BOQ
BOQ
DETAILED ESTIMATES
ITEM DESCRIPTION QUANTITY UNIT
NO.
1.00 PRELIMINARIES/GENERAL REQUIREMENTS
1.00 Mobilization/Demobilization 1.00 lot
2.00 Temporary Facilities, Board-ups & Billboards 1.00 lot
3.00 Water & Electricity 1.00 lot
Building Permits & Other Permits, Bldg. Plan Blueprints & Signatures for Ar., PEE, ME),
5.00 1.00 lot
Structural Analysis & Design, Program of Works, PERT/CPM & S-Curve
6.00 Safety Requirements 1.00 lot
7.00 Testing & Commissioning 1.00 lot
8.00 As-built Plans & Occupancy Permits 1.00 lot
PVC Door
0.7mL x 2.10mH Single-swing Solid Mahogany Panel Door on 2" x 6"
5.00 D4 Mahogany Jamb on paint finish with 6mm thk Fixed Clear Glass & 6.00 set(s)
Transom Window with complete accessories (refer to plans &
specifications)
1.00 Wall Hung Lavatory Granite Slab Finish with Bullnose (2faucet-2drain) set(s)
10W LED Pinlight at 750 Lumens with 6" Vertical Pinlight Fixtures
5.00 set(s)
(Recessed Type)
6.00 70W, 18" Metal Blade Orbit Ceiling Fan set(s)
LED Heavy Duty Emergency Light 2x0.5W 600 lumens, 4V 4AH Sealed
7.00 set(s)
Lead Acid Battery
8.00 Single-Gang Convenience Outlet (Flush Type) set(s)
9.00 Two-Gang Convenience Outlet (Flush Type) set(s)
10.00 Water Pump Waterproof Convenience Outlet (flush Type) set(s)
11.00 One-Gang Switch with LED Set (Flush Type) set(s)
12.00 Two-Gang Switch with LED Set (Flush Type) set(s)
OCM 7%
CONTRACTOR'S PROFIT 8%
VAT & EWT 7%
TOTAL INDIRECT COST
Prepared by:
JAYBERT V. DUMARAN
CIVIL ENGINEER
Approved by:
ATES
UNIT COST TOTAL COST
AMOUNT
MATERIAL LABOR MATERIALS LABOR
Sub-total 270,265.12 7,000.00 277,265.12
51,187.51 51,187.51 51,187.51
20,000.00 7,000.00 20,000.00 7,000.00 27,000.00
15,000.00 15,000.00 15,000.00
Sub-total - - -
55.00 - -
240.00 - -
525.00 157.50 - - -
360.00 - -
1,200.00 360.00 - - - 1.666667
78.12 23.44 - - -
Sub-total - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
85.00 21.25 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
55.00 13.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
60.00 15.00 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
30.00 7.50 - - -
30.00 7.50 - - -
55.00 13.75 - - -
535.00 133.75 - - -
Sub-total - - -
35.00 14.00 - - -
35.00 14.00 - - -
35.00 14.00 - - -
29.00 7.25 - - -
29.00 7.25 - - -
29.00 7.25 - - -
32.00 8.00 - - -
95.00 23.75 - - -
175.00 43.75 - - -
800.00 200.00 - - -
3,000.00 750.00 - - -
10,000.00 - -
600.00 150.00 - - -
450.00 112.50 - - -
280.00 70.00 - - -
280.00 70.00 - - -
7,000.00 1,750.00 - - -
3,000.00 750.00 - - -
600.00 150.00 - - -
450.00 112.50 - - -
450.00 112.50 - - -
7,000.00 1,750.00 - - -
3,000.00 750.00 - - -
600.00 150.00 - - -
7,000.00 1,750.00 - - -
3,500.00 875.00 - - -
80.00 20.00 - - -
3,500.00 875.00 - - -
80.00 20.00 - - -
280.00 70.00 - - -
265.00 66.25 - - -
280.00 70.00 - - -
5,000.00 1,250.00 - - -
3,000.00 750.00 - - -
Sub-total - - -
15.00 3.75 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
32.00 8.00 - - -
55.00 13.75 - - -
50.00 12.50 - - -
