Professional Documents
Culture Documents
Environment Audit 5th Line PDF
Environment Audit 5th Line PDF
Environment Audit 5th Line PDF
E507
Volume 5
a--
Public Disclosure Authorized
JUNE 2002
FlI r efiv
Environmental-Audit of Santacruz- Bonvali Serene Environmental Services
5Eh Railway line
TABLE OF CONTENTS
LIST OF TABLES
LIST OF FIGURES
LIST OF ANNEXURES
Annex Description
Number
l.A Terms of Reference for carrying out Environmental Audit of Railway Projects
11.B Legal Requirements
2. Site Photographs
3. Public Consultation Details
4. Environment/ Health/ Safety Inspection Sheet
5. Documentation to be maintained by contractor or railway site engineer on site
6. Format for survival reporting for tree plantation
Environmental Audit of Santacruz -Bonivali Serene Environmental Services
5Eh Railway line.
LIST OF ABBREVIATIONS
EXECUTIVE SUMMARY
1.0 INTRODUCTION
The Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects to
strengthen the suburban rail transport and road transport in Greater Mumbai and Mumbai
Metropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improving
public transport including the railway capacity.
As per requirement of The World Bank, Environmental Assessments (EA) was done for some
of these sub-projects in the years 1996 to 1998. Also, a consolidated EA was prepared for
the entire MUTP project. Environmental Management Plans (EMP) was prepared as a part
of these EAs, which included mitigation measures for minimising adverse environmental
impacts. Currently, several of these sub-projects are in different stages of construction and
MMRDA desires to carry out an assessment of the relevant EMPs.
This assignment pertains to the EMP assessment/audit for the 5 th line construction between
Santacruz and Borivali stations on Westem Railway (WR). This project is being implemented
by the Western Railway (WR).
Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services of
Serene Environmental Services (SES) to carry out Environmental Audit for railway projects of
MUTP.
The broad components of the project can be grouped under the following heads:
. Earthwork for laying of rail tracks between stations
Environmental Audit of Santacruz- Bonvali Serene Environmental Services;
5"h Railway line Project
AAQ near commercial and residential areas near railway stations, typically have elevated
AAQ levels due to sluggish traffic and highly built-up area with poor dispersion conditions.
However, areas between stations have much lower values.
Boundary wall have been constructed along the railway land, however this is not expected to
have much potential for noise attenuation, as residential building are located very close to the
tracks and are 3 to 4 storey high. Providing a barTier all along the track to this height may not
be feasible. Source reduction techniques by providing better track/wheel interface and track
modification may be more appropriate for noise reduction.
4.5 Landuse
This rail corridor is large built-up area with no significant ecological resources, water bodies
etc. There are mixed use and residential areas immediately adjacent to the corridor
boundary. At Malad and Goregaon few patches of vacant land are seen in between stations.
The land-use pattern has not change significantly due to the implementation of the project as
it has come up alongside the existing tracks.
As per survey conducted by MMRDA, there were no such structures present on this route.
A summary of the impacts during construction and operation phases of the project in given in
Table A
iv
Environmental Audlt of Santacruz- Borivalh Serene Environmental Services
5Zh Railway line Project
No. Parameter Impacts During Construction phase Impacts During operation phase
1. Air Quality Construction work is completed. Thus impacts on air No negative impacts durng operation phase.
quality due to construction activity cannot be assessed.
2. Noise Construction work is completed. Thus impacts on noise Existing baseline noise levels in this area exceeds the CPCB
levels due to construction activity cannot be assessed. noise standards for residential area. This is typically found
near the railway tracks where residential areas are located
quite close (30 to 50 m)to railway tracks.
Table A Cont..
No. Parameter Impacts During Construction phase Impacts During operation phase
3 Water Quality No water bodies of any significance such as lakes, rivers, No significant adverse impacts as effluent from
creek etc. present in the Santacruz-Borivali rail corridor. platforms will be treated in septic tanks and
No adverse environmental impact on any water body. discharged via soak pits/ or into existing sewers.
No other source of effluent during operation.
4. Natural Permission for felling of trees had been obtained from the No adverse impacts on ecology during operation
Habitats and Tree Officer. Area for tree plantation is limited due to phase. No forest and other sensitive ecological
Ecology dense built-up area on this route (See Photo 1 in Annex reserves located in the rail corridor.
2). However, WR is carrying out track-side and other
plantation for enhancement of the area wherever feasible.
(Photo 3 in Annex 2 shows plantation and fencing at
Andheri station)
5. Landuse The land-use pattern has not change significantly due to No adverse impacts expected.
the implementation of the project as it has come up
alongside the existing tracks.
6. Archaeological As per survey conducted by MMRDA, there were no such No adverse impacts expected.
and Cultural structures present on this route. More details are given in
Property. the Rehabilitation Action Plan (RAP) for MUTP and
Rehabilitation Implementation Plan (RIP) for the Project.
