THE CORNICHE PARK TOWERS (6 MONTHS LOOK AHEAD AUDIT SCHEDULE ) 

(DEC 2019 ‐ MAY 2020)
Dec Jan Feb Mar Apr May
S.No. AUDITEE TYPE SCOPE OF THE AUDIT AUDIT TEAM
1 AEB ‐ Design  External Resources & Programme Lead Auditor & Discipline Manager 18‐Dec‐19

2 AEB ‐ Supervision External Inspections Lead Auditor & Discipline Manager 25‐Dec‐19

3 QUANTEX External Cost & Budget Control Lead Auditor & Discipline Manager 02‐Jan‐20


MEP Materials & Procurement, 
4 Redco Al Mana  External Lead Auditor & Discipline Manager 09‐Jan‐20
Subcontractors
5 Internal Internal Design Management Lead Auditor & Discipline Manager 23‐Jan‐20

6 AEB ‐ Supervision External Non‐Conformance Reports Lead Auditor & Discipline Manager 12‐Mar‐20

7 QUANTEX External Cost Planning Lead Auditor & Discipline Manager 02‐Apr‐20

8 Redco Al Mana  External MEP Resourcing Programme Lead Auditor & Discipline Manager 09‐Apr‐20

9 Internal Internal Document Control Lead Auditor & Discipline Manager 23‐Apr‐20

LEGEND :  Executed Reported

Approved By:  Project Director Prepared by:  QA Manager

(Patrice Daens) ( John Gentle)

Form.Ref.PQA‐QAAT‐PP‐11‐13a‐FM Rev.2, Dated : 11 December 2019