Rab Rumah 2 Lantai

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 87

MATERIAL PRICE LIST

Project : Residential Project


Lokasi : Delegan, Pabelan, Sub-district Sukoharjo

No Code Type of Material Coef Unit Unit Price


1 2 3 4 5 6

1. A. MINING MATERIAL
A. 1 Stone 1.00 m³ Rp 199,875.00
A. 2 Stone Andesit 1.00 m³ Rp 196,800.00
A. 3 Stone Muka 1.00 m³ Rp 61,500.00
A. 4 Stone Palimanan 1.00 m³ Rp 153,750.00
A. 5 Stone Paras 1.00 m³ Rp 104,550.00
A. 6 Split Aggregate 15 - 20 cm 1.00 m³ Rp 199,875.00
A. 7 Split Aggregate 5 - 7 cm Manual 1.00 m³ Rp 206,000.00
A. 8 Split Aggregate 3 - 5 cm Manual 1.00 m³ Rp 209,100.00
A. 9 Split Aggregate 2 - 3 cm Manual 1.00 m³ Rp 212,175.00
A. 10 Split Aggregate 2 - 3 cm Mechine 1.00 m³ Rp 221,400.00
A. 11 Split Aggregate 1 - 2 cm Mechine 1.00 m³ Rp 227,550.00
A. 12 Split Aggregate 0,5 - 1 cm Mechine 1.00 m³ Rp 233,700.00
A. 13 Soil Embankment Cadas 1.00 m³ Rp 43,050.00
A. 14 Sand Tras 1.00 m³ Rp 172,200.00
A. 15 Sand Embankment 1.00 m³ Rp 184,500.00
A. 16 Soil Liat 1.00 m³ Rp 61,500.00
A. 17 Sand Installation 1.00 m³ Rp 221,400.00
A. 18 Sand Concrete 1.00 m³ Rp 227,550.00
A. 19 Sirtu 1.00 m³ Rp 209,100.00
A. 20 Lime Installation ( Kawur ) 1.00 m³ Rp 264,450.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6
2. B. Steel
B. 1 Filamen Zinc 1.00 kg Rp 18,450.00
B. 2 Filamen Bendrat 1.00 kg Rp 27,060.00
B. 3 Filamen Nyamuk 1.00 m2 Rp 30,750.00
B. 4 Besi Siku 1.00 kg Rp 18,450.00
B. 5 Besi Concrete / Tulangan 1.00 kg Rp 13,500.00
B. 6 Steel Profile / konstruksi 1.00 kg Rp 17,800.00
B. 7 Baja teralis 1.00 kg Rp 18,450.00
B. 8 Alumunium strip 1.00 m¹ Rp 30,750.00
B. 9 Nail Standard Bridge 1.00 kg Rp 14,500.00
B. 10 Nail Standard Triplek 2cm 1.00 kg Rp 27,060.00
B. 11 Nail Fisher 1.00 kg Rp 27,060.00
B. 12 Nail Eternit 1.00 kg Rp 27,060.00
B. 13 Nail Usuk / Reng 1.00 kg Rp 17,200.00
B. 14 Nail Asbes 1.00 kg Rp 27,060.00
B. 15 Nail Sekrup 1.00 kg Rp 27,060.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6
3. C. FABRICATED CONCRETE
C. 1 Readymix K-175 1.00 m³ Rp 729,000.00
C. 2 Readymix K-225 1.00 m³ Rp 753,300.00
C. 3 Readymix K-300 1.00 m³ Rp 854,000.00
C. 4 oli teer 1.00 liter Rp 7,000.00
C. 5 Formtie/Spacer 1.00 piece Rp 7,600.00
C. 6 Culvert Concrete U dia. 50 x 100 cm 1.00 m¹ Rp 35,650.00

4. D. Wall Intallation
D. 1 Brick 1.00 piece Rp 900.00
D. 2 Brick wall 10 x 20 x 40 cm 1.00 piece Rp 4,300.00
D. 3 Rosteer Timber jati 1.00 piece Rp 43,050.00
D. 4 Cement portland 40 kg ( Holcin ) 1.00 Kg Rp 1,250.00
D. 5 PC White 1.00 kg Rp 3,690.00
D. 6 Red Cement 1.00 m³ Rp 307,500.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

5. E. Timber
E. 1 Timber Jati Grajen Lokal Frame 1.00 m³ Rp 9,840,000.00
E. 2 Timber Jati Grajen Lokall Roof Design 1.00 m³ Rp 10,455,000.00
E. 3 Timber Jati Grajen for Frame 1.00 m³ Rp 17,220,000.00
E. 4 Timber Jati Grajen for Roof Design 1.00 m³ Rp 14,760,000.00
E. 5 Timber Kamper Beam 1.00 m³ Rp 10,086,000.00
E. 6 Timber Kamper Board 1.00 m³ Rp 11,070,000.00
E. 7 Timber Kruing Beam 1.00 m³ Rp 6,396,000.00
E. 8 Timber Kruing Board 1.00 m³ Rp 7,257,000.00
E. 9 Timber Bangkirai Beam 1.00 m³ Rp 12,915,000.00
E. 10 Timber Bangkirai Board 1.00 m³ Rp 15,375,000.00
E. 11 Timber Meranti 5/7 1.00 m³ Rp 6,150,000.00
E. 12 Timber Zincon ( for Begesting ) 1.00 m³ Rp 1,845,000.00
E. 13 Timber Lis Profil 1.00 m¹ Rp 9,200.00
E. 14 Timber Dudukan Fitting 1.00 Psc Rp 5,800.00
E. 15 Timber Perancah 1.00 m³ Rp 1,722,000.00
E. 16 Timber Acuan 1.00 m³ Rp 1,537,500.00
E. 17 Timber bakar 1.00 m³ Rp 250,000.00
E. 18 Bambu 1.00 bar Rp 11,070.00
E. 19 Dolken 1.00 bar Rp 18,450.00
E. 20 Formite/Penjaga jarak / Spacer 1.00 Psc Rp 12,250.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