"I
Environmental Audit of Santacruz- Bonvali Serene Environmental Services
dh Railway line Project
The entire construction work for the project is complete and thus EHS measures cannot be
audited/assessed for the construction phase. Also, as seen from the previous section, site
visits have not revealed any significant adverse environmental impact caused due the already
completed activity.
The EHS issues are addressed for the components given below
Critical EHS recommendations for the project are given below, more details on audit findings and
recommendations are available in Tables 5.1 to 5.3 of this reporL
1. Resettlement is currently being carried out by MMRDA as per RAP of GOM. Separate
Transit and permanent accommodations for project affected households should be audited at
least 6 monthly.
2. All necessary permissions to be taken for cutting trees/vegetation
3. Along with design of noise barriers, technology with low noise should be incorporated.
vii
Environmental Audit of Sentacruz- Bonvali Serene Environmental Seivices
dh Railway line Project
Construction Phase
1. Road wetting for earth-working operations to be done regularly for dust suppression..
2. All contractors to make sure that all dumpers and other vehicles being used at site have been
checked for vehicle emissions and have a valid PUC certificate.
3. A clear documented procedure to be made part of the tender documents for future projects,
requirng contractors to dispose debris in low-lying areas away from water bodies, as fill
material only.
4. Documentation such as quarry release receipt issued by the District Revenue officer at the
quarry site to be available at construction site.
5. Safety and hazard posters and signs should be clearly displayed at locations such as plafform
works, level crossings, Station building construction areas etc.
6. W.R. to assure that procedure for work permit is followed at all construction sites.
7. WR to assure that all contractors make available safety shoes, face masks, earplugs etc. as
applicable to the labourers. Such PPE's should be available on site and assessment should
be made during scheduled inspections.
WR to make sure that all above requirements (given in more detail in EMP tables 5.1 to 5.3)
should be made part of tender documents for future projects.
ODeration Phase
1. Regular maintenance of track side plantation.
2. Noise monitoring on Santacruz-Borvali route as given in Table 6.
Ste visits and interviews have revealed the following facts related to environmental
management organisation:
. In the consolidated EA report for MUTP, MRVC was reported to be the Project
Implementation Agency (PIA). However, Westem Railway '/VR) is the PIA for this
project. MRVC is the coordinating agency to facilitate communication between MMRDA
and WR.
o WR has not been involved in any of the earlier EA efforts. Environmental mitigation
measures identified in the earlier EA for this project and also identified in the consolidated
EA are not available with WR. However, WR has incorporated certain EHS elements in
the tender documents.
o Environmental monitoring is currently not required to be done by the contractors. Apart
from periodic safety inspections, currently there is no feedback mechanism for EHS
elements of the project.
The construction phase is completed and site observations have not revealed any significant
residual impacts on the site due to construction phase. Major significant impacts would be
the displacement of project affected people and cutting of vegetation along the ROW. The
monitoring of R&R components is being covered separately as a part of another study and
permissions have been taken earlier for cufting of vegetation
viii
Environmental Audit of Santacnuz- Borivali Serene Environmental Services
h Railway line Project
Comprehensive periodic site inspection programs for EHS elements and a regular
environmental monitorng program will best achieve the objectives of monitoring described
above for this project.
The recommended EMP monitoring and reporting mechanism, inspection schedule - format -
responsibilities, current institutional mechanism, training requirements etc. are given in detail
in Section 6.1 of this report. The cost for EMP for Santacruz-Borvali line is estimated at Rs.
1346000 (See Table 8).
ix
Environmental Audit of Santacruz- Borivali Serene Environmental Services
dh Railway line Project
1.0 INTRODUCTION
1.1 Background
The Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects to
strengthen the suburban rail transport and road transport in Greater Mumbai and Mumbai
Metropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improving
public transport including the railway capacity.
As per requirement of The World Bank, Environmental Assessments (EA) was done for some
of these sub-projects in the years 1996 to 1998. Also, a consolidated EA was prepared for
the entire MUTP project. Environmental Management Plans (EMP) was prepared as a part
of these EAs, which included mitigation measures for minimising adverse environmental
impacts. Currently, several of these sub-projects are in different stages of construction and
MMRDA desires to carry out an assessment of the relevant EMPs.
This assignment pertains to the EMP assessment/audit for the 5th line construction between
Santacruz and Borivali stations on Western Railway (WR). This project is being implemented
by the Western Railway (WR).
Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services of
Serene Environmental Services (SES) to carry out Environmental Audit for railway projects
of MUTP. The scope of work is as per TOR given in the RFP no. PD/MUTP/EA/701/2001
dated October 16, 2001 (Annex 1). The work was awarded to SES on November 7, 2001,
after final negotiations on November 6, 2001.
*' Assess the status of environmental impacts during ongoing construction and future
planned activities.
0 Assess whether any environmental mitigation measures are required based on on-going
completed works, if any.
l' Environmental mitigation measures for planned works, if required.
0- Document lessons that can be useful for future projects.
