primary
activities, materials, or other secondary activities).
b. Many other useful activity classifications exist. For example, activities can be classified as
value-added or nonvalue-added, as quality-related or environmental-related.
4. Methods to be used to gather activity information include interviews, surveys, and
observations.

Review textbook Exhibit 12-11, which provides an example of an activity dictionary.

Note that the activity dictionary names the activity, describes the
tasks that make up the activity, classifies the activity as primary or secondary,
lists the cost object(s), and identifies the activity driver.

Step 2: Assign the cost of resources to activities.


1. Costs may be assigned to activities using:
a. Direct tracing, when resources are exclusive to the activity.
b. Driver tracing, when resources are shared by several activities.
2. Resource drivers are the factors that measure the consumption of resources by activities.
a. Resource driver data can be collected using interviews, survey forms, questionnaires, and
timekeeping systems.
b. A work distribution matrix helps identify the amount of labor consumed by each activity.
It is a means of collecting the data required to assign labor resource costs to activities.
Step 3: Assign the cost of secondary activities to primary activities.
If there are secondary activities, then the costs of those must be assigned to the primary activities.

Review textbook Exhibit 12-13, which provides an example of the cost of a secondary
activity (supervising nurses) being reassigned to the primary activities.

Compare the costs of the primary activities after the reassignment (Exhibit
12-13) with those before the reassignment (Exhibit 12-12).

Step 4: Identify cost objects and specify the amount of each activity consumed by specific cost
objects.
1. Costs can be assigned to products or other cost objects in proportion to their usage of the
activity by:
a. Identifying the cost objects.
Activity-Based Costing 249

b. Measuring the demand that cost objects place on the activities.


2. Activity drivers measure the demands that cost objects place on activities.
3. Most ABC system designs choose between two types of activity drivers:
a. Transaction drivers measure the number of times an activity is performed.
 Examples: Number of treatments, number of requests
b. Duration drivers measure the time it takes to perform an activity.
 Duration drivers should be used when the time required to perform an
activity varies from transaction to transaction.
 Examples: Hours of hygienic care, monitoring hours
4. A bill of activities can be created to specify the product, expected product quantity, activities,
and amount of each activity expected to be consumed by each product.
Learning Objective #3
Review textbook Exhibit 12-14, which provides an example of a bill of activity for a cardiology
ward. It includes activities, activity drivers, and types of services that consume activities.

Step 5: Calculate primary activity rates.


Primary activity rates are computed by dividing the budgeted activity costs by practical activity
capacity.
Step 6: Assign activity costs to cost objects.
Using the primary activity rates, costs are assigned to the cost objects.

Review textbook Exhibit 12-15, which illustrates the final assignment of costs to cost objects.

C. Materials as an Intermediate Cost Object


1. Material-related activities, such as purchasing, inspecting, and moving materials, are
secondary activities because they are not directly consumed by the final cost objects.
2. The cost of material-related secondary activities will be first assigned to materials (an
intermediate cost object) and then to the final cost objects through direct tracing.

III. Homogeneous Pools of Activities

In the final stage of ABC, homogeneous cost pools can be used to reduce the number of activity rates
because fewer rates may
 Produce more readable and manageable product cost reports.
 Reduce the perceived complexity of an ABC system and increase its likelihood of managerial
acceptance.
 Increase the accuracy of cost assignments.
A. Activity Classification: The Key for Reducing the Number of Rates
1. Activities can be grouped in homogeneous sets if
a. They are logically related, and
b. They have the same consumption ratios for all products.
250 Chapter 12

2. A homogenous cost pool is the collection of overhead costs associated with a set of activities
that has the same process, the same activity level, and can use the same driver to assign cost to
products.
 The pool rate is the cost per unit of the chosen activity driver that can be computed as:
Homogeneous pool costs
Pool rate =
Activity driver s
’ practical capacity
3. Attributes that are useful for grouping activities into homogeneous cost pools include process,
activity-level, and activity-driver classifications.
a. Using process classification to create homogeneous cost pools.
(1) A process is a series of activities that are linked to perform a specific objective.
(2) The key to grouping activities is the notion of sharing a common objective or
purpose.
(3) Example: The procurement process’ common objective is to obtain parts for
production. Activities that can be linked together include purchasing, receiving, and
paying suppliers.