6. F. Roof Cover
F. 1 Tile Roof Concrete 1.00 Psc Rp 4,900.00
F. 2 Tile Roof Glasur Jatiwangi 1.00 Psc Rp 8,856.00
F. 3 Tile Roof Glasur Kebumen 1.00 Psc Rp 7,380.00
F. 4 Tile Roof Morando Jatiwangi 1.00 Psc Rp 4,300.00
F. 5 Tile Roof Morando Kebumen 1.00 Psc Rp 4,551.00
F. 6 Roof Joint Glasur 1.00 Psc Rp 12,300.00
F. 7 Roof Joint Kebumen 1.00 Psc Rp 11,070.00
F. 8 Roof Joint Pelintong 1.00 Psc Rp 9,800.00
F. 9 Roof Joint Cement 1.00 Psc Rp 9,800.00
F. 10 Roof Joint Soil 1.00 Psc Rp 8,600.00
F. 11 Roof Joint Vlam Kemiri 1.00 Psc Rp 4,900.00
F. 12 Tile Roof Magas Kebumen 1.00 Psc Rp 3,075.00
F. 13 Tile Roof Plentong Lokal 1.00 Psc Rp 1,476.00
F. 14 Tile Roof Press Cement 1.00 Psc Rp 4,900.00
F. 15 Tile Roof Vlam kemiri 1.00 Psc Rp 1,476.00
F. 16 Wave Asbes Wide 1m x 2m 1.00 sheet Rp 98,400.00
F. 17 Wave Asbes Small 1m x 1,2 1.00 sheet Rp 98,400.00
F. 18 Zinc Wave BJLS 0,3 (0,9m x 1,8m) 1.00 sheet Rp 123,000.00
F. 19 Zinc Wave BJLS 0,3 (0,9m x 2,1m) 1.00 sheet Rp 89,175.00
F. 20 Zinc Drainage BJLS 0,3 lebar 0,6 1.00 sheet Rp 34,071.00
F. 21 Zinc Drainage BJLS 0,3 lebar 0,9 1.00 sheet Rp 52,000.00
F. 22 Zinc Plat 90 x 180 cm 1.00 sheet Rp 76,875.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

7. G. Plafond Cover
G. 1 Hardflex 3 mm 100 x 100 cm 1.00 sheet Rp 22,100.00
G. 2 Teakwood 3mm 1.00 sheet Rp 135,300.00
G. 3 Teakwood 4mm 1.00 sheet Rp 147,600.00
G. 4 Tripleks Thickness 4 mm (kruing) 1.00 sheet Rp 84,870.00
G. 5 Tripleks Thickness 4 mm (Zincon) 1.00 sheet Rp 73,800.00
G. 6 Multipleks Thickness 4 mm 1.00 sheet Rp 8,300.00
G. 7 Multipleks Thickness 6 mm 1.00 sheet Rp 135,300.00
G. 8 Multipleks Thickness 8 mm 1.00 sheet Rp 147,600.00
G. 9 Multipleks Thickness 9 mm 1.00 sheet Rp 166,050.00
G. 10 Multipleks Thickness 12 mm 2.00 sheet Rp 204,180.00
G. 11 Gypsum 6,5 mm 1.00 sheet Rp 73,800.00
G. 12 Gypsum 9 mm 1.00 sheet Rp 86,100.00
G. 13 Gypsum board 1.00 sheet Rp 92,250.00
G. 14 Lis profil Gypsum 1.00 m Rp 12,300.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

8. H. Floor and Wall Cover


H. 1 Marmer Lokal 1.00 m² Rp 276,750.00
H. 2 Marmer import 1.00 m² Rp 1,537,500.00
H. 3 Ceramics 20x20 1.00 m² Rp 61,500.00
H. 4 Ceramics 20x25 dinding 1.00 m² Rp 67,650.00
H. 5 Ceramics 30x30 Smooth 1.00 m² Rp 58,400.00
H. 6 Ceramics 30x30 Design 1.00 m² Rp 71,300.00
H. 7 Ceramics 40x40 Smooth 1.00 m² Rp 79,950.00
H. 8 Ceramics 40x40 Color Design 1.00 m² Rp 92,250.00
H. 9 Ceramics 40x40 platinum 1.00 m² Rp 110,700.00
H. 10 Tile Paving 6cm 1.00 m² Rp 55,350.00
H. 11 Tile Paving 8cm 1.00 m² Rp 73,800.00
H. 12 Tile Paving 8cm K250 (Smooth) 1.00 m² Rp 104,550.00
H. 13 Tile Paving 8cm K250 (Color) 1.00 m² Rp 116,850.00
H. 14 Tile Paving 8cm K175 (Smooth) 1.00 m² Rp 89,175.00
H. 15 Tile Paving 8cm K175 (Color) 1.00 m² Rp 101,475.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

9. I. FINISHING MATERIAL
I. 1 Oil Painting 1.00 kg Rp 9,175.00
I. 2 Painting Meni Besi 1.00 Kg Rp 30,750.00
I. 3 Painting Meni Timber 1.00 kg Rp 30,750.00
I. 4 Painting Timber 1.00 kg Rp 59,000.00
I. 5 Painting Besi 1.00 kg Rp 59,000.00
I. 6 Painting Wall Eksterior 1.00 kg Rp 98,400.00
I. 7 Painting Wall Interior 1.00 kg Rp 24,600.00
I. 8 Pelitur 1.00 Ltr Rp 36,400.00
I. 9 Pelitur Jadi 1.00 Ltr Rp 85,000.00
I. 10 Plamur Wall 1.00 kg Rp 14,625.00
I. 11 Plamur Timber 1.00 kg Rp 29,175.00
I. 12 Painting Tile Roof 1.00 kg Rp 35,000.00
I. 13 Roll Painting 1.00 Psc Rp 20,500.00
I. 14 Brush 1 1/2" 1.00 Psc Rp 10,000.00
I. 15 Brush 2" 1.00 Psc Rp 12,500.00
I. 16 Brush 3" 1.00 Psc Rp 15,000.00
I. 17 Brush 4" 1.00 Psc Rp 21,500.00
I. 18 Amplas Timber 1.00 sheet Rp 6,150.00
I. 19 Amplas Besi 1.00 Psc Rp 6,150.00
I. 20 Serlak 1.00 Kg Rp 69,000.00
I. 21 Dempul / plamur 1.00 kg Rp 21,500.00
I. 22 Wood Filler ( Impra ) 1.00 kg Rp 27,000.00
I. 23 Glue Timber 1.00 kg Rp 15,990.00
I. 24 Glue kining ex aica aibon 1.00 kg Rp 79,950.00
I. 25 Soda Fire 1.00 kg Rp 30,000.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