*' Mitigate environmental impacts on the marine water quality, water flow due to
construction of bridges and other possible impacts as identified in the MLEA report of
Borivali - Virar Rail Quadrupling Project (BVQR), prepared by Montgomerry Watson
Consultants, Mumbai, 1998.
Environmental Audit of Santacruz- Borivah Serene Environmental Services
5e Railway line Project
The Santacruz - Borvali 5th railway line is necessary to improve the reliability of Suburban
trains, which are working beyond saturation level of line capacity. The scope of project
includes construction of 5 th railway line between Santacruz to Borivali covering about 15 kms.
Four additional 9-car rakes or 12-car rakes service could be introduced on this line to
enhance the capacity of suburban section of Western Railway.
1. Segregation of suburban and non-suburban traffic between Santacruz and Borivali, thus
releasing capacity on through lines to allow more suburban trains and create new route
for passenger trains to new passenger terminus at Bandra.
2. Provision of 5th line will provide additional three suburban 12-car rake paths from Borvali
to Churchgate.
The broad components of the project can be grouped under the following heads:
The broad project components and implementation status of the same are given below in
Table 1.1 and 1.2 respectively. Santacruz to Andheri line has started operating and track-
linking work is in progress in case of Goregaon to Borvali railway line. Photo I (Annex 2)
shows the completed 5th line with boundary wall. Photo 2 shows a view of a minor bridge
(subway extension).
2
Environmental Audit of Santacruz- Borivali Serene Environmental Services
eh Railway line Project
3
Environmentl Audit of Santacruz- Bonvali Serene Environmental Services
5 h Railway line Project
The various tasks and methodology followed for completing these objectives are given below
in Table 2.0. Methodology followed is as per the Inception Report of the project.
Water Quality
Construction of the project is complete and no impact on
surface or ground water quality expected. No water
monitoring envisaged
Impacts on water quality due to planned construction of
platforms, sanitary facilities etc will be assessed. No water
monitoring envisaged.
Soil Quality
All earthwork and construction of bridges etc are complete
Soil analysis is not envisaged.
4
Environmental Audit of Santacnrz- Borivali Serene Environmental Services
5e Railway line Project.
The applicable Indian environmental regulations, World Bank policies/directives and GOM
directives for all MUTP projects are given in detail in Annex lB. This EMP's for the
Santacruz-Borivali project have been prepared within the framework of the Consolidated
Environmental Assessment (CEA), Report for MUTP, 2002. The legal requirements
applicable to the Santacruz-Borivali project are as follows:
Relevant compliance action for these policies has been covered in the following Section 4.6
6
Environmental Audit of Santacruz- Bonvali Serene Environmental Services
eh
5 Railway line Project
For this project Environmental Assessment has not been carried out earlier and baseline
environmental data is not available. As discussed earlier, construction work for the project is
fully complete. Thus, impacts during construction phase of the project cannot be assessed.
However, residual impacts, if any, due to completed activities and ongoing activities have
been evaluated and are presented below. A summary of Impacts is presented in Table 3.
Santacruz - Borvali tracks run over almost a level terrain in the area. The area through out is
built-up. Some open areas are observed between Malad and Goregaon. Geology is typical
of the westem coast i.e. Basalt rocks overlain by alluvial soils / clays.
4.2 Climate
The climate of the area is characterized by high humidity nearly all year round, oppressive
summers season and well-distributed and heavy rainfall during the southwest monsoon
season. This suburban district receives heavy rainfall during the southwest monsoon season
between June and August.
Baseline data for the project site is not available. AAQ is being monitored by Municipal
Corporation of Greater Mumbai (MCGM) at several locations in Mumbai. Mronitoring is done
as per the methodology prescribed by Ministry of Environment and forests (MOEF), New
Delhi. One of the locations where monitoring is conducted regularly is near the Khar railway
station. Although this station does not lie between Santacruz and Borivali, it is on the same
line and located adjacent to Santacnrz to the south. This location is considered as an
example of area near the railway stations, having high density of vehicular traffic including
auto-rickshaws, buses, private vehicles etc. The annual average values for the year 2000 for
S02, NOx and SPM reported at Khar was 16.16 t1g/M 3 , 69.25 jig/M3 and 290 hig/M 3 . These
values may not represent the AAQ levels at other stations, but may be taken as an example.
The values for NOx and SPM exceed the AAQ annual average standards for residential areas.
These AAQ annual average AAQ standards for residential areas are as follows: S02 (60
[Lg/M 3 ); NOx (60 jig/m3); SPM (140 jig/rn3).
AAQ near commercial and residential areas near railway stations, typically have elevated
AAQ levels due to sluggish traffic and highly built-up area with poor dispersion conditions.
However, areas between stations have much lower values.
Environmental Audit of Santacruz- Borivali Serene Environmental Services
5 h Railway line Project
Impact Assessment
Baseline Data
Baseline data for the project site is not available. However, spot monitoring of noise (day
time) was done near the 5e line between Santacnrz and Andheri to assess noise impacts.
