Professional Documents
Culture Documents
Ass 1new
Ass 1new
Ass 1new
Individual Assignment 1
1. Plan a guideline related to authority regulation and documentation for any construction
project.
C6 (10 marks)
Table 1
Storm Duration = 20 min,
Rain (mm) at a 5 minutes interval
Number of intervals = 4
Date Total Rain (mm) 1st 2nd 3rd 4th
12.1.1972 47.6 9.2 12.8 12.8 12.8
7.12.1983 47.1 8.0 11.7 14.0 13.3
21.07.1992 43.8 9.5 12.3 11.2 10.9
3.12.1985 41.8 11.2 17.3 9.3 4.0
19.01.1999 40.8 4.8 13.3 12.0 10.7
27.4.2003 40.0 10.7 7.2 10.9 11.2
14.6.2005 38.4 9.3 10.3 9.7 9.0
30.6.1989 38.2 11.2 10.7 9.3 7.0
17.11.2001 37.1 9.6 12.8 10.7 4.0
4.2.1990 33.8 8.1 8.9 9.9 6.9
C3 & C4 (10 marks)
3. Referring to Figure 1, calculate the annual pollution loading (AN and TDS) in tonne/yr
for residential and commercial area. Given, mean annual rainfall, R is 2800 mm.
Residential 115 ha
Industrial 125 ha
Industrial 105 ha
Residential 86 ha
Residential 260 ha
Figure 1
C3 & C4 (10 marks)