Review textbook Exhibit 12-17, which illustrates process classification.

b. Using activity-level classification to create homogeneous cost pools.


(1) Activities can be grouped together if they are performed at the same general activity
level (same activity-level attribute).
(2) Classifying activities by the activity level helps management identify the appropriate
activity drivers because the costs of activities associated with the different levels
respond to different types of activity drivers.
(3) Four general activity categories include:
 Unit-level activities are those that are performed each time a unit is produced.
 Batch-level activities are those that are performed each time a batch is
produced.
 Examples: Setup, inspections (if done by sampling units from a batch),
purchasing, material handling
 Product-level activities are those performed that enable the various products of a
company to be produced.
 Examples: Engineering changes to products, developing product-testing
procedures, introducing new products, expediting goods
 Facility-level activities are those that sustain a factory’s general manufacturing
processes.
 Examples: Providing facilities, maintaining grounds, providing plant security

Review textbook Exhibit 12-18, which illustrates activity-level classification.

c. Using activity-driver classification to create homogeneous cost pools.


Activity-Based Costing 251

(1) The unit-level, batch-level, and product-level activities can be grouped together if
they have the same consumption ratio and share the same activity driver.
(2) Facility-level activities do not undergo the driver classification because they are
common to a variety of products.

Review textbook Exhibit 12-19, which illustrates activity driver


classification and the formation of homogeneous cost pools.

B. Comparison with Functional-Based Costing


1. In a functional-based system, the consumption of overhead is assumed to be explained only by
unit-level activity drivers.
 This may not reflect the activities actually being consumed by the products.
 Many of the costs being assigned in the functional-based fixed overhead category are
really batch-level, product-level, and facility-level costs that vary with drivers other than
unit-based drivers.
2. ABC systems recognize nonunit-based drivers and by better tracing costs to individual
products will:
 Improve product costing accuracy and decision making.
 Allow managers to exert more control over the activities that cause the costs.
 Allow managers to identify which of the activities add value and which do not.

IV. ABC System Concepts

Advances in information technology facilitate the development of an ABC database and ERP systems.
A. An ABC database is the collected data sets that are organized and interrelated for use by an
organization’s activity-based costing information system.
 A data set is a grouping of logically related data.

Learning Objective #4
252 Chapter 12

1. Creating an ABC database involves the following steps:


a. Define and model the entities that are involved in ABC.
b. Develop a conceptual view of the entities and the logical relationships between the
entities.
c. Identify the attributes associated with each entity.
d. Select a model that reflects the data structure implied by the entities and attributes, such
as relational structure.
 A relational structure uses a table to represent the overall logical view within a
database.
 ABC software typically uses a relational structure for data.
2. Activity relational table in an ABC database
a. The activity relational table provides important information to form homogeneous cost
pools and calculate pool rates.
b. Each activity is identified by an activity number, which serves as the unique primary key.
 A primary key is the attribute that uniquely identifies each row of data in the table,
i.e., a record.

Review textbook Exhibit 12-20, which provides an example of an activity relational table.

3. Product relational table in an ABC database


a. The product relational table is used to assign costs to products based on the activity
demands specified in the table.
b. The product number or name that uniquely identifies each product is used as the primary
key.
c. The use of concatenated keys helps assign costs to individual products.
 Concatenated keys are two or more keys that uniquely identify a record.
 Example: The product number and activity driver number are both used to assign
costs to individual products.

Review textbook Exhibit 12-22, which provides an example of a product relational table.