Photo 1 in Annex 2 shows a section of the completed 5th line with boundary wall and
residential areas next to it. Noise monitoring was done at a similar locations. The noise
monitoring locations and values are given below in Table 4.0
Impact Assessment
Boundary wall have been constructed along the railway land,-however this is not expected to
have much potential for noise attenuation, as residential building are located very close to the
tracks and are 3 to 4 storey high. Providing a barrier all along the track to this height may not
be feasible. Source reduction techniques by providing better track/wheel interface and track
modification may be more appropriate for noise reduction.
8
Environmental Audit of Santacruz- Borivali Serene Environmental Services
5e' Railway line Project
Impact Assessment
Durinq Construction Phase
Construction work is completed. Thus impacts on any water body due to construction activity
cannot be assessed. However, there are no water bodies of any significance (lakes, rivers,
creek etc.) present in the Santacnrz-Borivali rail corridor. In fact most of the area is dense
Built-up area. Thus there would not have been any adverse environmental impact on water
bodies.
Impacts
The land-use pattern has not change significantly due to the implementation of the project as
it has come up alongside the existing tracks.
9
Environmental Audit of Santacruz- Bonrvali Serene Environmental ServiCeS
5lh Railway line Project
As per survey conducted by MMRDA, there were no such structures present on this route.
Table 4.0 presents summarized impacts during construction and operation phase of project.
I(
Environmental Audit of Santacnrz- Bonvali Serene Environmental Services
h"' Railway line Project
No. Parameter Impacts During Construction phase Impacts During operation phase
1 Air Quality Construction work is completed. Thus impacts on air No negative impacts during operation phase.
quality due to construction activity cannot be assessed.
2. Noise Construction work is completed. Thus impacts on noise Existing baseline noise levels in this area exceeds the CPCB
levels due to construction activity cannot be assessed. noise standards for residential area. This is typically found
near the railway tracks where residential areas are located
quite close (30 to 50 m) to railway tracks.
No. Parameter Impacts During Construction phase Impacts During operation phase
3. Water Quality No water bodies of any significance such as lakes, rivers, No significant adverse impacts as effluent from
creek etc. present in the Santacruz-Borivali rail corridor. plafforms will be treated in septic tanks and
No adverse environmental impact on any water body. discharged via soak pits/ or into existing sewers.
No other source of effluent during operation.
4. Natural Permission for felling of trees had been obtained from the No adverse impacts on ecology during operation
Habitats and Tree Officer. Area for tree plantation is limited due to phase. No forest and other sensitive ecological
Ecology dense built-up area on this route (See Photo I in Annex reserves located in the rail corridor.
2). However, WR is carrying out track-side and other
plantation for enhancement of the area wherever feasible.
(Photo 3 in Annex 2 shows plantation and fencing at
Andheri station)
5. Landuse The land-use pattern has not change significantly due to No adverse impacts expected.
the implementation of the project as it has come up
alongside the existing tracks.
6. Archaeological As per survey conducted by MMRDA, there were no such No adverse impacts expected.
and Cultural structures present on this route. More details are given in
Property. the Rehabilitation Action Plan (RAP) for MUTP and
Rehabilitation Implementation Plan (RIP) for the Project.
12
Environmental Audit of Santacnuz-Bonvali Serene Environmental Services
dh Railway Line Project
5.1 Introduction
The previous sections described the changes observed in baseline environmental status and
the environmental impacts during construction and operation stages of the project. This
section is dedicated to evaluating the Environment, Health and Safety (EHS) mitigation needs
and institutional mechanisms for their implementation. EHS mitigation measures, monitoring
programs and reporting structure are required to be a part of an Environmental Management
Plan.
As discussed earlier, the entire construction work for the project is complete and thus EHS
measures cannot be audited/assessed for the construction phase. Also, as seen from the
previous section, site visits have not revealed any significant adverse environmental impact
caused due the already completed activity.
Thus, as far as this project is concemed, recommendations for EMP implementation include
the following:
* EHS mitigation measures that could be included as a requirement for contractors for
future works in this area.
* EMP monitoring and reporting during operational stage.
* Institutional mechanism for EMP implementation
EMP measures are presented in Table 5.1 to 5.3 for the design, construction and operation
stages. Tables 5.1 and 5.2 will be applicable only for future projects. Table 5.3 is
applicable to the operating stage of the current Santacruz-Borivali 5th line project.
14
Environmental Audit of Santacruz-Borivali Serene Environmental Services
dh Railway Line Project
o T/e EMP Measures given abovefor pre-constructionand constructionphases are applicablefor Future Railway Projectson this and
otlierroutes of WR.
** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting in
Section 6 and the inspection sheet and formats in Annex 4 and 5.