13.00 3.25 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
32.00 8.00 - - -
55.00 13.75 - - -
50.00 12.50 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
1,200.00 300.00 - - -
32.00 8.00 - - -
32.00 8.00 - - -
55.00 13.75 - - -
535.00 133.75 - - -
13.00 3.25 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
32.00 8.00 - - -
55.00 13.75 - - -
50.00 12.50 - - -
200.00 50.00 - - -
650.00 162.50 - - -
210.00 52.50 - - -
650.00 162.50 - - -
200.00 50.00 - - -
1,200.00 300.00 - - -
35.00 8.75 - - -
85.00 21.25 - - -
720.00 180.00 - - -
Sub-total - - -
1,440.00 360.00 - - -
85.00 21.25 - - -
336.00 84.00 - - -
480.00 120.00 - - -
5.00 1.25 - - -
240.00 60.00 - - -
420.00 105.00 - - -
420.00 105.00 - - -
Area
32.00 8.00 3,616.00 904.00 4,520.00 18.396 20.2356
32.00 8.00 1,440.00 360.00 1,800.00 3.655 4.0205
250.00 62.50 2,000.00 500.00 2,500.00 24.26
210.00 52.50 2,730.00 682.50 3,412.50
650.00 162.50 788.32 197.08 985.40
250.00 62.50 2,250.00 562.50 2,812.50
110.00 27.50 550.00 137.50 687.50
Sub-total - - -
450.00 112.50 - - -
4,500.00 1,125.00 - - -
4,500.00 1,125.00 - - -
2,500.00 625.00 - - -
600.00 150.00 - - -
10,000.00 - -
Sub-total - - -
mmisioning, supports, adapters, boxes and necessary
make the system operational.
600.00 150.00 - - -
1,500.00 375.00 - - -
960.00 240.00 - - -
650.00 162.50 - - -
600.00 150.00 - - -
94.00 23.50 - - -
72.00 18.00 - - -
45.00 11.25 - - -
32.00 8.00 - - -
28.00 7.00 - - -
54.00 13.50 - - -
54.00 13.50 - - -
66.00 16.50 - - -
54.00 13.50 - - -
54.00 13.50 - - -
54.00 13.50 - - -
240.00 60.00 - - -
240.00 60.00 - - -
168.00 42.00 - - -
168.00 42.00 - - -
420.00 105.00 - - -
94.00 23.50 - - -
168.00 42.00 - - -
370.00 92.50 - - -
150.00 37.50 - - -
250.00 62.50 - - -
33.00 8.25 - - -
444.00 111.00 - - -
180.00 45.00 - - -
33.00 8.25 - - -
35.00 8.75 - - -
4.00 1.00 - - -
4.00 1.00 - - -
280.00 70.00 - - -
280.00 70.00 - - -
360.00 90.00 - - -
5,000.00 1,250.00 - - -
5,000.00 1,250.00 - - -
5,000.00 1,250.00 - - -
5,000.00 1,250.00 - - -
8,000.00 2,000.00 - - -
80.00 20.00 - - -
480.00 120.00 - - -
800.00 200.00 - - -
450.00 112.50 - - -
450.00 112.50 - - -
10,000.00 2,500.00 - - -
10,000.00 2,500.00 - - -
6,500.00 1,625.00 - - -
Sub-total - - -
1,320.00 330.00 - - -
60.00 15.00 - - -
48.00 12.00 - - -
12.00 3.00 - - -
36.00 9.00 - - -
39.00 9.75 - - -
8.40 2.10 - - -
240.00 60.00 - - -
60.00 15.00 - - -
3.60 0.90 - - -
3,500.00 875.00 - - -
2,200.00 550.00 - - -
2,200.00 550.00 - - -
1,500.00 375.00 - - -
1,500.00 375.00 - - -
1,500.00 375.00 - - -
1,500.00 375.00 - - -
4,500.00 1,125.00 - - -
3,200.00 800.00 - - -
2,000.00 500.00 - - -
2,000.00 500.00 - - -
45.00 11.25 - - -
600.00 150.00 - - -
600.00 150.00 - - -
520.00 130.00 - - -
520.00 130.00 - - -
320.00 80.00 - - -
2,500.00 625.00 - - -
1,200.00 300.00 - - -
400.00 100.00 - - -
500.00 125.00 - - -
250.00 62.50 - - -
60.00 15.00 - - -
95.00 23.75 - - -
Sub-total - - -
ning, supports, adapters, boxes and necessary
make the system operational.
4,500.00 675.00 - - -
2,500.00 375.00 - - -
4,200.00 630.00 - - -
10,500.00 1,575.00 - - -
550,682.91
77,104.45
627,787.35
43,945.11
626,412.04
90,870.12
761,227.27
1,389,014.60
at there will be no Variation Orders.
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0
16.0
42.5 17.5
4.722222 0.048
2.833333
7.555556
Height or
Length Width Thickness
Item Work Type Description Qty
(m) (m) (m)
1.10 Excavation WF-1 39.10 0.40 0.70 -
1.20 Excavation WF-2 48.40 0.40 0.70 -
1.30 Excavation WF-3 49.00 0.60 0.70 -
1.40 Excavation SLAB 0.10 -
1.50 Excavation Footing 1.10 0.90 1.20 3.00
1.60 (-) Earthfill Column 0.20 0.30 1.00 3.00
1.70 Earthfill Footing 1.10 0.90 1.20 3.00
1.80 (-) Earthfill Masonry 48.40 0.15 0.70 -
1.90 Earthfill WF-2 48.40 0.40 0.70 -
Embankment Lot Area 31.2 24.6 0.70
Excavation
Earthfill
Compaction
Gravel Bedding
Soil Treatment
Embankment
Area Volume
15.64 10.95
19.36 13.55
29.40 20.58
208.05 20.81
3.56
0.18
3.38
5.08
8.47
537.26
= 69.45 m3 69.45
= 11.85 m3 11.85
= 208.05 m 2
208.05
= 10.40 m3 10.40
= 208.05 m 2
208.05
= 537.26 m 3
537.26
Item no. Description Quantity Unit Total Remarks
Item Work Type Description Length (m) Width (m) Height or Thickness (m)
1.10 Concrete WF-1 39.10 0.40 0.20
1.20 Concrete WF-2 48.40 0.40 0.20
1.30 Concrete WF-3 49.00 0.60 0.20
1.40 0.10
1.50 Concrete Footing 1.10 0.90 0.30
1.60 Concrete Column 0.20 0.30 1.00
1.70 Concrete S.O.G. 0.10
Rebar
Qty Area Volume Description Diameter
- 15.64 3.13 WF-1 10mm
- 19.36 3.87 WF-2 10mm
- 29.40 5.88 WF-3 10mm
- S.O.G. 400mm O.C. 10mm
3.00 0.89 S.O.G. 600mm O.C. 10mm
3.00 0.18 Footing 12mm
208.05 20.81 Column Vertical ties 12mm
Column Stirrup 10mm
Full Truss 1 2 1/2" x 2 1/2" x 4.5mm x 6m Angle bar
Full Truss 1 2" x 2" x 4.0mm x 6m Angle bar
Full Truss 2 2" x 2" x 4.5mm x 6m Angle bar
Full Truss 2 1 1/2" x 1 1/2" x 4.0mm x 6m Angle bar
Roof beams 1 1/2" x 1 1/2" x 4.0mm x 6m Angle bar
2"x4"x1.2mm C-PURLINS
34.2733333 Welding rod Fuji Weld #12
364.4
131.26
495.66
Rebar
TLen (m) Rebar length Qty
312.80 6 53
2347.40 6 392
730.30 6 122
768.50 6 129
160.91 6 27
70.20 6 12
54.00 6 9
48.00 6 8
120.00 6 20
135.45 6 23
63.63 6 11
62.46 6 11
336.90 6 57
447.10 6 75
5 boxes 13 120
0.07065
336.00 1 164
240.00 3 244.166
576.00 85.13325
40.69
4.256663