B. ABC and ERP Systems


1. ABC software selection is very important because:
 It should have the features that correlate with the functional capabilities of a firm’s
ABC system design.
 It should have at least three distinct modules: resources, activities, and cost objects.
2. ABC software selection must consider the firm’s ERP systems because ABC and ERP should
be integrated so that they can exchange vital information.

a. ERP systems are a major source of data for the ABC model by providing much of the
input data, including resource drivers, activity drivers, and resource costs.
Activity-Based Costing 253

b. ABC supports the ERP system as the operational control system by:
 Supplying accurate costs for products, customers, activities, and processes.
 Sending signals for directing continuous improvement efforts.
 Providing key information to support tactical and strategic decisions.
254 Chapter 12

KEY TERMS TEST


From the list that follows, select the term that best completes each statement and write it in the space provided.

ABC database nonunit-based drivers


activity attributes pool rate
activity dictionary primary activity
activity drivers primary key
activity inventory process
activity-based costing system product diversity
batch-level activities product-level activities
bill of activities relational structure
concatenated keys resource drivers
consumption ratio secondary activity
data set transaction drivers
duration drivers unit-based drivers
facility-level activities unit-level activities
homogeneous cost pool

1. The costing system that first traces costs to activities and then traces costs from activities to
products is a(n) ____________________________________________.

2. ___________________________ provide descriptive labels for individual activities.

3. ____________________________________ are performed each time a batch is produced;


____________________________________ are performed to enable the production of each
different type of product.

4. __________________________________ are factors that cause changes in cost as the units produced
change; __________________________________ are factors other than the number of units produced.

5. The listing of the activities performed within the organization is the ____________
_______________.

6. Factors that measure the demand placed on overhead activities by individual products are called
________________________.

7. The data structure that uses a table to represent the logical connections of a database is called a(n)
______________________________.

8. The proportion of an overhead activity consumed by a product is the ____________________ ________.

9. A(n) ______________ is a grouping of logically related data.

10. Activities that are performed each time a unit is produced are __________________.

11. A(n) ___________ is a series of activities that are linked to perform a specific objective.

12. If the collection of overhead costs associated with activities has the same process, the same level, and
can use the same driver to assign costs to products, it is a(n) ________ 
_____________________________________.
Activity-Based Costing 255

13. When products consume overhead in different proportions, there is _____________


_____________.

14. The collected data sets that are organized and interrelated for use by an organization’s activity-
based costing information system is the _________________________.

15. The homogeneous pool costs divided by the activity driver’s practical capacity is the
________________.

16. ____________________________ sustain a facility’s general manufacturing process.

17. The attribute that uniquely identifies each row of data in a table is the ____________________
________; two or more needed to uniquely identify a record are ____________________ ________.

MULTIPLE-CHOICE QUIZ
Complete each of the following statements by circling the letter of the best answer.

1. The activities that are performed each time a batch is produced are:
a. batch-level activities.
b. facility-level activities.
c. process-level activities.
d. product-level activities.
e. unit-level activities.

2. In a functional-based cost accounting system, which of the following activity drivers is used to assign
fixed overhead costs to products?
a. batch-level activities
b. facility-level activities
c. process-level activities
d. product-level activities
e. unit-level activities
256 Chapter 12

3. In a “pure” ABC system, which of the following would not be assigned to products?
a. batch-level activities
b. facility-level activities
c. process-level activities
d. product-level activities
e. unit-level activities

4. Which of the following would be classified as a product-level activity?


a. plant management
b. production scheduling
c. engineering changes
d. material handling
e. machine hours

5. Which of the following would be classified as a batch-level activity?


a. plant management
b. process engineering
c. engineering changes
d. material handling
e. machine hours

6. Which of the following is a true statement?


a. If nonunit-based overhead costs are a large proportion of overhead costs, the use of nonunit-based
drivers will cause large distortions in product costs.
b. If nonunit-based overhead costs are a small proportion of overhead costs, the use of nonunit-based
drivers will cause large distortions in product costs.
c. Nonunit-based activity drivers are factors that are proportional to the number of units
produced.
d. If products consume the nonunit overhead activities in the same proportion as unit overhead
activities, using a traditional overhead assignment method will cause costs to be distorted.
e. If products consume the nonunit overhead activities in the same proportion as unit overhead
activities, using a traditional overhead assignment method will not cause costs to be distorted.