15
Environmental Audit of Santacruz-Borivali Serene Environmental Services
5 th Railway Line Project
16
Environmental Audit of Santacruz-Borivali Serene Environmental Services
5th Railway Line Project
17
Environmental Audit of Santacruz-Borivali Serene Environmental Services
5"' Railway Line Project
Health and hygiene at Construction labour camps shall be located away from the nearest habitation to avoid WR - Site Engineer
construction labour camps conflicts and stress over infrastructure facilities. Site contractor & Dy. Chief
Health and hygiene at Engineer
construction labour camps The contractor will provide, erect and maintain necessary (temporary) living accommodation WR - Site Engineer
and ancillary facilities such as toilet blocks, potable water supply etc. for labour as per the Site contractor & Dy. Chief
standards set by various labour Act. Engineer
On completion of the works, all temporary structures shall be cleared away along with all WR - Site Engineer
wastes. All excreta and other disposal pits should be filled in and effectively sealed. The site Site contractor & Dy. Chief
should be left clean and tidy to the satisfaction of the engineer. Engineer
Delays and congestion on The construction plan shall be discussed in advance with Western Railway Authorities to WR - Site Engineer
tracks avoid delays in existing train schedules. Site contractor & Dy. Chief
Engineer
Traffic Control and Safety The contractor shall take all necessary measures for the safety of existing train traffic during WR - Site Engineer
construction and provide, erect and maintain such barricades, including signs, markings, Site contractor & Dy. Chief
flags, lights and flagmen as may be required by the engineer for the information and Engineer
protection of traffic. All such measures should as per requirement of Western Railway.
Special consideration shall be given in preparation of traffic control plan to the safety of
pedestrians (at railway crossings) and workers at night.
* Tie EMP Measuresgiven abovefor pre-construction and construction phases are applicablefor Future Railway Projectson this and
other routes of KR
** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting in
Section 6 and the inspection sheet and formats in Annex 4 and 5.
18
Environmental Audit of Santacruz-Borivali Serene Environmental Services
5" Railway Line Project
* The EMPMeasures given aboveforpre-constructionandconstructionphases are applicableforFutureRailway Projectson this and other
routes of WR
** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting in
Section 6 and the inspection sheet and formats in Annex 4 and 5.
19
Environmental Audit of Santacruz-Bonvali Serene Environmental Services
dh Railway Linre Project
20
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5th Railway line.
Ste visits and interviews have revealed the following facts related to environmental
management organisation:
. In the consolidated EA report for MUTP, MRVC was reported to be the Project
Implementation Agency (PIA). However, Westem Railway (WR) is the PIA for this
project. MRVC is the coordinating agency to facilitate communication between MMRDA
and WR.
* Environmental monitoring is currently not required to be done by the contractors. Apart
from periodic safety inspections, currentiv there is no feedback mechanism for EHS
elements of the project.
The monitoring of R&R components is being covered separately as a part of another study
and permissions have been taken earlier for cutting of vegetation.
Comprehensive periodic site inspection programs for EHS elements and a regular
environmental monitoring program will best achieve the objectives of monitoring described
above for this project. This is covered in Section below.
The construction of this line is complete and hence monitoring during construction phase is
not being provided. For future works, monitoring of air quality, noise levels etc. will need to be
defined based on actual location and site conditions of the project.
In the context of Railway projects of MUTP, an effective inspection program will go a long
way to assure implementation of various EHS mitigation measures for this project. The
program given here could be used for future construction activities on this line. The inspection
program needs to be dove-tailed into existing programs followed by WR and, the parameters
for inspection, inspection schedules etc. need to be clearly defined. The EHS parameters to
be monitored depend upon factors such as:
21
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5 Railway line.
Based on the site observations, level of awareness of contractor and WR staff, the following
program and procedure is suggested for effective monitoring of EHS implementation at future
construction sites covered by MUTP:
b. All site contractors to maintain log books and other documentation specified in
Annex 5.
c. Copy of the completed monthly inspectfon checklist should be sent by the Chief
Engineer (WR) to MMRDA every month for review. The Inspection checklist for a
month along with the corrective actfon plan, if any, shall reach MMRDA no later
than the 1?m day of the next month.
d. MMRDA to carry out independent 3rd- party inspection of various construction sites
(the sample sites indicated in this report could be visited at a minimum) every
quarter during the constructfon activity and also after construction is completed to
assess any residual environmental Impact A Project Management Consultant
(PMC) should be appointed for this purpose by MMRDA. Review checklist given in
Annex 4 could be used for this purpose.
22
Environmental Audit of Santacruz -Bonvalh Serene Environmental Services
5e Railway line.
Operation phase monitoring for this project is required mainly for the following:
* Ambient noise levels to determine baseline levels and track improvements accrued due to
implementation of source noise reduction. Ambient air monitoring is not suggested since
the operation will not contribute to air pollution (Electricity driven trains). Also no impacts
during operation stage expected on water quality and soil quality.
* Health and survival rates of the compensatory and other plantation done by WR.
* Monitoring of Rehabilitation and Resettlement (R&R) sites for the people displaced due to
the project. This will be done as a separate exercise not covered in this audit report.
23
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5 th Railway line
* At residential
area near new
platform
constructed at
Andheri
station
* At residential
area behind
boundary wall
200 m south of
Borivali
station.