10. J. SANITATION
J. 1 Washbak 1.00 Psc Rp 615,000.00
J. 2 Washtafel 1.00 Psc Rp 922,500.00
J. 3 Closet Jongkok Porselin 1.00 Psc Rp 184,500.00
J. 4 Fiber Glass (pail bath) 0,5 m3 1.00 Psc Rp 307,500.00
J. 5 Fiber Glass (pail bath) 1 m3 1.00 Psc Rp 922,500.00
J. 6 Water Tab ø 1/2 " ( Standard ) 1.00 Psc Rp 20,900.00
J. 7 Water Tab ø 1/2 " ( Medium ) 1.00 Psc Rp 36,900.00
J. 8 Water Tab ø 1/2 " ( Super ) 1.00 Psc Rp 79,950.00
J. 9 Water Tab ø 3/4 " ( Standard ) 1.00 Psc Rp 33,200.00
J. 10 Water Tab ø 3/4 " ( Medium ) 1.00 Psc Rp 37,500.00
J. 11 Water Tab ø 3/4 " ( super ) 1.00 Psc Rp 92,250.00
J. 12 Water Tab ø 1 " ( Standard ) 1.00 Psc Rp 47,355.00
J. 13 Water Tab ø 1 " ( Medium ) 1.00 Psc Rp 67,000.00
J. 14 Water Tab ø 1 " ( super ) 1.00 Psc Rp 73,800.00
J. 15 Seal Tabe 1.00 Psc Rp 6,150.00
J. 16 Stop Water Tab kuningan 3/4" 1.00 Psc Rp 42,000.00
J. 17 Stop Water Tab tipe handle 1,5" 1.00 Psc Rp 29,525.00
J. 18 Stop Water Tab tipe handle 2" 1.00 Psc Rp 31,650.00
J. 19 Fibe 1.00 kg Rp 22,100.00
J. 20 Water Collector 1000 lt 1.00 Psc Rp 1,845,000.00
11. K. Door and Window
K. 1 Glass Thickness 3 mm 1.00 m2 Rp 98,400.00
K. 2 Glass Thickness 5 mm 1.00 m 2
Rp 110,700.00
K. 3 Glass Thickness 6 mm 1.00 m2 Rp 116,850.00
K. 4 Glass Thickness 8 mm 1.00 m3 Rp 184,500.00
K. 5 Glass Thickness 5 mm 1.00 m2 Rp 123,000.00
K. 6 Glass Rayben 5mm 1.00 m3 Rp 102,090.00
K. 7 Hinge ( Standard ) 1.00 Psc Rp 14,760.00
K. 8 Hinge ( Medium ) 1.00 Psc Rp 24,600.00
K. 9 Hinge ( Super ) 1.00 Psc Rp 36,900.00
K. 10 Slot Standard 1.00 Psc Rp 98,400.00
K. 11 Key (Standard ) 1.00 Psc Rp 172,200.00
K. 12 Key ( Medium ) 1.00 Psc Rp 282,900.00
K. 13 Key (super ) 1.00 Psc Rp 338,250.00
K. 14 Ventilation (Standard) 1.00 Psc Rp 10,455.00
K. 15 Ventilation (Medium) 1.00 Psc Rp 20,900.00
K. 16 Ventilation (super) 1.00 Psc Rp 33,800.00
K. 17 Grendel (Standard) 1.00 Psc Rp 8,900.00
K. 18 Grendel (Medium) 1.00 Psc Rp 12,300.00
K. 19 Grendel (super) 1.00 Psc Rp 24,600.00
K. 20 Handel Window 1.00 Psc Rp 12,300.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

12. L. ELECTRICAL
L. 1 Light LED 9 Watt Philips 1.00 Psc Rp 30,750.00
L. 2 Light LED 6 Watt Philips 1.00 Psc Rp 27,675.00
L. 3 Light SL 18 Watt 1.00 Psc Rp 39,360.00
L. 4 Light SL 20 Watt 1.00 Psc Rp 43,050.00
L. 5 Swich Double 1.00 Psc Rp 22,100.00
L. 6 Swich single 1.00 Psc Rp 18,450.00
L. 7 Stop Kontak 1.00 Psc Rp 18,450.00
L. 8 Stop Kontak Digital 1.00 Psc Rp 276,750.00
L. 9 Stop Kontak Analog 1.00 Psc Rp 246,000.00
L. 10 Panel Control Lengkap 1.00 unit Rp 5,535,000.00
L. 11 Stabilizer 5000 Watt 1.00 unit Rp 3,874,500.00
L. 12 MCB 32 Amper 1.00 Psc Rp 246,000.00
L. 13 Viting porselin 1.00 Psc Rp 7,380.00
L. 14 Kabel Power 1.00 unit Rp 2,214,000.00
L. 15 Electrical Cable 1,5mm 1.00 m Rp 6,150.00
L. 16 Electrical Cable 2,5mm 1.00 m Rp 7,380.00
L. 17 Timber fitting 1.00 Psc Rp 5,800.00
L. 18 Isolasi 1.00 Psc Rp 5,000.00
No Code Type of Material Coef Unit Unit Price
1 2 3 4 5 6

13. M. ASPAL
1 Oil Soil 1.00 liter Rp 11,000.00
M. 2 Aspal Bitumen 60/70 1.00 kg Rp 14,760.00
M. 3 Aspal Curah 1.00 kg Rp 13,000.00

14. N. Pipe
N. 1 Pipe PVC AW (Length 4m)
N. 1.1 ø 1/2" 1.00 bar Rp 28,290.00
N. 1.2 ø 3/4" 1.00 bar Rp 33,200.00
N. 1.3 ø 1" 1.00 bar Rp 46,700.00
N. 1.4 ø 1,5" 1.00 bar Rp 86,100.00
N. 1.5 ø 2" 1.00 bar Rp 129,150.00
N. 1.6 ø 3" 1.00 bar Rp 233,700.00
N. 1.7 ø 4" 1.00 bar Rp 344,400.00
N. 1.8 ø 6" 1.00 bar Rp 713,400.00
N. 1.9 ø 8" 1.00 bar Rp 1,119,300.00
N. 2 Keni galvanis 1.00 Psc Rp 36,900.00

15. N. BUIS
O 1 Buis Concrete Length 1 m
O. 1.1 1/2 ø 20 cm 1.00 Psc Rp 28,290.00
O. 1.2 1/2 ø 30 cm 1.00 Psc Rp 33,200.00
O. 1.3 ø 20 cm 1.00 Psc Rp 46,700.00
O. 1.4 ø 30 cm 1.00 Psc Rp 86,100.00
O. 1.5 ø 40 cm 1.00 Psc Rp 129,150.00
O. 1.6 ø 50 cm 1.00 Psc Rp 233,700.00
O. 1.7 ø 60 cm 1.00 Psc Rp 344,400.00
O 2 Buis Concrete Length 1/2 m
O. 2.1 ø 80 cm 1.00 Psc Rp 713,400.00
O. 2.2 ø 100 cm 1.00 Psc Rp 1,119,300.00
Rp 199,875.00
Rp 196,800.00
Rp 61,500.00
Rp 153,750.00
Rp 104,550.00
Rp 199,875.00
Rp 206,000.00
Rp 209,100.00
Rp 212,175.00
Rp 221,400.00
Rp 227,550.00
Rp 233,700.00
Rp 43,050.00
Rp 172,200.00
Rp 184,500.00
Rp 61,500.00
Rp 221,400.00
Rp 227,550.00
Rp 209,100.00
Rp 264,450.00
Rp 18,450.00
Rp 27,060.00
Rp 30,750.00
Rp 18,450.00
Rp 13,500.00
Rp 17,800.00
Rp 18,450.00
Rp 30,750.00
Rp 14,500.00
Rp 27,060.00
Rp 27,060.00
Rp 27,060.00
Rp 17,200.00
Rp 27,060.00
Rp 27,060.00
19454225.35