7. Consumption ratios are:


a. the activities performed every time a batch is produced.
b. the proportion of each activity consumed by a product.
c. necessary for unit-level activities but not for batch- or product-level activities.
d. factors that cause costs to change as the level of activities change.
e. none of the above.
Activity-Based Costing 257

8. An activity-based costing system is one that:


a. traces costs to activities and then to products.
b. traces costs to resources and then to activities.
c. traces activities to costs and then to resources.
d. traces products to activities and then to resources.
e. uses a single plantwide rate for allocating overhead costs to products.

9. A homogeneous cost pool is one that:


a. does not change over time.
b. needs many activity drivers to be allocated to a cost object.
c. has only one type of material assigned to it.
d. can be explained with a single activity driver.
e. can be used only by the dairy industry.

10. Which of the following statements is incorrect regarding ABC and service industries?
a. Since service organizations do not have inventories, product costing (and thus ABC) will not be
necessary.
b. The output is more easily defined for a service organization than for a manufacturing
organization.
c. Activities in a service organization tend to be more standardized than activities in a manufacturing
organization.
d. Since the output of a service organization is consumed when produced, there will be no batch-level
activities.
e. None of the above statements are correct.

11. “Inspection of the first unit produced” is what type of activity?


a. batch-level
b. facility-level
c. process-level
d. product-level
e. unit-level

12. “Extruding plastic parts” is what type of activity?


a. batch-level
b. facility-level
c. process-level
d. product-level
e. unit-level
258 Chapter 12

PRACTICE TEST

EXERCISE 1
XYZ Company has identified the following overhead activities, costs, and activity drivers for the
coming year:
Activity Expected Cost Activity Driver Activity Capacity
Material-handling costs.............. $45,000 Number of moves..................... 450
Machine costs............................. 80,000 Machine hours.......................... 20,000
Order costs................................. 15,000 Number of orders..................... 750
Receiving costs........................... 30,000 Number of parts....................... 50,000
Setup costs................................. 50,000 Number of setups..................... 250

Assume that each activity corresponds to a process. XYZ ’s normal activity is 5,000 direct labor
hours. The following two jobs were completed during March:
Job X-1 Job Y-4
Direct materials........................................... $1,500 $2,000
Direct labor ($15 per hour).......................... $750 $750
Units completed........................................... 200 200
Number of moves........................................ 3 6
Machine hours............................................. 125 75
Number of orders........................................ 3 12
Number of parts.......................................... 200 800
Number of setups........................................ 1 4

Required:
1. Determine the unit cost for each job using direct labor hours to apply overhead.
Activity-Based Costing 259

EXERCISE 1 (CONTINUED)
2. Determine the unit cost for each job using the activity drivers to apply overhead.

3. Which method produces the more accurate cost assignment? Why?


260 Chapter 12

EXERCISE 2
Required:
Classify the following activities as unit-level, batch-level, product-level, or facility-level.

1. Marketing a product
2. Paying rent
3. Drilling a hole
4. Lighting the factory
5. Running the machines
6. Moving a batch
7. Engineering a product
8. Inspecting a machined part when it is completed
9. Ordering a purchased part
10. Setting up a machine
11. Using janitorial services
12. Paying insurance

EXERCISE 3
Acme Enterprises is a custom manufacturer of specialty circuit boards. The boards are produced
in batches in a single manufacturing facility. Each board requires an engineer to prepare the
specifications and schematic drawings. Once this design is complete, the equipment is set up
for the batch production. As each batch is completed, a sample of the units is inspected for
quality and tolerances. Costs have been assigned as follows:
Engineering..................................... $75,000
Setups............................................. 60,000
Labor.............................................. 50,000
Inspection....................................... 75,000
Factory lease................................... 30,000
Factory utilities............................... 12,000

The following activity drivers have been identified and their capacities determined:
Activity Driver Practical Capacity
Labor hours.................................... 5,000
Setup hours..................................... 2,000
Engineering hours........................... 2,500
Inspection hours.............................. 6,000
Machine hours................................ 10,000

The cost of the facility-level activities are assigned using machine hours.
Activity-Based Costing 261

EXERCISE 3 (CONTINUED)
Required:
1. Identify each activity as unit-level, batch-level, product-level, or facility-level.

2. Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that
will be used for computing pool rates. (Use machine hours as the activity driver for the factory lease and
factory utilities cost pools.)

3. Compute the pool rate for each pool you have identified in Requirement 2.
262 Chapter 12

EXERCISE 4
Alcatraz Company makes two models of an antitheft device. The portable model is relatively
small and is primarily for use in automobiles. The standard model is much larger and is
designed for houses and buildings. The Fabricating Department cuts, bends, and welds sheet
metal to produce the external box of the device. The box is also painted in this department. The
Assembly Department uses purchased parts to produce the internal workings and fits them into
the prepared metal boxes.
Alcatraz has conducted a special study to determine if an activity-based costing system would be
beneficial in determining the costs of the two products. The Fabricating Department is a more
complex department than the Assembly Department and has been chosen for a pilot test of an
ABC system. The following activities have been identified, along with their associated costs:
Depreciation................................................ $250,000
Factory lease............................................... 125,000
Inspection.................................................... 75,000
Factory maintenance.................................... 150,000
Materials handling....................................... 100,000
Power.......................................................... 50,000
Product engineering changes........................ 25,000
Setups.......................................................... 125,000
Department manager salaries....................... 60,000

The analysts have identified the following potential activity drivers and the capacity of each:
Portable Standard
Direct labor ($10 per hour)......................... $75,000 $90,000
Machine hours............................................. 4,000 6,000
Materials..................................................... $450,000 $650,000
Number of moves........................................ 1,500 1,500
Number of products..................................... 1 1
Number of setups........................................ 150 350
Units produced............................................ 15,000 17,500

Required:
1. Classify each activity according to activity level and identify an appropriate driver for each.
Activity-Based Costing 263

EXERCISE 4 (CONTINUED)
2. Create homogeneous cost pools and calculate pool rates. (Use the number of setups as the activity driver
for both inspection and setups costs. Machine hours serve as the activity driver for depreciation, factory
lease, factory maintenance, and department manager salaries.)

3. Use the pool rates to compute per unit overhead costs for the two products.
264 Chapter 12

“ CAN YOU? ” CHECKLIST


 Can you explain why functional-based costing systems may produce distorted costs?
 Can you explain why departmental rates, although better than plantwide rates, may still be inadequate?
 Can you explain how product diversity can affect overhead costs?
 Can you identify the signals that may indicate that functional-based costing is no longer working?
 Can you describe how an activity-based cost accounting system works? What are its features?
 Can you describe the differences between the various classifications or levels of activities and give several
examples of each?
 Can you describe how a firm’s ABC and ERP systems should be integrated and supportive of each other
by exchanging vital information?

ANSWERS

KEY TERMS TEST


1. activity-based costing system 10. unit-level activities
2. Activity attributes 11. process
3. Batch-level activities, product-level activities 12. homogeneous cost pool
4. Unit-based drivers, nonunit-based drivers 13. product diversity
5. activity inventory 14. ABC database
6. activity drivers 15. pool rate
7. relational structure 16. Facility-level activities
8. consumption ratio 17. primary key, concatenated keys
9. data set
Activity-Based Costing 265

MULTIPLE-CHOICE QUIZ
1. a 4. c 7. b 10. e
2. e 5. d 8. a 11. a
3. b 6. e 9. d 12. e