24
Environmental Audit of Santacnrz -Borivali Serene Environmental Services
eh Railway line.
The construction activities of the project are being implemented by WR. The existing organisational
structure of Railways for operation phase is given below in Figure 1.
Dy. Chief
Engineer
(Construction)
Borivali to Virar
Assistant Engineers
In the consolidated EA report for MUTP, it was envisaged that the monitoring and reporting
process for mitigation measures during construction should initiate from the contractor at the
lowest rung who will report to the Project Implementation Agency (PIA) through the Project
Management Consultant (PMC). PMC could be appointed for periodic 3r party review of the
EHS elements for the operating stages and for construction phases of any future projects.
25
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5 h Railway line.
For carrying out regular inspection for the EHS elements, the WR staff needs training for
appreciation of various EHS elements. The training program proposed is given in Table 7
below.
1 training program of 4 days as given above should be conducted every quarter to cover all
concemed WR staff. The training program can also be integrated into the WR induction-
training program.
Visits to country's having similar railway projects and with established and demonstrated EHS
Mahagement System, including demonstrated measures for noise attenuation could be visited
by concemed officials of WR. This will help in increasing awareness with WR and improve
technical skills for EHS management.
26
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5 h Railway line.
* Cost of Training has already been included for WR in BVQR project The staff of
WR for this 2 lines will be included under the same training program. The actual
cost for EMP for Santacruz-Borivali line will be Rs. 1,86,000.
27
Environmental Audit of Santacruz- Borivali Serene Environmental Services
5 th Railway line
ANNEX-1A
TERMS OF REFERENCE
MUMBAI URBAN TRANSPORT PROJECT
1 ASSIGNMENT:
2 BACKGROUND:
b) Report of Initial Environmental Examination for Thane- Kurla 5th and 6th lines
prepared by MMRDA in 2000-01.
The Consultant should use these reports as the basis to carry out the proposed
environmental audit
2 3 Somie of the projects may also involve construGtion in aieas. wlhichi are classified
as restricted areas unfder Coastal Regulation Zone (CRZ) Rules H-lence,
permiission needs to be obtained under CRZ FRules fromil thie Ministry of
Eiviroinilent and Forests. Governimlenit of Ildia for SUCIl projectS
MUMBAI URBAN TRANSPORT PROJECT
I ASSIGNMENT:
2 BACKGROUND:
b) Report of Initial Environmental Examination for Thane- Kurla 5th and 6th lines
prepared by MMRDA in 2000-01.
The Consultant should use these reports as thie basis to carry out thie proposed
environmental audit
2 3 Som1e of the projects m1ay also involve coristruGlior) In areas, which are classified
as restricted areas un1der Coastal Regulation Zone (CRZ) Rules I-fence,
perinission needs to be obtained under CRZ FPules from tire Ministry of
Eiivironment and Forests. Government of Indis foI SUCIn proJeCts
Assessnicut has not Iben cairied out for this project as unider the scrcereeing of
MUTP carried otit by Montigomlery Watson, it was placed in the category of
su)bproject w;thl possibly negligible unrpacts on the environmilent
- Final ret Slt ole Environmental Assessmaerit for the MUTP project prepared by
Montgo riery Watson Consultanits, Mumbai
- Final iepoit on l-nvironiunental Assessiment for Ille MUI'P project pi epaied b)y
Montgonllcy Watson Consultants, Mumbai
- The EIVIPs aiid tIlicir iniipleniientationi plans shoulce prepared iii GOiISilS1iato101
and agreemient with the MRVC and other concerned agencies
4 DOCUMENTS:
Prepare Environmental Audit report for the present exercise based on the
above tasks
assess whiether any activity of tihe project will have imnpacts on the
-
vi. Guidelines available (from the World Bank and elsewhere) oni environmental
issues related to electrical substation / transformers.
5 REPORTING REQUIREMENTS
The Consultanit will report to MMRDA and the following is tthe output schedule for
each ot' the four projects. The draft reports submitted by the Consultant will be
reviewed and monitored by a Technical Working Group (TWG) constituted by
MMRDA comprising of the representatives of MMRDA, MRVC, MCGM, and
NGO.
6 DURATION: '
The study should be cornpleted within a period of 8 weeks The total Consultant inputs
for the above assioniment is expected to be 6 person weeks.
7 CONSULTANT'S QUALIFICATIONS:
The Consultant for the assignment shall have acquired a post graduate degree in
Environmental Engineering with at least 7 to 10 years experience in preparing
Environmental Assessment reports, conducting Environmental Audits and good working
knowledge of environmental management in related projects.
Environmental Audit of Santacruz- Borivali Serene Environmental Services
5h Railway line
ANNEX- 1B
LEGAL REQUIREMENTS
LEGAL AND POLICY FRAMEWORK
1 The project will be implemented within the Indian legal framework and will also complywith
the safeguard policies of the World Bank. The applicable legal and policy framework is
descfibed below.