0.001136
1136 kg/m3
WORKER COST

Project : Residential Project


Lokation : Delegan, Pabelan, Sub-district Sukoharjo

No Work Type Unit Unit Cost


1 3 4 5

1 Manson
Mansor day Rp 50,000.00
Head Mansor day Rp 55,000.00
Labor day Rp 40,000.00
Foreman day Rp 50,000.00
2 Carpenter
Carpenter day Rp 50,000.00
Head Carpenter day Rp 55,000.00
Labor day Rp 40,000.00
Foreman day Rp 50,000.00
3 Vulcan
Vulcan day Rp 50,000.00
Head Vulcan day Rp 55,000.00
Labor day Rp 40,000.00
Foreman day Rp 50,000.00
4 Painter
Painter day Rp 50,000.00
Head Painter day Rp 55,000.00
Labor day Rp 40,000.00
Foreman day Rp 50,000.00
5 Another worker
Mekanik expert day Rp 86,100.00
Mekanik semi expert day Rp 61,500.00
Operator expert day Rp 60,000.00
Operator semi expert day Rp 55,000.00
Assistant Operator day Rp 73,800.00
Worker expert day Rp 60,000.00
Worker semi expert day Rp 40,000.00
Driver day Rp 60,000.00
Driver private day Rp 60,000.00
Assistant Driver day Rp 55,000.00
Security day Rp 40,000.00
Team leader/Koordinator Profesional worker day Rp 209,100.00
Profesional worker/ Hydrogeologist/Geophisicist/ Driller day Rp 159,900.00
Assistant Profesional worker day Rp 123,000.00
Crew/Staf Profesional worker/Operator Pump day Rp 86,100.00
PERHITUNGAN RAB
RUMAH 2 LANTAI
PT…….
JLN….

1 PEKERJAAN PERSIAPAN

No GAMBAR DESKRIPSI Calculation and Work Description Volume


1 Pekerjaan pembersihan lahan pembersihan lokasi
deskrispsi panjang x lebar x unit = jumlah
area lahan 16.00 x 14.00 = 224.00

= 224.00 224.00 m²
2 bowplank

Description = Tot. Point x Length x Width x Height = Sum


Board 2/20 34 x 1.00 x 0.02 x 0.20 0.68
wood 5/7 68 x 0.07 x 0.05 x 1.00 = 0.24
Description = Unit x Height x Diameter
Nail 68 x 0.07 x 0.0034 = 0.00004
0.00033692 kg

0.92 m3
PERHITUNGAN RAB
RUMAH 2 LANTAI
PT…….
JLN….

2 SOIL ACTIVITIES

No Sketch Kode Calculation and Work Description


1 TA.1 Soil Excavation Activity
Description Length x Width x Height x Unit = Sum
1.50 x 1.50 x 2.1 12.00 56.70

2 TA.2 Sand Embankment Beneath the foundation


Description Length x Width x Height x Unit = Sum
1.50 x 1.50 x 0.10 x 12 = 2.70
3 TA.3 Aanstamping Activity
Description Length x Width x Height x Unit = Sum
1.50 x 1.50 x 0.05 x 12 = 1.35

4 TA.4 beton pondasi cakar ayam


Description bagian atas x bagian bawah x Unit = Sum
0.13 x 0.59 x 12.00 = 0.93
5 Soil embankment is done in the left and right side TA.5 Soil Embankment (Left and Right Foundation)
in order to be a solid foundation. Description
Volume of Excavation = 56.70
Volume of Sand Embankment = 2.70
Volume of Aanstamping = 1.35
Volume of Foundation = 0.93 -
= 51.72
CHAPTER IV
ACTIVITIES VOLUME CALCULATION
CONSTRUCTION MANAGEMENT ASSIGNMENT
CIVIL ENGINEERING DEPARTMENT ENGINEERING FACULTY

No Drawing Sketch and Explanation Kode Calculation and Work Description


6 TA.6 Soil Embankment Beneath The Building Floor
Description luas x Height x Unit = Sum
220.00 x 0.10 x 1 = 22.00

7 TA.7 Sand Embankment Beneath The Building Floor


Description luas x Height x Unit = Sum
220.00 x 0.15 x 1 = 33.00
PERHITUNGAN RAB
RUMAH 2 LANTAI
PT…….
JLN….

Volume

56.70 m³
2.70 m³

1.35 m³

0.93 m³
51.72 m³
CHAPTER IV
ACTIVITIES VOLUME CALCULATION
STRUCTION MANAGEMENT ASSIGNMENT
NEERING DEPARTMENT ENGINEERING FACULTY

Volume

22.00 m³
33.00 m³
No
BEGSTINGKOL M
4 CONCRETE ACTIVITY

Drawing Sketch and


Description
Kode Calculation and Work Description Volume
1 BT.1 Begesting of Sloof
Description Length x Height x Unit side = Sum
8.00 x 0.30 x 3.00 x 2 = 4.80
3.50 x 0.30 x 3.00 x 2 = 2.10
BEGESTING SLOOF

5.15 x 0.30 x 4.00 x 2 = 3.09


4.15 x 0.30 x 3.00 x 2 = 2.49
3.50 x 0.30 x 1.00 x 2 = 2.10
6.00 x 0.30 x 1.00 x 2 = 3.60
1.50 x 0.30 x 2.00 x 2 = 0.90

19.08 m2
Description length x area 3/5 x side x Unit P/0.5 x unit = sum
reng 0.30 x 0.0015 x 4 x 16 x 3.00 = 0.086
0.30 x 0.0015 x 4 x 7 x 3.00 = 0.038
0.30 x 0.0015 x 4 x 10.3 x 4.00 = 0.074
0.30 x 0.0015 x 4 x 8.3 x 3.00 = 0.045
0.30 x 0.0015 x 4 x 7 x 1.00 = 0.013
0.30 x 0.0015 x 4 x 12 x 1.00 = 0.022
0.30 x 0.0015 x 4 x 3 x 2.00 = 0.011

0.29 m2
19.37 m2

Drawing Sketch and


No Kode Calculation and Work Description Volume
Description

2 BT.2 Begesting Ring of Beam


Description Length x Height x Unit side = Sum
for building 20.00 x 0.20 x 2 x 2 = 16.00
BEGESTING RING BALOK

10.00 x 0.20 x 2 x 2 = 8.00


6.00 x 0.20 x 1 x 2 = 2.40
5.00 x 0.20 x 1 x 2 = 2.00
4.50 x 0.20 x 1 x 3 = 2.70
4.00 x 0.20 x 1 x 2 = 1.60
3.50 x 0.20 x 6 x 2 = 8.40
3.00 x 0.20 x 5 x 3 = 9.00
2.05 x 0.20 x 1 x 2 = 0.82
2.00 x 0.20 x 4 x 2 = 3.20
1.50 x 0.20 x 3 x 2 = 1.80
1.45 x 0.20 x 1 x 2 = 0.58
56.5 m2
Description Length x Area(3/5) x side x Unit P/0.5 x unit = sum
reng 0.30 0.0015 3 40 2 = 0.108
0.30 0.0015 3 20 2 = 0.054
5 INSTALLATION ACTIVITY