PRACTICE TEST
EXERCISE 1 (XYZ COMPANY)
1. Total overhead = $45,000 + $80,000 + $15,000 + $30,000 + $50,000 = $220,000 / 5,000 DL hours = $44 per DL hour
Job X-1 Job Y-4
Materials........................ $1,500 $2,000
Labor.............................. 750 750
Overhead........................  2,200 (50 × $44)  2,200 (50 × $44)
Total............................... $4,450 $4,950
Divided by units............. ÷  200 ÷  200
Per unit........................... $22.25 $24.75
2. Materials handling $45,000 / 450 = $100 per move
Machine time $80,000 / 20,000 = $4 per machine hour
Ordering $15,000 / 750 = $20 per order
Receiving $30,000 / 50,000 = $0.60 per part
Setup $50,000 / 250 = $200 per setup
Job X-1 Job Y-4
Materials........................ $1,500 $2,000
Direct labor.................... 750 750
Moves............................. 300 (3 × $100) 600 (6 × $100)
Machine.......................... 500 (125 × $4) 300 (75 × $4)
Orders............................. 60 (3 × $20) 240 (12 × $20)
Parts............................... 120 (200 × $0.60) 480 (800 × $0.60)
Setups.............................    200 (1 × $200)    800 (4 × $200)
Total............................... $3,430 $5,170
Divided by units............. ÷  200 ÷  200
Per unit........................... $17.15 $25.85
3. Costs determined using the activity drivers are more accurate. The consumption ratios of the resources differ greatly between
the two products. The direct labor approach to apply overhead implicitly assumes the two products consume the overhead
resources in the same pattern as direct labor (50%-50%).

EXERCISE 2 (ACTIVITY CLASSIFICATIONS)

1. Marketing a product product-level


2. Paying rent facility-level
3. Drilling a hole unit-level
4. Lighting the factory facility-level
5. Running the machines unit-level
6. Moving a batch batch-level
7. Engineering a product product-level
8. Inspecting a machined part when it is completed unit-level
9. Ordering a purchased part batch-level
10. Setting up a machine batch-level
11. Using janitorial services facility-level
12. Paying insurance facility-level
EXERCISE 3 (ACME ENTERPRISES )
1. Engineering......................... Batch-level
Setups.................................. Batch-level
Labor................................... Unit-level
Inspection............................ Batch-level
Factory lease........................ Facility-level
Factory utilities.................... Facility-level

2.–3. At most, there will be five cost pools. It is possible that the three batch-level activities could be combined into a single
pool. If this were the case, the driver could be setup hours, engineering hours, or inspection hours.
Pool Activity Driver Rate
1 Engineering Engineering hours $30.00 ($75,000 / 2,500)
2 Setups Setup hours 30.00 ($60,000 / 2,000)
3 Inspection Inspection hours 12.50 ($75,000 / 6,000)
4 Labor Labor hours 10.00 ($50,000 / 5,000)
5 Lease and utilities Machine hours 4.20 [($30,000 + $12,000) / 10,000]

EXERCISE 4 (ALCATRAZ COMPANY)


1. Activity Level Driver
Depreciation Facility Machine hours
Factory lease Facility Machine hours
Inspection Batch Number of setups
Factory maintenance Facility Machine hours
Materials handling Batch Number of moves
Power Unit Machine hours
Product engineering changes Product Number of products
Setups Batch Number of setups
Department manager salaries Facility Machine hours

2. Pool Activities Costs Driver Quantity Rate


1 Inspection $ 75,000
Setups  125,000
$200,000 Number of setups 500 $400.00
2 Materials handling $100,000 Number of moves 3,000 $33.33
3 Product engineering changes $ 25,000 Number of products 2 $12,500.00
4 Depreciation $250,000
Factory lease 125,000
Factory maintenance 150,000
Power 50,000
Department manager salaries   60,000
$635,000 Machine hours 10,000 $63.50

3. Pool Portable Standard


Setups............................. $ 60,000 (150 × $400) $140,000 (350 × $400)
Moves............................. 50,000* (1,500 × $33.33) 50,000* (1,500 × $33.33)
Products.......................... 12,500 (1 × $12,500) 12,500 (1 × $12,500)
Machine hours................  254,000 (4,000 × $63.50)  381,000 (6,000 × $63.50)
Total............................... $376,500 $583,500
Divided by units............. ÷ 15,000 ÷ 17,500
Per unit........................... $ 25.10 $ 33.34

*rounded

266

You might also like