10. These regulations prepared under the MR & TP Act offer an alternatve to acquisibon under
LA Act by way of Transfer of Development Rights (TDR). The permissible Floor Space
Index (FSI) defines the development rights of every parcel of land in Mumbai. If apartcular
parcel of land is designated for a public purpose the landowner has an option of accepting
monetary compensabon under the LA Act 1894 or accept TDR (equivalent to the plot area
times the permissible FSI), which can be sold in the market for use elsewhere in Mumbai.
The DC Regulations have been amended to provide incentives for rehabilitation (including
resettlement of slum dwellers) in 1997. For landowners prepared to provide 225 sq.ft.
dwelling units free of cost to slum dwellers, the incentve is in the form of right to build and
sell floor space equivalent to that required for slum rehabilitation subject to the maximum
in-situ utirization of FSI of 2.5. The remainder of the total development rights can be used
as TDR. In case of land designated for resettlement of slum dwellers affected by
infrastructure projects, the land owner has an option of offering dwelling unitsto the project
implementing agency free of cost and getting the benefit of maximum of TDR equivalentto
floor area calculated at FSI of 3.5 (1 for land and 2.5 for the built-up area).
15. Mumbai with its history of- nearly three hundred years is rich in cultural property
particularly in the form of built herTtage. GOM and MCGM are acutely aware of the need to
conserve such heritage. GOM in 1995 with the involvement of NGOs listed over 600
buildings and precincts as of heritage significance. DCR 67 govems the development of
these listed buildings and precincts. GOM has also constituted a Heritage Conservation
Committee in 1995 to advise the Municipal Commissioner regarding development
permission to be granted in case of listed buildings and precincts. No development
permission can be granted of the listed buildings or within the precincts without the consent
of the Heritage Committee.
16. During the execution of works, if a 'chance find "of archaeological significance occurs, the
contract requires the contractor to immediately inform the employer and stop furtherwork.
Employer will in turn inform the state Archaeology Department for further investigation.
17. The only cultural properties that are directly affected by the sub projects are small
places of worship established by the community of squatters within the right of
way. These hav7e been created by the affected communities for their own use.
Such places of worship do not possess any historical or architectural significance
and may not therefore strictly qualify to be treated as cultural property.
Nevertheless they are treated as an integral part of preparation of RIPs. The
places of worship and other community assets are identified dunng the BSES.
Their rehabilitation is being implemented as a part of the R & R process in
consultation with the community The impact on these properties and the manner in
which such impacts can be identified can be classified in three categones. Firstly the
buildings that are only partially affected can be helped to add equivalent area elsewhere
adjacent to the building. Secondly structures that are fully affected by the right of way but
are patronized by the community that is not affected by the project could be rebuilt outside
the right of way in consultation with the community and with assistance of the NGO. In
some cases the entrance to the structure could be reoriented to ensure safety of the
devotees visiting the place. Thirdly the affected structuresthat patronized by the community
being resettled could be relocated in consultation with the community. In addition, the
community may agree to forego some places without insisting upon their resettlement
18. Natural habitats are defined as land and water areas where (i) the ecosystems' biological
communities are formed largely by native plant and animal species, and (ii) human activity
has not essentfally modified the area's primary ecological functions. All natural habitats
have important biological, social, economic, and existence value. Important natural habitats
may occur in tropical humid, dry, and cloud forests; temperate and boreal forests;
Mediterranean-type shrub lands; natural arid and semi-arid lands; mangrove swamps,
coastal marshes, and other wetlands; estuaries; sea grass beds; coral reefs; freshwater
lakes and rivers; alpine and sub alpine environments, including herb fields, grasslands, and
paramos; and tropical and temperate grasslands. Criticalnaturalhabitats include exisfing
protected areas and areas officially proposed by governments as protected areas (e.g.,
reserves that meet the criteria of the World Conservation Union [IUCN] classifications i.e.
Strict Nature Reserve/Wilderness Area: protected area managed for science or wilderness
protecton; Il-Nabonal Park: protected area managed mainly for ecosystem protection and
recreation; Ill-Natural Monument: protected area managed mainly for conservation of
specific natural features; IV-HabitatVSpecies Management Area: protected area managed
mainly for conservation through management intervention; V-Protected
Landscape/Seascape: protected area managed mainly for landscape/seascape
conservation and recreation; and VI-Managed Resource Protected Area: protected area
managed mainly for the sustainable use of natural ecosystems. The conservabon of natural
habitats, like other measures that protect and enhance the environment, is essential for
long-term sustainable development. The Bank therefore supports the protection,
maintenance, and rehabilitation of natural habitats and their functions in its economic and
sector work, project financing, and policy dialogue. The Bank supports, and expects
borrowers to apply, a precautionary approach to natural resource management to ensure
opportunities for environmentally sustainable development.