No Drawing Sketch and Description Kode Calculation and Work Description


Calculation and Work Description Volume
PERHITUNGAN VOLUME PEKERJAAN

6 PEKERJAAN ATAP
No Sket Gambar dan Penjelasan Kode Uraian Pekerjaan dan Perhitungan
1 AT.3 Pek. kuda-kuda baja profil 2L 70.70.9
Uraian Pjg total x unit x brt / m = jml
Kuda-kuda baja 28.87 x 5.00 x 2.00 = 288.70

2 AT.3 Pek. gording C 145.75.20.4,5


Uraian pjg unit x brt / m = jml
Gording C 145.75.20.4,5 12 x 6.00 x 2.50 = 180.00

3 AT.3 Pek. sagrod


Uraian pjg x unit x brt / m = jml
Sagrod 3.38 x 24.00 x 0.39 = 31.64

4 AT.3 Pek. plat baja tebal 5 mm


Uraian lebar x tinggi x tebal x bj = jml
Plat tebal 5 mm 0.45 x 0.2 x 0.005 x 7850 = 3.53
0.45 x 0.12 x 0.005 x 7850 = 2.12
0.35 x 0.15 x 0.005 x 7850 = 2.06
0.35 x 0.15 x 0.005 x 7850 = 2.06
0.3 x 0.8 x 0.005 x 7850 = 9.42
0.3 x 0.8 x 0.005 x 7850 = 9.42
0.32 x 0.8 x 0.005 x 7850 = 10.05
0.32 x 0.8 x 0.005 x 7850 = 10.05
= 146.13
5 AT.3 Baut Φ10 mm
Uraian diameter x panjang x unit x bj = jml
0.01 0.006 74 x 7850 = 34.854
6 KA.1 Pek. rangka atap (usuk, reng, balok gording)
Pek. Usuk 5/7
Uraian Panjang x Lebar x Tinggi x Jumlah x Unit = Jumlah
4.95 x 0.05 x 0.07 x ((12/0.4)+1) x 2.00 = 1.074

Pek. Reng 2/3


Uraian Jumlah x Lebar x Tinggi x Panjang x Unit = Jumlah
(4.95/0.27)+1 x 0.02 x 0.03 x 12 x 2.00 = 0.278

Pek. Balok Gording 5/7


Uraian Panjang x Lebar x Tinggi x Jumlah x Unit = Jumlah
12.00 x 0.05 x 0.07 x 6 x 2.00 = 0.504

7 AT.1 Pek. pasang genteng


Uraian Panjang x Lebar x Unit = Jumlah
12.00 x 4.95 x 2 = 118.80

8 AT.2 Pek. Pasang Bubungan


Uraian Panjang x Unit = Jumlah
12.00 x 1.00 = 12

9 AT.6 Pek. Pasang Talang


Uraian Panjang x ( Lebar + Tinggi ) x Unit = Jumlah
12.00 x (0.2 + 0.3) x 2.00 = 12.000
TUNGAN VOLUME PEKERJAAN

Volume
288.70 kg

180.00 kg

31.64 kg

146.13 kg

34.85 kg
1.86 m2

118.80 m2

12.00 m

12.00 m2
5 PLAFOND ACTIVITY
CHAPTER IV
RUMAH 2 LANTAI
PT…….
JLN….

6 ROOF FRAME ACTIVITY

No Drawing Sketch and Explanation Kode Calculation and Work Description Volume
CHAPTER IV
UMAH 2 LANTAI
PT…….
JLN….

Volume
7 DOORS AND WINDOWS ACTIVITY

No Drawing Sketch and Description Kode Calculation and Work Description


Calculation and Work Description Volume
CHAPTER IV
ACTIVITIES VOLUME CALCULATION
CONSTRUCTION MANAGEMENT ASSIGNMENT
CIVIL ENGINEERING DEPARTMENT ENGINEERING FACULTY

8 FLOOR AND WALL ACTIVITY


CHAPTER IV
ACTIVITIES VOLUME CALCULATION
CONSTRUCTION MANAGEMENT ASSIGNMENT
ENGINEERING DEPARTMENT ENGINEERING FACULTY
9 PAINTING ACTIVITY
11 ELECTRICAL INSTALLATION
VOLUME RECAPITULATION ACTIVITY
PROJECT : Residential Construction
LOCATION : Blulukan, Colomadu, Karanganyar

No. Kode Unit Description


1 2 2 3

1 SI PEKERJAAN PERSIAPAN
Err:509 m² pembersihan lokasi
Err:509 -
m² Board 2/20
m² wood 5/7
kg Nail

2 TA SOIL ACTIVITIES
TA.1 m³ Soil Excavation Activity
TA.2 m³ Sand Embankment Beneath the foundation
TA.3 m³ Aanstamping Activity
TA.4 m³ beton pondasi cakar ayam
TA.5 m³ Soil Embankment (Left and Right Foundation)
TA.6 m³ Soil Embankment Beneath The Building Floor
TA.7 m³ Sand Embankment Beneath The Building Floor

3 BT CONCRETE ACTIVITY
BT.1 m² Begesting of Sloof
BT.2 m² Begesting Ring of Beam
BT.3 m² Begesting Kantilever
BT.4 m² Begesting of Column
BT.5 m³ Err:509
BT.6 m³ Kolom
BT.7 m³ Beam 15/20 cm3 f'c = 16,9 MPa (K 200)
BT.8 m³ Err:509
BT.9 kg The main reinforcement bar of Sloof 1
BT.10 kg The main reinforcement of Beam
BT.11 kg The main reinforcement of Column
BT.12 kg -
BT.13 kg The Stirrup reinforcement of Sloof
BT.14 kg The Stirrup reinforcement of Column
BT.15 kg The Stirrup reinforcement of Beam
BT.16 m³ Dug Beton Beneath sills
BT.17 m³ Mortar Beneath the floor Act.

4 PS INSTALLATION ACTIVITY
PS.1 m² pekerjaan trasram
PS.2 m² pekerjaan dinding
PS.3 m² pekerjaan plesteran
PS.4 m² pekerjaan acian
PS.5 m² Pek. Sponengan

5 PF PLAFOND ACTIVITY
PF.1 m² Memasang Langit-langit Gypsum
PF.2 m² Memasang list langit-langit

6 KA ROOF FRAME ACTIVITY


KA.1 m³ Pekerjaan Penutup atap
KA.2 m³ -
KA.3 m³ Err:509
KA.4 m³ Err:509
KA.5 buah Err:509
KA.6 buah Err:509
KA.7 buah Err:509

7 PJ DOORS AND WINDOWS ACTIVITY


PJ.1 m³ Pek. Kusen ,Daun Pintu & Jendela model 1
PJ.2 m² Pintu model 2
PJ.3 m³ Pintu model 3
PJ.4 buah Pintu model 4
PJ.5 buah Jendela model 1
PJ.6 buah jendela model 2
PJ.7 buah jendela model 3

8 LT FLOOR AND WALL ACTIVITY


LT.1 m² Pemasangan kramik 30 x 30 cm (Kamar mandi)
LT.2 m² Pemasangan kramik 40 x 40 cm
LT.3 m² Pemasangan Paving Abu-Abu Tebal 6cm Segi Empat

9 CT PAINTING ACTIVITY
CT.1 m² Pengecatan Bidang Kayu Baru
CT.2 m² Pengecatan Tembok Baru Interior
CT.3 m² Pengecatan Tembok Baru Eksterior
CT.4 m² Pengecatan Plafond

10 SN SANITATION ACTIVITY
SN.1 m' Pasang Pipa PVC air bersih
SN.2 m' Err:509
SN.3 m' Err:509
SN.4 buah Err:509
SN.5 buah Err:509
SN.6 buah Err:509
SN.7 buah Err:509
SN.8 buah Err:509
SN.9 buah Err:509
SN.10 buah Err:509
SN.11 m³ Err:509
SN.12 m³ Err:509
SN.13 m³ Err:509
SN.14 buah Err:509
SN.15 m³ Err:509
SN.16 m³ Err:509
SN.17 m³ Err:509
SN.18 m³ Err:509

11 LT ELECTRICAL INSTALLATION
LT.1 buah Pasang Lampu TL 18 Watt
LT.2 buah Pasang Stop Kontak
LT.3 buah Pasang Saklar gaanda
LT.4 m' -
LT.5 m' Err:509
LT.6 buah Viting Installation activity

12 TM #REF!
TM.1 buah #REF!
TM.2 m³ #REF!

13 GR #REF!
GR.1 m³ #REF!
GR.2 m³ #REF!
GR.3 m³ #REF!
GR.4 m³ #REF!
GR.5 #REF!
VOLUME RECAPITULATION ACTIVITY

Work Volume
4

224.00

0.68
0.24
0.00004

56.70
2.70
1.35
0.93
51.72
22.00
33.00

19.37
81.76
0.07
114.23
Err:509
9.64
6.91
Err:509
770.63
1,316.53
1,666.03
-
88.04
78.18
127.33
0.02
8.96

17.14
942.18
2,027.90
2,027.90
-

288.00
230.20

173.40
0.00
Err:509
Err:509
Err:509
Err:509
Err:509

2.00
3.00
6.00
2.00
7.00
1.00
4.00

48.91
226.42
14.41

28.00
2,027.90
2,027.90
288.00

63.05
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509

23.00
17.00
20.00
Err:509
Err:509
32.00

#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
Cost Estimation (RAB) of Residential Construction
Activity : Residential Construction
Location / Year Estimation : Desa Blulukan, Kab. Karanganyar

No Type of Activity Volume Unit Unit Cost Sum


1 2 3 4 5 6=3x5

1 PEKERJAAN PERSIAPAN
pembersihan lokasi 224.00 m² Rp 6,500 Rp 1,456,000
-
Board 2/20 0.68 m² Rp 10,000 Rp 6,800
wood 5/7 0.24 m² Rp 10,000 Rp 2,380
Nail 0.00 kg Rp 10,000 Rp 0

2 SOIL ACTIVITIES
Soil Excavation Activity 56.70 m³ Rp 31,250 Rp 1,771,875
Sand Embankment Beneath the foundation 2.70 m³ Rp 233,900 Rp 631,530
Aanstamping Activity 1.35 m³ Rp 374,349 Rp 505,371
beton pondasi cakar ayam 0.93 m³ Rp 708,087 Rp 655,893
Soil Embankment (Left and Right Foundation) 51.72 m³ Rp 14,000 Rp 724,132
Soil Embankment Beneath The Building Floor 22.00 m³ Rp 62,910 Rp 1,384,020
Sand Embankment Beneath The Building Floor 33.00 m³ Rp 276,930 Rp 9,138,690

3 CONCRETE ACTIVITY
Begesting of Sloof 19.37 m² Rp 128,373 Rp 2,486,351
Begesting Ring of Beam 81.76 m² Rp 228,014 Rp 18,641,624
Begesting Kantilever 0.07 m² Rp 222,794 Rp 14,963
Begesting of Column 114.23 m² Rp 222,794 Rp 25,450,146
Err:509 Err:509 m³ Rp 909,261 Err:509
Kolom 9.64 m³ Rp 909,261 Rp 8,768,457
Beam 15/20 cm3 f'c = 16,9 MPa (K 200) 6.91 m³ Rp 909,261 Rp 6,281,742
Err:509 Err:509 m³ Rp 909,261 Err:509
The main reinforcement bar of Sloof 1 770.63 kg Rp 152,694 Rp 117,670,455
The main reinforcement of Beam 1,316.53 kg Rp 152,694 Rp 201,025,468
The main reinforcement of Column 1,666.03 kg Rp 152,694 Rp 254,392,602
- - kg Rp 152,694 Rp -
The Stirrup reinforcement of Sloof 88.04 kg Rp 152,694 Rp 13,443,791
The Stirrup reinforcement of Column 78.18 kg Rp 152,694 Rp 11,937,999
The Stirrup reinforcement of Beam 127.33 kg Rp 152,694 Rp 19,441,764
Dug Beton Beneath sills 0.02 m³ Rp 909,261 Rp 14,403
Mortar Beneath the floor Act. 8.96 m³ Rp 454,144 Rp 4,069,131

4 INSTALLATION ACTIVITY
pekerjaan trasram 17.14 m² Rp 105,195 Rp 1,803,046
pekerjaan dinding 942.18 m² Rp 101,962 Rp 96,066,322
pekerjaan plesteran 2,027.90 m² Rp 32,039 Rp 64,971,787
pekerjaan acian 2,027.90 m² Rp 18,113 Rp 36,730,339
Pek. Sponengan - m² Rp 9,953 Rp -

5 PLAFOND ACTIVITY
Memasang Langit-langit Gypsum 288.00 m² Rp 29,430 Rp 8,475,725
Memasang list langit-langit 230.20 m² Rp 18,012 Rp 4,146,362

6 ROOF FRAME ACTIVITY


Pekerjaan Penutup atap 173.40 m³ Rp 8,097,536 Rp 1,404,112,742
- - m³ Rp 8,097,536 Rp -
Err:509 Err:509 m³ Rp 8,097,536 Err:509
Err:509 Err:509 m³ Rp 7,692,780 Err:509
Err:509 Err:509 buah Rp 88,468 Err:509
Err:509 Err:509 buah Rp 106,918 Err:509
Err:509 Err:509 buah Rp 28,456 Err:509

7 DOORS AND WINDOWS ACTIVITY


Pek. Kusen ,Daun Pintu & Jendela model 1 2.00 m³ Rp 21,967,815 Rp 43,935,630
Pintu model 2 3.00 m² Rp 775,504 Rp 2,326,511
Pintu model 3 6.00 m³ Rp 130,733 Rp 784,395
Pintu model 4 2.00 buah Rp 33,563 Rp 67,125
Jendela model 1 7.00 buah Rp 17,800 Rp 124,600
jendela model 2 1.00 buah Rp 26,400 Rp 26,400
jendela model 3 4.00 buah Rp 17,800 Rp 71,200

8 FLOOR AND WALL ACTIVITY


Pemasangan kramik 30 x 30 cm (Kamar mandi) 48.91 m² Rp 1,707,866 Rp 83,535,986
Pemasangan kramik 40 x 40 cm 226.42 m² Rp 682,811 Rp 154,602,033
Pemasangan Paving Abu-Abu Tebal 6cm Segi Empat 14.41 m² Rp 128,294 Rp 1,848,148

9 PAINTING ACTIVITY
Pengecatan Bidang Kayu Baru 28.00 m² Rp 53,385 Rp 1,494,780
Pengecatan Tembok Baru Interior 2,027.90 m² Rp 14,524 Rp 29,453,220
Pengecatan Tembok Baru Eksterior 2,027.90 m² Rp 33,967 Rp 68,880,665
Pengecatan Plafond 288.00 m² Rp 12,192 Rp 3,511,152

10 SANITATION ACTIVITY
Pasang Pipa PVC air bersih 63.05 m' Rp 56,320 Rp 3,550,976
Err:509 Err:509 m' Rp 551,440 Err:509
Err:509 Err:509 m' Rp 379,855 Err:509
Err:509 Err:509 buah Rp 30,354 Err:509
Err:509 Err:509 buah Rp 9,900 Err:509
Err:509 Err:509 buah Rp 325,464 Err:509
Err:509 Err:509 buah Rp 703,100 Err:509
Err:509 Err:509 buah Rp 12,000 Err:509
Err:509 Err:509 buah Rp 9,000 Err:509
Err:509 Err:509 buah Rp 2,000 Err:509
Err:509 Err:509 m³ Rp 45,350 Err:509
Err:509 Err:509 m³ Rp 38,250 Err:509
Err:509 Err:509 m³ Rp 145,250 Err:509
Err:509 Err:509 buah Rp 145,250 Err:509
Err:509 Err:509 m³ Rp 96,750 Err:509
Err:509 Err:509 m³ Rp 329,430 Err:509
Err:509 Err:509 m³ Rp 310,950 Err:509
Err:509 Err:509 m³ Rp 314,670 Err:509

11 ELECTRICAL INSTALLATION
Pasang Lampu TL 18 Watt 23.00 buah Rp 53,175 Rp 1,223,025
Pasang Stop Kontak 17.00 buah Rp 18,883 Rp 321,003
Pasang Saklar gaanda 20.00 buah Rp 25,100 Rp 502,000
- Err:509 m' Rp 250,949 Err:509
Err:509 Err:509 m' Rp 190,949 Err:509
Viting Installation activity 32.00 buah Rp 18,329 Rp 586,531

12 #REF!
#REF! #REF! buah Rp 268,990 #REF!
#REF! #REF! m³ Rp 149,137 #REF!

13 #REF!
#REF! #REF! m³ Rp 31,250 #REF!
#REF! #REF! m³ Rp 454,144 #REF!
#REF! #REF! m³ Rp 152,694 #REF!
#REF! #REF! m³ Rp 909,261 #REF!
#REF! - Rp 191,114 Rp -
Cost Estimation (RAB) of Residential Construction

Total
7

Rp 1,465,180

Rp 14,811,511
Err:509

Rp 199,571,493

Rp 12,622,087
Err:509

Rp 47,335,861

Rp 239,986,167

Rp 103,339,817
Err:509

Err:509

#REF!
#REF!
#REF!
TUGAS
MANAJEMEN KONSTR
PROGRAM STUDI TEKNIK SIPIL FA
UNIVERSITAS MUHAMMADIYA

CURVA "S" PERENCANAAN GEDU


Ds. Pabelan, Kec. Kartasura, K

Total Bobot Bulan-1


No Uraian Perkerjaan
Harga (%) 1 2 3 4 5
1 2 3 4

1 #REF! Rp - #REF! #REF! #REF! #REF!


1 pembersihan lokasi Rp 1,456,000.00 #REF!
2 - Rp - #REF!
3 Board 2/20 Rp 6,800.00 #REF!

2 #REF! Rp - #REF! #REF! #REF! #REF!


1 SOIL ACTIVITIES Rp - #REF!
2 Sand Embankment Beneath the foundation Rp 631,530.00 #REF!
3 Aanstamping Activity Rp 505,371.15 #REF!
4 Err:509 Err:509 Err:509

3 #REF! Rp - #REF! #REF! #REF!


1 Sand Embankment Beneath The Building Floor Rp 9,138,690.00 #REF!
2 - Rp - #REF!

4 #REF! Err:509 Err:509


1 Pek. Tulangan Pokok + Begel Sloof Rp 83,301,958.91 #REF!
2 Pek. Tulangan Pokok + Begel Kolom Rp 83,030,000.00 #REF!
3 Pek. Tulangan Pokok + Begel Ring Balok Rp 23,155,837.72 #REF!
4 Pek. Begesting Sloof Rp 4,358,952.00 #REF!
5 Pek. Begesting Kolom Rp 13,163,545.46 #REF!
6 Pek. Begesting Ring Balok Rp 7,545,262.92 #REF!
7 Pek. Sloof Beton 15/15 cm Rp 2,954,481.75 #REF!
8 Pek. Kolom Beton 15 Cm/15 Cm Rp 1,384,066.22 #REF!
9 Pek. Ring Balok Beton 15 Cm/15 Cm Rp 799,115.61 #REF!
10 Pek.Kolom Beton 12 /12 cm Rp 478,901.36 #REF!
11 Pekerjaan Rabat Beton Rp 1,131,033.50 #REF!
12 Pekerjaan Dug Rp 4,279.59 #REF!

5 #REF! Err:509 Err:509


1 Pek. Pasangan Batu Bata Rp 28,602,176.94 #REF!
2 Pek. Pasangan Kedap Air Rp 950,720.00 #REF!
3 Pek. Pasangan Batu Bata Atap Gunungan Rp 223,256.25 #REF!
4 Pek. Plesteran Dinding Rp 11,480,634.20 #REF!
5 Pek. Acian Dinding Rp 6,482,587.33 #REF!
6 Pek, Sponengan Rp 1,148,441.73 #REF!

6 #REF! Err:509 Err:509


1 Err:509 Rp 4,146,362.40 #REF!
2 Err:509 Rp - #REF!
3 Memasang list langit-langit Rp - #REF!
4 Err:509 Err:509 Err:509
5 ROOF FRAME ACTIVITY Rp - #REF!
6 Err:509 Err:509 Err:509
7 Pekerjaan Penutup atap Err:509 Err:509

7 #REF! Rp - #REF!
1 - Rp - #REF!
2 DOORS AND WINDOWS ACTIVITY Err:509 Err:509
3 Err:509 Rp 2,326,511.40 #REF!
4 Pintu model 2 Rp 784,395.00 #REF!
5 Pintu model 3 Rp 67,125.00 #REF!
6 Pintu model 4 Rp 124,600.00 #REF!
7 Jendela model 1 Rp 26,400.00 #REF!
8 jendela model 2 Rp 71,200.00 #REF!

8 #REF! Rp 1,494,780.00 #REF!


1 Pemasangan kramik 40 x 40 cm Rp 154,602,032.66 #REF!
2 Pemasangan Paving Abu-Abu Tebal 6cm Segi Empat Rp 1,848,148.05 #REF!

9 #REF! Rp - #REF!
1 - Rp 3,511,152.00 #REF!
2 SANITATION ACTIVITY Rp - #REF!

10 #REF! Err:509 Err:509


1 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509
3 Err:509 Err:509 Err:509
4 Err:509 Err:509 Err:509

11 #REF! Rp 586,531.20 #REF!


1 Memasang Closet Jongkok Porselen Rp 651,930.00 #REF!
2 Memasang Pipa PVC type AW Ø 3/4" Rp 1,353,251.25 #REF!
3 Memasang Pipa PVC type AW Ø 4" Rp 16,373,123.25 #REF!
4 Memasang Kran Ø ¾" atau ½" Rp 126,337.50 #REF!
5 Memasang Bak mandi batu bata 1 : 2 Rp 1,053,580.00 #REF!
6 Memasang westafel Rp 408,745.00 #REF!
7 Memasang Floor drain Rp 98,490.00 #REF!

12 #REF! #REF! #REF!


1 #REF! #REF! #REF!
2 #REF! #REF! #REF!
3 - #REF! #REF!
4 - Rp - #REF!
5 - Rp - #REF!
6 - Rp - #REF!
7 Err:509 Err:509 Err:509
8 Err:509 Err:509 Err:509
9 Err:509 Err:509 Err:509
10 Err:509 Err:509 Err:509
11 Err:509 Err:509 Err:509
12 Err:509 Err:509 Err:509
13 Err:509 Err:509 Err:509
14 Err:509 Err:509 Err:509

15 #REF! Err:509 Err:509


Err:509
1 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509
3 Err:509 Err:509 Err:509
4 Err:509 Err:509 Err:509
5 Err:509 Err:509 Err:509
Err:509
1 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509
3 Err:509 Err:509 Err:509
4 Err:509 Err:509 Err:509
5 Err:509 Err:509 Err:509
6 Err:509 Err:509 Err:509

TOTAL #REF! #REF! #REF! #REF! #REF! #REF! #REF!


KOMULATIF BOBOT #REF! #REF! #REF! #REF! #REF!
TUGAS
AJEMEN KONSTRUKSI
DI TEKNIK SIPIL FAKULTAS TEKNIK
S MUHAMMADIYAH SURAKARTA

ENCANAAN GEDUNG LEMBIMJAR


Kec. Kartasura, Kab. Sukoharjo

Bulan-2 Bulan-3 Bulan-4


1 2 3 4 1 2 3 4 1 2 3 4 5
5

100
99.21
98.43
97.64
96.85
96.06
95.28
94.49
93.70
92.91
92.13
#REF! 91.34
90.55
89.76
88.98
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 88.19
87.40
86.61
85.83
85.04
84.25
83.46
82.68
81.89
81.10
80.31
79.53
78.74
77.95
Err:509 Err:509 Err:509 Err:509 Err:509 77.17
76.38
75.59
74.80
74.02
73.23
72.44
71.65
Err:509 Err:509 Err:509 Err:509 70.87
70.08
69.29
68.50
67.72
66.93
66.14
65.35
64.57
#REF! #REF! #REF! #REF! 63.78
62.99
62.20
61.42
60.63
59.84
59.06
58.27
57.48
56.69
#REF! #REF! #REF! #REF! 55.91
55.12
54.33
53.54
#REF! #REF! #REF! 52.76
51.97
51.18
50.39
Err:509 Err:509 Err:509 49.61
48.82
48.03
47.24
46.46
45.67
#REF! #REF! #REF! #REF! 44.88
44.09
43.31
42.52
41.73
40.94
40.16
39.37
38.58
#REF! #REF! #REF! #REF! 37.80
37.01
36.22
35.43
34.65
33.86
33.07
32.28
31.50
30.71
29.92
29.13
28.35
27.56
26.77
25.98
Err:509 25.20
24.41
23.62
22.83
22.05
21.26
20.47
19.69
18.90
18.11
17.32
16.54
15.75
14.96
14.17
Err:509 Err:509 #REF! #REF! #REF! #REF! #REF! Err:509 #REF! Err:509 Err:509 Err:509 Err:509 13.39
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 12.60
11.81
Sukoharjo, 28 Desember 2011 11.02
Dosen Pengampu 10.24
9.45
8.66
7.87
7.09
Ir. H. M. Nur Sahid, MM.MT. 6.30
5.51
4.72
3.94
3.15
2.36
1.57
0.79
RECAPITULATION
COST ESTIMATIMATION (RAB)

No Work types Jumlah Bobot (%)


1 2 3 4

1 PEKERJAAN PERSIAPAN #REF! #REF!


2 - #REF! #REF!
3 Soil Embankment Beneath The Building Floor #REF! #REF!
4 Begesting of Column #REF! #REF!
5 - #REF! #REF!
6 - #REF! #REF!
7 - #REF! #REF!
8 Pemasangan kramik 30 x 30 cm (Kamar mandi) #REF! #REF!
9 Pengecatan Tembok Baru Eksterior #REF! #REF!
10 Err:509 #REF! #REF!
11 Err:509 #REF! #REF!
12 #REF! #REF! #REF!

TOTAL ( A ) #REF! #REF!


PPN 10 % x ( A ) #REF!
TOTAL ( A + PPN ) = B #REF!
IMB = 1.75% x 60% x (B) #REF!
TOTAL ESTIMATION #REF!
ROUNDUP Rp 250,000,000.00
TOTAL 18 UNIT Rp 4,500,000,000.00
Four Billion Four Hundred Million Rupiah
TUGAS
MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA

Rekapitulasi
Rencana Anggaran Biaya (RAB) Total
Pekerjaan : Pembangunan Gedung Toko
Lokasi / Tahun Anggaran : Ds. Getas Pejaten, Kec. Jati, Kab. Kudus

No. Uraian Pekerjaan Jumlah


1 2 3
1 Harga Tanah (Rp 400.000,00 /m2) Rp 72,000,000
2 Pekerjaan Jalan Sepanjang 100m Rp 3,168,000
3 Pekerjaan Drainase Rp 14,003,000
4 Pekerjaan Bangunan Toko Rp 171,134,993
5 Landscape (Taman & Gazebo uk. 2x2) Rp 7,000,000
Jumlah (A) Rp 267,305,993
PPN 10% x (A) Rp 26,730,599
Jumlah (A + PPN) = B Rp 294,036,592
IMB = 1,75% x 60% x (B) bowsom Rp 3,087,384
Jumlah Total Anggaran Rp 297,123,976
Dibulatkan Rp 497,389,000
Empat Ratus Sembilan Puluh Tujuh Juta Tiga Ratus Delapan Puluh Sembilan Ribu Rupiah
Bobot (%)
4

bu Rupiah

You might also like