19. From this perspective one of Mumbai's notable natural habitat is limited to the 103 sq.km.
Nabonal Park at Borivaii, which is located in the northern part of the peninsula between the
two rail corridors. The National Park is protected underthe Indian Forest Act. None of the
sub-projects passes through the National Park. The other important Natural Habitat is the
coastal wetlands in the eastern and western suburbs and along the Vasai creek. These are
protected by the Coastal Regulation Zone (CRZ) Notification of 19 February 1991.
20. The Operational Directve 4.30 describes Bank policy and procedures on
involuntary resettlement, as well as the conditions that borrowers are expected to
meet in operations involving involuntary resettlement. Planning and financing
resettlement of projects are an integral part of preparation for projects that cause
involuntary displacement MUTP will require resettlement of about 19000
households (68000 persons) The World Bank Policy on Involuntary Resettlement
is therefore applicable to the project. In compliance with to this policy an R & R
Policy has been prepared and adopted by GOM for MUTP. RAP providing the
overall framework of policy, entitlements, consultative processes, grevance
redressal mechanism, component costs and monitoring and evaluation mechanism
has already been prepared. Sub-project specific RIPs are being prepared.
23. World Bank has other safeguard policies dealing with Pest Management, Forestry, Safety
of Dams and Projects in International Waterways or in Disputed Areas These are however
not applicable to MUTP.
Environmental Audit of Santacruz- Borivali Serene Environmental Services
5h Railway line
ANNEX- 2
SITE PHOTOGRAPHS
Environmental Audit of Santacruz- Borivali Serene Environmental Services
dhRailway line
~ ~ ~ ~
F~~~~~~ i *A V
1. The Completed 5 th Line With Boundary Wall And Residential Areas Next To It
o_R~~~~~~~~L -S*
- - ~. -; _~
B- X -.
+,'~~~~~~~~~~~~~~j
/ f /
! * - \/.* 4
f7>4_ .cgi TeCmlt
> /
ANNEX-3
Consolidated
EA
November 23, Mumbai Cross section of Public Notices in English, List of
2001 Marathi Society, NGOs, Marathi and Hindi to participants,
Patrakar Representatives of the leading English and Minutes of the
Sangh, CST govemment Marathi newspapers, Meeting,
Mumbai departments, local Draft Consolidated EA Photographs,
authorities, project report, Executive Pamphlets,
implementation Summary in English and Consolidated
agencies, World Bank Marathi made available at EA reports,
academia and the PICs at MMRDA and Executive
consultants in the Mankhurd well in Summary, Non
transport and advance. Pamphlets each Technical
environment field, in English, Hindi and Summary at
Joumalists Marathi were distributed PiC. Records of I
amongst the general written
public and in the project comments,
affected areas through e.mail
environmental and social messages etc
NGOs. Public Notice and mesges,net
Executive Summary kept maitaied
on MMRDA's web site
well in advance.
November 24, Goregaonkar Project Affected Public Notices in English, List of
2001 English Households (PAHs), Marathi and Hindi to participants,
School, NGOs, Representatives leading English and Minutes of the
Goregaon of the project Marathi newspapers, Meeting,
(West) implementation Draft Consolidated EA Photographs,
Mumbai agencies, World Bank, report, Executive Pamphlets,
Joumalists, etc. Summary and Non Consolidated
Technical Summary in EA reports,
English and Marathi made Executive
available at PICs at Summary, Non
MMRDA and Mankhurd Technical
well in advance. Summary at
Pamphlets each in PIC. Records of
English, Hindi and Marathi written
were distributed amongst comments,
the general public and in e.mail
the project affected areas messages, etc
through environmental maintained
and social NGOs. Public
Notice and Executive
Summary kept on
MMRDA's web site well in
I advance.
Environmental Audit of Santacruz -Borivali Serene Environmental Services
5 h Railway line.
NOISE -
3) All vehicles / DG sets have working silences
Yes No_
4) High noise generating operations in NA
residential areas limited to daytime only. (eg.
DG sets, drilling, fabrication etc.) Yes No_
NA _
WATER POLLUTION -
5) Log book of construction waste generated &
disposed available Yes No
NA
6) Any signs of contamination of nearby water
bodies due to construction operation. Yes _ No
If yes, method employed by contractor for its NA
control - dyke / embankment etc.
ECOLOGICAL ISSUES
8) Have any tree > 1Om girth or sensitive
vegetation such as mangroves cut at Yes No_
construction site and stretch NA
Annex 4 Cont.
Environment I Health I Safety Elements Compliance Status Comments I
Remarks for
improvement
LAND POLLUTION / DEGRADATION -
11) Waste Logbook of debris generated and Yes_ No
disposal available on site. NA
Annex 4 Cont
1) Road watering daily schedule and source of water in the following format:
4) Copy of permission for tree felling from Tree officer / Forest Dept.
5) Amount of material taken from quarry, quarry location, copy of permit by District collector
etc.
6) Number of personnel protective equipment (PPE) avail at site (safety helmets, safety
belts, shoes, belts etc.)
ANNEX 6
FORMAT FOR SURVIVAL REPORTING FOR TREE PLANTATION
Date of Survey:
Name of Surveyor: