2.

6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

REQUEST FOR PROPOSAL

FOR

THE WORK

OF

Design, Engineering, testing at manufacturers works, supply,


packing and forwarding, transportation, unloading, storage at site,
erection/installation, testing, commissioning and operation &
maintenance for Five (5) years of 2.6 MWp/2.0 MW grid connected
Solar PV power project with Captive mechanism at NH16,
Chowdavaram village, Guntur District in Andhra Pradesh on Turnkey
EPC Basis

Tender/RFP Number: KTL/RFT/SPV-01


Date: 28-08-2019

ISSUED BY:

KALLAM TEXTILES LTD


NH16, Chowdavaram, Guntur, Andhra Pradesh 522019
Tel. Phone No.:0863-2344019, Mobile No: 8985950219
Email Id: infosp@ksml.in
Website: www.ksml.in

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 0
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

INDEX
SECTION NO. CONTENT PAGE NO.
SECTION - I INVITATION FOR BID (IFB)
INSTRUCTION TO BIDDERS
From 2 to 28
PRE-QUALIFICATION CRITERIA
APPENDIX 1: BID EVALUATION CRITERIA (BEC)
SECTION - II TECHNICAL SPECIFICATION From 29 to 109
ANNEXURE A – APPROVED MAKES From 110 to 111
ANNEXURE B – PROJECT CHARACTERISTICS OF PV
From 112 to 114
PLANT (TO BE FILLED BY EPC CONTRACTOR)
ANNEXURE C – TECHNICAL SPECIFICATIONS OF KEY
From 115 to 118
COMPONENTS (TO BE FILLED BY EPC CONTRACTOR)
ANNEXURE D – LIST OF SPARES (TO BE FILLED BY EPC
From 119 to 119
CONTRACTOR)
ANNEXURE E – LIST OF DEVIATIONS From 120 to 120
CONCEPT NOTE FOR PG TESTCONCEPT NOTE FOR PG
From121 to 126
TEST
SECTION - III GENERAL CONTRACT CONDITIONS From 127 to 170
SECTION - IV SPECIAL CONDITIONS OF CONTRACT - COMMERCIAL From 171 to 189
SPECIAL CONDITIONS OF CONTRACT -TECHNICAL From 190 to 202
SECTION - V FORMS From 203 to 203
SCHEDULE A: FORMAT FOR BANKGUARANTEE From 204 to 206
TOWARDS EMD
SCHEDULE B: PRICE BID From 207 to 208
SCHEDULE C: BREAK UP OF PRICE BID From 209 to 211
SCHEDULE D: DIRECT AND INDIRECT TAXES From 212 to 214
SCHEDULE E: QUALIFICATION CHECKLIST OF THE From 215 to 216
BIDDER
SCHEDULE F: LIST OF SIMILAR WORKS HANDLED From 217 to 217
SCHEDULE G: FORMAT FOR SPARES AND From 218 to 218
CONSUMABLES / SPECIAL TOOLS AND TACKLES
SCHEDULE H: DEVIATION SCHEDULE From 219 to 219
SCHEDULE I: FORMAT FOR BANK GUARANTEE From 220 to 222
TOWARDS PERFORMANCE GUARANTEE
SCHEDULE J: LIST OF ACCEPTABLE BANKS From 223 to 223
SCHEDULE K: FORMAT FOR LETTER OF DISCHARGE From 224 to 224
SCHEDULE L: FORMAT FOR POWER OF ATTORNEY From 225 to 226
SCHEDULE M: FORMAT FOR AFFIDAVIT From 227 to 227

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 1
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Contents
SECTION - I ...................................................................................................................................................8
INSTRUCTIONS TO BIDDER ..........................................................................................................................8
1 INVITATION FOR BID (IFB) ....................................................................................................................9
2 INSTRUCTION TO BIDDERS................................................................................................................ 11
3 DEFINITIONS, ABBREVIATIONS & INTERPRETATIONS ....................................................................... 12
4 PRE-QUALIFICATION CRITERIA .......................................................................................................... 15
5 BID DOCUMENT ................................................................................................................................ 17
6 BID SUBMISSION ............................................................................................................................... 18
7 VALIDITY OF BID ................................................................................................................................ 19
8 BID EXAMINATION ............................................................................................................................ 19
9 EARNEST MONEY / SECURITY DEPOSIT............................................................................................. 19
10 ORGANIZATION ............................................................................................................................. 20
11 NO COMPENSATION FOR SUBMISSION OF BID ............................................................................ 21
12 CHECKLIST OF DOCUMENTS TO BE SUBMITTED IN THE OFFER.................................................... 21
13 DEVIATIONS / EXCEPTIONS ........................................................................................................... 23
14 BID REQUIREMENTS...................................................................................................................... 23
15 AWARD OF WORK ......................................................................................................................... 24
16 PRICE ............................................................................................................................................. 24
17 TAXES & DUTIES ............................................................................................................................ 25
18 TERMS OF PAYMENT..................................................................................................................... 25
19 TRANSFER OF BID DOCUMENTS / BID TRANSFER......................................................................... 25
20 SIGNING OF CONTRACT AGREEMENT........................................................................................... 25
APPENDIX 1: BID EVALUATION CRITERIA (BEC) ........................................................................................ 26
SECTION - II ............................................................................................................................................... 29
TECHNICAL SPECIFICATION ...................................................................................................................... 29
1 PROJECT OVERVIEW ......................................................................................................................... 30
2 SCOPE OF WORK ............................................................................................................................... 34
3 DETAILED SCOPE OF THE CONTRACT ................................................................................................ 36
4 RESOURCE ASSESSMENT AND ENERGY YIELD .................................................................................. 43
5 PROJECT WARRANTIES ..................................................................................................................... 44
6 OPERATION AND MAINTENANCE (O&M) ......................................................................................... 46
7 RELEASE OF INFORMATION .............................................................................................................. 49
8 COMPLETION OF CONTRACT ............................................................................................................ 49

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 2
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

9 LIMIT OF CONTRACT ......................................................................................................................... 49


10 GENERAL ....................................................................................................................................... 49
11 SPECIFICATION FOR CIVIL WORK & MECHANICAL STRUCTURE ................................................... 50
12 SOLAR PV MODULE ....................................................................................................................... 56
13 SOLAR INVERTER ........................................................................................................................... 64
14 STRING MONITORING BOX (In case of required) .......................................................................... 72
15 DC SOLAR CABLES ......................................................................................................................... 75
16 DC POWER CABLES........................................................................................................................ 78
17 DC PLUG IN CONNECTORS AND HARNESS FOR FIELD CABLING ................................................... 79
18 SCADA/ Plant Monitoring System ................................................................................................. 82
19 AC CABLES (1.1 kV) (FREE ISSUE ITEM BY KTL) ............................................................................. 87
20 LT PANELS (FREE ISSUE ITEM BY KTL) ........................................................................................... 89
21 EARTHING SYSTEM........................................................................................................................ 97
22 LIGHTNING PROTECTION SYSTEM .............................................................................................. 104
23 FIRE DETECTION AND FIGHTING (FREE ISSUE ITEM BY KTL) ....................................................... 107
24 WMS............................................................................................................................................ 107
25 METERING SYSTEM (FREE ISSUE ITEM BY KTL) ........................................................................... 109
ANNEXURE A – Approved Makes............................................................................................................ 110
ANNEXURE B – Project Characteristics of PV Plant (To Be Filled By EPC Contractor) ............................ 112
ANNEXURE C – Technical Specifications of Key Components (To Be Filled By EPC Contractor) ............ 115
ANNEXURE D – List of Spares (To Be Filled by EPC contractor) .............................................................. 119
ANNEXURE E – List Of Deviations ........................................................................................................... 120
CONCEPT NOTE ON PG TEST .................................................................................................................. 121
1 Project Details ................................................................................................................................. 122
2 Definitions ....................................................................................................................................... 122
3 Introduction .................................................................................................................................... 122
4 Reference Project Characteristics ................................................................................................... 122
5 Performance Guarantee (Generation Guarantee) ......................................................................... 122
6 Instruments Used............................................................................................................................ 123
7 Performance Guarantee LD for Shortfall ........................................................................................ 123
8 Performance Guarantee Incentive: ................................................................................................ 125
9 PG test Conditions .......................................................................................................................... 125
10 Guaranteed Availability and LD for Shortfall .............................................................................. 126
11 Exception and Remedies ............................................................................................................. 126
SECTION - III ............................................................................................................................................ 127

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 3
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

GENERAL CONTRACT CONDITIONS ........................................................................................................ 127


1 RIGHTS OF KTL ................................................................................................................................ 128
2 CLARIFICATIONS / AMENDMENTS BY KTL ...................................................................................... 128
3 CONFIDENTIALITY OF DOCUMENTS................................................................................................ 129
4 CAUTION AND DISCLAIMER ............................................................................................................ 129
5 CONTRACT STRUCTURE .................................................................................................................. 130
6 INTERPRETATION OF CONTRACT DOCUMENTS:............................................................................. 130
7 INSTRUCTIONS TO BIDDER.............................................................................................................. 130
8 TERMINATION FOR DEFAULT & ENCASHMENT OF PERFORMANCE BANK GUARANTEE ............... 131
9 BREACH OF CONTRACT ................................................................................................................... 133
10 NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK ..................................... 133
11 CHANGES IN CONSTITUTION ...................................................................................................... 133
12 MEMBERS OF THE KTL NOT INDIVIDUALLY LIABLE ..................................................................... 133
13 KTL NOT BOUND BY PERSONAL REPRESENTATIONS .................................................................. 134
14 NOTICES ...................................................................................................................................... 134
15 LIENS ........................................................................................................................................... 134
16 KTL NOT LIABLE TO PAY COMPENSATION .................................................................................. 134
17 EXECUTION OF CONTRACT ......................................................................................................... 134
18 RESPONSIBILITY FOR LEVEL AND ALIGNMENT ........................................................................... 136
19 TESTS FOR QUALITY OF WORKS .................................................................................................. 136
20 SAMPLES ..................................................................................................................................... 136
21 MATERIALS OBTAINED FROM DISMANTLING............................................................................. 136
22 ARTICLES OF VALUE FOUND ....................................................................................................... 137
23 SECURITY ARRANGEMENTS ........................................................................................................ 137
24 CARE OF WORKS ......................................................................................................................... 137
25 DRAWINGS TO BE SENT AT SITE ................................................................................................. 137
26 BILLING ........................................................................................................................................ 137
27 ALTERATIONS IN SPECIFICATIONS AND DESIGNS AND EXTRA WORK INCLUDING SUPPLIES ..... 138
28 NOTICE OF CLAIMS FOR ADDITIONAL PAYMENT........................................................................ 139
29 ACTION WHERE NO SPECIFICATION IS ISSUED ........................................................................... 139
30 LIABILITIES FOR DEFECTS, IMPERFECTIONS ETC. AND RECTIFICATION THEREOF ...................... 139
31 TESTING....................................................................................................................................... 140
32 START-UP TESTS: ......................................................................................................................... 140
33 PAYMENT OF CONTRACTOR’S BILL ............................................................................................. 141
34 RECEIPT FOR PAYMENT............................................................................................................... 141

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 4
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

35 CERTIFICATE AND PAYMENTS ARE NO EVIDENCE OF COMPLETION .......................................... 141


36 PATENT, COPYRIGHT, AND TRADEMARK .................................................................................... 141
37 SUBLETTING / ASSIGNMENT ....................................................................................................... 142
38 ARBITRATION .............................................................................................................................. 143
39 FORCE MAJEURE ......................................................................................................................... 144
40 POST COMMISSIONING SERVICES .............................................................................................. 144
41 DOCUMENTS ............................................................................................................................... 144
42 FIELD MANAGEMENT AND CO-ORDINATION OF WORK ............................................................ 145
43 DEFECTS PRIOR TO TAKING OVER............................................................................................... 145
44 DEFECTS AFTER TAKING OVER .................................................................................................... 146
45 WAIVER OF DEFAULT .................................................................................................................. 146
46 SUSPENSION OF WORK ............................................................................................................... 146
47 POWER OF ENTRY ....................................................................................................................... 147
48 CONTRACTOR’S SUBORDINATE STAFF AND THEIR CONDUCT .................................................... 148
49 AGENCIES AT SITE ....................................................................................................................... 149
50 SUB CONTRACTS ......................................................................................................................... 149
51 SUPPLY OF THE MATERIAL .......................................................................................................... 149
52 ASSISTANT TO THE ENGINEER .................................................................................................... 150
53 DISCREPANCIES BETWEEN INSTRUCTIONS ................................................................................. 150
54 POSSESSION PRIOR TO COMPLETION ......................................................................................... 150
55 RIGHTS OF VARIOUS INTERESTS ................................................................................................. 150
56 LABOUR LAWS AND SAFETY REGULATIONS................................................................................ 150
57 HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS ......................................................... 154
58 SAFETY REGULATIONS ................................................................................................................ 154
59 FIRST AID AND INDUSTRIAL INJURIES ......................................................................................... 155
60 SMOKING PROHIBITED IN NON-SMOKING AREAS...................................................................... 155
61 BARRICADES ................................................................................................................................ 155
62 DAMAGE TO PROPERTY .............................................................................................................. 156
63 FINAL BILL WITH LETTER OF DISCHARGE .................................................................................... 156
64 INSURANCE ................................................................................................................................. 156
65 LIQUIDATION, DEATH, BANKRUPTCY ETC................................................................................... 158
66 RESPONSIBILITY FOR PERFORMANCE OF CONTRACT ................................................................. 159
67 RESPONSIBILITY FOR COMPLETENESS ........................................................................................ 159
68 DISPATCH AND BILLING SCHEDULE ............................................................................................ 159
69 PACKING, IDENTIFICATION AND MARKING ................................................................................ 160

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 5
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

70 TYPE QUALITY OF MATERIALS AND WORKMANSHIP ................................................................. 160


71 CONTRACT DRAWINGS AND DOCUMENTS................................................................................. 162
72 ERRORS AND OMISSIONS............................................................................................................ 163
73 APPROVAL BY THE KTL ................................................................................................................ 163
74 GENERAL SPECIFICATION ON QUALITY SYSTEM, INSPECTION AND TEST OF PLANT AND
EQUIPMENT AT MANUFACTURER'S PREMISES ...................................................................................... 164
75 COMPLIANCE WITH LAWS AND REGULATIONS .......................................................................... 165
76 SECRECY TITLES ........................................................................................................................... 165
77 REJECTION OF DEFECTIVE PLANT................................................................................................ 166
78 NEGLIGENCE ............................................................................................................................... 166
79 PROGRESS REPORT ..................................................................................................................... 167
80 MAINTENANCE AND GUARANTEE .............................................................................................. 167
81 FURTHER THE GUARANTEES AS SPECIFIED IN TECHNICAL SPECIFICATION DOCUMENT ........... 167
82 FURTHER, THE WARRANTY DETAILS AS SPECIFIED TECHNICAL SPECIFICATION DOCUMENT OF
THIS BID SHALL BE APPLICABLE .............................................................................................................. 168
83 SAFETY CODE .............................................................................................................................. 169
84 GOVERNING LAW AND JURISDICTION ........................................................................................ 169
85 LANGUAGE .................................................................................................................................. 169
86 STATUTORY REGULATIONS AND JURISDICTION ......................................................................... 169
87 INDEMNITY ................................................................................................................................. 169
88 OBSERVANCE BY SUB-CONTRACTOR .......................................................................................... 170
SECTION - IV ............................................................................................................................................ 171
SPECIAL CONDITIONS OF CONTRACT– COMMERCIAL ........................................................................... 171
1 CONTRACT PRICE ............................................................................................................................ 172
2 EPC CONTRACT PRICE ..................................................................................................................... 172
3 O&M CONTRACT PRICE................................................................................................................... 172
4 ERECTION OF EQUIPMENT.............................................................................................................. 173
5 PERFORMANCE AND O&M BANK GUARANTEE DEPOSIT ............................................................... 173
6 PAYMENT MILESTONES .................................................................................................................. 175
7 PAYMENT PROCEDURE ................................................................................................................... 177
8 COMPLETION PERIOD ..................................................................................................................... 177
9 LIQUIDATED DAMAGES................................................................................................................... 178
10 WARRANTY AND GUARANTEE .................................................................................................... 178
11 HANDING OVER –TAKING OVER ................................................................................................. 178
12 CONTRACTOR AND OWNER OBLIGATIONS ................................................................................ 179

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 6
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

13 SCOPE OF WORK AS PER THE TECHNICAL DOCUMENT .............................................................. 183


14 CONDITIONS FOR OPERATIONS & MAINTENANCE OF THE SOLAR POWER PLANT .................... 184
15 BATTERY LIMIT ............................................................................................................................ 184
16 SCOPE OF WORK AS PER THE TECHNICAL DOCUMENT WHICH SHALL BE FOLLOWED .............. 184
17 PERSONNEL ................................................................................................................................. 186
18 INSURANCE ................................................................................................................................. 186
19 MEASUREMENT OF ENERGY AND METERING ............................................................................ 186
20 PAYMENTS FOR O&M ................................................................................................................. 187
21 HANDING OVER THE PLANT AFTER EXPIRY OF O&M TERM ....................................................... 187
22 FINAL PAYMENT .......................................................................................................................... 188
23 FAILURE OF THE CONTRACTOR TO COMPLY WITH THE PROVISIONS OF THE CONTRACT ......... 188
SPECIAL CONDITIONS OF CONTRACT - TECHNICAL ............................................................................... 190
1 THE BIDDER ..................................................................................................................................... 191
2 DESIGN & DRAWINGS ..................................................................................................................... 196
3 MATERIALS AND WORKMANSHIP .................................................................................................. 198
4 WORK PROGRAM ............................................................................................................................ 200
5 PERFORMANCE TESTS ..................................................................................................................... 200
6 DEFECTS LIABILITY........................................................................................................................... 201
SECTION - V ............................................................................................................................................. 203
SCHEDULES ............................................................................................................................................. 203
SCHEDULE A: FORMAT FOR BANK GUARANTEE TOWARDS EMD........................................................... 204
SCHEDULE B: PRICE BID .......................................................................................................................... 207
SCHEDULE C: BREAK UP OF PRICE BID .................................................................................................... 209
SCHEDULE D: DIRECT AND INDIRECT TAXES ........................................................................................... 212
SCHEDULE E: QUALIFICATION CHECKLIST OF THE BIDDER ..................................................................... 215
SCHEDULE F: LIST OF SIMILAR WORKS HANDLED................................................................................... 217
SCHEDULE G: FORMAT FOR SPARES AND CONSUMABLES / SPECIAL TOOLS AND TACKLES .................. 218
SCHEDULE H: DEVIATION SCHEDULE ...................................................................................................... 219
SCHEDULE I: FORMAT FOR BANK GUARANTEE TOWARDS PERFORMANCE GUARANTEE ..................... 220
SCHEDULE J: LIST OF ACCEPTABLE BANKS .............................................................................................. 223
SCHEDULE K: FORMAT FOR LETTER OF DISCHARGE ............................................................................... 224
SCHEDULE L: FORMAT FOR POWER OF ATTORNEY ................................................................................ 225
SCHEDULE M: FORMAT FOR AFFIDAVIT ................................................................................................. 227

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 7
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SECTION - I
INSTRUCTIONS TO BIDDER

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 8
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1 INVITATION FOR BID (IFB)


Ref No: KTL/RFT/SPV-01 Date: 28-08-2019
To,
PROSPECTIVE BIDDERS

SUB: TENDER DOCUMENT / RFP FOR DESIGN, ENGINEERING, TESTING AT MANUFACTURERS


WORKS, SUPPLY, PACKING AND FORWARDING, TRANSPORTATION, UNLOADING, STORAGE AT
SITE, ERECTION/INSTALLATION, TESTING, COMMISSIONING AND OPERATION & MAINTENANCE
FOR FIVE (5) YEARS OF 2.6 MWP/2.0 MW GRID CONNECTED SOLAR PV POWER PROJECT WITH
CAPTIVE MECHANISM AT CHOWDAVARAM VILLAGE, GUNTUR DISTRICT IN ANDHRA PRADESH
ON TURNKEY EPC BASIS

Dear Sir/Ma’am,

1.1 Kallam Textiles Limited having registered office at NH-16, Chowdavaram, Guntur, Andhra Pradesh,
CIN No. L18100AP1992PLC1013816, invites bids under single stage from eligible bidders for the
subject job, in complete accordance with the following details and enclosed Tender Documents.
1.2 The brief details of the tender are as under:SS

Design, Engineering, testing at manufacturers


works, supply, packing and forwarding,
transportation, unloading, storage at site,
NAME OF WORK/ BRIEF SCOPE erection/installation, testing, commissioning
(A)
OF and operation & maintenance for Five (5) years
WORK/ JOB of 2.6 MWp/2.0 MW grid connected Solar PV
power project with Captive mechanism at
Chowdavaram village, Guntur District in
Andhra Pradesh on Turnkey EPC Basis
(B) TENDER NO. & DATE KTL/RFT/SPV-01 dated 28-08-2019

(C) TYPE OF BIDDING SYSTEM Two Bid System

(D)
TYPE OF TENDER Manual

(E) COMPLETION/CONTRACT 4 Months from the date of issuance of NOA/


PERIOD LOA by Client
INR 23,600/- including GSTto be submitted
(F) BID PROCESSING FEE (NON- either through NEFT/RTGS transfer in the
REFUNDABLE) account of KTL or in the form of DD along with
the response to RFP in favour of “Kallam

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 9
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Textiles Limited”, payable at Guntur Account


Detail : Andhra Bank
A/C Number :015013046105166,
IFSC Code: ANDB0000150
Guntur Main Branch
INR 12,50,000/- including GST
to be submitted either through NEFT/RTGS
(G) EARNEST MONEY DEPOSIT transfer in the account of KTL or in the form of
(EMD)/ BID BOND Bank guarantee or DD along with the response
to RFP in favour of “Kallam Textiles Limited”,
payable at Guntur.
Date: 12thSep 2019 to 13th Sep 2019 at
10:00AM
(H) DATE, TIME & VENUE OF PRE- Place: Kallam Textiles Limited ,
BID MEETING
NH-16, Chowdavaram, Guntur, Andhra
Pradesh
(I) PRE-BID CLARIFICATION RELEASE Date: 17th SEP 2019
DATE
(J) DUE DATE & TIME OF BID- Date: 23th SEP 2019
SUBMISSION Time:15:00 Hrs
C/O , G.Nagireddy - Project Coordinator
Mobile : +91-8985950219
NAME, DESIGNATION, ADDRESS C/O , Brijesh Manvar-Consultant
(K) AND OTHER DETAILS (FOR Contact Number: +91 - 9429460156
SUBMISSION OF RESPONSE TO
RFP) Kallam Textiles Limited ,
NH-16, Chowdavaram, Guntur, Andhra Pradesh
Email Id: infosp@ksml.in
For Technical Query:
Name: Mr. Brijesh Manvar
Designation: Assistant Manager - Design
Contact Number:+91-9429460156
Email Id: brijeshmanvar@gensol.in
(L)
CONTACT DETAILS OF TENDER
For Commercial Query:
Name:Sri G V KRISHNAREDDY -
Designation: JMD and CEO
Contact Number:+91-9989997493
Email Id: jmd@ksml.in

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 10
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

2 INSTRUCTION TO BIDDERS
2.1 The Bidder is advised to read carefully all instructions and conditions appearing in this document
and understand them fully. All information required as per the bid document must be furnished
and the schedules contained herein should be duly filled in. Failure to provide the information
as required may render the bid technically unacceptable. The bid shall be submitted in English
Language only. All foreign language documents shall be translated in English. All translated
documents shall be self-certified.

2.2 The Bidder in quoting his rate shall for all purposes, whatsoever, be deemed to have themselves
independently obtained all relevant and necessary information for the purpose of preparing his
tender. The correctness or completeness of the details, given in the tender documents is not
guaranteed. The Bidder is required to satisfy themself in all respects, before the submission of
offer.

2.3 The Bidder shall be deemed to have examined the tender document, to have obtained his own
information in all matters whatsoever that might affect carrying out works at the scheduled
rates and to have satisfied themself to the sufficiency of his tender. Any error in description or
quantity or omission in the Contract Document shall not vitiate the contract or release the
Contractor from executing the work comprised in the contract according to drawings and
specifications at the scheduled rates. He is deemed to know the scope, nature and magnitude of
the works and requirement of materials, equipment, tools and labor involved, wage structures
and as to what all works he has to complete in accordance with the contract documents
irrespective of any defect, omissions or errors that may be found in the contract documents.
The Contractor shall be deemed to have visited the site and the surroundings, to have satisfied
themself to the working conditions at the site, labor etc., transportation facilities, probable sites
for labor accommodation and store go-downs etc. and all other factors involved in the execution
of work.

2.4 "Instructions to Bidder " shall be read in conjunction with the General Conditions of Contract,
Special Conditions of Contract(Technical and Commercial) and Technical Specifications ,
Specifications of work, drawings and any other documents forming part of this contract
wherever the context so requires.

2.5 Notwithstanding the sub-division of the Documents into these separate sections and Volumes,
every part of each shall be deemed to be supplementary of every other part and shall be read
with and into the contract so far as it may be practicable to do so.

2.6 Where any portion of the General Conditions of Contract is repugnant to or at variance with any
provisions of the Instruction to Bidder, then unless a different intention appear, the provisions

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 11
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

of the Instructions to Bidder shall be deemed to override the provision of the General
Conditions of Contract and shall to the extent of such repugnancy of variation prevail.

2.7 Wherever it is mentioned in the specifications that the Contractor shall perform certain work or
provide certain facilities, it is understood that the Contractor shall do so and the cost, if any,
deemed to be included in the price.

2.8 The materials, design and workmanship, the job specifications contained herein and codes
referred to shall satisfy the relevant Indian Standard. Where the job specifications stipulate
requirements in addition to those contained in the standard codes and specification, these
additional requirements shall also be satisfied.

3 DEFINITIONS, ABBREVIATIONS & INTERPRETATIONS


3.1 Definitions & Abbreviations

In the contract documents as herein defined where the context so admits, the following words and
expressions will have the following meaning:
“Acceptance Certificate” shall mean the certificate issued to the Contractor signed by the Engineer-
in charge appointed by the Owner for completion of works and clearing the said tests on
commissioning of the plant; “Act” shall mean Electricity Act-2003;
“Agreement” means the EPC cum O&M contract including EPC part and O&M part; “Alteration
Order" shall mean an order given in writing by the Engineer In-charge to effect additions to or
deletion from and alterations in the works;

“Bid" shall mean the techno-commercial response to the tender/RFP document.

"Bidder "/ “Tenderer” shall mean the person or the persons, firm or company, consortium who has
submitted their bid individually or jointly on consortium basis, against this bid to KTL and includes
the Bidders legal representative, his successors and permitted assignors and its subsidiaries and
affiliates,

“Bidding Consortium / Consortium (s)” shall mean the reference to the group of companies each
being a member in a Bidding Consortium, if the Bid for the proposed project has been made jointly
by more than one company.
"CEA" shall mean Central Electricity Authority, a statutory body, under the Ministry of Power,
Government of India;
"CEIG" shall mean Chief Electrical Inspectorate for Government;
“CERC” shall mean Central Electricity Regulatory Commission;
“Commission” / “DERC” shall mean District Electricity Regulatory Commission;
“Commissioning Certificate” shall mean the certificate to be issued by the Engineer –In Charge
appointed by KTL, when contractor has completed all its contractual obligations;

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 12
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

“Commissioning of the project” or “Commissioning” shall mean injecting power from the power
project to the delivery point after successful completion of the said tests;
"Contract" shall mean the Agreement between KTL and the Contractor for the execution of the
work including therein all contract documents;
"Contract Documents" shall mean collectively the Bid Document, Drawings, and Specifications,
Schedule, Appendix, agreed variations, if any, and such other documents consisting the bid and
acceptance thereof;
"Contractor" or “Successful Bidder” shall mean the Bidder selected to execute the contract
pursuance to this bid;
"Construction Equipment" shall mean all appliances and equipment of whatsoever nature for the
use in or for the execution, completion, operation or maintenance of the work unless intended to
form part of the permanent work;
“Contract Period” shall mean Five (5) months from the date of issue of Letter of Award (LOA) up to
commissioning of the project and thereafter Five (5) year of Operation and Maintenance period for
the project;
“Day” shall mean the 24 hours period beginning and ending at 12.00 midnight IST;
“Delivery Point” shall be the 400V Bus of the existing KTL Existing LT Panel;
"Drawings" shall include maps, plans and tracings or prints thereof with any modifications approved
in writing by the Engineer In-charge and such other drawings as may from time to time, be
furnished or approved in writing by the Engineer In-charge;
"Effective Date" shall mean the date of issue of letter of Award after first communication of
acceptance of bid;
"Electricity" shall mean the electrical energy in KWH (kilowatt-hours);
"Engineer-In-charge" shall mean the person designated as such by KTL and shall include those, who
are expressly authorized by the KTL to act for and on its behalf for operation of this contract;
"EPC" shall mean Engineering, Procurement & Construction;

"EPC Contract Price" shall mean the quoted EPC price by the Bidder to complete the project as
defined in Scope of work and including any other work required for completion of the project in all
respect;
“Financial Year” or “Fiscal Year” runs from April 1 of the prior year through March 31 of the next
year.
“KTL/Owner" shall mean Kallam Textiles Limited registered under the Indian Companies Act 1956;
"GOI" shall mean Government of India
“Grid System” means KTL33 kV Power transmission/distribution system through which delivered
energy is evacuated and distributed;
“IEC” means International Electro Technical Commission; is the world’s leading organization that
prepares and publishes International Standards for all electrical, electronic and related technologies;

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 13
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

“Interconnection facilities” shall mean all the facilities installed by the Contractor to enable KTL to
receive the Delivered Energy from the Project at the Delivery Point, including transformers, and
associated equipment, relay and switching equipment, protective devices and safety equipment;
“Installed capacity” shall mean the capacity of the project at the generating terminal(s) and shall be
equal to 2.6 MWp;
"I.S." shall mean specifications of Bureau of Indian Standards (BIS)
"IITM" shall mean Indian Institute of Tropical Meteorology, Bangalore;
"IREDA" shall mean Indian Renewable Energy Development Agency", “KV” shall mean Kilovolts;
"KW" shall mean Kilowatt;
"KWh" shall mean Kilowatt-hour;

“Law” shall mean any valid legislation, statute, rule, regulation, notification, directive or order,
issued or promulgated by any Governmental Instrumentality;
“Letter of Award” means the letter from KTL to the contractor conveying its acceptance of the bid
subject to such reservations as may have been stated therein;
"Metering Point" for purposes of recording of Delivered Energy will be the Delivery Point and shall
include two separate sets of calibrated trivector meters with 0.5s Class and suitable 0.5s CT at 400V
at Evacuation Point. The Energy Meters to be integrated with Plant monitoring system/ SCADA with
suitable communication system. The cumulative of all the trivector meters energy delivered is
considered as total solar plant delivered energy. Electronic HT meters, at 33kv side of the substation
as per the technical specifications and regulation of local DISOM/TRANSCO main meter installed by
the Contractor at bus bar of the project and the check meter installed by the Contractor complying
to REC requirements and both sealed by the Statutory Authority in presence of the Power Producer,
having facilities to record both export and import of electricity to/from the grid. HT meter and it’s
accessories supply by KTL;
"MNRE" means Ministry of New and Renewable Energy, a Central Government Ministry responsible
to develop and deploy new and renewable energy for supplementary energy requirement of the
country;
“Month” shall mean a calendar month according to the Gregorian calendar beginning at 12.00
midnight from the last day of preceding month and ending at 12.00 midnight on the last day of that
month
"MW" shall mean Megawatt;

"O&M" shall mean Operation & Maintenance of Solar power project;

"O&M Contract Price" shall mean the price quoted by the Bidder for operation and maintenance of
Solar Power Plant;
“Organizational chart” is a diagram that shows the structure of the proposed team by the Bidder
along with the relationships and relative positions of the proposed team
“Operational Approval” shall mean successful completion of all installation and commissioning
activities, grid connection, successful completion of start-up tests and achieving committed
generation as per Technical Document

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 14
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

“Parent Company / Holding Company” shall be construed as reference to any company or


corporation of which the other company or corporation is a subsidiary i.e. at least 51% stake in the
subsidiary is held by the Parent Company;
“Point of Interconnection” means a connection at which electricity is transferred to the Distribution
network of the KTL or the transmission network of the transmission licensee.
“PCN” shall mean Project Concept Note”;

“PDD” shall mean Project Design Document”;

“PPA” shall mean Power Purchase Agreement;

"Project" shall mean the development, design & Engineering, financing, manufacturing, delivery,
construction, project management and commissioning of the Solar Photovoltaic grid interactive
power station with 2.6 MWp installed capacity including Five (5) years operation and maintenance
of the same complete in all respects and all activities incidental thereto;
"Prudent Utility Practices" means those practices, methods, techniques and standards, that are
generally accepted for use in electric utility industries taking into account conditions in India, and
commonly used in prudent electric utility engineering and operations to design, engineer, construct,
test, operate and maintain equipment lawfully, safely, efficiently and economically as applicable to
power stations of the size, service and type of the Project, and that generally conform to the
manufacturers' operation and maintenance guidelines;
"Site" shall mean any and all parcels of real property, rights-of-way, easements and access roads
located in (Project Location), upon which the Project and its related infrastructure will be located;"
"Specification" shall mean the various technical specifications attached and referred to in the bid
documents. It shall also include the latest edition including all appended corrigendum of relevant
Indian Standard Published before entering into account;
“SPV Power Plant/Solar Power Plant/Power Plant” shall mean Solar Photovoltaic Grid Connected
Power Plant;
"Sub-Contractor" shall mean any person or firm or company (other than the Contractor) to whom
any part of the work has been entrusted by the Contractor, with the written consent of the KTL;
“Tariff” shall mean tariff for Solar Photovoltaic grid connected Power plant.

“Week” means seven consecutive calendar days;

"Work" shall mean the works to be executed in accordance with the contract or part thereof as the
case may be and shall include all extra, additional, altered, or substituted works as required.

4 PRE-QUALIFICATION CRITERIA
4.1 General Eligibility Criteria:

a. The Bidder should be a body incorporated in India under the Companies Act, 1956 or
2013 including any amendment thereto, Government owned Enterprises who are
registered and incorporated in India and engaged in the business of Power/

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 15
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Infrastructure, Limited Liability Partnership Firms registered as per LLP Act 2008,
barring Government Department as well as those firms against whom sanction for
conducting business is imposed by Government of India and barring those firms with
whom business is banned by the Employer.
b. A copy of certificate of incorporation shall be furnished along with the bid in support of
above.
c. Proprietorship Firms and Partnership Firms are allowed to participate in the bidding
process (either individually or in Joint Venture/ Consortium). In case of Joint Venture /
Consortium, Each member shall be submit a copy of certificate of incorporation along
with the bid.

4.2 Technical Eligibility Criteria:

a. The Bidder shall have an experience of design, supply, installation and commissioning
and Operational &Maintenance of at least Five (5) numbers of 0.5 MW& above (each
in a single location) capacity and two (2)numbers of 1 MW & above(each in a single
location) capacity of rooftop Solar Power Plants or above in India, which have been
successfully commissioned after 01 January 2014 and in operation for at least one (1)
year as on the Deadline for Submission of Bid.
b. The Bidder shall have an experience of design, supply, installation and commissioning
of solar photovoltaic based grid connected power plant(s) of cumulative installed
capacity of 8 MW rooftop solar plants or above in or outside India in last 5 years.
c. Bidder shall submit, in support to the above, the list of projects commissioned along
with their work order/ LOI and the commissioning certificates along with the certificate
of plant being in operation. A Job executed by a Bidder for its own plant/ project
cannot be considered as experience for the purpose of meeting Qualification Criteria of
this Tender Document.
d. Bidder is not Black Listed by any Public and Private Companies/ group/ bodies/
agencies/ Government offices.
e. In case of JV / Consortium, The Lead Member should meet above mentioned Technical
Eligibility Criteria.

4.3 Financial Eligibility Criteria:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 16
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

a. Average Annual Turnover of the Bidder for last two (2) financial years shall be at least
Rupees Twenty Crore Only (Rs. 20, 00, 00,000/-).
b. The Net Worth of the Bidder during the last Financial Year shall be at least Rs.3Crore
(Rs. Three Crore Only), wherein the Net Worth shall be calculated as follows:
Net Worth = (Equity + Reserves) – (Revaluation reserves+ intangible assets +
miscellaneous expenses to the extent not written off + carried forward losses).
c. The Bidder shall provide a copy each of audited annual report to ascertain their
turnover & net-worth.
d. The Bidder shall submit audited annual report of FY 2014-15, FY 2015-16, FY 2016-17,
FY 2017-18 and FY 2018-19.
e. In case of JV / Consortium, Lead member or each member should jointly meet the
above mentioned financial criteria.

The Bidder will be evaluated as per the clause no. 16 of ITB and Appendix 1.

5 BID DOCUMENT
5.1 Bidder shall sign each page of bid document as token of their acceptance of bid terms and
conditions and submit the same with its proposal. Bid shall be prepared by typing or printing with
indelible black ink on white paper in consecutively numbered pages and each page signed along
with duly filled format given in the Schedule(s).

5.2 Bidder has to give compliance on the scope of work mentioned in the technical specifications.

5.3 All amendments/addendum/revisions to Bid documents issued subsequently by Kallam Textiles


Limited if any, must be signed and submitted along with the bid and the bid submitted by the
Bidder shall take into account all such amendments/addendum/revisions. The Bidder is advised
to submit the bid, strictly based on the terms and conditions and specifications contained in the
documents and not to stipulate any deviations. If acceptance of the terms and conditions given in
the bid documents has any price implications, the same shall be considered and included in the
price part. Kallam Textiles Limited can reject any or all offers without assigning any reasons
whatsoever.

5.4 The bid shall be signed by anyone legally authorized to enter into commitments on behalf of the
Bidder. The Bidder shall submit Power of Attorney in favor of the person who is authorized to
enter into commitments on behalf of Bidder. Bid documents are non-transferable.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 17
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

6 BID SUBMISSION
6.1 Bid shall be prepared and submitted in double sealed envelope with description of the work. The
full name, postal address, telegraphic address, e-mail and telephone / fax number of the Bidder
shall be written on the bottom left corner of the sealed cover.
6.2 Bid must be submitted by the time and date mentioned in the letter of invitation of bid.
6.3 The bids so submitted shall be the following manner:
6.4 PART-I: Technical Bid
Technical Bid shall contain un-priced complete technical package including drawings &
documents and all commercial terms & conditions along with blank price format. The bid
document duly signed on all pages in token of acceptance should be enclosed.

Earnest Money Deposit (EMD)/Bid Bond and Bid Documents Fees should be in separate Envelope
in Technical Bid package.

6.5 PART-II: Price Bid


The PART-II (Price Part) of offer should be packed in second envelope and should contain the
PRICE only. This sealed envelope should be super scribed “Price Offer” with nature of work.

Detailed Price Break-Up: The price bid shall contain prices strictly as per price schedule with
detailed break-up as per Formats enclosed in both in figures & words.

6.6 A set of Part-I and Part-II above may be sealed in two separate covers and on top of each cover
the correct Part No. and respective title as per clause No. 3.1 above must be indicated. These
should be put in one cover envelope and sealed.

6.7 The sealed Bid shall be submitted to,

C/O Sri G V KRISHNAREDDY - JMD and CEO,


Kallam Textiles Limited ,
NH-16, Chowdavaram, Guntur, Andhra Pradesh

Last date and time of submission of your offer:


Last date and time of submission of your offer complete in all respect shall be 15:00 hrs
23/09/2019 Office hours

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 18
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

7 VALIDITY OF BID
7.1 The bid and the prices schedule included shall remain valid for a period of 180 days from the date
of opening of the bid within which period the Bidder shall have no right to withdraw, revoke or
cancel his offer or unilaterally vary the offer submitted or any terms thereof.

8 BID EXAMINATION
The Bidder is required to carefully examine the Technical Specification, terms and Conditions of
Contract, Drawings, and other details relating to supplies as given in the Bid Document.

The Bidder shall be deemed to have examined the bid document including the Draft
agreement/contract, obtained information on all matters whatsoever that might affect carrying out
the manufacture & supply activities and satisfied themself with the adequacy of his bid. He is
deemed to have known the scope, nature and magnitude of the supplies and the requirements of
material and labor involved and as to all supplies he has to complete in accordance with the
Contract.

Bidder is advised to submit the bid based on conditions stipulated in the bid Document. Bidder’s
standard terms and conditions will not be considered. Kallam Textiles Limited reserves the right to
evaluate the offer containing deviations in the manner it deems fit.

Kallam Textiles Limited will not be bound by any Power of Attorney granted by the Bidder or
changes in the composition of the Bidder Company / firm made subsequent to submission of the
offer or award of the contract. Kallam Textiles Limited may, however, on receiving request from the
Bidder, recognize such power of attorney and the changes after obtaining proper legal advice, the
cost of which will be chargeable to the Bidder.

The cancellation / alteration / amendment / modification of any documents such as Power of


Attorney, Partnership Deed, Memorandum and Articles of Association, etc. should be
communicated by the Bidder to Kallam Textiles Limited in writing, well in time, failing which, Kallam
Textiles Limited shall have no responsibility or liability for any action taken on the Strength of the
said documents.

Bid not submitted as per the instructions are liable to be rejected. Bid shall confirm in all respects
with requirements and conditions referred in this bid document.

9 EARNEST MONEY / SECURITY DEPOSIT


The Interested Bidders shall submit a Earnest Money / Security Deposit in the following manner:
Rs.12,50,000 (INR Twelve Lac Fifty Thousand Only)

From any scheduled Bank having branch in Guntur, Andhra Pradesh or any entity approved by
Employer in the form of Bank guarantee as per format set out in Schedule A (SCC Commercial) or in
the form of a Demand Draft payable in favor ofKallam Textiles Limited, valid for a period of 180 (One
Hundred Eighty) days after the date of Proposal submission specified in this Tender / Bid Document.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 19
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Earnest Money / Security Deposit of the successful Interested Parties shall be returned within
seven (7) days of the receipt of an acceptable performance bank guarantee in favour of the Kallam
Textiles Limited in accordance with the Agreement to be executed between the Parties. The
successful Interested Bidders shall keep the Earnest Money / Security Deposit valid until the date of
submission of the performance guarantee.

The Earnest Money / Security Deposit of the unsuccessful bidders shall be returned to them after
Award of Work by Kallam Textiles Limited to the successful Bidder within 10 days.

The Earnest Money / Security Deposit shall be forfeited, if:

(a) The Interested Bidders has, without the written consent of Kallam Textiles Limited, withdrawn
its Proposal during the Proposal Validity Period; or

(b) The Interested Bidders has refused to accept the correction of errors in its Proposal in
accordance with this RFP/Bid Document; or

(c) The Interested Bidders has executed the Agreement with Kallam Textiles Limited, but has
failed to deliver a performance bond in accordance with the Agreement; or

(d) The Interested Bidders has failed to execute the Agreement within Thirty (30) days of being
required to do so by Kallam Textiles Limited.

10 ORGANIZATION

10.1 In case the Bidder is a Partnership firm, certified copy of the partnership deed together with a
certified extract from the registrar of firms containing names & addresses of all the partners of
the firm should be furnished along with the offer.

10.2 In case of Company (whether private or public), certified copy of the "Certificate of
Incorporation" together with certified Memorandum and Articles of Association & a list
containing names & address of all Directors should accompany the offer.

10.3 In case of Proprietorship Firm, the name & address of Proprietor should be furnished.

10.4 In case of consortium, the lead/major/minor members of the consortium shall be identified
clearly. The Lead Member of the consortium shall be the Bidder. The Lead Member of the
consortium shall be the single point of contact for the purpose of this RFP till the Effective Date.
The number of members in the consortium shall be limited to two (2). The roles and
responsibilities of the consortium members shall be identified and indicated in clear terms. The
Bidder shall submit the original copy of the agreement executed in legally bound manner stating
the responsibility of all the members of consortium. Please note that the lead and major
members of the consortia shall be liable jointly and severally for successful completion of the
contract.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 20
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

11 NO COMPENSATION FOR SUBMISSION OF BID

11.1 The Bidder shall bear all costs associated with the preparation and submission of his offer, and
Kallam Textiles Limited will in no case be responsible or liable for those costs, under any
conditions. The Bidder whose bid is not accepted shall not be entitled to claim any costs,
charges and expenses of and incidental to or incurred by them through or in connection with his
submission of bid even though the Kallam Textiles Limited may elect to modify / withdraw the
invitation of Bid.

12 CHECKLIST OF DOCUMENTS TO BE SUBMITTED IN THE OFFER

12.1 Part –I: Technical Bid

12.2 The Technical Bid will consist of the following:

Letter regarding submission of bid along with following enclosures in the sequence given here
in below and in case any particular item is not enclosed shall be marked as "NOT SUBMITTED"
in the list of enclosure to the Covering Letter.
i. Time Schedule - Detailed time schedule indicating various activities, which Bidder proposes to
complete within the time of completion of work in the form of PERT Chart with definable
mile-stones taking into account the scope of work of his various Sub-Contractors. The PERT
chart should be provided in MS project.

ii. Technical Parameters of the Bidder or any member of the consortium in case of a consortium
- Duly filled in Questionnaire on Technical Parameters of the Organization.

iii. Last three years income tax returns.

iv. Experience of Works of Similar Nature - Details of work of similar nature carried out/being
carried out by the Bidder (in the Format as shown in Schedule-F). In addition, Performance
certificate in the Format shown in Schedule E should be enclosed.

v. Spares for One (1) year Normal Operation and Special Tools and Tackles - A list of
recommended spares, special tool and tackle instruments and appliances for normal
operation of Plant for a period of Five (5) years to be supplied under the Contract in the
Format shown in Schedule-G.

vi. In case of Consortium, the Consortium shall submit Consortium agreement.

vii. Power of Attorney - Power of Attorney / Authorization with the seal of the Company of
person signing the documents in the Format provided in Schedule L.

viii. In case of a Consortium, each member of the Consortium shall submit Power of Attorney in
favor of the Lead Member of the Consortium in the Format provided in Schedule L.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 21
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ix. Bidder will submit PVSyst report with guaranteed generation, PG, Temperature, GHI monthly
in excel format for each Orientation/ Tilt from PVSyst as a part of contract for 5 year O&M
period. PVsyst details shall be approved by Owner/ Consultant.

x. Deviations/Exception, if any - If the Bidder proposes deviations from the bid documents, such
deviations shall be kept to the minimum and shall be underlined / highlighted. Bidder shall
also summarize such deviations with cross reference to the main bid documents in a separate
document as per Schedule-H. Bid prepared in any other form shall be liable to be rejected.

xi. The Bidder should confirm that it has not been banned or de-listed by any Govt./Quasi-Govt./
Private Agencies or PSU's. If so banned, this fact must be clearly stated by Bidder in its offer in
the Format provided in Schedule M. However, it may not necessarily be a cause for
disqualifying the bid.

xii. All bidders are required to submit duly completed forms and confirmation on adherence for
all the Annexures (Technical Specification document). Bids are likely to get rejected if any of
the following submissions are found missing. The Annexures are:

 ANNEXURE A – Approved Makes

 ANNEXURE B – Project Characteristics Of PV Plant

 ANNEXURE C – Technical Specifications Of Key Components

 ANNEXURE D – List Of Spares

 ANNEXURE E – List Of Deviations

xiii. In addition to above, Bidders are also required to submit conceptual design and drawings, with
their proposed project components. This shall essentially include but not be limited to:
a) All the submittals as indicated in technical specifications for key project components

b) Energy yield prediction report (PVSYST report)with Guarantee Generation for 5 Year O&M
period

c) Typical plant power evacuation schematics (DC &AC SLD)

d) Conceptual overall plant layout

e) Module Mounting Structure configuration with walkway and lifeline

f) Project Implementation Schedule

12.3 PART-II: Price Bid

i. Price Schedule and Contract Price Break-Up must be provided as per Formats provided in
Schedule-B and Schedule C.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 22
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

13 DEVIATIONS / EXCEPTIONS

12.1 No deviations or exceptions to Kallam Textiles Limited’s terms and conditions and /or
pricing requirements will be accepted. Bidder may make due allowance in his prices for
compliance with the terms and conditions contained herein. Should it, however, become
totally unavoidable, the Bidder should propose any addition/deviation/alterations to any
of the terms and conditions contained in these document, the same must be expressed
clearly in Schedule-H accompanying the bid, without making any corrections on the body
of the bid documents, in the absence of which it will be deemed as acceptance by the
Bidder of all terms and conditions contained therein.

12.2 Bidders not indicating any Deviations / exceptions (as per Schedule – H) are deemed to
have agreed with the terms and condition of the bid document.

14 BID REQUIREMENTS

13.1 Bidder is advised that Kallam Textiles Limited intend to fully evaluate the technical and
un-priced commercial submissions. It is important that Bidder clearly demonstrates his
ability, giving to Kallam Textiles Limited a high level of confidence that they will be able to
perform the contract within the schedule time and meet and other requirements listed in
the bid document. Failure to do so may result disqualification of the bid.

13.2 The Bidder shall have technical, financial & legal expertise to carry out the assignment
and be fully conversant with prevailing laws and regulations of the GOI and State
Government for setting up of the Solar Power Projects.

13.3Award of Bid:

The Procedure for Finalization of BID would be as follows:


a) The following factors shall be used for the evaluation of Bid:

i. First the Technical bids shall be opened and evaluated.


ii. Then the price bid of technically qualified bidders shall be opened and an Evaluated
Bid Value (EBV) shall be calculated using the following parameters:

 Engineering Procurement Construction (EPC) Contract Price;


 Net Present Value (NPV) of O&M Price of Five (5) years;
 Net Electrical Energy Generation Guarantee for 5 year(NEEGG); and
 A constant discounting rate for calculating the NPV

iii. The Bid with the lowest Evaluated Bid Value for the Project shall be considered as L-1
and the Successful Bidder for the Project. The Bid with next lowest value shall be
considered as L-2 and so on. For a better understanding, please refer Appendix 1: Bid
Evaluation Criteria (BEC). An illustrative calculation of EBV has been presented for

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 23
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

better clarity in this direction.

iv. Upon short listing and subsequent finalization of the bidders may be concluded through
reverse auction. The Bidders shall abide by the rules of Reverse auction guidelines of
KTL. For the successful Bidder, KTL will issue a letter of award (LOA) to the selected
bidder prior to expiry of bid validity. Subsequently, the detailed contract will be issued in
due course. The selected EPC contractor shall immediately start working on the project
upon receiving the LOA.

b) If required KTL reserves the right to negotiate with (lowest) L-1 bidder before finalization
of the tender.

c) KTL reserves the right to accept any bid and to reject any or all bids. It also has the right
to award partial capacities of the project to multiple bidders other than L1 bidder.

d) KTL shall not be in any case obliged to furnish any information / clarifications /
explanations to the unsuccessful bidders other than refunding of EMD.

15 AWARD OF WORK

14.1 Upon short listing and subsequent finalization of the bidders may be concluded through
Reverse auction. The Bidders shall abide by the rules of reverse auction guidelines of
Kallam Textiles Limited. For the successful Bidder, Kallam Textiles Limited (KTL) will issue
a letter of award (LOA) to the selected bidder prior to expiry of bid validity. Subsequently,
the detailed Contract will be issued in due course. The select EPC contractor shall
immediately start working on the project upon receiving the LOA.

14.2 Kallam Textiles Limited (KTL) shall not be obliged to furnish any information / clarification
/ explanation to the unsuccessful Bidders with regard to non-acceptance of their bids.

16 PRICE

15.1 The Bidder shall quote the price for design, engineering, manufacturing, supply, handling
storage, civil works, erection, testing & commissioning along with O&M charges per unit
basis of the project, for the scope of works described in Technical Specifications. As per
the Price Schedule ,it shall include all applicable taxes, duties, cess, and insurance charges
etc. The breakup of the total bid price shall be indicated as per Formats attached as
Schedule-C.

15.2 The Bidder shall not bill separately for any accessories and items required for making the
Solar Power Plant machinery workable and its price will be deemed to be included in the
quoted price.

15.3 Prices for supply, erection and civil engineering work shall be inclusive of all applicable
taxes and duties cess etc. However, taxes and duties shall be indicated separately along
with prevailing rates as per Price Format enclosed.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 24
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

15.4 The price as stated above shall remain firm and not subject to any variations till
completion of entire scope of work as per Bidder’s scope, except the change in law
adjustment within the agreed delivery/commissioning schedule. The benefit on account
of decrease in taxes, duties, cess if any shall be availed by Kallam Textiles Limited, if
accrued during the stipulated / extended commissioning period.

15.5 The rate shall be written in English both in words and in figures. Corrections, if any, shall
be made by crossing out, initialing, dating & rewriting. In case of discrepancies between
the figures and words in the rates, the later shall prevail.

17 TAXES & DUTIES

The quoted price shall be inclusive of all taxes & levies according to the legislation in effect as on the
final date of bid submission. However, on account of change in law or levy of any additional taxes or
duties in the nature of Indirect-tax in respect of the activities undertaken by the contractor, the
same shall be payable in addition to the charges calculated on the basis of quoted amount. Similarly,
the contractor shall transfer any downward changes in taxes and duties to Kallam Textiles Limited
(KTL).

18 TERMS OF PAYMENT

Subject to any deduction, which the Kallam Textiles Limited (KTL) may be authorized to make the
Contract. Price shall be payable as per the clause 6 of SCC Commercial of bid.

19 TRANSFER OF BID DOCUMENTS / BID TRANSFER

The transfer of bid documents to others is prohibited.

20 SIGNING OF CONTRACT AGREEMENT

19.1 The bid document shall be the basis for the final Contract to be entered into with the
successful Bidder. No deviation from the terms and conditions specified shall be
acceptable.

19.2 On the bid being accepted by the Kallam Textiles Limited (KTL) at its option, a Contract
will be signed and executed by and between the Kallam Textiles Limited and the
successful Bidder, within a reasonable time. All costs, charges and acceptance of and
incidentals to the execution of the said contract including stamp duties shall be borne by
the Contractor.

19.3 Technical specifications included in this bid document are only for information and are
not exhaustive. The Bidder shall have to submit the detailed specifications for machines
and other related work and shall be discussed before award of work.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 25
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

APPENDIX 1: BID EVALUATION CRITERIA (BEC)


The Evaluated Bid Value (EBV) shall be calculated using the following parameters to be quoted by
the Bidder:

i. Quoted EPC Contract Price,


ii. Quoted Annual Net Electrical Energy Guaranteed Generation (NEEGG) from PVsyst at the end
point ofsolar metering of the solar plant for each year during the O&M period (of 5 years),
iii. Quoted O&M Contract Price for each year during the O&M period (of 5 years),

Parameters assumed constant for evaluation of each Bidder:


iv. Discount Factor of 13.80%1 annually.

The Evaluated Bid Value (EBV) shall be calculated using the abovementioned parameters as
follows:

Step 1 Quoted EPC Contract Price at the zeroth (0th) year


Step 2 Net Present Value (NPV) of 5 years of O&M Cost
quoted by the Bidder
Step 3 (ADD) EPC Contract Price and NPV of O&M Cost for 5
years
Step 4 Summation of quoted NEEGG for 5 years
Step 5 (Divide) (Sum of EPC Contract Price and NPV of each year
O&M Contract Price for 5 years) by (Summation
of quoted NEEGG for 5 years) i.e. (Step3/Step4)

The Evaluated Bid Value (EBV) shall be the Net Present Value (NPV) as calculated above.

Evaluated Bid Value (EBV) = EPC Cost + NPV of each year O&M Contract Price of 5 years

ΣNEEGG of 5 years

The Bidder with the lowest EBV in Rs/ kWh shall be the Successful Bidder.

EXAMPLE:
The following example will further clarify the methodology of comparison:
Values quoted by bidders are with orange text in the light blue boxes of the tables below:

1https://www.sbi.co.in/portal/web/interest-rates/benchmark-prime-lending-rate-historical-data

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 26
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Figures quoted by Bidder 1


Year NEEGG O&M Cost
kWh INR
1 3723200 806000
2 3667352 886600
3 3641681 975260
4 3616189 1072786
5 3590875 1180065
Capacity MWp 2.6
Total NEEGG N 18239297
Discount factor 13.80%
EPC Price (in Rs) E ₹ 8,99,60,000.00

NPV of O&M Cost quoted for 5 years (in Rs) NPV


₹ 33,12,565.18
Sum of EPC and NPV of O&M Cost quoted for 5 years (in
S = NPV + E ₹ 9,32,72,565.18
Rs)
EBV (in Rs/ kWh) EBV = S/N ₹ 5.11

Figures quoted by Bidder 2


Year NEEGG O&M Cost
kWh INR
1 3744000 858000
2 3687840 943800
3 3662025 1038180
4 3636391 1141998
5 3610936 1256198
Capacity MWp 2.6
Total NEEGG N 18341192.27
Discount factor 13.80%
EPC Price (in Rs) E ₹ 9,23,00,000.00

NPV of O&M Cost quoted for 5 years (in Rs) NPV


₹ 35,26,279.06
Sum of EPC and NPV of O&M Cost quoted for 5 years (in
S = NPV + E ₹ 9,58,26,279.06
Rs)
EBV (in Rs/ kWh) EBV = S/N ₹ 5.22

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 27
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Conclusion:

 EBV of Bidder 1 is Rs. 5.11 per kWh.


 EBV of Bidder 2 is Rs. 5.22 per kWh.
 EBV of Bidder 2 is higher than Bidder 1.
Hence, Bidder 1 would be L-1 and would be preferred as the Successful Bidder compared to
Bidder 2.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 28
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SECTION - II
TECHNICAL SPECIFICATION

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 29
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

TECHNICAL SPECIFICATION FOR TURNKEY EPC CONTRACTOR

1 PROJECT OVERVIEW
M/s Kallam Textiles Limited (KTL) as Owner invites open tender from eligible applicants, who fulfil
qualification criteria for the work – “Design, Engineering, Supply, Storage, Civil work, Erection of
structure, Erection of Solar Panels, Testing & Commissioning of 2.6 MWp/2.0 MW (indicative capacity)
Rooftop Solar PV project under Captive plant scheme including Operation and Comprehensive
Maintenance (O&M) of the project under CAPEX Model on it’s Factory shed. The site for setting up of
solar plants has been identified by owner and details are mentioned in this document.

1.1 Site Overview

Figure 1 Google earth view

The rooftop solar power plant propose capacity is 2.6 MWp/2.0 MW on marked shed as shown in
figure 1 google earth view and following are the list of priority wise GI shed/RCC roof for installation of
2.6 MWp/2.0 MW rooftop solar plant:

 Open end spinning unit

 Ginning Unit

 Spinning Unit- South side

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 30
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Spinning Unit- RCC roof

 Admin Building- RCC roof

 Spinning Unit- North side

All sheds have metal trapezoidal sheet (GI) which can be used cumulatively for installation of
proposed2.6 MWp/2.0 MW solar plant capacity on them.

Spinning unit have some shed made of asbestos sheet and the same shall be replaced by GI shed by the
KTL.

Open end spinning Unit, Ginning Unit, Spinning Unit and Admin Building have installation capacity of2.6
MWp Solar power plant under captive system on same GI Shed.

1.2 PV Plant Overview

 To save roof space Owner has chosen to go with Crystalline modules with efficiency more than
18.5%for GI shed and Bifacial Crystalline modules with efficiency more than 18.5% for RCC roof
for it’s 2.6 MWp/2.0 MW Solar Power project. The Bidder will quote for long rail based on
existing purlin loading module mounting structures on shed with same angle (flat mounted) of
shed.

 Bidder are expected to design and deliver 2.6 MWp/2.0 MW output power at metering point
with around 30% overloading in DC capacity. Solar Metering point shall be at 400 V in client
existing main LT panels at seven different locations. Existing HT metering point is at 33 kV
switchyard.

 In order to minimize DC & AC ohmic losses, String inverters, LV switchgear shall be located as
per the design layout and client or its consultant’s approval.

 Module Mounting Structure, Module & Inverter design and installation shall be as per OEM’s
guideline and the same shall need approval from owner or it’s consultant.

 Bidder have to utilize all south orientation shed first then remaining capacity will be install on
north orientation shed considering the shadow analysis for all object which may cause shadow
on the proposed PV module array proposed locations. The same shall be verified by owner or
it’s consultant.

 Bidder should consider different Inverters for each orientation of shed. Bidder should not mix
MPPT of same inverter for different orientation, tilt and shed. Bidder shall provide Inverter
level string level monitoring facility for calculate Plant performance orientation wise.

 KTL shall provide necessary Solar and HT meter arrangement with main & check meter as per
Local Discom / Transco guidelines.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 31
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 The detailed technical specification of the equipment expected to be supplied by the bidder
and the works to be completed as per technical specification mentioned in this document. The
bidder is advised to conduct site visit, go through the specification and scope before submitting
their offer.

 Total Solar Plant shall be guaranteed generation for satisfactory performance for 5 Years.

 Further the bidder shall guarantee the Performance of solar PV Modules and Inverters and
other items as mentioned in detailed Technical specification of the respective components.

1.3 Owner (KTL) free issue items and services:

KTL shall provide following free issue items and services to bidder:
 All liaisoning approvals

 Solar LT Panels including Metering cubical

 AC Cable

 Fire protection system

1.4 Electrical Characteristics

 DC System: This shall essentially be applicable from solar PV array up to the solar inverter. The
operating voltage of inverters shall essentially depend upon the MPPT range; however, the
maximum system voltage should be 1500V.

 LV System: AC Low Voltage System post inverter shall be again linked to inverter specifications;
however, the output power should have three phases with a nominal frequency of 50Hz.

1.5 Electrical Losses

a) All components of the PV Plant Electrical system shall be designed by the Bidder to minimize
electrical losses and not exceeding an averaged 1.0% DC losses in case of string inverter at STC.

b) The Maximum losses or voltage drop in the AC cables (from Inverter output to Evacuation point
at plant LT Panel) shall be limited to 1.5% of the rated voltage in case of String inverter at STC.

c) All cable's voltage drop /losses shall be calculated at maximum operating temperature of the
conductor when carrying full load current.

1.6 Site Climatic Conditions

The following conditions has been assessed for the proposed location and may be considered by the
bidder for their project component selection and system designs.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 32
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Parameter Values
Design Temperature 50°C
Minimum Temperature 19° C
Maximum Temperature 39.3° C
Humidity Up to 99 RH%
Annual Rainfall 905 mm
Maximum Wind Speed As per IS 875

1.7 Site Details

Parameter Details of Site

Village: Chowdavaram

Project Site Location District: Guntur


State: Andhra Pradesh

Latitude: 16.257847° N
Plot Co-ordinates
Longitude:80.335402°E

Available Roof Area (Acres) Approx. 6.33

Tentative Capacity that can be housed 2.6 MWp/2.0 MW

Type of Roof Metal Shed

Type of Electricity connection HT

Main Metering Voltage 33 KV

Solar Evacuation Voltage 400 V

Suitability of multiple commercially established solar PV technologies have been evaluated for the
proposed site. The Techno- Commercial evaluation was based & as a result, KTL has opted for
crystalline PV technology with same tilt of shed and Bifacial solar PV technology for RCC roof for its 2.6
MWp/2.0 MW Plant.

1.8 CODES AND STANDARDS

The work shall be performed in conformity with these specifications, standard specifications,
installation standards and Codes of Practice of national and international standards specified or
referred in the Tender.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 33
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

In addition, the work shall also conform to the requirements of latest edition/ amendments of the
following:

1. Jawaharlal Nehru National Solar Mission guidelines

2. MNRE guidelines & specifications

3. The Indian Electricity Act/ CEA Guidelines and the Rules framed there under

4. The Fire Insurance Regulations

5. The regulations laid down by the Chief Electrical Inspector of the state government.

6. The regulations laid down by the Factory Inspector.

7. The regulations laid down by the Central Electricity Authority.

2 SCOPE OF WORK

The Scope of work of the bid proposal is design, planning, engineering, procurement (manufacturing /
supply), construction / erection, testing, commissioning and 5 (five) years of operation & maintenance
along with 1 years Defect Liability Period (DLP) of solar PV plant as a turnkey EPC contract according to
terms and conditions set out herein.

The turnkey EPC contract shall be in accordance with all applicable regulations and permits so that the
solar PV plant fulfills the requirement by Project developer and the technical specifications as
specifically mentioned under this contract. The turnkey development of solar PV plant by the turnkey
EPC contractor shall essentially include:

• Basic project planning, solar resource assessment, energy yield predictions for project life cycle
of 25 years, basic and detailed designing, project component selection, preparing engineering and
construction drawings and all other requirements as required for successful commissioning of the plant
up to the 33 kV HT metering within plant.

• Manufacturing, supply, sourcing, procurement, transportation of all solar PV plant


equipment’s, required insurance, electrical components, structural components, civil engineering
material, mechanical engineering components, construction machinery and all other construction
equipment as required for development, implementation, construction, testing, commissioning of the
up to the 33 kV HT metering within plant.

• Water and electricity during construction shall be provided at a single point by the Owner.
Obtaining permits and approvals from all local stakeholders, CEIG, government statutory bodies,
obtaining permissions from electrical inspector, liaison with DISCOM utility for evacuation
infrastructure, power system study for feasibility of solar plant (if required by any approval authority)
and charging of solar PV plant and HT metering as required for completion and successful commission
of plant shall be under KTL’s scope. For that require, all documentation and support shall be provide by
Bidder to Owner.

• All the operations not expressly included, that are necessary for proper functioning of the solar
PV plant and fulfilment of the guaranteed performance, rules, regulation, and applicable codes, being

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 34
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

the meaning of necessarily all these things, which are inherent to the Project and without which the
solar PV plant would be unable to start operating commercially.

• Commissioning of the solar PV plant, Performance Guarantee test, monthly and yearly
performance evaluations and performance guarantee tests as required by the KTL during the O&M
Period.

• Comprehensively warranting the entire solar PV plant against all defects through a defects
liability period (DLP) of 1 years, providing Yearly Performance Guarantees for the O&M period and
maintaining a maximum plant availability for getting guaranteed generation during O&M period.

• Operation and Maintenance (O&M) of the entire solar PV plant for a period of 5 years from the
date of handover of the plant by project team to operation team and supplying all the required spares
recommended by respective manufacturers of all project components during O&M period.

• Training’s personnel for operation and maintenance, handing over the plant to KTL, provision
of all the documentation necessary for the correct performance and maintenance for the life cycle time
of solar PV plant.

• The Bidder will guarantee yearly guaranteed generation. These values would be measured on
hourly and daily basis through SCADA/Plant Monitoring system up to metering point of the Plant. For
contractual purpose, the penalty would be levied on the Bidder on the basis of annual PG test having
not met. 3(three) Monthly generation would become a basic/milestone for joint-gap analysis,
identifying, improvement opportunities & implementing corrective actions and measures. This process
will be followed for the duration of the O&M services being provided by the Bidder.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 35
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

3 DETAILED SCOPE OF THE CONTRACT

Sr. No. DESCRIPTION PRIMARY SCOPE REVIEW APPROVAL

A PERMITS AND APPROVALS

A.1 Roof finalization Owner Consultant Owner

A.2 Roof sheet Replacement Owner Consultant Consultant

A.3 Electrical Inspector Approval Process Owner Consultant -

A.4 All Approvals documentation preparation EPC Consultant Owner

CEIG approvals/ Clearances/ Documents


A.5 Owner Consultant -
preparation and Submission /Approval

DISCOM approvals/ Clearances/ Documents


A.6 Owner Consultant -
preparation and Submission /Approval

All Statutory Approvals/ Clearances/


A.7 Owner Consultant -
Documents Preparation and Submission

Building and construction permits for


A.8 Owner Consultant Owner
Inverter rooms

Water supply for construction and


A.9 Owner Consultant Owner
operations

Electricity supply for construction and


A.10 Owner Consultant Owner
operations

All other approvals as required for project


A.11 Owner Consultant Owner
completion and evacuation

A.12 Local Taxes and Duties Exemption, if any EPC EPC Owner

B PRE-CONSTRUCTION ACTIVITIES

B.1 Soil investigation report for ERT EPC Consultant Owner

B.1 water quality report for MCS EPC Consultant Owner

B.2 Solar resource assessment EPC Consultant Owner

B.3 Module finalization EPC Consultant Owner

B.4 Project component selection EPC Consultant Owner

B.5 Conceptual design, schematics and layouts EPC Consultant Owner

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 36
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

B.6 Energy yield predictions for project life cycle EPC Consultant Owner

Performance Guarantee prediction for


B.7 EPC Consultant Owner
project life cycle

Project Capacity, Tracking Methodology, Tilt


B.8 EPC Consultant Owner
& Pitch Finalization

Performance Guarantee for 5 year annual


B.9 EPC Consultant Owner
average calculated at metering point.

Project scheduling, planning and


B.10 EPC Consultant Owner
sequencing

B.11 Procurement and delivery schedule EPC Consultant Owner

B.12 Submission of drawing schedule on MDL EPC Consultant Owner

B.13 Submission of construction drawings EPC Consultant Owner

B.14 Quality assurance plan EPC Consultant Owner

Method statements and various operating


B.15 EPC Consultant Owner
manuals

B.16 Construction & Field quality plan EPC Consultant Owner

Technical specification sheets for all


B.17 EPC Consultant Owner
equipment

Health, Safety and Environmental policy for


B.18 EPC Consultant Owner
project

Design plant and allied systems according to


B.19 EPC Consultant Owner
the approved project configuration

Detailed engineering of the entire PV plant


B.20 up to point of interconnection including EPC Consultant Owner
system study analysis for solar plant

C PROCUREMENT (Supplies)

C.1 Solar PV modules EPC Consultant Owner

C.2 PV Grid Tie Inverters EPC Consultant Owner

Module mounting structures with all


C.3 EPC Consultant Owner
hardware and module-fixing ancillaries.

String Monitoring boxes with monitoring


C.4 arrangements and all consumables (if EPC Consultant Owner
Required)

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 37
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

C.5 Solar Plant Monitoring System EPC Consultant Owner

C.6 DC Cables EPC Consultant Owner

C.7 AC Cables Owner Consultant Owner

C.8 Control and Communication Cables EPC Consultant Owner

C.9 LV Panels Owner Consultant Owner

C.10 Lightning arrestors (ESE type for Solar Plant) EPC Consultant Owner

C.11 Fire protection system Owner Consultant Owner

C.12 Weather Station EPC Consultant Owner

C.13 Metering cubical Owner Consultant Owner

C.14 Earthing Material EPC Consultant Owner

C.15 Module Cleaning System EPC Consultant Owner

C.16 Walkway EPC Consultant Owner

C.17 Saftey Lifeline EPC Consultant Owner

C.18 Rooftop Guardrail EPC Consultant Owner

All procurement as required to complete


project implementation, testing and
C.19 EPC Consultant Owner
commissioning up to point of
interconnection and metering.

List of spare item for commissioning &


C.20 EPC Consultant Owner
Operations for 5 year

D LOGISTICS

D.1 Packaging and forwarding EPC - Owner

D.2 Transportation to site EPC - Owner

Comprehensive marine, transit, storage,


D.3 EPC - Owner
erection all risk insurance cover

Loading, unloading, handling, storage and


D.4 EPC - Owner
safety of all equipment

D.5 Vehicle Approval EPC - Owner

E SITE PREPERATION

Site preparation for entire PV plant up to


E.1 EPC Owner
point of interconnection

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 38
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

E.2 Tree trimming up to Shed level Owner Consultant Owner

Removal of existing Water pipe line and


E.3 Owner Consultant Owner
Existing fascia above Spinning Unit building

Change Asbestos roof sheet to GI sheet of


E.4 Owner Consultant Owner
Spinning Unit

All earthwork including excavation, back


E.5 EPC Consultant Owner
filling and compaction

Inverter Control Room construction at each


E.6 Owner Consultant Owner
Solar termination point

E.7 First Aid Station, Safety and health facilities EPC Consultant Owner

E.8 Monkey ladder at Ginning Unit Owner Consultant Owner

Storage provision for solar system


E.9 EPC Consultant Owner
equipment with locking facility

F CIVIL ENGINEERING WORKS

F.1 Installation of Lifeline on shed EPC Consultant Owner

F.2 Installation of Guardrail on shed for safety. EPC Consultant Owner

F.3 Installation of Walkway on shed EPC Consultant Owner

Foundations for module mounting


F.4 EPC Consultant Owner
structures(in case of RCC roof )

Construction & Fabrication work for cable


F.5 EPC Consultant Owner
Tray, Earth Strip, Pipes etc

Foundations as required for all electrical


F.6 systems including inverters, LT panels, EPC Consultant Owner
distribution boards, WMS, LA etc.

F.7 Construction of Inverter control room Owner Consultant Owner

All other civil and structural works as


F.8 EPC Consultant Owner
required completing the plant.

F.9 Module Cleaning System EPC Consultant Owner

Reconstruct road and other factory


F.10 EPC - Owner
damages during Solar Plant execution Work

G ELECTRICAL ENGINEERING WORKS

Temporary cabling as required for


G.1 EPC - Owner
construction power

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 39
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

PV module, MC4 Connector, MMS, SMB,


G.2 EPC Consultant Owner
Inverters, DC and AC cables as required.

G.3 Earthing and lightning protection system EPC Consultant Owner

Auxiliary power supply system including all


cabling as required for Module cleaning
G.4 EPC Consultant Owner
System, Plant Monitoring System, WMS and
LT panel etc.

Controls and monitoring system including


G.5 EPC Consultant Owner
SCADA/ plant management system

Performance monitoring from solar PV


G.6 EPC Consultant Owner
string level to Solar meter

Electrical spares as required for defects


G.7 EPC Consultant Owner
liability period

H INSTALLATION OF MISC. SYSTEMS

H.1 Supply and Installation of weather station EPC Consultant Owner

H.2 Fire protection system EPC Consultant Owner

RO water discharge mechanism in line with


H.3 pollution control board guidelines and EPC Consultant Owner
approval etc.(in case of required)

PROJECT AND CONSTRUCTION


I
MANAGEMENT

I.1 Project Management EPC Consultant Owner

I.2 Site Supervision EPC Consultant Owner

I.3 Project scheduling and tracking EPC Consultant Owner

I.4 Drawing Schedules EPC Consultant Owner

I.5 Equipment Delivery Schedules EPC Consultant Owner

I.6 Construction Schedules EPC Consultant Owner

I.7 Overall Project Status Reports EPC Consultant Owner

Witnessing factory test for all major


I.8 Owner/EPC Consultant Owner
equipment

I.9 Factory Tests Reports EPC Consultant Owner

I.10 Quality Assurance / Quality Control EPC Consultant Owner

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 40
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

I.11 HSE monitoring EPC Consultant Owner

J POST CONSTRUCTION ACTIVITIES

Removal of all temporary constructions and


J.1 EPC Consultant Owner
equipment.

Finishing the main approaches roads,


J.2 EPC Consultant Owner
ladders and walkways within the plant.

Performance Guarantee test procedure and


J.3 EPC Consultant Owner
final report

J.4 As built drawings in Pdf and Autocad file EPC Consultant Owner

All type of Calculation & report to be submit


J.5 EPC Consultant Owner
in Excel and Word file

Handing over copies of operation, planning,


J.6 installation and troubleshooting manuals EPC Consultant Owner
and test report for all project components

Clearing Punch points raised by


J.7 EPC Consultant Owner
consultant/Owner

Internet Connection for Plant Monitoring


J.8 Owner Consultant Owner
System (GSM/LAN)

K TESTING AND COMMISSIONING

Mechanical completion test / Provisional


K.1 EPC Consultant Owner
acceptance test

K.2 Pre-commissioning and Commissioning Test EPC Consultant Owner

K.3 Preliminary PG test acceptance test EPC Consultant Owner

K.4 Handing over plant to owner EPC Consultant Owner

Performance Guarantee test for entire


K.5 EPC Consultant Owner
O&M period

K.6 Consumables required for all these tests EPC Consultant Owner

Standard and special test instruments, tools


K.7 EPC Consultant Owner
and equipment required for all the tests

K.8 Reporting and documentation of all tests EPC Consultant Owner

K.9 Recording of all tests EPC Consultant Owner

L OPERATIONS AND MAINTENANCE

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 41
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

5 year comprehensive operation and


L.1 maintenance with Performance Guarantee EPC - Owner
included with one year DLP

L.2 1 year warranties for DLP EPC - Owner

Mandatory Spares and consumables as per


L.3 EPC Consultant Owner
agreed list

Final performance Guarantee (PG) test and


L.4 acceptance there of after 5 year of O&M EPC - Owner
period

L.5 Training of owner's personnel EPC - Owner

L.6 Insurance Cover EPC - Owner

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 42
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

4 RESOURCE ASSESSMENT AND ENERGY YIELD

The bidder shall be legally bound for the plant performance guarantee committed during the
submission of Techno - Commercial bids. Long term energy yield prediction for the defects liability,
warranty of One (1) years and O&M period of 5 years shall essentially be a key parameter in shortlisting
of Bidders. In addition to first year energy yields, the Bidders shall submit long term prediction clearly
indicating the PV module initial and annual degradations.

4.1 Reference Solar Resource

The annual energy yield of a PV plant is dependent on solar resource of the site. Bidder is required to
source solar data along with wind speeds and temperature from SOLARGIS/Meteonorm (Meteonorm
Ver.7.1.4 or higher). Owner reserves the right to technically assess the data source independently and
compare the selection with onsite measurements if available.

4.2 Benchmarks for Energy Yield Computation

Energy yield prediction essentially depends on simulations and loss assumptions. Bidder must use
PVSyst version (6.8) or latest as the simulation tool for energy yield predictions. Obsolete / Older
version is not acceptable.

The simulation must take into account all losses including AC losses up to the Solar evacuation point.
The PVSYST simulation report (in.pdf format) shall clearly indicate simulation parameter, near shading
definition, horizon shading definition, main results and main PV components used and the loss
diagram.

Assumption of losses largely depends on the past experience of the bidder in similar locations and
climatic conditions. However, the loss benchmarks presented in the below table may be maintained for
computation.

Loss Description

Shading Loss The site can be considered free from any near obstacles and horizon. The
maximum benchmark for shading loss shall be capped at 1.0%.

Incident Angle Modifier Although this shall depend on the module selected, maximum
(IAM) Loss benchmark for IAM loss is 2.7%.

Low Irradiance Low irradiance loss essentially depends on the characteristics of the
module and the intensity of the incident radiation. This value shall
depend on module selected and the solar resource data used for
simulation.

Module Temperature Loss Every ˚C rise in temperature above STC shall reduce the efficiency of PV
module.

Soiling Loss Bidders are advised to evaluate the dust profile on site and define the
O&M strategy for maintaining the soiling loss up to a maximum of 2%.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 43
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Module Quality Loss Modules are sold with a nominal peak power and a given positive
tolerance within which the actual power is guaranteed to lie.

Module Mismatch Loss Although this loss depends on Bidder’s capability to connect PV modules
of same current/ voltage profiles in series, the Bidders shall submit
manufacturer’s confirmation on uniform current/ voltage profiles for
delivered batch of modules.

DC Cable Loss Electrical resistance in the cable between the modules and the input
terminals of the inverter give rise to ohmic losses (I²R). Maximum
benchmark for this assumptions shall be 1.0 % in case of string inverter.

Inverter Performance Bidders shall take Euro efficiency or Californian efficiency @ 400 VAC for
energy yield computations. Minimum benchmark for this efficiency shall
be 98.3%.

AC Cable Loss AC losses shall occur in four areas, LV AC cabling up to metering. Bidders
are expected to provide detailed losses segregating said areas with
appropriate justifications. Maximum benchmark for this assumptions
shall be 1.5 % in case of string inverter.

Plant Unavailability Bidders are expected to offer maximum plant availability and achieve
maximum guaranteed generation.

Auxiliary Consumption Bidder shall consider the energy consumption arising due to the auxiliary
equipment such as electrical equipment and monitoring equipment in
the energy yield calculation.

4.3 Module Degradation

Bidder shall warrant linear power degradation values for 25 years as per the contract. The values shall
be supported by manufacturer’s confirmation based on past experience and track record on proposed
modules. Manufactures warranty should be guaranteed by 3rd party with certification document.
Module manufactures warranty to be guaranteed by third party insurer.

5 PROJECT WARRANTIES

The captioned allocated Project capacity of solar PV project shall be implemented through a turnkey
EPC contract including comprehensive warranties &O&M of 5 (five) years as per mentioned in other
areas of contract from the date of commissioning and commercial operations. The project warranties
shall essentially include but will not be limited to:

5.1 Defects Warranties

Not-withstanding individual component warranties, the bidder shall provide 5 (five) years
comprehensive warranty for defects in the entire solar PV plant right from PV modules, all spares and
consumables to the point of interconnection and metering. The bidder shall warrant the project free
from any and all defects including unseen and latent in all project components and workmanship.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 44
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

In case of any manufacturing defect or underperformance of any project component, the bidder shall
guarantee supply, installation, testing and commissioning of defective project components at no cost to
the Owner. In case of defects due to improper handling of project components or failure of
components, noncompliance of statutory / regulatory by bidder’s O&M team, the bidder shall be
responsible for repairing / Replace any/ all defects. Owner shall be liable to claim additional monetary
compensation for loss of energy generation caused due to shortfall in energy generation.

Any replacement made or component repaired by the bidder during O&M period shall continue to be
in warranty for balance warranty period along with an additional extended warranty for 12 months
with no charge to the Owner. The extended warranty shall come in effect upon completion of original
warranty period.

5.2 Project Components Warranty

Project components warranty can essentially be construed as guarantees / warranties provided by the
project component manufacturers beyond the defects liability period, performance warranty period
and extended warranties. Best in Class OEM warranty to be provided for all equipment and all such
warranty for any of the project components shall be transferred to the Owner after completion of
O&M period. Owner shall reserve the right to call for extended warranties from the manufactures and
same shall be agreed by the Bidder and product manufacturer. The warranty of various project
components should be as below:

Sr. No. Equipment Warranty period

1. PV Modules (Minimum) At least 10 years ( Any additional warranty


extended by manufacturer is preferable)

2. PV Modules (performance warranty) At least 25 (twenty-five) years with at the end


of10 years minimum 91% (ninety one percent)
power output and at the end of minimum
25years82% (eighty two percent) power
output.

linear power degradation values for minimum


25 years

3. Mechanical Structures and At least 5 years


accessories

4. DC cables with all accessories At least 5 years

5. String Combiner Box and accessories At least 5 years

6. Grid Tied Inverters At least 5 Years warranty for European make


Inverter
10 Years warranty for Chinese make Inverter

Extended warrantee amount to be


incorporate in offer for next 25 years for all

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 45
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

makes Inverter.

7. Walkway & Rail guard system and At least 10 years


it’s accessories

8. WMS, Control and monitoring At least 5years


system including software and
hardware

9. Earthing system At least 5years

The manufacturer’s product warrantees for other supply materials shall be passed on from the
manufacturer to KTL Authority.

6 OPERATION AND MAINTENANCE (O&M)

6.1 General

The plant after successful 30days testing period and commissioning shall be taken over by KTL.
However, comprehensive regular maintenance of the plant is within the scope of the successful
tenderer for the specified period. The bidder shall operate and maintain the plant and equipment by
suitable personnel. The spares required for maintenance of the plant is within the scope of the bidder.
The comprehensive maintenance is inclusive of regular/Break down maintenance, preventive
maintenance as per the manufacturer‘s manuals, etc. to ensure maximum availability of the equipment
and to get the better performance and maximum output from the plant. All the break-downs, repairs,
etc. are to be attended by the bidder immediately so as to put the plant in service within the least
possible time in any case not later than the periods mentioned in this technical specification.

6.2 Scope of Annual Operation and Maintenance

The scope of work stipulates bidder to provide comprehensive Operations and Maintenance (O&M) of
SPV plant along with grid connecting system for a period of 5 years from project commissioning and
preliminary acceptance. Bidders are required to submit separate price for 5 years of O&M and
applicable spares, the additional period shall start after completion of defects liability period.

During O&M period, KTL personnel shall have unrestricted entry to the solar plant and Control/inverter
Rooms any time. KTL may suitably depute its personals to associate with O&M activities. Bidder shall
assist them in developing expertise through their day to day O&M activities. All records of maintenance
must be maintained by the bidder which can be accessed by KTL. These records are to be handed over
to KTL after the O&M period of contract.

The Bidder shall be responsible for supply of all spare parts, repairs / replacement of any defective
equipment(s) at his own cost as required from time to time during the O&M period.

A template form for list of spares and consumables is presented in Annexure D, the bidder shall submit
this list along with its Techno - Commercial offers.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 46
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Bidders shall submit list of spares recommended by respective project component suppliers (OEM). The
list shall include spares required for 5 years of operation, with justification on the recommended spares
and consumable quantities.

The list of spares provided by the bidder shall be considered as inventory up to the end of Warranty/
Defects Liability Period (DLP). If the spares are consumed during this period, bidder shall maintain the
inventory spares as per the list till the end of warranty/ DLP. No cost shall be paid to the bidder on this
account.

6.3 Detailed Scope of Annual Operation and Maintenance:

The bidder shall be responsible for the Operation and Maintenance of the entire Solar PV plant along
with grid connecting system during the O&M period. The brief scope of works is listed below. The
details shall be further elaborated by the bidder in the O&M manual to be submitted to KTL for
approval.

 Ensuring successful operation of SPV Plant for optimum energy generation.

 Ensuring Breakdown maintenance, Preventive maintenance, overhauls, arranging visit of O&M


experts (when required) to maximize the availability of the solar plant.

 Daily work of the operators involves logging the voltage, current, power factor, power and
energy output of the SPV plant, temperature, logging down individual String & Inverter output
data once a day.

 The operator shall record monthly energy output of each Inverter, LT Panel, Solar Meter & HT
Meter and reports shall be prepared on performance of SPV plant.

 Submission of periodical reports to the owner on the energy generation& operating conditions
of the SPV plant.

 Ensuring Safety and protection of the plant by deputing sufficient security persons.

 Monitoring, controlling, trouble shooting, maintaining of records, registers.

 Supply of all type of spares, consumables and fixing /application of the same.

 Cleaning of the Solar plant including Inverter room on regular basis and as and when required.

 Cleaning of drains, cable tray, Inverter cooling Fan etc.

 Module washing as per as per approved schedule.

The bidder shall at their own expense provide all amenities to his workmen as per applicable laws and
rules.

The Bidder shall ensure that all safety measures are taken at the site to avoid accidents to his
employees or his Co-bidder’s employees.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 47
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Bidder shall immediately report the accidents, if any, to the Engineer in charge & to all the
concerned authorities as per prevailing laws of the state.

The Bidder shall comply with the provision of all relevant Acts of Central or State Governments
including payment of Wages Act 1936, Minimum Wages Act 1948, Employer's Liability Act 1938,
Workmen's Compensation Act 1923, Industrial Dispute Act 1947, Maturity Benefit Act 1961, Employees
State Insurance Act 1948, Contract Labor (Regulations & Abolishment) Act 1970 or any modification
thereof or any other law relating whereto and rules made there under from time to time.

In order to ensure longevity, safety of the core equipment and optimum performance of the system the
bidder should use only genuine spares of high quality standards (buy from OEM only).

Bidder shall Deploy Plant in Charge, adequate number of technical support staff and other supporting
personnel during the O&M period.

Bidder is required to maintain adequate O&M spares during the O&M contract period of the Solar PV
plant with the view to maximize availability of the plant. In case, Bidder uses mandatory spares
available with KTL and provided by KTL, the bidder shall have to return/replenish the spare(s) of the
matching quality, quantity and rating within shortest possible time.

At the time handing over of the plant by the bidder to KTL, the bidder shall handover equipment and
spares in healthy condition.

Bidder has to take Comprehensive Annual Maintenance Contract (AMC), for O&M Period, from OEM
for the following components:

 Module

 Inverter

 Plant Monitoring System/ SCADA

 DC/AC cable and other accessories

Bidder shall be responsible to carry out all test and work as required by statutory regulation in effect as
on date of Techno-commercial bid opening, during O&M period.

6.4 Insurance

6.4.1 Workmen’s Compensation Insurance

This insurance shall protect the Bidder against all claims applicable under the Workmen’s
Compensation Act, 1948 (Government of India). This policy shall also cover the Bidder against claims
for injury, disability disease or death of his or his Sub-Bidder’s employees, which for any reason are not
covered under the Workmen’s Compensation Act, 1948. The liabilities shall not be less than the
following:

Workmen's Compensation - As per Statutory Provisions

Employee's Liability - As per Statutory Provisions

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 48
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

6.4.2 Comprehensive General Liability Insurance

The insurance shall protect the Bidder against all claims arising from injuries, disabilities, disease or
death of members of public or damage to property of others, due to any act or omission on the part of
the Bidder, his agents, his employees, his representatives and Sub-Bidders or from riots, strikes and
civil commotion.

The hazards to be covered will pertain to all the Works and areas where the Bidder, his Sub-Bidders, his
agents and his employees have to perform work pursuant to the Contract.

7 RELEASE OF INFORMATION

The bidder shall not communicate or use in advertising, publicity, sales releases or in any other medium
photographs or other reproduction of the works under this contract, or description of the site,
dimensions, quality or other information, concerning the work unless prior written permission has been
obtained from the Purchaser.

8 COMPLETION OF CONTRACT

Unless otherwise terminated under the provisions of any other relevant clause, this contract shall be
deemed to have been completed at the expiration of the guarantee period, completion of maintenance
contract period, and fulfilment of all contractual terms and conditions.

9 LIMIT OF CONTRACT

Equipment supplied shall be complete in every respect with all mountings, fittings, fixtures and
standard accessories normally provided with such equipment and / or needed for erection, completion
and safe operation of the equipment as required by applicable codes though they may not have been
specifically detailed in the respective specifications unless included in the list of exclusions. All similar
standard equipment provided, shall be interchangeable with one another.

10 GENERAL

The Bidder shall be responsible for provision of health and sanitary arrangement more particularly
described in contract labour (regulation and abolition Act), safety precautions, etc. as may be required
for safe and satisfactory execution of the contract.

The Bidder shall fulfil all his obligations in respect of accommodation including proper facilities for the
personnel employed by them.

The bidder shall be responsible for the proper behaviour at site and observance of all regulations by the
staff employed by them.

Insurance for the labour engaged shall be the responsibility of the bidder till the equipment is taken
over after completion of works in full shape and completion of maintenance period, as per applicability,
by the KTL. The insurance of the labour engaged for maintenance of the plant by the bidder shall also
be the responsibility of the bidder and responsibility of those personnel engaged by KTL shall be taken

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 49
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

care by KTL. The bidder shall be responsible for settlement of insurance claims arising out of
accident/injury to staff employed by them.

11 SPECIFICATION FOR CIVIL WORK & MECHANICAL STRUCTURE

11.1 Site Preparation

The site preparation shall include all the work as required for installation of a utility scale solar PV plant
as per standard industry practices. The contractor should follow the safety guidelines according to the
rules and regulations.

This shall essentially include but not be limited to:

o Site cleaning before and after installation.

o Construction of cable trench, if required.

o Demolition of any obstacle, if required.

11.2 Module Mounting Structure (MMS)

This section covers the loads and design requirement of the structures and all other items required to
furnish and install a complete mounting structural system. For shed, Module mounting structure
material should be aluminium (Grade 6063-T6) and the load should be transfer on existing structure
purlin. For RCC roof, Module mounting structure material should be HDG steel (Hot dipped galvanised
steel) with minimum 80 micron coating layer/Aluminum. All aluminum structure member shall be
anodized as per relevant standard. All Connection of module mounting structure to existing purlin
should be zero seepage. No water leakage should happen during the lifespan of the project. The
complete MMS and connections shall be designed & submitted for KTL/Consultant approval before
start of work/fabrication. Module mounting structure should be designed to be compatible with robot
cleaner and have a docking station. If any water leakage found during and after the installation,
contractor shall be responsible for the damages for the material and goods if any and for rectification
of it.

Design Loads

Dead Load: The load obtained by summing up the weight of modules and self-weight of Structure
including struts, necessary fittings, etc. to be added as Dead load.

Wind Load: The wind load (positive and negative) normal to surface on the modules and wind load on
the structural members. The basic wind speed (i.e. design wind speed) of the site shall be taken as IS
875 Part-3. Design wind speed factors K1, K2, K3 and K4 shall be as per IS: 875-III, for all Modules
Mounting Structures (MMS). The pressure derived from the above parameters shall be considered as
minimum pressure and shall be further increased accounting the external and internal pressure
coefficients applicable for different slopes.

The bidder shall provide module mounting structure design in compliance with IS 8147 and shall
analyse the structure in staad.pro software. In addition, Manual design calculation shall be provide for
all sections and connection used in mounting structure.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 50
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Fasteners & Connections:

All Fasteners (nuts, bolts and washers) shall be of Stainless steel (SS304) conform to relevant IS code.
All module-mounting clamps shall be of Aluminium and shall be anodised as per relevant standard. The
module mounting structure rail should be attached to existing structure purlin with self-drilling screws.
Self-drilling screws/fastener with EPDM washer shall be used conforming to class 3 as per AS: 3566.1
and AS: 3566.2. All EPDM rubber shall have capability to withstand during high temperature variation.

11.3 Cable Trays & Accessories

Cable trays and the associated accessories including tray covers shall be Pre-fabricated type Hot Dip
Galvanized steel sheets. All load of cable tray should be transfer on existing structure purlin. No cable
to be exposed to sun and always to run in pipe, conduit or covered cable tray.
The nominal width of cable trays shall be 50, 100, 150, 300, 450, 600 and 900 mm. The cable trays shall
be supplied in standard lengths of 2500 mm.
Types of trays used are perforated type. The Flange height shall be considered for perforated type trays
as75/100 mm.
The thickness for cable trays shall be considered 2 mm and the thickness for cable tray cover shall be
considered 1.6 mm.
The maximum spacing between the rungs of the ladder type cable tray shall be considered as 250 mm.
Cable tray covers shall be provided for trays as indicated in the project drawings.
Accessories: The cable tray accessories are Vertical Elbows, Horizontal Bends, Adjustable Bends,
Crosses, Tees and Reducers, etc. All accessories shall have minimum bending radius of According to the
cable laid over it.
The scope covers all these trays and special accessories including covers, coupler plates, bolts, hinges
for all type of trays as listed in items.
Connecting piece or coupler plate is used to connect two trays & accessories.
All finished cable trays and accessories shall be free from sharp edges, corners, burrs and unevenness
with edge protection
Galvanizing: All cable trays, tray accessories, tray covers & tray supports including washers, etc. shall be
hot dip galvanized as per IS 4759. If the galvanizing of the samples found to be defective, the entire
batch of steel shall be re-galvanized at bidder’s cost.
The cables are to be layed through cable trays and make them monkey menace proof.
Cable Tray Support
The cable tray supporting structures shall be of steel and hot dip galvanized. This supporting structure
shall comprise of two parts, which shall be Vertical support channels & Horizontal supporting arms. This
Horizontal supporting arms shall be welded to the Vertical support channels to form the cable
supporting structure as shown in the drawing and this structure shall be welded to the Embedded Plate
(EP) on the wall in case of wall mounted cable trays, EP in the ceiling in case of ceiling mounted cable
trays and EP on floor in case of floor mounted cable trays to mount the cable trays. Bridge way in
bidder scope to mount cable from one unit to another unit. The complete support system shall be
designed & submitted for Client approval before start of work/fabrication.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 51
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Accessories/ Fittings

All accessories/ fittings required for making the installation complete shall be supplied by the bidder.
All Fasteners (nuts, bolts and washers) shall be of HDG of minimum grade 8.8 confirm to relevant IS
code. Special coated self-drilling screws/fastener with EPDM washer shall be used conforming to class 3
as per AS: 3566.1 and AS: 3566.2

11.4 Module Cleaning System

The contractor has to provide permanent piping system for module washing system. The solar PV plant
shall have water storage tank of capacity considering 3 day’s water requirement and minimum 2
cleaning cycles per month (although the cleaning cycles may vary with seasons/to meet PG dependent
on soiling loss fixed for plant). The water requirement shall be as minimum 2.5 litters/module. The RO
water shall be provided to contractor at one location of plant and contractor has to make permanent
pipeline arrangement for O&M purpose. The Module cleaning system is to be designed keeping in mind
future upgradability to robot cleaning system with docking station.
Suitable pumping system shall be provided to supply water for module washing purpose. The pump,
suction strainer, with pressure relief valve with return water to storage tank, pressure gauges, flow
meter, and isolation valve shall have permanent canopy arrangement to provide safety against rain.
The pipeline system should be complete with all fittings and other accessories i.e. elbow, tee, flow
meter, SS full bore ball valves, brass/SS quick release coupling suitable for water cleaning nozzle. All
fittings shall be brass threaded and UPVC brass threaded as per relevant standard. All GI/UPVC pipes
should be as per IS 1239 and IS 4985 of suitable grade and pressure class shall be used for entire water
supply system for module cleaning. If bidder shall use UPVC pipe then it shall not be direct contact with
sun light and can be installed in a tray with proper cover. The arrangement shall be in such a way that
water should be available at all points of module for cleaning with proper pressure as per OEM
guidelines so that cleaning of modules can be done properly and efficiently. The quick coupling point
should not be more than 12 meters from further most point of the module to avoid accidental
walkover on modules by cleaning workers. The module cleaning system after installation to be pressure
tested 1.5 times the designed pressure. Sufficient number of cleaning nozzles with female quick
coupling to be provided (10 Nos.)

11.5 Walk way & Support system.

1. All Walk way shall be of shall be of FRP confirm to relevant standards. The depth of fiber grate
should be minimum 25mm. The dead load of walk way material should be transfer on existing
structure purlin. The FRP material should have special coating for UV protection since all walkway
are exposed to sun all time. In addition, it should have capability on withstand against higher
temperature. All FRP material shall be fire resistance, should have Lower electrical & thermal
conductivity. The walking surface of walkway should be non-Skid. Excess distance between walk
ways and modules should not exceed Four meters horizontally for module cleaning.

 All FRP material shall be comply with ASTM D 3917 – 96.

 For cleaning of Modules maintenance person should walk on walkway only with help of safety
lifeline and as per O&M Manuals.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 52
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The nominal width of walk way shall be considered 350 mm to 400 mm.
Walkway Support
The walkway supporting structures material shall be Aluminium (Grade 6063-T6) and all load should be
transfer on existing structure purlin. Walk way support system should be provide at every 1 meter.
Connection of walkway support system to purlin should be zero seepage. This supporting structure
shall comprise of three parts, which shall be Vertical support, Horizontal supporting arms and struts
channel to provide horizontal surface/zero degree slope for walking surface. The complete support
system shall be designed and submitted to KTL/Consultant for approval before start of work/
fabrication. The walk way system to be completed first before commencement of any other work so
that the erection workers will not walk on the roof sheets.

Accessories/ Fittings
All accessories/ fittings required for making the installation complete shall be supplied by the bidder.
All Fasteners (nuts, bolts and washers) shall be of Stainless steel (SS304) conform to relevant IS code.
Special coated self-drilling screws/fastener with EPDM washer shall be used conforming to class 3 as
per AS: 3566.1 and AS: 3566.2

11.6 Life line & Safety Rail (Guard Rail)

The contractor has to provide permanent lifeline system over roof for safety purpose. The rope of
lifeline shall be of SS 316. The lifeline should be properly fixed with existing shed purlins. Lifeline shall
be provided parallel to all walkway lines. The support system for lifeline shall be of steel/MS with hot
dip galvanization. All other accessories for fixing lifeline shall be of SS 304. The contractor has to submit
design of lifeline to KTL/Consultant before manufacturing/supply.

The handrail shall be provided on the periphery of the shed for protection against fall. All railing shall
be of steel/MS and should be hot dip galvanised as per IS 4759. The fixing arrangement should be base
plate type and it should be fixed in such a way that all loads of handrail should be directly transfer to
the existing shed purlins. All fixing location of structure should be properly sealed by using EPDM
rubber so that water leakage can be prevented.
Contractor can propose other solution for preventing water leakage inside the shed but in any case,
there should not be any water leakage within the plant/shed through the life of project. If any water
leakage found during and after the installation, contractor shall be responsible for the damages for the
material and goods if any and for rectification of it.

11.7 Ladder.

Ladder shall be SS/Al. All Ladders shall be designed and submitted for client approval before start of
work/fabrication. A staircase would be preferred where ever possible.
Accessories/ Fittings
All accessories/ fittings required for making the installation complete shall be supplied by the bidder.
All Fasteners (nuts, bolts and washers) shall be of HDG of minimum grade 8.8 conform to relevant IS
code.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 53
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

11.8 Technical Requirements Supply

 All MS members’ materials should be Hot Dipped Galvanized (Minimum 80 micron coating) for
corrosion protection.

 All SS Material to be SS304 and aluminum to be anodized.

 All members should meet minimum galvanization as per relevant Standards.

 The structure shall be designed by considering maximum Wind speed of as per IS-875-part-3.
Foundation and mounting system shall be provide for all electrical equipment as per relevant IS
standards.

11.9 Plumbing work

All plumbing material should be GI/UPVC. It shall be used for all portable water distribution supply and
plumbing works.

All fittings of plumbing work shall be of brass as per relevant standard.

The Sintex or equivalent make PVC storage water storage tank conforming to IS: 12701 shall be
provided with requirement, complete with all fitting including float valve, stop cock, flow meter etc.
Masonry Work.

Brick works shall be using at least class designation 7.5 of approved quality as per IS: 1077, IS: 2212 and
IS: 3495. Concrete blocks shall be of minimum compressive strength of 7.5 N/mm2 and shall be of
Grade-A as per IS: 2185.Stone masonry work with hard stone in building works, foundation, plinth and
drains shall be Coursed Rubble or Random Rubble masonry work with stone of good quality and
durability. The masonry surface shall be plastered with minimum 18mm plaster in case of MCR walls.
The stone masonry work shall be in line with IS: 1597, IS: 1122 and IS: 1126.

The cement mortar for all kind of masonry work shall be in the ratio 1 cement and 6 sand by weight.
Bricks of class designation 5.0 and 3.5 may be permitted to have slight distorted & rounded edges
provided no difficulty shall arise on this account in laying of uniform courses in non-load bearing
structures and shall be subjected to approval of NUIPL. Tolerances on dimensions up to +/- 8% shall be
permitted. Dimension test to be carried out as per IS code.

Suitable damp proof course shall be provided the proportion of cement, sand & aggregate shall be
1:2:4 using 6 mm down stone chips with a water proofing admixtures. The thickness of damp-proof
course shall be minimum 40 mm.

11.10 Plastering

All external surfaces shall have 18 mm cement plaster in two coats, under layer 12 mm thick cement
plaster 1:5 and finished with a top layer 6 mm thick cement plaster 1:6.White cement primer shall be
used as per manufacturer’s recommendation.

11.11 Grouting

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 54
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Cement mortar (1:2) grout with non-shrink additives shall be used for grouting below base plate of
column. The grout shall be high strength grout having a minimum characteristic compressive strength
of min 30 N/mm2 at 28 days.

11.12 Structural Works

For the steel structure, all hot rolled structural steel design shall be carried out as per IS 800. Structural
steel shall conform IS 2062, Pipe shall be as per medium/high grade of IS 1161, Chequered plates shall
conformed to 3502 and Hollow steel sections for structural use shall conform to IS: 4923.

All aluminium works shall be as per relevant standard. The grade of aluminium shall be 6063-T6 or
equivalent. All aluminium structural members shall be anodized as per relevant standard. Contractor
has to submit all MTC to KTL/consultant before supply/production.

11.13 Reinforced Concrete Structure, Allied Works and Foundation

All RCC works shall be design mix as per IS: 456-2000. For structural concrete items, Ordinary Portland
cement (43 Grade) conforming to IS: 8112 and Fly ash based Portland pozzolana cement conforming to
IS: 1489 (Part1) shall be used for superstructure. Type of cement for sub-structures shall be decided
based on the final Soil Investigation report.

Coarse aggregate for concrete shall be crushed stones chemically inert, hard, strong, durable against
weathering of limited porosity and free from deleterious materials. It shall be properly graded. It shall
meet the requirements of IS: 383.

Sand shall be hard, durable, clean and free from adherent coatings of organic matter and clay balls or
pellets. Sand, when used as fine aggregate in concrete shall conform to IS: 383. For plaster, it shall
conform to IS: 1542 and for masonry work to IS: 2116 Reinforcement steel shall be of high strength
deformed TMT steel bars of grade minimum Fe-500 and shall conform to IS: 1786. Ductile detailing in
accordance with IS: 13920 shall be adopted for superstructure and substructure of all RCC buildings
/structures.

The following minimum grades of concrete for design mix and nominal mix shall be adopted for the
type of structures noted against each unless not specified elsewhere.

M 25 - All RCC structural elements, precast concrete and foundation.

The bidder shall carry out the design mix of M-25 grade concrete on priority. The design mix shall be
approved from Client before start of work.

IS: 2502 Code of Practice for Bending and Fixing of Bars for concrete Reinforcement must be complied
for reinforcements. IS: 5525 and SP: 34 shall be followed for reinforcement detailing. A minimum 75
mm thick PCC shall be provided below RCC wherever RCC is laid over the ground. Proper and sufficient
formwork/shuttering shall be provided for the required period as per IS: 456.

11.14 List of Applicable Indian Standards for Civil & Structure Work

i. IS:2062 - Hot Rolled Steel for Medium and High Tensile Structural Purposes
ii. IS:1079 - Hot Rolled Carbon Steel Sheet and Strip

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 55
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

11.15 IS:811 - Cold Formed Light Gauge Structural Steel Sections

iii. IS:513 - Cold Reduced Low Carbon Steel Sheet and Strip
iv. IS:808 - Dimensions for Hot Rolled Steel Beam, Column, Channel and Angle Sections
v. IS:1730 - Dimensions for Steel Plates, Sheets Strips and Flats For General Engineering
Purposes
vi. IS:8910 - General Technical Delivery Requirements for Steel and Steel Products
vii. IS:813 - Scheme of Symbols for Welding
viii. IS:1364 - Hexagon Head Bolts, Screws and Nuts Of Product Grades A And B
ix. IS:1367 - Technical Supply Conditions for Threaded Steel Fasteners
x. IS:1368 - Dimensions for ends of parts with external ISO metric threads
xi. IS:2016 - Plain Washers
xii. IS:2629 - Recommended Practice for Hot-Dip Galvanizing of Iron And Steel
xiii. IS:2633 - Method for Testing Uniformity of Coating on Zinc Coated Articles
xiv. IS:4759 - Hot-Dip Zinc Coatings on Structural Steel and other Allied Products
xv. IS:4826 - Specification for Hot-Dipped Galvanized Coatings on Round Steel Wires
xvi. IS:5216 - Recommendations on Safety Procedures and Practices in Electrical Work
xvii. IS:1646 - Code of Practice for Fire Safety of Buildings (General): Electrical Installations
xviii. NEC 318 - Cable trays
xix. IS 875: Part 1&2 -Code of practice for the design loads for building and structure.
xx. IS 875: Part 3 - Code of practice for the design loads for buildings and structures-Wind
loads.
xxi. IS 800: 2007 - Code of practice for use of structural steel in general building
construction.
xxii. IS 4759 - Hot-dip zinc coatings on structural steel and other allied products.
xxiii. IS 8147 - Code Of Practice For Use Of Aluminium Alloys In Structures
xxiv. IS 801 - Code of practice for use of Cold formed light gauge steel structural members in
general buildings.
xxv. IS: 811 - Cold Formed Light Gauge Structural Steel Sections

SPECIFICATION FOR ELECTRICAL SYSTEM & EQUIPMENT

12 SOLAR PV MODULE

12.1 GENERAL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 56
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

KTL is looking for developing a 2.6 MWp/2.0 MW solar PV project with crystalline solar PV Modules for
metal roof and bifacial modules for RCC roof with minimum 18.5% efficiency. KTL would like to invite
offers based on preferred list of module manufactures presented in this section and the performance
parameter presented in below sections. Three times IEC certification BOM / PVEL (DNV-GL)- Reliability
test BOM shall be consider mandatory for Indian module manufacturers and preferable for imported
module manufactures. Prefer would be given to modules BOM which have been Extended IEC tested or
BOM which is part of CDF submitted to PVEL (DNV-GL)/RETC for reliability testing. The proposed
modules will be evaluated based on efficiency, first year and annual degradation, quality, performance
and cost. Incase EPC is not able to procure such modules they can propose to bid BOS EPC and KTL will
give modules to EPC as Free supply.

12.2 QUALITY CERTIFICATION

The solar PV modules shall typically be tested for durability and reliability according to standards
developed by the International Electro - Technical Commission. Extended Standards IEC61215 (for
crystalline silicon modules) include, amongst others, tests for thermal cycling, humidity and freezing,
mechanical stress and twist, hail resistance and performance under fixed test conditions. The below
table summarizes major PV quality standards that all the modules shall comply. These tests are an
accepted quality mark and indicate that the modules can safely withstand extended use. In case of
PERC module should be tested for LETID (Light and elevated Temperature Induced Degradation) not to
be confused with LID.

Crystalline silicon terrestrial photovoltaic (PV) modules- Design


Extended IEC 61215 qualification and type approval
Minimum of 3 times IEC certified (preferable)

IEC 61853 - Part 1 PV module performance testing and energy rating

IEC 61730 PV module safety qualification

IEC 60364-4-41 Protection against electric shock

IEC 61701 Resistance to salt mist and corrosion

IEC 60904 Photovoltaic devices

EN 50380 Datasheet and nameplate information for photovoltaic modules

IEC 62790 Junction boxes for PV Modules – safety requirements & test

Comply with the National Electric Code (NEC), OSHA and the
UL 1703 National Fire Prevention Association. The modules perform to at
least 90% of the manufacturer’s nominal power.

IEC 62804 (draft std.)


Equivalent TUV-Rhineland For PID Free Module
std. PID Free Module

The certified product conforms to the EU health, safety and


Conformité Européenne (EC)
environmental requirements.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 57
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

BIS certificate For PV Modules as per new guidelines

PVEL Test report Reliability test report for minimum 25 years by DNV-GL (preferable)

12.3 PRODUCT GUARANTEE

The Bidder shall be legally bound to provide a linear performance guarantee ensuring that entire plant
will be fully functional with desired output for minimum 10 years from the date of commissioning. PV
modules shall be guaranteed for workmanship and performance in-line with that provided by
manufacturer and shall be industry accepted. Defects liability shall include but not limited to glass,
frame bowing, de-lamination, water ingress, junction box arching, hot spots, etc. The product
guarantee will not be limited for modules but will also include termination connectors, cables and all
associated accessories. In the event of failure during guarantee period, manufacturer shall replace
module free of cost or refund the then current market price of modules. The modules with product
warranty of 25 years shall be given preference in bid evaluation criteria.

12.4 NOMINAL POWER GUARANTEE

In addition to the product guarantee, manufacturers shall grant linear nominal power guarantees for a
minimum period of 25 years. Under these guarantees manufacturer shall ensure that module will
deliver nominal power output based on manufacturer provided annual degradation rate. The output
shall be measured at string level. The nominal power guarantees shall be in lieu of manufacturing
defects and workmanship: the minimum set terms shall be as - Power warranty shall be 91% for
minimum 10 years and 82% for minimum 25 years. Modules with lower degradation will be give
preference.

12.5 PRODUCT LIFE

Although the products will be guaranteed for minimum 10 years and power performance will be
guaranteed for minimum 25years. The design life for the modules is expected to be over minimum30
years from commissioning. The manufacturers shall submit accelerated lifetime laboratory test reports
upon winning the bid for the Bidder. PVEL tested module by DNV-GL shall be given preference.

12.6 NOMINAL POWER RATING

For the development of proposed 2.6 MWp/2.0 MW plant, the module peak power rating is greater
than 370 Wp. The system voltage should be 1500 V. The Bidders are expected to offer respective
ratings based on manufacturer’s production availability and compliance with the client’s benchmarked
track record. Linear warranty will be measured annually against committed degradation for the defined
period.

12.7 NOMINAL POWER TOLERANCE


The nominal power tolerance of modules shall be positive power tolerance only. No negative tolerance
of module shall be accepted by KTL. The range of positive tolerance shall be up to +3%. Modules with
higher positive tolerance shall be give preference.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 58
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

12.8 EFFICIENCY

Minimum acceptable efficiency of all the modules under standard test conditions is 18.5%. However,
preference may be given to modules having higher efficiency than desired.

12.9 TEMPERATURE COEFFICIENTS

Variation in temperature has a significant effect on electrical parameter of PV modules. The following
are the benchmark for the maximum temperature coefficients for all the proposed modules by
manufacturers:

 Temperature Coefficient of Pmpp 0.38%/°C (for Crystalline)

 Temperature Coefficient of Voc - 0.30%/°C (for Crystalline)

12.10 MODULE MANUFACTURERS EXPERIENCE BENCHMARKS

In the event Bidder proposes alternate module to the preferred list, minimum experience benchmark
for the proposed modules shall be:

 Manufacturers shall have a production track record for a minimum of five (5) years
with having executed a single order of minimum 20 MWp of crystalline modules for a
single project.

 Modules proposed by the Bidder shall have a minimum operational track record of five
(5) years preferably in the Indian like climatic conditions. Offers shall be supported by
client testimonial for technical performance. Incase 5 year track record is not available
reliability reports should be provided for the CDF which includes the proposed BOM.

12.11 SPECIFIC CONSTRUCTION REQUIREMENTS

In addition to the best construction requirements of respective manufacturers, the following are the
specific requirements for all the crystalline modules:

 Bidder shall provide spare module additionally with 2% of total numbers of modules proposed
for 2.6 MWp solar plant technology wise.

 Current binning of modules shall be employed so that current mismatch of modules in a pallet
does not exceed 0.1 A. Different colour codes shall be provided on the modules as well as
pallet for identification of different bins. Minimum five nos. of bins will be allowed for each
module rating.
 All the modules shall be equipped with IP68 or higher protection level junction box and
appropriately sized output power cable of symmetric length with twist locking connectors.

 Each module should have two 4/6 sq.mm stranded UV resistant output cables each terminated
with connectors adaptive to MC4 type connector directly. MC4 type connector should be TUV

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 59
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

certified. The positive (+) terminal has a male connector while the negative (-) terminal has a
female connector. For 1500V modules are used, the connecting cable shall be as per EN-50618.

 Walking on modules will not be allowed and modules should be replaced with new once if
found.

 SPV module shall perform satisfactorily with temperatures between -10° C and +60° C.

 The module should also be PID resistance.

 Fill factor for proposed PV modules shall not be less than 0.7.

 In order to minimize power loss due to partial shading on modules, all modules shall be
equipped with bypass diodes. Surge protection devices to be provided at array junction
box/combiner box and modules shall be provided with minimum (03) bypass diodes.

 Modules shall be capable of withstanding a wind pressure of 2400 Pa or the local wind loading,
whichever is greater. The Anodised Aluminim frame should be of minimum 36mm size.

 Modules may be subjected to high intensity hail storms thus appropriate measures should be
taken for selecting glass. The Glass thickness should not be less than 3.2mm.

 Module frames shall be corrosion resistant and shall have adequate holes for mounting, water
drain and connecting ground conductor. All modules shall be appropriately grounded.

 All the modules in the PV plant should be arranged in a way so as to minimize the mismatch
losses.

 The minimum clearance between the lower edge of the modules and Shed/RCC shall be
minimum as per OEM Guidelines. All installation of modules shall be as per OEM guidelines.
Bidder shall verify all terms and conditions for maintaining material and Linear power output
warranty.

 Each PV module used in any solar power project must use a RF identification tag. The following
information must be mentioned in the RFID used on each module (This can be inside or outside
the laminate, but must be able to withstand harsh environmental conditions.) Following
information shall be available within RFID tag.

o Name of the manufacturer of PV Module

o Name of the Manufacturer of Solar cells

o Month and year of the manufacture (separately for solar cells and module)

o Country of origin (separately for solar cells and module)

o I-V curve for the module at Standard Test Condition (1000W/m², AM 1.5, 25⁰ C)

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 60
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

o Wattage, Im, Vm and FF for the module

o Unique Serial No and Model No of the module

o Date and year of obtaining IEC PV module qualification certificate ix. Name of the test
lab issuing IEC certificate

 Other relevant information on traceable of solar cells and modules as per ISO 9000.

 KTL will appoint third party inspector for testing of Solar modules during manufacturing, The
contractor to coordinate the manufacturing dates of solar modules from the manufacturer
and intimate the dates to KTL at least 15 days in advance

 Module manufacture should have approved from BIS.

Bidder should be submit from module supplier to submit comfort letter that the BOM used
for modules being supplied is same as per the CDF used for obtaining IEC and other
certifications.

12.12 NAME PLATE

All individual modules which shall provide the information given below for identification. They shall be
clearly visible and shall not be hidden by equipment wiring. Type of labels and fixing of labels shall be
such that they are not likely to peel off/ fall off during the life of the panel.

o Manufacturer Name

o Model Number, Serial Number

o Overall Dimensions(WxL x D)

o Weight (kg)

o Maximum Power (PMAX), Voltage (VMP), Current (IMP)

o Short Circuit Current (ISC), Open Circuit Voltage (VOC)

o Main System Voltage

o Reference Bifacial factor (for Bifacial Module)

o Relevant standards, Certification lab. Name

o Warnings, if any

12.13 SUBMISSION

Upon winning the Contract the Bidder shall submit following manufacturer’s documents:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 61
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 IEC certificate

 3 times IEC Certificates (if applicable and must be for Indian manufactures)

 MQP & FAT Document

 Warranty Documents

 3rd party verified .PAN Files

 Technical literature giving complete specifications and information of modules

 Handling plan of modules right through from loading at manufacturer’s factory to installation.

 General Arrangement drawing of module, showing front and rear view, overall dimensions,
installation plans, termination arrangements, packing dimensions and weights.

 Bill of material

 Linear power generation certificate for minimum 25 years

 Bifacial factor test report (for Bifacial module)

 LETID test report (if applicable)

 Module Cleaning guidelines

 Independent test characteristics

 Current verses voltage at various irradiance levels

 Power verses voltage at various irradiance levels

 Open circuit voltage verses irradiance under standard test conditions

 Short circuit current verses irradiance under standard test conditions

 Power verses temperature variation

 Open circuit voltage verses temperature variation

 Short circuit current verses temperature variation

 Installation manual and flash lists of the modules

Note:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 62
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

i. The above mentioned technical specs are minimal in nature, the seller on the basis of its
experience and expertise can offer better specifications, mentioning in detail such
deviations with relevant justifications.

ii. Each inverter should use only one type of module model. The vendor confirms that the
distribution of quantities between individual module models complies with the same.

iii. Bidder shall use one type of module for shed and one type of module use for RCC roof.
Bidder can not consider more than one type of module with respect to Shed and RCC
roof.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 63
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

13 SOLAR INVERTER

In view of project size, Operations and Maintenance requirements, KTL is essentially looking for
developing its 2.6 MWp/2.0 MW, for 1000V solar PV project with string inverters. It is essential for the
plant to have a cumulative inverter AC rating/ capacity corresponding to the maximum Pnom ratio of
1.30. KTL would like to invite offers based on track record benchmarks and performance parameter
presented in below sections. Vendor have to propose string inverter for the project. For string
inverters, the minimum capacity shall be greater than and equal to 50 KW for shed and for RCC roof
minimum capacity shall be greater than and equal to 20 KW respectively. Bidder shall be use optimiser
with Inverter where shadows area cover in mostly morning and evening time for achieving guaranteed
generation.

13.1 Quality Certification:

Inverters shall be compliant to most recent standards (and latest amendments if any) developed by the
IEC and EN. The below table presents a non-exhaustive list of standards to which inverters should
conform according to European practice.

EN 61000-6-2:2005 Electro - Magnetic Compatibility (EMC). Generic standards. Immunity for


industrial environments.

EN 61000-6-4:2007 Electro - Magnetic Compatibility (EMC). Generic standards. Emission


standards for industrial environments.

IEC 62109 -1 &2 Safety of power converters for use in PV power systems

IEEE 1547 / IEC 62116 Utility-interconnected photovoltaic inverters- Test procedure Islanding
prevention measures

IEC 61683: 1999 Photovoltaic systems - Power conditioners - Procedure for measuring
efficiency.

IEC 60068/ Equivalent Environmental Testing


BIS Standard

IEEE 693-2005 Recommended practice for Seismic Design of Equipment

IEC 62116: 2014 Testing procedure of Islanding Prevention Methods for Utility-Interactive
Photovoltaic Inverters.

IEC 60529 Ingress Protection

IEEE 519 - 2014 Recommended practice & requirements for harmonic control in electrical
power system.

EN 53030 Overall efficiency of grid connected photovoltaic inverters

EN 61439-1: 2011 Low voltage switchgear

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 64
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

IEC / EN 60730 -11 For software

Local Grid Code For LVRT, HVRT & Night time reactive power, CEA Guidelines 2012 or
latest

BDEW 2008 & Grid Code Technical guidelines for generating plant connected to medium voltage
compliance network (If available)

13.2 Power Quality Requirements

The power quality requirements for utility scale grid connected solar power generation are under
development. However, the following shall be non-exhaustive specific requirements:

 Nominal Output Voltage frequency: 50 Hz

 Continuous operating frequency: 47.5 to 52 Hz

 Continuous operating AC voltage range: ± 10%

 Operating power factor range: ± 0.8 lead or lag

 Maximum Input DC Voltage: 1500/1000 V

 Total harmonic distortion limits on AC side: less than 3%.

 Maximum Ambient temperature: At least 50 ° C

 Humidity: 95 % non-condensing

 Maximum noise level (at 1 mtr distance): 75 db

 DC Injection into the grid: DC injection shall be limited to 1% of the rated current of the
inverter as per IEC 61727.

 Flicker: As per IEC61000

13.3 Cooling and Ventilation

To prevent the maximum permissible temperature in the inverter room from being exceeded because
of internal heat emission of inverters and other auxiliaries in the inverter room, the inverter room in
the PV station shall be proper cool. Heat ventilation calculation shall be provide by bidder and get
approval from Consultant/KTL.

The Ventilation plant capacity and air quality of inverter room shall be as per inverter and other
auxiliary’s manufacturer’s recommendations. Filter banks at the air inlet of the inverter room shall be
provided to prevent dust ingress.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 65
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

13.4 Design Basis

The Bidders are expected to independently understand and analyze the site conditions prior to system
configuration. The Bidder may offer the Owner with multiple options of system configurations based on
product availability and capacities. Subsequently, it will be the Owner’s call for selecting most optimum
system. However, the entire project shall have uniform capacities, makes and configurations.

13.5 Efficiency Benchmarks

Minimum acceptable peak efficiency shall be 98.3%, however preference may be given to inverters
having higher efficiency than desired. European efficiency though an accepted European method of
measuring inverter efficiency for Europe, may also be significant for Indian climatic conditions. It thus
should be >98% for proposed inverters.

13.6 Product Warranty

The Bidders shall be legally bound to provide a performance guarantee ensuring that entire plant will
be fully functional with desired output for 60 months from the date of commissioning. Consequently,
irrespective of the manufacturer’s guarantee to EPC contractors (Bidders) the inverters will be
guaranteed for a minimum period of five years. This warrantee will not be limited only for inverters but
will also include all associated accessories, instrumentation and control. Bidder shall provide 99%
uptime warranty for 10 years from Inverter manufactures.

13.7 Extended Warranty

It is essential that the product should give a consistent performance for 25 years life cycle of the
project. All the Bidders should give an option of extended manufacturer’s comprehensive warranties
with onsite support beyond the guarantee period of 5 years up to 25 years. Bidder shall provide 10
years warranty for all Chinese make Inverter and 5 years warranty for all European make inverter. The
Bidders are required to maintain adequate inventory spares on site during the product warranty period
and extended warranty period. It is expected manufacturers shall provide satisfactory training to
Owner’s technical team at regular interval as decided by the Owner.

13.8 Experience Benchmarks

Manufacturers shall have a production track record for a minimum of one (1) years with having
executed a single order of minimum 2 MW.

Inverters proposed by the manufacturer shall have a minimum operational track record of six months
preferably in the Indian like climatic conditions. Offers shall be supported by Owner testimonial for
technical performance.

13.9 General Requirements of Inverter

In addition to the best construction requirements of respective manufacturers, following are the
specific requirements for all proposed string inverters:

 Transformer-less inverters shall be preferred.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 66
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 The Inverters shall be tested against the sand storm and dust according to IEC 60068-2-68

 The Inverter shall remain connected to the grid as per Central Electricity Authority Technical
(standards for connectivity to the grid) regulation 2007 with all latest amendments and its
components shall be designed accordingly.

 Maximum Power Point Tracker (MPPT) - Inverter configurations should be equipped with
multiple independent MPPT trackers resulting in enhanced system performance. One MPPT for
two strings will be Preferable.

 Inverters shall be capable of operating at varying power factor preferably in between 0.8 lag to
0.8 lead and shall be able to inject or absorb reactive power.

 Inverters shall operate at ambient temperature of 50° C without deration.

 Inverters shall be equipped and capable of low and high voltage ride through and frequency
feature.

 Internal Surge Protection Device (SPD) (minimum type-2) shall be provided in the Inverter on
DC and AC side. It shall consist of Metal Oxide Varister (MOV) type arrestors. The discharge
capability of the SPD shall be at least 12.5kA at 8/20 micro second wave as per IEC 61643-12.

 Inverters should be equipped with appropriately designed EMC filters at either ends and sine
wave filters at the AC end.

 Inverter shall be facility to reactive power control at night, active and reactive power control,
power ramp rate control.

 Inverter shall have string level monitoring for current and displayed in Plant monitoring
system/SCADA management and I-V curve testing (if applicable).

 Surge Protection Device

 DC Disconnector switch

 AC Disconnector switch (if available)

 AC Surge Protection Device

 Power, Voltage, Amps Monitoring

 Inverters shall be equipped with all required hardware for data collection and communication
with SCADA system/ Plant Monitoring System. It shall have a facility of direct external
communication and control to client.

 Inverters shall be equipped with appropriately sized forced ventilation system.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 67
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Inverters with outdoor duty installation shall have a minimum degree of protection of IP65.
Also additional shed (covered from sides, back & top) to be provided for the inverter for
outdoor installation.

 The string inverter enclosure protection class shall be IP 65 or better protection.

 The string inverter should be placed inside a canopy shed with no rainfall and direct contact in
sunlight, if installed in open.

 EPC contractor has to submit temperature endurance test report of complete assembly during
detail engineering stage.

 Inverters shall be equipped with a key switch for start and stop operations. For viewing various
data related to inverter, provision of display shall be made within the inverter. Inverter shall
also display all major error codes in case of any abnormality during the operation.

 Inverter shall be suitable for grounding of positive or negative pole if required. Protective
earthing arrangements shall also be provided.

 The inverter should be designed for parallel operation through galvanic isolation. Solid state
electronic devices shall be protected to ensure smooth functioning as well as ensure long life of
the inverter.

 In case auxiliary supply of Inverter is met internally, then it should have sufficient power
backup to meet the LVRT requirement. EPC contractor needs to submit the detail auxiliary
supply arrangement for inverter during detail engineering stage.

 Bidder has to provide necessary minimum clearance as per manufacturer’s recommendation


from the nearest wall or any other equipment.

 The Inverter shall include appropriate self-protective and self-diagnostic feature to protect
itself and the PV array from damage in the event of inverter component failure or from
parameters beyond the inverter safe operating range due to internal or external causes. The
self-protective features shall not allow signals from the inverter front panel to cause the
inverter to be operated in a manner which may be unsafe or damaging. Faults due to
malfunctioning within the inverter, including commutation failure, shall be cleared by the
inverter protective devices.

 The inverter must be self-managing and stable in operation.

 In case of grid failure, the Inverter shall be re-synchronized with grid after revival of power
supply. Bidder to furnish the time taken by Inverter to be re-synchronized after restoration of
grid supply during detailed engineering.

 Inverter shall have active power limit control, reactive power and power factor control feature.
Plant operator shall be able to provide (manual intervention) Active power, reactive power and

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 68
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

power factor control/limit set point local control display unit (or Laptop computer). All required
hardware and software required for this purpose shall be provided by Bidder.

 Inverter shall have thermal overloading protection to prevent failure of switching devices (i.e.
IGBT) and other components of Inverter. Inverter shall automatically regulate/limit the power
output in order to reduce the Inverter cabinet and switching devices temperature. Bidder to
submit the Inverter Output power vs ambient temperature curve during details engineering
stage.

 Inverter shall have protection against:

 AC / DC over Current

 Synchronous loss protection

 Cooling system failure protection

 PV array ground Fault monitoring and detection

 PV array insulation monitoring with sequential fault monitoring

 Over Temperature protection

 AC and DC under & over Voltage protection

 Reverse Current

 Type 1+2 Surge protection for AC, DC, auxiliary and control circuits

 LVRT

 Anti-islanding protection

 Grid monitoring

 PID recovery function

 PV String Current Monitoring

 Leakage current protection

 Ground fault monitoring

13.10 Modes of Operation

Standby Mode:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 69
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The control system shall continuously monitor the output of the solar power plant until preset value is
exceeded & that value to be indicated in datasheet.

Basic System Operation (Full Auto Mode):

The system shall automatically ‘wake up’ in the morning and begin to export power provided there is
sufficient solar energy and the grid voltage and frequency is in range. The inverter should also
automatically wake up after grid power failure(power cut).

Maximum Power Point Tracker (MPPT):

MPPT control algorithm shall adjust the voltage of the SPV array to optimize solar energy fed into the
grid.

Sleep Mode:

Automatic ‘Sleep’ mode shall be provided so that unnecessary losses are minimized at night. Bidder to
provide threshold dc voltage of the inverter to enter in sleep mode and back to standby mode in the
technical datasheet. The power conditioner must also automatically re-enter standby mode when
threshold of standby mode reached.

During evening and night (non-solar generation hours) the inverter shall be in sleep mode in order to
minimize the internal power loss. Maximum loss in sleep mode shall be less than 0.05% of inverter
rated power.

Maximum Power Tracking:

Maximum power point tracker shall be integrated in the power conditioner unit to maximize energy
drawn from the Solar PV array. The MPPT should be microprocessor based to minimize power losses.
The details of working mechanism of MPPT shall be provided by the Bidder. The MPPT must have
provision for constant voltage operation.

String Inverter:

 String inverter shall have suitable communication port (RS485/TCP-IP/PLC) for SCADA/ Plant
Monitoring System integration. All necessary hardware, software and accessories used for
communication with SCADA/ Plant Monitoring System (including Data logger if supplied) at
both the ends shall be provided by the bidder.

 String inverter shall have monitoring capability and reporting to SCADA/Plant Monitoring
system. Any special software if required for this purposes shall be provided for local and
remote monitoring and report generation.

 Anti-PID device along with all hardware and communication cable/device shall be provided or
Inverter should have inbuilt PID recovery function. Data logger used in Anti-PID device shall be
integrated with SCADA system/Plant Monitoring system.

 DC fuse requirement for PV string at string inverter end shall be as per string
manufacturer/system requirement and same shall be finalized during detail engineering stage.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 70
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Provision for DC isolator switch inside (in-built) or Outside String Inverter shall be provided as
per string inverter manufacturer practice.

 Provision for AC electrical isolation device (such as MCB/MCCB) inside (in-built) or Outside
String Inverter shall be provided as per string inverter manufacturer practice.

 Local Display unit for viewing important parameters, configuration and troubleshooting
purpose shall be provided as per string inverter manufacture practice.

13.11 Earthing of Inverters

System earthing of inverter shall be applied as per recommendations of inverter manufacturer. The
detail specification for panel earthing for safety has been mentioned elsewhere in this specification.

13.12 Submission

Upon securing the project, the Bidder shall submit following manufacturer’s documents for the
inverters opted.

 GTP

 Electrical schematic drawings

 Key component list / specification / Make / life cycle

 Inverter & its component’s Reliability Evaluation Report

 Temperature de-rating factor of main component

 QAP

 FAT Procedure & Report

 Type Test Report

 PID recovery function document

 General Arrangement drawing showing front and rear view, overall dimensions, installation
plans, termination arrangements, packing dimensions and weights.

 Installation & O&M manual

 Independent test characteristics

 Inverter efficiency verses relative power.

 Inverter efficiency versus temperature.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 71
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Total efficiency verses Standardized MPPT power.

 Temperature de-rating curve of the Inverter

Makes

As per Annexure- A

14 STRING MONITORING BOX (In case of required)

SMBs are used in multi-string photovoltaic systems to combine the individual strings electrically and
connect them to the Inverters. It shall have protection devices to protect the PV modules from
current/voltage surges. SMB should be capable to monitor the individual string currents, voltage and
total current of all the strings connected to SMB. The no. of strings to be combined to single input of a
SMB shall be limited to maximum two (02).

Voltage rating of the selected component shall be 1500V (min) as per system requirement.

14.1 Quality Certification:

String Combiner Boxes shall be compliant to most recent standards (and latest amendments if any)
developed by the IS, IEC and EN. Regulations applicable in the area where equipment is to be installed
shall be followed. The below table presents an on-exhaustive list of standards to which junction boxes
should conform.

IEC 61730 PV component standards

IEC 60664 Creepage distances and clearances

IEC 50548 Junction boxes

UL-1741 Combiner boxes

IEC 529 Degree of protection provided by enclosures

UL-SU 6703 Fuses

EN 60715 Chromated DIN Rail

UL 94 Fire Resistant/ flammability

UL 746C UV Resistant

IEC 62262 Mechanical Impact Resistance

IS 2147/IEC 60529 Enclosure Protection

IEC 61643-12 Surge Protection

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 72
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

IEC 62208 Enclosure for low voltage Switchgear and control gear assemblies

IEC 60439-1 Low voltage switchgear and control gear assemblies Part 1:
General Rules

IEC 60364-7-712 Requirements for special installations or locations- Solar PV


power supply systems

Preference shall be given to manufacturers with maximum quality certifications for example by TUV,
CE, UL, etc.

14.2 General

o SMB shall be equipped with appropriately sized fuses on the positive side with inverters
with appropriate grounding as per Inverter manufacture guideline.

o SMB shall be equipped with monitoring hardware so as to monitor status and performance
of input strings. The gateway protocol for communication shall be uniform throughout the
system. The String monitoring box shall have RS-485 port for communication.

o String Combiner Boxes shall be equipped with appropriately sized string fuses as
recommended by PV module manufacturers. Basic string configuration/ array design shall
be as per data sheet/ design recommended by the module manufacturer prior to
development/ implementation.

o EPC Contractors/ Manufacturers are required to supply required spares for 2.5% of the
total supply quantity of all string combiner boxes. This will essentially include consumables
and hardware. Also minimum 2 spare inputs to be kept in each SMB.

o Maximum designed temperature shall be considered as 50°C and humidity of 95%. The
internal temperature rise within the enclosure shall not be more than 10⁰ C above the
design ambient temperature rise.

o String Monitoring Box has to be PC/FRP enclosure.

14.3 Construction

o The enclosure shall be dust proof, non-conductive, impact resistant, UV resistant, flame
retardant and shall be made from fiber glass reinforced/ Polycarbonate suitable for
outdoor applications with IP66 protection, IK08 rating. Minimum 3 mm thickness to be
provided for enclosure.

o SMB shall be provided with continuous gasket made of EPDM or better material seamless
gasket for providing water tightness and preventing ingress of dust. The gasket shall be
held in position in groove provided in the enclosure and shall be pressed all around
uniformly by suitably shaped projection of the door.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 73
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

o All live parts inside the SMB shall be insulated and shall withstand a DC test voltage of 2.5
kV for 1 minute. SMB shall carry a warning label indicating that all active part in the boxes
may be live.

o In order to provide protection to all cables and modules, string fuses shall be provided in
positive of the string cabling. However, in case of negative grounded inverters, string fuse
shall be provided in positive leg only as per recommendation of inverter manufacturer.
String fuses shall be of cylindrical type mounted on appropriately sized non exposed type
fuse block or fuse holders, gPV category and dedicated to solar applications and conform to
IEC 60269-6 or UL-2579 standards. String fuses should be so designed that it should protect
the modules from reverse current overload.

o Minimum 5 mm gap to be provided between fuse holders. The fuse holders/ block may be
DIN rail adapted.

o Live part insulation is requirement for safety of operations personnel. The construction has
to ensure the same. Standard 1500 V DC protection as in case of other component shall be
applicable.

o The PV Disconnector shall be designed for DC 1500 V specifically used for protecting
photovoltaic systems against over currents. The Disconnector shall allow the fuse
replacement horizontally. It shall be type tested to carry the nominal current till Min.
ambient temperature of 60 Deg C without any de-ration inside the String Junction box.
Switching part shall necessarily contain reinforced break chamber, with an integrated arc-
extinguishing system for the PV arc. PV disconnector terminals need to be Silver plated.
The PV disconnector need to have a positive break indication and will have to comply with
IEC 60947-3 PV-1 and PV-2 for critical current.

o All the SMB shall be equipped with type1+2, 40 kA maximum discharge current three
varistors type surge protection devices.

o The surge arrester shall be associated with a dedicated disconnector, the opening of which
will not turn off the downstream circuit.

o The SMB shall be suitable for either free stand mounting or on the module mounting
structures.

o All SMBs shall have an embossed aluminum plate describing string numbers, capacities,
voltages and designated identification number.

o Operating temperature of the cable glands should be a minimum of 100° C. Minimum


protection level of all glands shall be IP68.

o String monitoring box should be provided with Lock Out Tag Out (LOTO) arrangement from
outside of the box, so that no one can open in on condition as well as SMB also provided

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 74
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

with the arrangement to avoid the direct contact to terminals and live parts even after
opening of the SMBs.

o The boxes will have suitable cable entry points fitted with cable glands of appropriate sizes
for outgoing cables. EN certified MC4 connector should be provided at incoming side of the
combiner boxes. The glands shall be suitable for as per design main DC Copper cables. MC4
connectors shall be suitable for 6 mm2 solar grade DC cable.

o The current measurement technology used in monitoring system shall be shunt type.

o Separate auxiliary supply should be provided in SMB from nearest LT panel (approved by
KTL).

o Engraved core identification plastic ferrules marked to correspond with the wiring diagram
shall be fitted at both ends of each wire. Ferrules shall fit tightly on wires shall not fall off
when the wire is disconnected from terminal blocks.

14.4 Submission

The Bidders shall submit following documents from Manufacturer/ Supplier.

 Quality certifications by TUV, CE, UL

 Technical literature giving complete product specifications

 GTP, GA, BOM, Type test reports

 Heat Load calculation & type test report

 All material datasheet & test certificate

Makes

As per Annexure- A

15 DC SOLAR CABLES

Cables shall be compliant to most recent standards (and latest amendments if any) developed by the
IEC or EN for UV resistant DC cables for solar PV applications. The table below presents a non-
exhaustive list of standards to which cables should confirm.

EN 50618 and IEC 60228, Class 5 Design & dimension of Tinned fine copper strands

UL4703 Photovoltaic Wires

IEC 60332-1 Fire performance

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 75
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

IEC 61034 Smoke emission

IEC 60287 Conductor temperature

IEC 60216 Temperature index and service life of over 20 years

IEC 60754-1 Halogen free

EN 50396 Ozone resistance

IEC 60811 Resistant to chemicals and oils

EN 50618 Annexure E Weathering / UV resistance

15.1 Specific Design Requirements

In addition to the best manufacturing practices of manufacturers of cables, following are the specific
requirements for all DC Solar cables unless anywhere specified:

 DC cable should be electron beam cross linked XLPO type

 Bidder have consider 6 mm2DC cable at string level for all Shed.

 Cables should be solar grade and should be UV ozone and high temperature resistant.

 Positive and negative DC cables should be laid in separate cable tray.

 Cable shall be laid in UPVC pipes, where separate cables trays are not provided.

 Filling factor for conduit is 40 % and all conduit end portion should be filled by appropriate
sealant. Bidder have to take approval on Sealant material from KTL/ Consultant.

 The cables shall be designed for a nominal DC voltage of 1500V & max. DC voltage of 1.8KV
with an operating temperature range of 0° C to 90° C

 The maximum conductor temperature shall not exceed 90°C during continuous operation at
full rated current. The temperature after short circuit for 5 seconds shall not exceed 250° C
with initial conductor temperature of 90° C.

 Manufacturers shall indicate the overload capacities that the cable can carry and its duration,
when operating initially at a conductor temperature of 90° C, with peak conductor temperature
of 125° C.

 Bidder shall be use proper termination accessories for cable dressing & laying work like UV
protected cable tie, ferules, Cable tag etc as per standard practice.

15.2 General Requirement

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 76
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Conductors shall be fine wire strands of electrolytic grade high conductivity annealed tinned
copper.

 Its grade shall be “A” & flexibility class will be 5.

 Conductors shall be multi-stranded, smooth, uniform in quality and free from scale and other
defects.

 Cables of 6 mm2 shall be of solar grade and have Insulation and outer sheath shall be of high
grade XLPO compound. Material should be flame retardant & halogen free. Its curing should be
EBXL.

 Cables of 6 mm2 shall be tied along the solar PV module mounting structures, these cables are
essentially required to be UV, ozone and high temperature resistant. Only UV resistant cable
ties shall be used in regular intervals.

 Cables connecting strings to SMBs or String Inverter shall be encased in flexible UPVC pipes
while crossing one module to other module. The pipes shall be UV resistant and Halogen free
with withstanding temperature not less than 125°C.

 DC rated plug and socket connectors in case used for interconnecting harness to combiner
boxes. These connectors shall be hermetically sealed with IP 68 class protection and double
insulated. These connectors shall be crimp free ready to plug type for easy installation.

 Cable sizing shall consider de-rating factors such as installation method, depth of installation,
cable group factor, temperature effect etc. for optimized designs.

 Cable rolls shall be of minimum 1000 m, cabling shall be in uniform lengths with no joints.

 All DC cabling shall be provided with appropriate alphanumeric ferrules for easy identification
of strings and further circuits at both end.

15.3 Submission:

 GTP / QAT / FAT Plan & Reports

 Cable Cross-sectional drawing

 Type test certificates

 Conformity Certificate of compliance for applicable standard like IEC/TUV & etc.

 De-rating factor & Installation method

Makes

As per Annexure- A

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 77
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

16 DC POWER CABLES

The section herein describes general specifications for DC power cable connecting SMB and inverter for
solar PV applications.

16.1 Quality Certification:

Cables shall be compliant to most recent standards (and latest amendments if any) developed by the
IEC and EN for UV resistant DC cables for solar PV applications and should be TUV certified. Table below
presents a non-exhaustive list of standards to which DC Cables should conform.

IS: 7098-2 (2011) or Cross linked polyethylene insulated PVC sheathed cables, Part
latest 2: For working voltage from 3.3 kV up to and including 33 kV

IS: 3961 Recommended current ratings for cables

IS: 8130 Conductors for insulated electric cables and flexible cords

IS: 2982 Copper conductor in insulated cables and cords

IS: 3975 Mild steel wires, strips and tapes for armoring cables

Specification of elastomeric insulation of sheath of electric


IS: 6380
cables

IS: 434(I and II) Specification for rubber insulation cables

IEC: 230 Impulse tests on cables and their accessories

NEC Code 2008


Cables for photovoltaic installations
Article 690

IS: 13573-1 (2011) Cable Accessories for Extruded Power Cables

IS: 10418 (1982) Drums for electric cables

IS: 209 Specification for Zinc

16.2 Specific Design Requirements

1) Cables sizes shall be selected considering the power loss, current carrying capacity, voltage
drop, maximum short circuit duty and the period of short circuit to meet the anticipated
currents.
2) Cables shall be 1.9/3.3kV AC or 1.8kV DC grade, single core, electrolytic grade annealed
copper conductor, extruded XLPE insulated, round wire or flat strip Armoured with extruded
PVC outer sheath (ST-2).

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 78
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

3) The DC Power conductor shall be electrolytic grade Copper conductor with smooth, uniform
in quality, free from scale and any defects. Conductor shall be compacted stranded and
circular.
4) Conductor shall be insulated with cross-linked polyethylene (XLPE) insulation material
conforming to relevant IEC standard.
5) Cables shall be Armoured with (Aluminium or GI) flat strip or round wire armour.
6) Outer Sheath shall be of suitable grade PVC (ST-2). Compound applied by extrusion process.
Colour of the outer sheath shall be black. Colour of the outer sheath shall be black for
negative pole and red for positive pole. For outdoor / in Air application, Outer sheath with
Anti-UV and Anti-Ozone properties shall be provided also. For underground application, outer
sheath with Anti-rodent & Anti-termite properties shall be provided also.
7) The maximum conductor temperature shall not exceed 90⁰ C during continuous operation at
full rated current. The temperature after short circuit for 1.0 second shall not exceed 250o C
with initial conductor temperature of 90⁰ C.
8) Underground cables to be laid as per IS 1255 standards and drawing approved by client or its
consultant.
9) Positive and Negative cables to be run in separate trays.

16.3 Submission

The Bidder shall submit following documents for all the cables. Manufacturer/ Supplier shall submit
valid type test certificates issued by a National or International Testing Authority.

 GTP / QAT / FAT Plan & Reports

 Cable Cross-sectional drawing

 Type test certificates

 Conformity Certificate of compliance for applicable standard like IS / IEC/TUV & etc.

 De-rating factor & Installation method

Makes

As per Annexure- A

17 DC PLUG IN CONNECTORS AND HARNESS FOR FIELD CABLING

Cable connector to be used for connecting SPV modules and String Combiner Boxes shall be in
accordance with DIN EN 50521. Connector shall be of plug and socket design to be plugged together by
hand but can be separated again using a tool only.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 79
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The section herein describes general specifications for Male/Female Connectors or harness used for
interconnecting Solar PV modules.

17.1 Quality Certification for Connectors:

Connectors shall be compliant to most recent standards (and latest amendments if any) developed by
the IS, IEC and EN. Regulations applicable in the area where equipment is to be installed shall be
followed. Below table presents a non-exhaustive list of standards to which connectors should conform.

IEC 61730 PV component standards

IEC 62852:2014 Latest PV connectors

UL 6703 PV connectors

EN 50521 + A1 Safety requirements test

IEC 529 Degree of protection provided by enclosures

Crimped connections – General requirements, testmethods &


IEC 60352-2
practical guidance

Preference shall be given to manufacturers with maximum quality certifications for example by TUV,
CE, UL, etc.

17.2 General Requirement

 Connectors shall be over molded type ready to plug. Maximum designed temperature shall be
considered as 55°C and humidity of 95%.

 Rated voltage of Male/ Female connectors shall be 1500VDC 1000V DC.

 The connectors shall be rated at 15A/30A continuous current as per detailed design& suitable
for 6 mm2 solar cable (designed as per EN-50618).

 PV connectors, wire harness and Y- harness with inline fuse on positive side fuse shall be
provided.

 The connectors shall be MC4 compatible type.

 The connectors shall be tested at 8kV AC voltage, 50Hz for one minute.

17.3 Specific Requirement

Y type harness assembly shall include snap in locking type (removable) in line fuse connector assembly
in each string connection (+VE side) as required. This shall also be over molded type having male -
female connectors and fuse holder. Assembly shall be internally locked.

17.4 Specific Construction Requirement

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 80
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 The connector shall be snap in locking type made up of Polycarbonate/ Polyamide material
suitable for outdoor applications with IP68 protection rating when in mated condition.

 The connector shall be ozone resistant, halogen free, dust proof, non-conductive UV resistant,
with high inflammability value.

 Insulating material should be PPE / Noryl / Polycarbonate / Polyamide.

 Heat & Fire resistance category shall be as per UL94 –V0.

 Assembly shall be snap in locking type.

 Connector shall be suitable for ambient temperature range of -40°C to 90° C and upper limiting
temperature shall be 125°C when connected.

 The Connector system should be compatible to the PV module's connectors and shall confirm
EN50521+A1.

 Contact material shall be tin plated copper alloy with multi-contact technology.

 System shall be designed for minimum contact resistance between connectors.

 Contact resistance at termination shall be or below 0.25 milli-ohms (typical).

 The connectors shall be provided with over voltage category - III/pollution degree of 3.

 Minimum safety class-II shall be considered for connectors.

 The connectors shall be suitable for crimped design at site with solar DC cables.

 Vendor shall provide suitable no of spanners for termination purpose.

 Connectors shall have good resistance to ammonia and shall also pass salt mist spray test.

17.5 Submission

Bidders shall submit following documents from Manufacturer/ Supplier.


 Compatibility Report to be submitted with PV Module and SMB side connectors

 GA, GTP, QAP and FAT report

 Quality certifications by TUV or UL.

 Technical literature giving complete product specifications.

 BOM / Makes and specifications, Certifications of all components.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 81
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Makes

As per Annexure- A

18 SCADA/ Plant Monitoring System

KTL requires a comprehensive ―Plant Monitoring System and Remote Monitoring System”, covering
both DC and AC sides, for 2.6 MWp/2.0 MW Solar PV plant. The scope includes design, supply, erection
and commissioning of Plant Monitoring System with all accessories, auxiliaries and associated
equipment and cables for the safe, efficient and reliable operation of entire solar plant and its auxiliary
systems at the plant.

Bidder shall include in his proposal all the Hardware, Software, Panels, and Redundant Power Supply
and associated Cable etc. needed for the completeness even if the same are not specifically appearing
in this specifications.

Bidder shall get approval of monitoring back calculations for SCADA/Plant monitoring system from
Consultant/KTL. In Plant monitoring portal, bidder shall show deviation of Bidder and consultant
calculation.

Plant Monitoring System shall have the provision to perform the following functions:

 Real-time acquisition and display of data, status, alarms and trends

 Monitoring of Switchgears (ACB) and Inverters, sensors.

 Ability to create dashboards

 Automatic diagnostics and AI capability ( preferred)

 Power generation forecast (preferred)

 Display and storage of measured values

 Display and storage of derived/calculated/integrated values

 Display and Storage of Alarm, Event and Trends

 Generate, store and retrieve user configurable Sequence of Event (SOE) Reports

 I-V Curve testing

 Generate, store and retrieve user configurable periodic reports

 PV plant performance, Generation report, Warning notifications, fault alarms, errors via mobile
messenger and e-mail Plant monitoring system/SCADA shall have facility to generate report in
MS Excel file type.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 82
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Plant monitoring of essential parameters on the web authorized with user id and password
using standard modem (Internet connection for transferring data to web shall be taken by
Bidder in the name of KTL Site for O & M period).

 System self-supervision

Plant monitoring system/SCADA shall have facility to control Inverter active and reactive power as per
requirement mentioned in respective chapter. Plant monitoring system shall also be able to acquire
real time Data, Status and Alarm from following equipment included but not limited to as required or
offered under the scope of this specification:

i. LV Switchgear (ACB)

ii. Weather Monitoring Equipment(Sensors)

iii. Multi-function meter(Solar LT Panel)

iv. Solar Meter & Check Energy Meter

v. Inverter

vi. String level monitoring

vii. Plant monitoring system/SCADA /Data logger Hardware, Accessories and


Communication link

viii. Any other equipment required as per specification

 Type of signal from equipment (Hard wired or Soft) shall be as per specification of the
equipment mentioned in the respective chapter and approved during detail engineering.

 SCADA/ Plant monitoring shall provide real time performance monitoring according to IEC
61724 standard. In case of conflict between this specification and those (IS codes, standards,
etc.) referred to herein, the former shall prevail.

 An industrial redundant RS485 and Ethernet LAN (as per application) shall be distributed
throughout the field for communication to field devices.

 All the power supply module, Ethernet switches and network accessories for non-air
conditioned area shall be suitable for operating in ambient temperature of 50 Deg. C Minimum.

 Provision of generating alarm/ error code based on equipment status, failure of equipment,
nuisance tripping to be provided. There shall be configurable thresholds values for key
parameter such as low current in specific strings or across plant for evaluating the
performance.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 83
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Provision for presenting key plant characteristics and historic data in terms of graphs and
reports, real time trends shall be provided.

 Monitoring system shall be designed with different dashboards for various users such as Plant
O&M team, senior management. The recorded data shall be sequential right from the SMB
input to the metering point at the outgoing feeder of the main 400 V panel located in the Main
panel Room. The data shall be compatible and transferable to MS Office excel. The source of
power for SCADA system and all related hardware shall be from auxiliary power supply. An
additional UPS having a minimum 4 hours backup shall be provided dedicatedly for this system.

 The Plant monitoring system/SCADA system should have time synchronization GPS clock to
ensure there are no discrepancies.

Plant monitoring system/SCADA system shall include the following standard protocols as a minimum.

a) Modbus (TCP/IP, RS485)

Any other protocol on which the offered equipment (by Bidder) will communicate with SCADA

Following plant performance (PG) long term data as a minimum with time stamping and interval as
indicated in below table but not limited to shall be stored daily on historian for analysis and analytic
report.

Important plant data for a very long duration (plant life) Storage

Sr. Parameter Time Interval


No.
1 Weather Monitoring Stations data: 1 (One) Minute
Global Horizontal Irradiance, Global Inclined Irradiance., Module
temperature , Ambient Temperature, Wind Speed, Wind
Direction, Remote Dust monitor.
2 Calculated Daily Global Horizontal Insolation, Global Inclined 24 (Twenty Four)
Insolation for each tilt of shed Hours
3 Power Conditioning Unit (Inverter): 1 (One) Minute
String DC Voltage, Current and Power, SMB/SMU Current
(Inverter end), Inverter AC output voltage and current(All 3
phases and lines),AC power (Active, Reactive and Apparent),
Power Factor andAC energy (All 3 phases and cumulative) and
frequency
6 MFM and Energy meter data: 1 (One) Minute
Active & Reactive Power, Import and Export Energy, Current and
Voltage, Power factor, Frequency

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 84
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

7 Daily energy export from each Inverter 24 (Twenty Four)


Hours
8 Total sum of daily energy export from all Inverter 24 (Twenty Four)
Hours

Software Documentation and Software Listings

All technical manuals, reference manuals, user’s guide etc., in English required for
modification/editing/addition/deletion of features in the software of the PLC System shall be furnished.
The Bidder shall furnish a comprehensive list of all system/application software documentation after
system organization for Employer’s review and approval. All The software listings for application
software, Project data files etc. shall be submitted by the Bidder.

All the SCADA Software with license Key shall be handed over to KTL on the DVD/ CD media. All the
hardware and software shall be licensed to KTL.

Software License
The Bidder shall provide software license for all software being used in Bidder’s System. The software
licenses shall be provided for the project (e.g. organization or site license) and shall not be
hardware/machine-specific. That is, if any hardware/machine is upgraded or changed, the same license
shall hold good and it shall not be necessary for Employer to seek a new license/renew license due to
up gradation/change of hardware/machine in Bidder’s System at site. All licenses shall be valid for the
continuous service life of the plant. User ID and password for remote view can only be changed by
SCADA Administrator.

 Bidder shall provide plant monitoring system licenses for minimum 5 years free of issue to KTL
after commissioning of solar plant.

 Following is the recommended specifications for RS485 & IO Cables.

 For RS485: 2 X 0.5sq.mm(Minimum size and at actual as per design) , ATC multi-strand (class-5),
insulated core, two twisted pair, overall screened with ATC drain wire, GI round wire Armored,
PVC sheathed, DIN47100 color, standard, FRLS cable.

 For Optical Cabling: 8F, Armored, Single or Multi-Mode as per requirement

 Optic Fiber cable shall be 6/8/12 core, galvanized corrugated steel taped armored, fully water
blocked with dielectric central member for outdoor/indoor application so as to prevent any
physical damage. The cable shall have multiple single-mode or multimode fibers on as required

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 85
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

basis so as to avoid the usage of any repeaters. The core and cladding diameter shall be 9 +/-1
micrometer and 125 +/- 1 micrometer respectively.

 The outer sheath shall have Flame Retardant, UV resistant properties and are to be identified
with the manufacturer‘s name, year of manufacturing, progressive automatic sequential on-
line marking of length in meters at every meter on outer sheath.

 The cable core shall have suitable characteristics and strengthening for prevention of damage
during pulling viz. Steel central number, Loose buffer tube design, 4 fibers per buffer tube
(minimum), Interstices and buffer tubes duly filled with Thixotropic jelly etc. The cable shall be
suitable for maximum tensile force of 2000 N during installation, and once installed, a tensile
force of 1000 N minimum. The compressive strength of cable shall be 3000 N minimum & crush
resistance 4000 N minimum. The operating temperature shall be -20 deg. C to 70 deg. C.

 All testing of the optic fiber cable being supplied shall be as per the relevant IEC, EIA and other
international standards.

 Bidder to ensure that minimum 100% cores are kept as spare in all types of optical fiber cables.

 Cables shall be suitable for laying in conduits, ducts, RCC trenches and racks installation. Cable
shall not contact with direct Sun light.

 Spliced/ Repaired cables are not acceptable.

 Penetration of water resistance and impact resistance shall be as per IEC standard.

Makes

As per Annexure- A

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 86
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

19 AC CABLES (1.1 kV) (FREE ISSUE ITEM BY KTL)

19.1 Quality Certification

All AC Cable for solar plant shall supply by KTL and design shall prepare by bidder as per below
technical specification. For quality assurance for bidder, KTL will arrange jointly inspection for AC cable
before dispatch of it.

The cables shall be compliant to most recent standards (and latest amendments if any) developed by
the Indian Standards. The table below presents a non-exhaustive list of standards to which the cables
should conform.

IS: 7098-1 Cross linked polyethylene insulated PVC sheathed cables, Part 1: For working
(Latest) voltage up to and including 1100 V

IS 3961 Recommended current ratings for cables

IS 5831 PVC insulation and sheath

IS 8130 Conductors for insulated cables

IS 3975 Mild steel wires, strips and tapes for armoring of cables

IS 1255 Installation and maintenance of power cables

IS 1554-1 PVC insulated (heavy duty) electric cables for working voltage up to and
including 1100 V

IS: 2982 Copper conductor in insulated cables and cords

IEC-754 (Part-I) Tests on gases evolved during combustion of electric cables

ASTM-O -2843 Standard test method for density of smoke from the burning or decomposition
of plastics

IEC-332 Tests on electric cables under fire conditions. Part-3: Tests on bunched wires
or cables (Category-B)

IS 10810 Methods of tests for cables

IS: 209 Specification for Zinc

IS: 3975 Mild steel wires, strips and tapes for armoring cables

IEC 230 Impulse tests on cables and their accessories

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 87
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

IS: 10418 (1982) Drums for electric cables

19.2 Specific Design Requirements

 Cable from Inverter to LT panel (Solar DB) shall be 1.1 kV grade, Copper conductor, multi core,
extruded XLPE insulated with extruded PVC inner sheath (ST-2), single wire or strip Armoured
(as per requirement) & extruded (ST-2) PVC outer sheath

 Cables sizes shall be selected considering the power loss, current carrying capacity, voltage
drop, maximum short circuit duty and the period of short circuit to meet the anticipated
currents.

 High quality XLPE insulating compound of natural colour shall be used for insulation. Insulation
shall be applied by triple extrusion process and shall be chemically cross linked.

 Cables shall be 1.1 kV grade, single/ multi core, extruded XLPE insulated with extruded PVC
inner sheath (ST-2), single wire or strip Armoured (as per requirement) & extruded (ST-2) PVC
outer sheath. Also, outer sheath shall have UV and Ozone resistance properties for outdoor
installation and Anti-termite and Anti-rodent properties in case of buried installation.

 The conductor shall be high conductivity annealed Copper or Aluminium and shall be smooth,
uniform in quality, free from scale & any defects.

 The aluminium used for armouring be of H4 grade as per IS 8130 with maximum resistivity of
0.0282mm2 perm at 20oC.

 The maximum conductor temperature shall not exceed 90oC during continuous operation at
full rated current. The temperature after short circuit for second shall not exceed 250oC with
initial conductor temperature of 90oC.

 Cables shall be armoured with mild steel wires or strips.

 The outer sheath shall be of suitable grade PVC (ST-2). Compound applied by extrusion process.
Colour of the outer sheath shall be black. All AC cableling shall be provided with engraved core
identification plastic ferrules marked to correspond with the wiring diagram shall be fitted at
both ends of each wire. Ferrules shall fit tightly on wires shall not fall off when the wire is
disconnected from terminal blocks.

19.3 Cabling

 Cables shall be laid on cable trays and through pipe sleeves wherever required and necessary
according to IS1255 or any other relevant Indian standards. All such trays, sleeves shall be built
and provided by the Bidder.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 88
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Cables shall be laid in hume pipes at all road crossings. After the laying and straightening of
cables, it should be covered with a min 80 mm thick layer of sand.

 All cable terminations shall be mechanically and electrically sound and shall comply with
relevant standards and Indian electricity regulations.

 Cable samples shall be taken and tested from each lot for ascertaining the conformity of the lot
to the requirements of the specification.

19.4 Cable Identification:

Cable identification shall be provided by embossing on every one meter on the outer sheath the
following:

 Manufacturer’s name or trade mark

 Voltage grade

 Year of manufacture

 Type of insulation

 No. of core and size of cables

19.5 Submission

The Bidders shall submit manufacturer’s documents for all the cables.

a. GTP / Cross section drawing / QAP / FAT procedure & Test reports

b. Manufacturer/ Supplier shall submit type test certificates issued by a National or International
Testing Authority.

c. Following the award of contract, Bidder shall supply type non-exhaustive test reports of each of
the cable types.

Makes

As per Annexure- A

20 LT PANELS (FREE ISSUE ITEM BY KTL)

All LT panel for solar plant shall supply by KTL and design shall prepare by bidder as per below technical
specification. For quality assurance for bidder, KTL will arrange jointly inspection for LT panels before
dispatch of it.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 89
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

All the switchboards shall be compliant to most recent standards (and latest amendments if any)
developed by the IS, IEC and EN. Regulations applicable in the area where equipment is to be installed
shall be followed. The below table presents a non-exhaustive list of standards to which switchboards
should conform.

IS 13947 Low Voltage AC Switchgear and Control Gears Specifications

IS 8623 Low Voltage AC Switchgear and Control Gear Assemblies

IS 4237 General requirements for AC switchgear & control gear for voltage not
exceeding 1000 V

IS 2147 Degree of protection for enclosures for low voltage switchgear and control gear

IS 5082 Electrolytic Copper/ Aluminium

IS 2516 Circuit Breakers, voltages up to 1000 Volts

IS 4064 Air Break Switches, Air Break Disconnector, for voltages not exceeding 1000 V
AC.

IS 375 Marking & Arrangement for Switchgear, Bus Bars, main connections and
auxiliary wiring.

20.1 General

All the AC low voltage switchboards shall be suitable for operation with 400 V, 50 Hz and 3/4 wire
system. The overall construction of the LV Switchboards shall be factory assembled with fabrication
processed on CNC type or equivalent machines.

20.2 Construction

 The switch boards shall be dead front totally enclosed, cubicle type suitable for floor
mounted free standing/ wall mounted indoor installations. The design shall be totally
dust - tight damp - proof and vermin proof offering degree of protection not less than IP-
42 for indoor applications. Outdoor Panel are not acceptable.

 All equipment and components shall be neatly arranged and shall be easily accessible for
operation and maintenance. Replacement /Maintenance of individual equipment/
component shall be possible without switching off or isolating the other equipment’s/
components.

 Each panel shall be provided with undrilled, removable type glandplate. For all single
core cables, gland plate shall be of non-magnetic material. The gland plate shall be
provided with gasket to ensure enclosure protection.

 All panel edges and cover / door edges shall be reinforced against distortion by rolling,
bending or by the addition of welded reinforcement members. The top covers of the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 90
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

panels should be designed such that they do not permanently bulge/ bend by the weight
of maintenance personnel working on it.

 Adequate size cable compartment should be provided for easy clamping of all the
incoming and outgoing cables irrespective of top or bottom entries.

 All live parts inside the switchboards shall be insulated and shall withstand a DC test
voltage of 2.5 kV for 1 minute. Switchboards shall carry a warning label indicating that all
active part in the boxes may be live.

 All MFMs (Class 0.5) shall be of digital electronic with LED display and shall have RS-485
port for SCADA/ Plant Monitoring System communication.

 The minimum clearance in air between phases and between phases and earth for the
entire busbars shall be 25mm and more. For all other components, the clearance
between "two live parts", "a live part and an earthed part", shall be at least ten (10) mm
throughout. However, for busbars the clearances specified above should be maintained
even when the busbars are sleeved or insulated. All connections from the busbars up to
switch / fuses/MCCB/ Breaker shall be fully insulated and securely bolted to minimize the
risk of phase to phase and phase to earth short circuits. All busbars and jumper
connections shall be of high conductivity aluminum alloy / copper of adequate size. LT
Panels shall be followed by Form 2 of IEC.

 All Panel shall be provided with three phase and neutral busbars (3P,4W System).

 Entire busbar system shall be insulated with PVC sleeves. Busbar sleeves shall be
compliant to UL224 (Extruded insulating tubing), CE/UL certified, having fire retardant
properties and working temperature of 105°C.

 The cross-section of the busbars shall be uniform throughout the length of switchboard
section and shall be adequately supported and braced to withstand the stresses due to
the specified short circuit currents. Neutral busbar short circuit strength shall be same as
main busbars.

 All busbars shall be adequately supported by non-hygroscopic, noncombustible, track-


resistant and high strength sheet molded compound or equivalent type polyester fiber
glass molded insulator. Separate supports shall be provided for each phase and neutral
busbar. If a common support is provided, anti-tracking barriers shall be provided
between the supports.

 Insulator and barriers of inflammable material such as Hylam shall not be accepted. The
busbar insulators shall be supported on the main structure.

 All busbar joints shall be provided with high tensile steel bolts, belleville / spring washers
and nuts, so as to ensure good contacts at the joints. Nonsilver plated busbar joints shall

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 91
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

be thoroughly cleaned at the jointed locations and suitable contact grease shall be
applied just before making a joint. All bolts shall be tightened by torque spanner to the
recommended value. The overlap of the busbars at each joint surface shall be such that
the length of overlap shall be equal to or greater than the width of thebusbar. All copper
to aluminium joints shall be provided with suitable bimetallic washers.

 All busbars shall be colour coded as per IS: 375.

 The Bidder shall furnish calculations establishing the adequacy of bus bar sizes for
specified current ratings.

 Panel space heaters shall be provided and the supply for this shall be tapped from
incomer, before the isolating switch/circuit breaker. Incoming circuit to space-heater
shall have an isolating switch, HRC fuse and neutral link of suitable rating. Space heaters
should have high voltage tested at 2 KV for 1 min, Insulation resistance greater than 10
MΩ and power rating within +/- 5%. Panel illumination and plug-socket shall also be
tapped from the space heater supply.

 A Copper / Aluminium earth bus shall be provided at the bottom of each panel and shall
extend throughout the length of each switchboard. It shall be welded / bolted to the
framework of each panel and breaker earthing contact bar. Vertical earth bus shall be
provided in each vertical section whssich shall in turn be bolted / welded to main
horizontal earth bus.

 The earth bus shall have sufficient cross section to carry the momentary short circuit and
short time fault current to earth without exceeding the allowable temperature rise.

 All non-current carrying metal work of the switchboard shall be effectively bonded to the
earth bus. Electrical conductivity of the whole switchgear enclosure framework and truck
shall be maintained even after painting.

 All metallic cases of relays, instruments and other panel-mounted equipment shall be
connected to earth by independent stranded copper wires of size not less than 2.5 sq.
mm. All the equipment mounted on the door shall be earthed through flexible
wire/braids. Insulation color code of earthing wires shall be green. Earthing wires shall be
connected to terminals with suitable clamp connectors, soldering is not acceptable.

 Looping of earth connections, which would result in loss of earth connections to other
devices, when a device is removed, is not acceptable. However, looping of earth
connections between equipment to provide alternative paths to earth bus is acceptable.

 All hinged doors having potential carrying equipment mounted on it shall be earthed by
flexible wire/ braid. For doors not having potential carrying equipment mounted on it,
earth continuity through scraping hinges/ hinge pins of proven design may also
acceptable. The Bidder shall establish earth continuity at site also.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 92
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 All switchboards shall be supplied completely wired internally up to the terminals, ready
to receive external cables.

 All auxiliary wiring shall be carried out with 650V grade, single core stranded copper
conductor, colour coded, PVC insulated wires. Conductor size shall be 1.5 mm2 (min.) for
control circuit wiring and 2.5 mm2 (min) for CT and space heater circuits.

 Extra flexible wires shall be used for wiring to devices mounted on moving parts such as
hinged doors. The wire bunches from the panel inside to the doors shall be properly
sleeved or taped.

 All wiring shall be properly supported, neatly arranged, readily accessible and securely
connected to equipment terminals and terminal blocks.

 All internal wiring terminations shall be made with solderless crimping type tinned
copper lugs which shall firmly grip the conductor or an equally secure method. Similar
lugs shall also be provided at both ends of component to component wiring. Insulating
sleeves shall be provided over the exposed parts of lugs to the extent possible. Screw-
less (spring loaded) / cage clamp type terminal shall also be provided with lugs.

 Printed single tube ferrules marked to correspond with panel wiring diagram shall be
fitted at both ends of each wire. The wire identification marking shall be in accordance
with IS: 375. Red Ferrules should be provided on trip circuit wiring.

 Cable termination arrangement for power cables shall be suitable for heavy duty, 1.1 kV
grade, stranded aluminium/ Copper conductor, PVC/ XLPE insulated, armoured /
unarmoured and PVC sheathed cables. All necessary cable terminating accessories such
as supporting clamps and brackets, hardware etc., shall be provided by the bidder, to suit
the final cable sizes.

 All power cable terminals shall be of stud type and the power cable lugs shall be of
tinned copper solderless crimping ring type conforming to IS: 8309. All lugs shall be
insulated/ sleeved.

 All Switchgears, MCCs, Distribution Boards, Fuse boards, all feeders, local push-button
stations etc. shall be provided with prominent, engraved identification plates.

 All name plates shall be of non-rusting metal or 3-ply Lamicoid, with white engraved
lettering on black background. Inscription & lettering sizes shall be subject to Employer's
approval.

 Caution name plate "Caution Live Terminals" shall be provided at all points where the
terminals are likely to remain live and isolation is possible only at remote end.

 The gaskets, wherever specified, shall be of good quality EPDM / neoprene with good
ageing, compression and oil resistance characteristics suitable for panel applications.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 93
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 The bidder shall, ensure that the equipment offered will carry the required load current
at site ambient conditions specified and perform the operating duties without exceeding
the permissible temperature as per indian standards / specification. Continuous current
rating at 50 deg C ambient in no case shall be less than 90% of the normal rating
specified.

 ON/OFF status and protection trip status of incomers and bus coupler (if available) be
provided for SCADA system/Plant Monitoring System.

 It shall be the responsibility of the bidder to fully coordinate the overload and short
circuit breakers/fuses with the upstream and downstream circuit breakers / fuses, to
provide satisfactory discrimination.

 Further the various equipment supplied shall meet the requirements of type ii class of
co-ordination as per IS: 8544.

 All sheet steel work shall be pretreated, in tanks, in accordance with is: 6005. Degreasing
shall be done by alkaline cleaning. Rust and scales shall be removed by pickling with acid.
After pickling, the parts shall be washed in running water. Then these shall be rinsed in
slightly alkaline hot water and dried. The phosphate coating shall be "class-c" as specified
in is: 6005. The phosphated surfaces shall be rinsed and passivated. After passivation,
electrostatic powder coating shall be used. Powder should meet requirements of is
13871 (powder costing specification). Finishing paint shade for complete panels
excluding end covers shall be RAL9002 & RAL5012 for extreme end covers of all boards,
unless required otherwise by the employer. The paint thickness shall not be less than 50
microns.

 All switchboards shall be divided into distinct vertical sections (panels), each comprising
of the following compartments.

o BUSBAR COMPARTMENT:A completely enclosed bus bar compartment shall be


provided for the horizontal and vertical busbars. Bolted covers shall be provided
for access to horizontal and vertical busbars and all joints for repair and
maintenance, which shall be feasible without disturbing any feeder compartment.
Auxiliary and power busbars shall be in separate compartments.

o SWITCHGEAR / FEEDER COMPARTMENT: All equipment associated with an feeder


of rating above 100A shall be housed in a separate compartment of the vertical
section. ACB shall be provided for feeders of rating 800A and above. The design of
the vertical section for such an arrangement shall ensure ease of termination of
power cables of size & quantity as per system requirement. The compartment
shall be sheet steel enclosed on all sides with the withdrawable units in position or
removed. Insulating sheet at rear of the compartment is also acceptable. The front
of the compartment shall be provided with the hinged single leaf door with captive
screws for positive closure.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 94
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

o CABLE COMPARTMENT/CABLE ALLEY: A full-height vertical cable alley of


minimum 250mm width shall be provided for power and control cables. Cable
alley shall have no exposed live parts and shall have no communication with
busbar compartment. Cable terminations located in cable alley of capacity more
than 400 A shall be designed to meet the Form IV b (as per IEC 61439) for safety
purpose. Wherever cable alleys are not provided for distribution boards,
segregated cable boxes for individual feeders shall be provided at the rear for
direct termination of cables. For circuit breaker external cable connections, a
separately enclosed cable compartment shall also be acceptable. The bidder shall
furnish suitable plugs to cover the cable openings in the partition between feeder
compartment and cable alley. Cable alley door shall be hinged.

o CONTROL COMPARTMENT: A separate compartment shall be provided for


relays and other control devices associated with a circuit breaker.

20.3 MCCB/ CIRCUIT BREAKER

 Input side MCCB shall be TM type & output side MCCBs/Circuit Breaker shall be microprocessor
based release. MCCB shall have Ics = Icu =100% at rated voltage & frequency.

 Circuit breakers shall be air break, horizontal draw out type (EDO), and shall have fault making
and breaking capacities as specified in "Technical Parameters". The circuit breakers which meet
specified parameters of continuous current rating and fault making / breaking capacity only
after provision of cooling fans or special device shall not be acceptable.

 All switches, circuit breakers & connector should confirm to IEC 60947, part 1,2,3/IS 60947

 Circuit breakers shall be fixed type module, air break type, having trip free mechanism with
quick make and quick break type contacts. Circuit breakers shall have current limiting feature.
MCCBs/Circuit Breaker of identical ratings shall be physically and electrically interchangeable.
MCCBs/Circuit Breaker shall be provided with 1 NO and 1NC auxiliary contacts.

 The MCCBs/Circuit Breaker being offered shall have common/interchangeable accessories for
all ratings like aux. switch, shunt trip, alarm switch etc.

 The MCCBs/Circuit Breaker shall have the current discrimination up to full short circuit capacity
and shall be selected as per manufacturer’s discrimination table.

 MCCBs/Circuit Breaker with LSIG protection and current limiting feature shall be provided for
main out comer of LT Panel, Feeder Panel etc as per requirement.

20.4 Fuses

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 95
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 All fuses shall be of HRC cartridge fuse link type. Screw type fuses shall not be accepted. Fuses
for AC circuits shall be rated for 80kA rms (prospective) breaking capacity at 400V AC and for
DC circuits, 20kA rms breaking capacity at 240V DC.

 Fuse shall have visible operation indicators. Insulating barriers shall be provided between
individual power fuses.

 Fuse shall be mounted on insulated fuse carriers, which are mounted on fuse bases. Wherever
it is not possible to mount fuses on carriers, fuses shall be directly mounted on plug-in type of
bases. In such cases one set of insulated fuse pulling handles shall be supplied with each
switchboard.

 The Neutral links shall be mounted on fuse carriers which shall be mounted on fuse bases.

20.5 Temperature-Rise (For LT Switch-Gear Having Capacity More Than 400A)

The temperature rise of the horizontal and vertical busbars and main bus links including all power draw
out contacts when carrying 90% of the rated current along the full run shall in no case exceed 55 deg C
with silver plated joints and 40 deg C with all other types of joints over an outside ambient temperature
of 50 deg C. The temperature rise of the accessible parts/external enclosures expected to be touched in
normal operation shall not exceed 20deg. C. The temperature rise of manual operating means shall not
exceed 10deg. C for metallic & 15 deg. C for insulating material. Temperature rise for the busbars shall
be carried out at 90% of the rated current.

20.6 General Instructions

Upon securing of the project, the Bidder shall make following essential submissions:

 General Arrangement drawing of the switchboard, showing front view, plans, overall
dimensions, foundation plans, floor cut-outs/ RCC trenches for external cables and elevations,
transport sections and weights.

 Power and control circuit schematics, terminal plans showing terminal numbers, ferrules
markings, device terminal numbers and function, etc.

 Bill of Material and component lists along with makes for all the switchboards.

Following are the documents that shall be submitted along with the deliveries in 4 Sets.

 Test certificates for various switchgears.

 Technical literature giving complete information of the components, including bus bar sizing
calculations.

 Erection, operation and maintenance manual complete with all relevant information, drawings
and literature for auxiliary equipment and accessories, characteristics curves for relays etc.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 96
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 A comprehensive spare parts schedule.

20.7 Submission

The Bidders shall submit manufacturer’s documents for all the cables.

d. GTP / GA / Electrical Schematic drawings

e. QAP

f. FAT procedure & FAT Report

g. Manufacturer/ Supplier shall submit type test certificates issued by a National or International
Testing Authority.

Makes

As per Annexure- A

21 EARTHING SYSTEM

The entire PV plant area shall be appropriately earthed with adequate number of earth Pits. Earthing
system shall comply with the latest edition of IS 3043 describing code of practice of earthing and
IEEE80. The earthing system shall have complete earthing network comprising of wires,earth flats,
electrodes and earth bonding of all relevant necessary non-current carrying metal parts of
equipment’s/ apparatus shall be connected as required. The EPC contractor has confirmed that they
have sufficiently verified the site conditions to provide adequate earthing and protection to the plant.

The earthing system includes earth electrodes, earth flats, earthing cables installation of earth
electrode in suitable pit size, construction of earth pit with cover for the installation, connection of
earth electrode with equipotential earth bus and connection of equipment to equipotential earth bus.

21.1 Codes and Standards

IS: 3043 Code of practice for Earthing.

IEEE: 80 IEEE guide for safety in AC substation grounding

Standard for qualifying permanent connections used in substation


IEEE: 837
grounding

Code of Practice for the protection of building and allied


IS: 2309
structures against lightning.

IS: 2629 Recommended practice for hot dip galvanizing of iron & steel

IS: 2633 Method for testing uniformity of coating on zinc coated articles

IS: 513 Cold rolled low carbon steel sheets and strips

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 97
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Methods for determination of mass of zinc coating on zinc coated


IS: 6745
iron & steel articles.

21.2 Specific Design Requirements

 Earthing network within the PV plant on shed may be of GI. All mounting structures, string
combiner boxes shall be connected to earth grid with appropriate size of earth conductor.
Sufficient earth Pits shall be planned to maintain earth resistance (less than 1 ohm) ensuring
hazard free operation of PV plant. Each equipment shall be earthed through an additional
protective conductor with equipotential bonding conductor.

 All the earth pits shall be appropriately connected to maintain overall resistance of system shall
be below acceptable limits (less than 1 ohm).

 All the earthing pits shall be provided with test links and located at 150 mm above ground level
in an easily accessible position for testing.

 All the earth pits shall be kept at minimum 2meter away from the edge or civil foundation of
any building/ equipment. Also the distance between nearby earth pits shall be minimum 3.5
meter.

 To ensure the continuity of the earth conductor all the joints between risers from the
equipment and main earth conductor shall be electric arc welded. Welded joints shall be
coated with bitumen paint.

 The material used for making connections shall be compatible with the earth pipe and the
earthing conductor so that galvanic corrosion is minimized. In all cases, the connections have to
be mechanically strong.

 Protective conductors shall be suitably protected against mechanical and chemical


deterioration. Joints of protective conductors shall be accessible for inspection and testing.

 Earthing installations shall be provided to all apparatus framework or other non-current


carrying metalwork associated with each system.

 Earth conductors shall be laid along with cable trays containing power cables should be placed
at the top.

 Earthing conductor connections to equipment should be made onto vertical surfaces only. The
earth grid should be run at a minimum depth of 60 cm below ground.

 All SCADA/Remote monitoring system panel shall be provided with separate earthing network
dedicated for instrument earthing complying with requirements of SCADA/Remote monitoring
system vendor. It should be separate from Plant electrical earthing & Lightning earthing grid.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 98
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

21.3 Specific Construction Requirements

21.3.1 Earth Electrode

The earth electrode is in direct contact with the ground provides means for conducting earth current
with ground. Earth Electrode material should have good electrical conductivity and mechanical strength
and should not corrode in wide variety of soil conditions. For an effective earthing system, following
type of earth electrodes can be used as below:

Earth Pipe size: Cast iron pipe, 125 mm (OD), 10 mm thick 3.5 meter length.

21.3.2 Earthing Enhancement Compound

A low resistance earth electrode system is important to provide a low impedance path for the better
dissipation of lightning/Fault currents, and to protect personnel and equipment by minimizing and
equalizing voltage potential differences. Earthing (ground) enhancement materials shall be used to
improve the ground electrode resistance. Earth enhancement material shall be a superior conductive
material which improves earthing effectiveness, especially in areas of poor conductivity (rocky ground,
areas of moisture variation, sandy soils etc.). It shall be tested and should conform to the requirements
of IEC 62561-7.It shall have the following characteristics:

 High conductivity, improves earth’s absorbing power and humidity retention capability, non-
corrosive in nature having low water solubility but highly hygroscopic.

 Carbon based with min 95% of fixed carbon content premixed with corrosion resistant cement
to have set properties. Cement shall not mix separately & shall not have Bentonite.

 Resistivity of less than 0.2 ohms -meter.

 It shall not depend on the continuous presence of water to maintain its conductivity and shall
be permanent & maintenance free and in its “set form”, maintains constant earth resistance
with time.

 It shall not dissolve, decompose or leach out with time and shall be environmental friendly,
suitable for soils of different resistivity and any kind of earth electrode.

The Earth enhancement material shall be supplied in sealed, moisture proof bags, marked with
Manufacturer’s name or trade name, quantity etc. The minimum quantity of earth enhancement
compound to be used with each earth pit shall be 50 Kg.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 99
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

21.3.3 Galvanized Steel Flat (GS) Flat

GS/GI Flat (Strip) conductor shall comply to IS 4759 with Galvanization of 85 Micron as per IS. Material
shall be clean and free from mechanical defects.

21.3.4 Technical Details for AC Earthing System

This section covers equipment earthing for String Inverter, Lightning Arrestor, LT Switchgear Panel and
other similar panel Electronic earthing installed at Inverter room.

The Bidder shall furnish the detailed design and calculations for Employer's approval for equipment
earthing. Bidder shall obtain all necessary statutory approvals for the system.

Fault current for earthling design and calculation shall be as mentioned in relevant chapter.

The earth conductors shall be free from pitting, laminations, rust, scale and other electrical, mechanical
defects.

The material of the earthing conductors shall be as follows:

 Conductors above ground level and in built up RCC trenches – Hot dip galvanized iron
(HDGI)

 Conductors buried in earth – Hot dip galvanized iron (HDGI)

 Earth electrodes – Cast iron pipe, 125 mm (OD), 10 mm thick 3.5 meter long (As per KTL
standard) or to be selected from earth fault calculation whichever is higher

The sizes of earthing conductors for various electrical equipment shall be confirmed during detailed
engineering as per approved earthing calculation.

Metallic frame of all electrical equipment shall be earthed by two separate and distinct connections to
earthing system. Steel columns, metallic stairs, and rails etc. of the building housing electrical
equipment shall be connected to the nearby earthing grid conductor by one earthing ensured by
bonding the different sections of hand rails and metallic stairs. Metallic sheaths/screens, and armour of
multi-core cables shall be earthed at both ends. Metallic Sheaths and armour of single core cables shall
be earthed at switchgear end only unless otherwise approved. Portable tools, appliances and welding
equipment shall be earthed by flexible insulated cable.

Each continuous laid lengths of cable tray shall be earthed at minimum two places by G.I. flats to
earthing system, the distance between earthing points shall not exceed 30 meter. Wherever earth mat
is not available, necessary connections shall be done by driving an earth electrode in the ground.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 100
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Supporting Structure of Inverter, LT Panel and other similar panel shall be effectively earthed by two
separate and distinct connections to earthing system with AC G.I. flats. String Inverter have body
earthing and potential earthing as per guideline of equipment manufacturer.

Neutral connections and metallic conduits/pipes shall not be used for the equipment earthing.
Lightning protection system down conductors shall not be connected to other earthing conductors
above the ground level.

Connections between earth leads and equipment shall normally be of bolted type. Contact surfaces
shall be thoroughly cleaned before connections. Equipment bolted connections after being tested and
checked shall be painted with anti-corrosive paint/compound.

Connections between equipment earthing leads and between main earthing conductors shall be of
welded type. For rust protection the welds should be treated with red lead compound and afterwards
thickly coated with bitumen compound. All welded connections shall be made by electric arc welding.

Resistance of the joint shall not be more than the resistance of the equivalent length of conductors.

Earthing conductors buried in ground shall be laid minimum 600 mm below grade level unless
otherwise indicated in the drawing. Back filling material to be placed over buried conductors shall be
free from stones and harmful mixtures. Back filling shall be placed in layers of 150 mm.

Earthing conductors embedded in the concrete floor of the building shall have approximately 50 mm
concrete cover.

A minimum earth coverage of 300 mm shall be provided between earth conductor and the bottom of
RCC trench/foundation/underground pipes at crossings. Earthing conductor crossings, the road can be
installed in pipes.

Wherever earthing conductor crosses or runs at less than 300 mm distance along metallic structures
such as gas, water, steam pipe lines, steel reinforcement in concrete, it shall be bonded to the same.
Earthing conductors along their run on columns, walls, etc. shall be supported by suitable welding /
cleating at interval of 1000mm and 750mm respectively.

Earth pit shall be constructed as per IS: 3043. Electrodes shall be embedded below permanent moisture
level. Minimum spacing between two electrodes shall be 3.0 Mtrs. Earth pits shall be treated with salt
and charcoal if average resistance of soil is more than 20 ohm meter. However, based on the soil
resistivity data of the site, in case, the earthing resistance requirements as per applicable standard is
not met, bidder may have to provide special earthing arrangement like chemical earthing etc. in order

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 101
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

to meet the earthing resistance requirements. For chemical earthing, compound shall have pH between
6-8. It shall be used with compatible electrode (cu, cu bonding) as per guidelines of compound
manufacturer. It shall not shrink or expand over the period of time and shall be maintenance free.
Chemical earthing Compound as per afore-mentioned specification. On completion of installation
continuity of earth conductors and efficiency of all bonds and joints shall be checked. Earth resistance
at earth terminations shall be measured and recorded. All equipment required for testing shall be
furnished by bidder.

Depth of burial of main earth conductor shall be 600mm below grade level.

Where conductor crosses trenches, pipes, ducts, tunnels, rail tracks, etc., it shall be at least 300mm
below them.

Conductor joints shall be made by electric arc welding or any other method if approved during detail
engineering, with resistance of joint not more than that of the conductor. Welds to be treated with red
lead for rust protection and then coated with bitumen compound for corrosion protection. In addition
to Equipment earthing pit and 1 (one) no. Isolated earth pit for electronic earthing shall be provided.
Electronic earth pit shall be connected as per guideline of equipment manufacturer.

21.3.5 Solar Array Earthing (For DC Side Earthing)

This section covers earthing for Module, Module Mounting structure, SMB & its mounting structure,
Walkway, Guardrail and other accessories.

Each Module mounting structure (MMS), SPV Module frames, DC Cable tray, Life line, Walkway, Guard
rail, SMB mounting arrangement for String Combiner Boxes, Metallic Junction Boxes, Metal
frames/Panel, Metallic Pipes of the solar array and all individual accessories shall be effectively earthed
by two separate and distinct connections to earthing system. Earthing system for solar array shall
consist interconnected earth pits connected by25X6 GI flat and earthing Conductor of size not less than
120 SQMM laid at the depth of 600 MM below the ground Equipment and structure in the solar
rooftop shall be earthed incompliance to the IS: 3043 (Code of Practice for Earthing) and Indian
Electricity Rules/Acts.

The Bidder shall furnish the detailed design and calculations for Owner’s approval as per IEEE80-
2000/IS 3043 to determine the number of earth pit and size of earth conductor. However, the No. of
earth pits for the solar area shall select as per the calculation for the Solar PV Project and size of earth
buried conductor shall not be less than 25X6 GI flat. Minimum size of riser conductor to connect the
structures to buried earthing conductor in the solar farm shall be 25X6 GI Flat. Location of earth pits

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 102
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

shall be uniformly distributed in the solar farm and shall be interconnected in a single mesh. Location of
earth pit and laying of earth conductor shall be approved during detail engineering.

System Requirement for the solar array:

Life Expectancy 25 Years

System fault level as per system requirement

Soil resistivity Actual as per site conditions

Min. Steel corrosion 0.12mm/year

Connection of G.I. flats with minimum overlapping 150 mm shall be bolted (SS-304 fasteners to be
used) and electric arc welding. Portion of galvanized structure which undergoes welding at site shall be
coated with two coats of cold galvanizing and anti-corrosion paint afterwards thickly coated with
bitumen compound. All welded connections shall be made by electric arc welding.

Earth Conductor Joints by electric arc welding, with resistance of joint not more than that of the
conductor.

Each PV Module frame shall be earthed in accordance with module manufacturer guidelines. In case
module frame earthing is to be separately provided, it shall be earthed as per manufacture guideline
with flexible copper cable with copper lug at suitable location of module frame. Both ends of the loop
of copper cable for earthing shall be connected with nearest earthed structure or earth conductor.

Bidder shall seek owner’s approval for connecting solar array earth mat on roof with any other earth
mat/earth grid of the solar PV plant.

Earth pit shall be constructed as per IS: 3043. Electrodes shall be embedded below permanent moisture
level. Minimum spacing between earthing electrodes shall be 3000mm. Chemical treated earth pits
shall be provided in array side as per given specification in this clause anywhere.

On completion of installation, continuity of earth conductors and efficiency of all bonds and joints shall
be checked. Earth resistance at earth terminations shall be measured and recorded. All equipment
required for testing shall be furnished by bidder.

Size of earth conductor, nos. of earth pits given in this clause is applicable for solar array earthing only.
Method and practice of laying of earthing conductor, earth pits not mentioned herewith but given
elsewhere in this specification is applicable to solar array earthing also.

21.4 Testing

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 103
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The earthing pits and the earthing network tested for following on completion of the installation:

 Earth resistance of electrodes

 Continuity of conductors, joints, etc.

21.5 Submission

The Bidder shall make following essential submissions:

o Site plan indicating earth pits, earthing strip routing, road cross overs, etc.

o Earthing calculations along with schematic drawing for the entire network

o Drawing showing the dimensions, materials and position of all components, earth electrodes,
earth conductors, etc.

22 LIGHTNING PROTECTION SYSTEM

The Solar PV Power plant should be provided with Lightning and overvoltage protection. The “Lightning
Protection System” must be completed prior to start-up of commissioning activities of the project. The
main aim of overvoltage protection is to reduce the overvoltage to a tolerable level before it reaches
the PV or other sub - system components. The source of overvoltage can be lightning or other
atmospheric disturbance.

The Lightning Conductors shall be made as per NFC Standards in order to protect the entire Array Yard
from Lightning stroke. Necessary concrete foundation for holding the lightning conductor in position, to
be made after giving due consideration to maximum wind speed and maintenance requirement at site
in future.

22.1 Codes and Standard

The Lightning protection system & the components used shall conform to the latest edition of the
following codes / Standards, relevant other Indian standards & International standards as applicable.

NFC-17-102 For E.S.E. type Lightning arrester

IS: 2309 Code of practice for protection of Building & Structure against lightning

BS EN:50164
Testing of all metallic part connected to lightning arrester
IEC:62561
UNE 21186-96: For E.S.E. type Lightning arrester

22.2 Down Conductors

Down conductors shall be as short and straight as practicable and shall follow a direct path to earth
electrode.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 104
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Each down conductor shall be provided with a test link at 1000 mm above ground level for testing but it
shall be in accessible to interference. No connections other than the one direct to an earth electrode
shall be made below a test point.

All joints in the down conductors shall be welded type. Down Conductor shall be install over roof and
wall or others with use of Insulator as per manufacture guideline.

Down conductors shall be cleated on outer side of building wall, at 750 mm interval or welded to
outside building columns at 1000 mm interval.

Lightning conductor on roof shall not be directly cleated on surface of roof. Supporting blocks of
Insulator shall be used for conductor fixing at an interval of 1000 mm.

All metallic structures within a vicinity of two meters of the conductors shall be bonded to conductors
of lightning protection system.

Lightning conductors shall not pass through or run inside GI Conduits.

Testing link shall be made of galvanized steel of size 25x 6mm.

Hazardous areas handling inflammable/explosive materials and associated storage areas shall be
protected by a system of aerial earths.

22.3 Lightning Protection System for Solar Array

Complete Solar Array with associated structure shall be protected from Direct Lightning Stroke.
Lightning Protection for solar array shall be achieved with Early Streamer Emission (ESE) Air Terminal
system.

Suitable earthling and equipotential bonding shall be ensured for the air termination rods as per
applicable standard/Equipment manufacturer guidelines.

Current carrying parts and accessories such as clamps, fasteners, down conductor, Test links and earth
termination etc. shall be preferably procured from OEM of Air Terminals if it is supplied by them as part
of lighting protection system.

Location and layout of ESE terminal shall be in such a manner that it cast no shadow on the PV Modules
during 09:00 AM to 04:00 PM (Minimum). Number and location of ESE air terminal shall be decided
during detail engineering. For this purpose, design calculation and AutoCAD drawing of the layout of
ESE terminal shall be submitted for approval.

ESE air terminal shall be type tested in any national/international approved lab for advance triggering
time (ΔT) and lighting Impulse current test and type test report shall be submitted for approval.

Each ESE air terminal shall be provided with separate earthling termination and test link for
equipotential bonding of lighting protection system as per OEM guidelines/NFC 17 -102. Each ESE air

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 105
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

terminal shall be equipped with lightning stroke counter to be fixed at suitable height in serial on the
down conductor.

ESE air terminal shall be erected on isolated foundation to be approved by Client. If required, Suitable
guy wire shall be used to support the mast of ESE terminal against the wind.

Makes

As per Annexure- A

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 106
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

23 FIRE DETECTION AND FIGHTING (FREE ISSUE ITEM BY KTL)

24 WMS

EPC contractor shall provide weather-monitoring sensor to provide adequate meteorological data to
evaluate system performance. Station shall essentially include sensors but not limited to monitoring of
global irradiation on tilted plain, ambient temperature, module temperature, wind speed and direction.

Dedicated Pyranometer shall be used for measurement of global irradiation on tilted plain. Only Kipp &
Zonen or equivalent make Pyranometer shall be used in weather station. Total 2 Nos. of Pyranometer
shall require for Ginning Unit &Open end spinning unit, for spinning unit require 2 Nos. of Pyranometer
and 1 no. of Pyranometer for RCC solar plant as per detailed design engineering. 1 No. of Pyranometer
sensor required to measure GHI (Global horizontal irradiation).

Weather station along with data logger (Recording resolution of 1 minute) shall be located at strategic
point and shall be capable of collecting the data points and sample frequency. The weather Station
shall have capability of recording and storing environmental data without AC power for seven (7) days.
Main auxiliary power to be provided from nearest ACDB. Also, on device data storage should be
provided with an internal SD card of suitable capacity for minimum 31 days storage. The data should be
readable in.csv format, and should be downloadable by an external USB port. The length of the data
cable from any of the sensor to data logger shall not exceed 20 m. The accuracy of any of the following
sensors should be as per manufacture. All the data collected from the weather monitoring station
should be transferred and stored in the SCADA system.

AMBIENT TEMPERATURE SENSOR with solar radiation shield


(a) Ambient Temperature Sensor: Range: - 5 °C to + 95°C, Accuracy: ± 0.1°C. over 0 to 70°C
range, Resolution: 0.1° C, Units of Measure: °C

GLOBAL IRRADIATION PYRANOMETER:


Classification to ISO 9060:1990 - Secondary Standard and IEC 60904 standards
Spectral range (50% points) - 285 to 2800nm
Sensitivity - 7 to 14 V/W/m²
(b)
Impedance - 10 to 100 Ω
Expected output range (0 to 1500 W/m²)- 0 to 20mV
Maximum operational irradiance - 4000 W/m²
Response time (63%) < 1.7s

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 107
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Response time (95%) < 5s


Non-stability (change/year) < 0.5%
Non-linearity (100 to 1000 W/m²) < 0.2%
Directional response (up to 80° with 1000 W/m² beam) < 10 W/m²
Tilt response (0° to 90° at 1000 W/m²) < 0.2%
Detector type - Thermopile
Operational temperature range - -40°C to +80°C
Humidity range - 0 to 100% non-condensing
Ingress Protection (IP) rating - 67

(c) TILTED IRRADIATION PYRANOMETER: Specification As mentioned above ( C )

Solar Radiation Sensor Mount Kit:


For Horizontal Mount: Consists of a rectangular plate, mounting bracket, and mounting
hardware. Dimensions and weight should be as per requirement.
(d)

For Tilted Mount : Consists of a rectangular plate, mounting bracket, and mounting
hardware, Includes slots that can be adjusted to any angle from horizontal to vertical.

Surface Temperature Sensor: (PT 100 sensor)


The sensor should be in silicon rubber under self-adhesive aluminium film. After removing
protective film, it can be glued directly on the surface to be monitored. To be ensured
(e) that sensor holds over entire plant life cycle.
Sensor Element : resistance thermometer (thin film) with four connections in accordance
with DIN 43760 and BS 1904
Operating temperature : -35 to 100°C

Dust/PV soiling monitoring sensor/solution :

(f) Standard as per both approved make

Approved make : kipp & zenon,Campbell

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 108
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Anemometer
Wind Speed :
Range: 0.5 to 60 m/sec, Accuracy ±0.3 m/sec (≤ 10 m/sec) and ± 2% (≥ 10 m/sec),
(g) Resolution 1.0 unit, Units of Measure Wind Speed: m/s and km/h
Wind Direction :
Range 0 – 360°, Accuracy ± 0.1°, Units Displayed East, West, North, South, N-E, N-W, S-E &
S-W

Stand Alone Power Supply Arrangement


Power Supply Charger/Regulator: 12/24 VDC, 100% solid state, True 0 to 100% PWM duty
(h)
cycle, Rated for 25% overloads to auxiliary power supply to sensors & SCADA/DATA
logger.

MOUNTING HARDWARE
Supply of 3 m long mast made from corrosion resistant galvanised steel. It should support
the attachment of sensors and mounts, solar panel and environmental enclosures to
(i)
allow installation over RCC roof along with lightning and grounding rods, grounding
cables, grounding cable clamps, grounding stakes and UV resistant cable ties. One guy kit
to be provided to improve the wind load withstand capacity.

Makes

As per Annexure- A

25 METERING SYSTEM (FREE ISSUE ITEM BY KTL)

Solar plant shall consists of metering system as per local DISCOM rules and regulation. All the Metering
CT, PT, Metering Panel and HT meter shall be as per local DISCOM rules & regulation for plant side.
Each Solar meter shall install and selection as per local DISCOM rules and regulation. Approved makes
of solar meter and HT meter as per Andhra Pradesh solar policy (latest) and local DISCOM.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 109
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ANNEXURE A – Approved Makes


Sr.No Components Preferred Make
Adani/Canadian Solar /GCL/ Hanwha Q cells / Jinko / JA
1 Solar PV Modules solar / Longi/ LG /REC/Sunpower/Trina / Vikram Solar /
Waaree
2 Inverter ABB/Delta/ Huawei / Sungrow / Solaredge/SMA
Module Mounting Structures
3 Birla /Jindal (AL), Essar/Jindal /TATA/SAIL (GI)
(Raw Material)
4 MC4 Connectors/ Y Connector Staubli /Bizlink
5 DC Fuses Cooper Bussmann / Littelfuse
6 String Monitoring Unit Hensel / Trinity Touch / Solaris
ABB/ GE /GPM/Trinity Touch / Prescinto/Proposed
7 Solar Plant Monitoring System
Inverter make own Portal / Schneider/ Equivalent
8 Solar Cable (DC Cable) Leoni/ Lapp
LT Power Cables (including SMB
9 Torrent/ Universal
to Inverter cables)
10 Control Cable Finolex / Lapp
11 Communication cable Lapp

Kipp & Zonen/Campbell


12 Weather Monitoring Sensors
Pyranometer – Campbell / Kipp & Zonen
13 Surge Protection Devices ABB / Citel / DEHNguard / Pheonix
14 LT Switchgear ABB / Schneider / Siemens
15 Power Contactors ABB / Schneider / Siemens
Push Buttons & Indication
16 Siemens / Teknic / Schneider / Abb
Lamps
Control Switches / Selector
17 Switzer / Kaycee / Siemens / Salzer
Switches
Terminal Blocks (Control)-
18 Elmex / Phoenix / Connectwell / Wago.
Wags Screwless
19 Protection Relays ABB / Siemens / GE/Schneider
20 Tri-vector Meter- LT & HT Secure / Local Discom approved make
Electronic Digital MFM (A/ V/
21 Secure
pf/ Hz/ kWh)
22 Instrument Transformers Metering CT – PT: Approved makes from Local discom
23 Cable Glands Comet/Cosmos

For GI-Globe Electrical Industries / Ratan/ Mettalite /


Cable tray and associated
24 Indiana / Technocraft / Premier / Patny/ Gk Smith/Ike/S3
hardware as per specification
Energy/Equivalent

25 LED Indicating Lamps Altos / GE Power Control / Schneider / Siemens / Teknic


26 Earthing Material JMV/ Balaji/ Ashlok/ VNT/ SABO/Raychem
Lightning Arrestor with lighting
27 VNT/ JMV/ SABO/LPI/Raychem
counter

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 110
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Bolts, Nut and


28 Kundan/APL or Equivalent
Washers(Fasteners)
29 Painting System Berger/Asian Paints/Jenson Nicholson
30 Anchor Fasteners Hilti /Fischer
31 Self-Drilling screw Hilti
GI/UPVC Pipe and fittings
32 Astral/Apolo/Supreme /Jindal or Equivalent
(Module Cleaning System)
UPVC pipe (DC
33 Cable,Communication Astral/Apolo/Supreme
Cable,Control Cable laying)
34 Booster pump Kirloskar /Crompton/Lubi
35 Water Tank Sintex/Supreme
36 EPDM rubber 3M/Hilti
37 FRP Walk way Hindustan Fibre Tech / Fiber tech composite or Equivalent
38 Life Line-SS Reputed

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 111
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ANNEXURE B – Project Characteristics of PV Plant (To Be Filled By EPC


Contractor)
Sr.No. Parameter Unit Values

1 Sources used for following Data (for each shed/tilt/orientation)

Solar Resource

Global Horizontal Irradiation (GHI)

Global Tilt Irradiation (GTI)

Temperature

Precipitation

Wind
2 Project Capacity

AC Capacity KW

DC Capacity KWp

Overloading capacity of project (KWp/KW) %

3 String Details (Maximum)

Module capacity Watt

Number of Modules in a String Nos.

String Power Capacity kWp

Open Circuit Voltage of String(Voc) V

Short Circuit Current of String(Isc) A


4 SMB Details

Number of Inputs Nos.

String Combiner Box(SMB) Power Capacity kWp

Open Circuit Voltage of SMB(Voc) V

Short Circuit Current of SMB(Isc) A


5 Inverter Details

Number of Inverter with rating use in


Design

(i) Input Data

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 112
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Inverter Manufacturer and Model

Nominal DC Power kWdc

Maximum DC Power kWdc

MPPTVoltage Range Vdc

Maximum DC Voltage Vdc

Maximum DC Current Adc

Number of DC inputs Nos.

Number of MPPT Nos.

Number of Strings per MPPT Nos.

Threshold voltage Vdc


(ii) Output Data

Continuous AC Power at 50°C kWac

Nominal AC Voltage with Tolerance Vac


(iii) Efficiencies

Maximum Efficiency %

European Efficiency %

CEC Weighted Efficiency %


6 String Summary per Inverter

Modules per String Nos.

Strings per Inverter Nos.

Strings per MPPT

Nominal Power Ratio

Inverter Maximum Power (Pmax) at STC kWp


7 Module Mounting Structure

(i) Fixed Structure (Shed)


Manufacturer and Model of Mounting
O
Tilt
O
Azimuth

RoofCoverage Ratio %

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 113
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Area per KW m2

(i) Fixed Structure (RCC)

Manufacturer and Model of Mounting


O
Tilt
O
Azimuth

RoofCoverage Ratio %

Area per KW m2

8 System Loss Factor

Low irradiance %

Module temperature %

Soiling %

Shading %

Module quality %

Module mismatch %

DC ohmic %

Inverter performance %

Auxiliary Consumption %

AC ohmic %

Total Annual Loss Factor %

First Year Degradation %

Annual Degradation %
9 Plant Performance

Guaranteed Generation KWh

Year1 KWh

Year2 KWh

Year3 KWh

Year4 KWh

Year5 KWh

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 114
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ANNEXURE C – Technical Specifications of Key Components (To Be Filled


By EPC Contractor)
Bidders are expected to completely fill in the following data sheets and submit along with offer.

Solar PV Modules

Bidders may offer a maximum of three different models of Mono-PERC modules depending on
availability and manufacturing capacities.

Option 1 Option 2

Model

Peak Power Watts (Wp)

Power Output Tolerance (%)

Cell Type & No. of Cells

No. Bypass Diodes

Fill Factor

Under standard operating conditions at Irradiance 1000 W/m2 and Temperature 25°C

Encapsulated Cell Efficiency (%)

Module Efficiency (%)

Maximum Power Voltage(V)

Maximum Power Current(A)

Open Circuit Voltage(V)

Short Circuit Current(A)

Nominal operating conditions at Irradiance 800 W/m2 and Ambient Temperature 40°C

Maximum Power(W)

Maximum Power Voltage(V)

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 115
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Maximum Power Current(I)

Open Circuit Voltage(V)

Short Circuit Current(A)

Temperature Ratings

Nominal Operating Cell Temperature

Temperature Coefficient of Pmpp

Temperature Coefficient of Voc

Temperature Coefficient of Isc

Efficiency Reduction

(From1000W/m2to200 W/m2)

How many times IEC certified module? (Single


/double/ Triple)

PVEL test report of module by DNV-GL will provide


or not?

Nominal Power Output

0–5 years(W)

6–10years(W)

11–25years(W)

25–30years(W)

Inverters

S.
Parameter Units Option 1 Option 2
No.

(i) Make and Model

(ii) Input (DC)

Rated DC Power

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 116
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Maximum DC Power

Maximum DC Voltage

MPPT Voltage Range

DC Nominal Voltage
Minimum DC Voltage/ Start
Voltage
Maximum Input Current/ String

Numbers of MPPT

Numbers of Strings per MPPT

Imax of Each MPPT

Isc of Each MPPT


(iii) Output (AC)

AC Nominal Power

Nominal AC Voltage

Nominal AC Current

AC Frequency Range

Max Power Factor(Cosφ)

Max THD
(iv) Efficiency

Max. Efficiency

Euro Efficiency
(v) Power Consumption

Internal Consumption in
Operation
Internal Night Consumption

External Auxiliary Supply Voltage

Operating Temperature Range

Degree of Protection

Noise Emission

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 117
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Overall Dimensions
(vi) Power optimizer (if use)
Make and Model

Number of inputs module

Input DC Power

Maximum DC voltage

MPPT Voltage Range

Max. Efficiency
Maximum system allowable
voltage
Dimension (W X L X H)

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 118
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ANNEXURE D – List of Spares (To Be Filled by EPC contractor)


The Bidders are required to attach the List of Spares to be maintained at the plant store yard for
operation and maintenance of the plant for a period of 5 years including the warranties, replacement
cost, etc.

SPARES LIST

Sr. Unit Total Total


Description of Material Unit Qty. GST
No Price Price Price

10

Total Price

Note: Use additional sheets of the same format, if required.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 119
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

ANNEXURE E – List Of Deviations


(To be submitted in Bidder’s Company Letter Head)

Statement of Variations &


Section Page No. Reason / Notes
Deviations

Note: Use additional sheets of the same format, if required.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 120
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

CONCEPT NOTE ON PG TEST

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 121
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1 Project Details
DC capacity : 2.6 MWp

PG test period for plant acceptance : 90Days

2 Definitions
“Commissioning” – 100% Completion, functioning, installation and testing of DC and AC capacity,
connectivity of SCADA and WMS in working condition and Thirty days of successful operation of plant
without any equipment downtime.

“Handover” – 100% completion of scope of work including 100% closure of punch points if any.

3 Introduction

The purpose of this document is to define the measurement procedure and technique for plant
performance guarantee measurement technique.

The referred plant is located the state of Andhra Pradesh in the Southern part of India. The plant
irradiance shall be measure with the help of Pyranometer installed for Global horizontal irradiation
measurement & at all different orientation at plane of array, with help of the tilt kit. The Solar
irradiance sensor shall be cleaned on daily basis to ensure accurate reference data for plant
performance measurement.

4 Reference Project Characteristics

1 Project Location Chowdavaram, Guntur, Andhra Pradesh

2 Project Capacity 2.6 MWp

3 Project Overloading Ratio DC:AC = 1:1.30

4 MMS #Fixed tilt type MMS

5 Performance Guarantee (Generation Guarantee)


Bidder shall quoted minimum value of Annual Generation (G) for 2.6 MWp plant shall be 3.9 MU and
limiting value of 4.5 MU.

Maximum Generation difference between current O&M year to next O&M year will be considered at
0.65 % maximum. Bidder shall submit generation guarantee base on 0.65 % (Δ) year on year
degradation for 5 years O&M period.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 122
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Bidder will submit PVSyst report with guaranteed generation, PG, Temperature, GHI in excel format for
each Orientation/ Tilt/ Roof from PVSyst as a part of contract for 5 year O&M period. PVsyst details
shall be approved by Owner/ Consultant.

Once successful commissioning of solar plant with 30 days test period, PG test shall carried out for a
period of 90 days after completion of commissioning period and on a yearly basis based on guarantee
given as per EPC contract. PG test shall start with starting of O&M period.

6 Instruments Used

The data collection and recording will be done using SCADA/Plant Monitoring system platform and
physical at actual site. Weather sensors, meter and the data logger used for Acceptance Test are
permanently located at the site.

7 Performance Guarantee LD for Shortfall

(I) Liquidated damage apply for failure in achieving the guaranteed performance of the Plant:

The following is the Procedure stipulated for Performance Guarantee (PG) Test:

7.1 The final acceptance test as to prove the Performance Guarantee shall be conducted at Site
by the Contractor in presence of the KTL/Consultant.

7.2 This test shall be binding on both the parties of the Contract to determine compliance
of the equipment with the functional guarantee. Any special equipment, instrumentation
tools and tackles and manpower, required for the successful completion of the
Performance Guarantee Test shall be provided by the Contractor free of cost. The accuracy
class of the instrumentation shall be as per the relevant clause of documents.

7.3 The procedure for PG demonstration test shall be as follow:

 Any consecutive Three months period from the date of commissioning for the purpose
of conducting performance guarantee test shall be chosen on the discretion of KTL.
Bidder is required to quote the annual target generation in the techno-commercial bid.
 Bidder has also to quote the month wise Target Generation for all the different tilt
Orientation for solar plant capacity combined for PG test.
 Bidder shall provide performance guarantee for 5 years at the time of bidding that will be
consider as a part of contract and evaluation.
 In addition to the pyrometers to be supplied under the scope of work, the contractor
shall install calibrated Pyranometer at horizontal plane and at all different orientation
of plane of array locations with help of the tilt kit mutually agreed by Contractor and
KTL.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 123
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 Contractor shall also install data logger to store all the pyranometers data during test
period. A valid test reports for the installed pyranometers shall be submitted by
the Contractor for approval to KTL. The output of all pyranometers mounted on
horizontal plane and plane of array shall be made available at SCADA for all time after
commissioning of the project. The pyrometer to be kept cleaned all the time.
 Actual energy exported from the plant shall be noted for three consecutive month
period. For this purpose, the net energy exported at 400V solar evacuation point
located in solar plant near to client LT panels and Pyranometer reading shall be noted
at agreed frequency on daily basis for entire PG test period.
 PVSyst to be prepared by bidder and submit as a part of contract.
 This measured value of energy shall be compared with Month wise Target Generation
for the PG test.
 Following factors shall be considered for computing the target Generation and
shortfall (if any):
o Effect of any meteorological parameters shall not be considered except of
solar radiation.
o Variation of Performance Guarantee on account of Generation loss due to
grid outage.
o The measured global solar radiation of the period of the outage of the power
evacuation system shall be excluded to calculate the cumulative global
Insolation for the month.
 Further, if the plant is not able to achieve the target generation as per the PG
procedure during the test period, then contractor shall compensate KTL with an
amount equivalent to the loss of generation based on sample calculation @ INR 54.90
per kWhr shortfall.
 A sample calculation of PG test for shortfall in energy generation for period from 15th
March to 12th June and LD calculation for XX KWp/Orientation/Tilt of the site is given
below:

Month March April May June


Global Solar insolation of the month
(kWhr/(m2Xday) (Data Provided by KTL) 174.7 178.7 184.7 144.6
(I)
Target Generation (KWhr) (Final Target
71721 72591 74435 59580
generation from GPVSyst) (II)

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 124
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

No of test days of the month (III) 15 30 31 12


Reference Solar insolation (A= I x III/
84.53 178.70 184.70 57.84
Ndm*)
Modified Target Generation of the
34703.71 72591.00 74435.00 23832.00
month KWhr (B= II x A/I)
Measured Global Horizontal Solar
82.34 180.35 182.68 55.47
insolation (kWhr/m2) (C)
Corrected Target Generation(KWhr)
33803.70 73261.26 73620.93 22855.48
(D=B x C/A)
Measured Generation at 400V Metering
32927.04 73937.71 72815.76 21918.98
(KWhr) (E)
Shortfall in energy for PG test (F=D-E) 876.66 -676.45 805.17 936.51

GPVSyst= Total sum of all PVSyst Generation /Orientation/ Tilt

Ndsm= Nos of days in the month

# Negative (-) value denotes excess generation


Total Short fall in Energy for the test period 876.66-676.45+805.17+936.51=1941.89 KWhr
(Ftotal):
Modified Target generation for the test 205561.71 KWhr
period (Btotal):
Target yearly generation (Gyear): 753274 KWhr
Yearly shortfall in generation(∆GSyear) 753274 x 1941.89/205561.71=7115.99 KWhr
: Gyear x Ftotal / Btotal
Yearly loss of Revenue and applicable LD : 7115.99 x 54.90
(INR) : ∆GSyear x R x N = Rs 3,90,667.90

N= Present worth Factor taking discount factor of 12% for 25 Years: 7.84313

R=Unit rate of factory = 7.0 Rs

LD for per unit shortfall in generation= N x R=7.84313x7 =54.90 Rs /kWhr

8 Performance Guarantee Incentive:

Bidder shall get incentive in case of getting higher generation with respect to targeted generation
during PG test and O&M period. KTL shall provide 2 Rs/KWhr for every excess unit of generation
reference to targeted generation at LT metering point during PG test and Rs 1/KWhr during O&M
period.

9 PG test Conditions

 Pyranometer must be cleaned daily as per time schedule approved by


Consultant/Owner. Cleaning log should be maintain daily in log book with data and
time, which should be signed on daily basis by owner’s representative.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 125
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

 WMS including Pyranometer shall be monitoring by KTL’s CCTV surveillance system


continuously.
 Module cleaning cycle as per contractor schedule. The schedule shall be made part
of the contract as well.
 Data used for the calculation will be extracted from the Data Monitoring system
installed at site and approved by the Consultant/ Owner.
 PG test shall be performed for each solar evacuation point individually. Bidder have
to pass PG test for all solar plant as per contract.
 During PG testing period Plant availability of the facility must be 100 % over such
period.

10 Guaranteed Availability and LD for Shortfall

The bidder shall maintain maximum plant availability factor for achieving Guarantee generation as per
contract during O&M period.

Due to unavailability of plant, if the plant is not able to achieve the target generation as per the PG
procedure during the O&M period, then contractor shall compensate KTL with an amount equivalent
to the loss of generation based on actual factory tariff@ INR 7.0 per kWhr shortfall.

11 Exception and Remedies

Grid Unavailability and System Downtime

System downtime for reasons beyond contractor’s control like Force Majeure & grid unavailability
during O&M period should be excluded from Performance Guarantee calculations. Radiation & it’s
deemed generation during non-grid availability and due to force majeure conditions will not be
considered for performance calculation.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 126
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SECTION - III
GENERAL CONTRACT CONDITIONS

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 127
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1 RIGHTS OF KTL
KTL reserves its right to accept or reject any bid, or to annul the bidding process and reject all bids any
time prior to the award of Contracts, without thereby incurring any liability to the affected Bidder or
Bidders or any obligation to inform the affected Bidder or Bidders of the grounds of the KTL’s action.

The KTL reserves its right to vary, modify, revise, amend or change any of the terms and conditions of
the Bid.

The decision regarding acceptance of bid by the KTL will be full and final.

The KTL is free to phase out the work if it feels it necessary.

The decision taken by the KTL in the process of Bid evaluation will be full and final. The KTL has been
authorized as competent and final decision-making authority as far as the present bid for EPC cum
O&M of 2.6 MWp Solar Power Project is concerned.

2 CLARIFICATIONS / AMENDMENTS BY KTL


KTL may issue clarifications/amendments in the form of addendum/corrigendum during the bidding
period and may also issue amendments subsequent to receiving the offers. For the
addendum/corrigendum issued during the bidding period, Bidder shall confirm their impact in the bid.
For clarifications issued by KTL subsequent to receiving offers, the Bidder shall confirm receipt and for
any impact on the quoted prices. The Bidder shall follow the instructions issued along with
addendum/corrigendum.

Bidder shall examine the documents thoroughly and submit to KTL any apparent conflict, discrepancy
or error. KTL shall issue any appropriate clarification or amendment. Any failure by Bidder to comply
with the aforesaid shall not excuse the Bidder, if subsequently awarded the contract, from performing
the service in accordance with the agreement.

KTL reserves the right to review/evaluate and make their own assessment of the offers in its entirety
and seek more clarifications/information with reference to all or any other information/documents
submitted. Bidders are informed that KTL is neither under any obligation in resorting to short-listing of
Bidders for qualifying, nor to give reasons for either qualifying or disqualifying any Bidder. KTL is not
under any obligation to proceed with or any part thereof.

Bidder shall be prepared to furnish clarifications/information, however, if asked for and attend
discussions, as required by KTL at short notices. Bids from those Bidders who fail to turn up for
discussions or furnish the required clarifications called for by KTL to his satisfaction may not be
considered.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 128
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

3 CONFIDENTIALITY OF DOCUMENTS
Bidder shall treat bid documents and contents therein private and confidential. The bid document is
exclusively prepared for the said project and is an intellectual property of KTL. If, at any time, during
the bid preparation period, the Bidder decides to decline to offer, all documents must be immediately
returned.

4 CAUTION AND DISCLAIMER


The Bidder shall be responsible for obtaining and verifying all necessary data and information. In case
any clarification is required, the same may be obtained from KTL.

Clarifications of Contents of Tender Document

In case an intending Bidder requires any clarification in connection with, or any point covered in, the
tender documents, or as to any matter or work to be done or not to be done by them in the event the
contract for the work is awarded to them, he must submit a request for such clarification in writing and
through Email so as to reach the Company as otherwise prescribed in S.C.C. (Special Conditions of
Contract) Copies. Such clarifications furnished by the Bidder will be supplied to all other intending
Bidders to whom the tender documents may have been sold by KTL. Such clarifications will constitute
addenda/corrigenda to, and be read as part of the tender document.

KTL will not be bound by any verbal/oral clarification or interpretation of the tender document or of
any matter(s) connected with works to be executed in accordance with the tender documents, which
may be made by any of its employee, representatives or agent.

Any neglect or failure on the part of the Bidder in obtaining necessary and reliable information upon
the foregoing or any other matters affecting the contract shall not relieve them from any risks or
liabilities or the responsibility from completion of the works at the scheduled rate/s & time and in strict
accordance with the contract document/s.

Addenda/ Corrigenda

Addenda/Corrigenda to this tender document may be issued to clarify documents or to reflect


modification in the specifications or terms & conditions or scope of work or for any other reasons.

Addenda/corrigenda to these tender documents, if issued by the company, shall form an integral part
of this tender document and must be signed and submitted along with the bid.

Currencies of Bid & Payment

The unit rates and prices shall be quoted by the Bidder entirely in Indian National Revenue i.e. Indian
Rupees.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 129
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

5 CONTRACT STRUCTURE
In case of commercial requirement, KTL may place separate contracts for supply and services as
mentioned below:

For detailed designing, engineering, manufacturing, supply and delivery at site of equipment &
material.

For all approvals, all construction work at site, erection and commissioning etc., complete in all respect.

For comprehensive operation and maintenance of the 2.6 MWp Grid Connected Solar Photovoltaic
Power Plant for a period of Five (5) years from the date of commissioning and Acceptance of plant

For offshore supply and services, in case of commercial requirement KTL may choose to place contracts
for offshore separately.

6 INTERPRETATION OF CONTRACT DOCUMENTS:


Several documents forming the contract are to be taken as mutually explanatory. Should there be any
discrepancy, inconsistency, error or omission in the contract or any of them, the matters may be
referred to Engineer-in –Charge, whose decision shall be final and conclusive and the Contractor shall
carry out work in accordance with his decision.

7 INSTRUCTIONS TO BIDDER
"Instructions to Bidder " shall be read in conjunction with the General Conditions of Contract,
specifications of work, drawings and any other documents forming part of this contract wherever the
context so requires.

Notwithstanding the sub-division of the Documents into these separate sections and Volumes, every
part of each shall be deemed to be supplementary of every other part and shall be read with and into
the contract so far as it may be practicable to do so.

Where any portion of the General Conditions of Contract is repugnant to or at variance with any
provisions of the Instruction to Bidder, then unless a different intention appear, the provisions of the
Instructions to Bidder shall be deemed to override the provision of the General Conditions of Contract
and shall to the extent of such repugnancy of variation prevail.

Wherever it is mentioned in the specifications that the Contractor shall perform certain work or
provide certain facilities, it is understood that the Contractor shall do so and the cost, if any, deemed to
be included in the price.

The materials, design and workmanship, the job specifications contained herein and codes referred to
shall satisfy the relevant Indian Standard. Where the job specifications stipulate requirements in

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 130
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

addition to those contained in the standard codes and specification, these additional requirements
shall also be satisfied.

8 TERMINATION FOR DEFAULT & ENCASHMENT OF PERFORMANCE


BANK GUARANTEE
Contractor’s Event of Default

The occurrence of any of the following events at any time during the contract period shall constitute an
Event of Default by the Contractor:

The Contractor fails to deliver or execute any or all of the goods within the time period(s) under the
contract or any extension thereof granted by the Owner and the LD limit as specified in Special
Condition of Contract Commercial is breached.

The Contractor does not replenish or provide fresh performance guarantee upon encashment of
Performance guarantee by KTL

The Contractor fails to perform any other obligations(s) under the contract.

The Contractor assigns mortgages or charges or purports to assign, mortgage or charge any of its assets
or rights related to the project in contravention of the provisions of this Agreement.

The Contractor transfers or novates any of its rights and/ or obligations under this agreement, in a
manner contrary to the provisions of this Agreement; except where such transfer is in pursuance of a
Law; and does not affect the ability of the transferee to perform, and such transferee has the financial
capability to perform, its obligations under this Agreement oris to a transferee who assumes such
obligations under this Agreement and the Agreement remains effective with respect to the transferee;

If (a) the Contractor becomes voluntarily or involuntarily the subject of any bankruptcy or insolvency or
winding up proceedings and such proceedings remain uncontested for a period of thirty (30) days, or
(b) any winding up or bankruptcy or insolvency order is passed against the Contractor, or (c) the
Contractor goes into liquidation or dissolution or has a receiver or any similar officer appointed over all
or substantially all of its assets or official liquidator is appointed to manage its affairs, pursuant to Law,
Provided that a dissolution or liquidation of the Contractor will not be a Contractor Event of Default if
such dissolution or liquidation is for the purpose of a merger, consolidation or reorganization and
where the resulting company retains creditworthiness similar to the Contractor and expressly assumes
all obligations of the Contractor under this Agreement and is in a position to perform them.

The Contractor repudiates this Agreement and does not rectify such breach within a period of thirty
(30) days from a notice from KTL in this regard

The Contractor is in breach of any of its material obligations pursuant to this Agreement, and such
material breach is not rectified by the Contractor within thirty (30) days of receipt of first notice in this
regard given by KTL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 131
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The equity stake of the Parent Company/Ultimate Parent Company falls below the minimum prescribed
in this RFP

If the contract is suspended for a period as provided in this RFP.

Owner’s Event of Default

The occurrence of any of the following at any time during the Contract period shall constitute an Event
of Default by the Owner:

Failure or refusal by Owner to pay any portion of undisputed monthly bill for a period of 90 days after
due date

The Owner repudiates this agreement and does not rectify such breach even within a period of thirty
(30) days from a notice from Contractor in this regard.

If the Owner becomes voluntarily or involuntarily the subject of proceeding under any bankruptcy or
insolvency laws or goes into liquidation or dissolution or has a receiver appointed over it or liquidator is
appointed, pursuant to Law, except where such dissolution of KTL is for the purpose of a merger,
consolidated or reorganization and where the resulting entity has the financial standing to perform its
obligations under this Agreement and creditworthiness similar to Owner and expressly assumes all
obligations under this agreement and is in a position to perform them.

Termination for Contractor’s Default

Upon the occurrence of an event of default as set out in the herein this document, KTL may deliver a
Default Notice to the Contractor in writing which shall specify in reasonable detail the Event of Default
giving rise to the default notice, and calling upon the Contractor to remedy the same.

At the expiry of 30 (thirty) days from the delivery of this default notice and unless the Parties have
agreed otherwise, or the Event of Default giving rise to the default notice has been remedied, KTL may
deliver a Termination Notice to the Contractor. The Performance guarantee provided by the Contractor
shall be forfeited and no amount due to the Contractor shall be paid by the Owner.

Where a Default Notice has been issued with respect to an Event of Default, which requires the co-
operation of both KTL and the Contractor to remedy, KTL shall render all reasonable co-operation to
enable the Event of Default to be remedied without any legal obligations

Termination at KTL/Owner’s Convenience. The KTL/Owner may terminate the Contract by written
notice at any time without assigning any reason whatsoever. However, written notice of not less than
thirty (30) days shall be provided by the Owner. If this Agreement is terminated by the Owner as per
this Article, the Contractor shall be entitled to the payment of its Services duly performed up-to the
date of termination of this Contract as also any unavoidable, and demonstrable and reasonable costs of
demobilization or for cancellation of any subcontract which it may have issued.

Termination for Owner’s Default

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 132
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Upon the occurrence of an event of default as set out in the clause above, Contractor may deliver a
Default Notice to the Owner in writing which shall specify in reasonable detail the Event of Default
giving rise to the default notice, and calling upon the Owner to remedy the same.

At the expiry of 30 (thirty) days from the delivery of this default notice and unless the Parties have
agreed otherwise, or the Event of Default giving rise to the default notice has been remedied,
Contractor may deliver a Termination Notice to the Owner

9 BREACH OF CONTRACT
The Contractor shall be responsible and be liable for failure to comply with any part of the contract. In
the event of the plant being not successfully commissioned then for the purpose of calculating the
damages, loss etc. the Contractor shall be responsible for total value of the different components
under this contract.

10 NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK

If at any time from the commencement of the work, KTL shall for any reason whatsoever not require
the whole work including supplies or part thereof as specified in the contract to be carried out, KTL
shall give notice in writing of the fact to the contractor, who shall have no claim to any payment or
compensation whatsoever on account of any profit or advantage which he might have derived from the
execution of the contract in full, but which he did not drive in consequence of the full amount of the
work not having been carried out neither shall he has any claim for compensation by reason for any
alterations having been made in the original specification, drawing, designs and instruction which shall
involve any curtailment from the originally contemplated.

11 CHANGES IN CONSTITUTION

Where the Contractor is a partnership firm, the prior approval in writing of the KTL shall be obtained
before any change is made in the constitution of the Firm. Where the Contractor is an individual or a
Hindu undivided Family business concern, such approval as aforesaid shall, likewise be obtained before
such Contractor enter into any agreement with other parties, where under, the reconstituted Firm
would have the right to carry out the work hereby undertaken by the Contractor.

12 MEMBERS OF THE KTL NOT INDIVIDUALLY LIABLE


No office bearer of the KTL shall in any way be personally bound or liable for the acts or obligations of
the KTL under the contract or answerable for any default or omission in the observance of performance
of any acts, matters, of things, which are herein contained.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 133
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

13 KTL NOT BOUND BY PERSONAL REPRESENTATIONS

The Contractor shall not be entitled to any increase on the scheduled rates or other right or claim
whatsoever by reason of any representation, explanation statement or alleged representation, promise
or guarantees given or alleged to have been given to them by any person.

14 NOTICES

14.1 Service of Notice on Contractor

Any notice hereunder may be served on the Contractor or his duly authorized representative by
registered mail direct to the address furnished by the contractor. Proof of issue of any such notice shall
be conclusive of the contractor having been duly informed of all contents therein.

Service of Notice on KTL

Any notice to be given to the KTL under the terms of the contract shall be served by sending the same
by Registered post to or delivering the same at the office of KTL.

15 LIENS

If at any time, there should be evidence or any lien or claim for which the KTL might have become liable
and which is chargeable to the Contractor, the KTL shall have the right to retain out of any payment
then due or thereafter to become due an amount sufficient to completely indemnify KTL against such
lien or claim and if such lien or claim be valid, KTL may pay and discharge the same and deduct the
amount so paid from any money which may be or may become due and payable to the Contractor. If
any lien or claim remain un-settled after all payments are made, the Contractor shall refund or pay to
the KTL all money that the latter may be compelled to pay in discharging such lieu or claim including all
costs and reasonable expenses.

16 KTL NOT LIABLE TO PAY COMPENSATION

The contractor shall have no claim against the KTL for any damages or for compensation for the reason
of any failure or omission on the part of the KTL to carry out the provisions of the Contract for any
reason beyond its control. However, the KTL would consider such instances on their merit.

17 EXECUTION OF CONTRACT

17.1 General

All the activities of the contract shall be executed in strict conformity with the provisions of the
contract documents and with such explanatory detailed drawings, specifications and instructions as
may be furnished from time to time to the Contractor by the KTL mentioned in the contract or not. The

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 134
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Contractor shall be responsible for ensuring that the contract is executed in the most substantial,
proper and workmanlike manner with the quality of materials and workmanship in strict accordance
with the specifications and to the entire satisfaction of the KTL.

The Co-ordination and inspection of the day-to-day work under the contract shall be the responsibility
of the Engineer-in-Charge or his authorized representative. The Contractor in which the aforesaid
written instructions will be entered will maintain a work order book. The Contractor or his authorized
representative will sign these by way of acknowledgement within 12 hours.

17.2 Construction of Plant and Equipment

The Contractor shall provide and install all necessary construction plant, equipment and machinery
required for the execution of the work under the contract, at his own cost and shall use such methods
and appliances for the purpose of all the operations connected with the work covered by the contract
which shall ensure the completion of works(s) within the specified time.

The Contractor shall submit full details of construction plant, equipment and machinery proposed to be
deployed for the work(s) along with its planning schedule.

17.3 Work in Monsoon and De-watering

The execution of work may entail working in the monsoon also. The contractor must maintain a
minimum labor force as may be required for the job and plant and execute the construction and
erection according to the prescribed schedule. No extra rate will be considered for such work in
monsoon.

During monsoon and other period, it shall be the responsibility of the contractor to keep the
construction work site free from water at its own cost.

17.4 Setting out Works

The Engineer-in-Charge shall furnish the Contractor with only the four corners of the work site and a
level bench mark and the Contractor shall set out the works and shall provide an efficient staff for the
purpose and shall be solely responsible for the accuracy of such setting out.

The Contractor shall provide, fix and be responsible for the maintenance of all stacks, templates, level
marks, profiles and other similar things and shall take all necessary precautions to prevent their
removal or disturbance and shall be responsible for the consequence of such removal or disturbance
should the same take place and for their efficient and timely reinstatement. The approval thereof or
joining with the Contractor by the Engineer-in-Charge in setting out the work shall not relieve the
Contractor of any of his responsibilities.

Before beginnings the works, the Contractor shall at his own cost, provide all necessary materials for
proper layout of the work in accordance with the scheme for bearing marks acceptable to the Engineer-
in-Charge. No work shall be started until all these points are checked and approved by Engineer-in-

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 135
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Charge in writing but such approval shall not relieve the Contractor of any of his responsibilities. The
contractor shall also provide all labour, materials and other facilities, as necessary for the proper
checking of layout and inspection of the points during construction.

On completion of work, the Contractor shall submit the geodetic documents according to which the
work was carried out.

18 RESPONSIBILITY FOR LEVEL AND ALIGNMENT

The Contractor shall be entirely and exclusively responsible for the horizontal and vertical alignment,
the level and correctness of every part of the work and shall rectify effectually and errors or
imperfections therein. The Contractor, at his own cost, shall carry out such rectification when
instructions are issued to that effect by the Engineer-in-Charge.

19 TESTS FOR QUALITY OF WORKS

All materials and workmanship shall be of respective kinds described in the contract document and in
accordance with the instructions of the Engineer-in-Charge and shall be subjected from time to time to
such tests at contractor's cost as the Engineer-in-Charge may direct at the place of fabrication or at the
site or at any such places. The contractor shall provide assistance, instruments, machines, labor and
materials as are normally required for examining, measuring and testing any workmanship as may be
selected and required by the Engineer-in-Charge.

All the tests that will be necessary in connection with the execution of the work as decided by
Engineer-in-Charge shall be carried out at the cost of Contractor at Government or any other testing
laboratory as directed by Engineer-in-Charge.

20 SAMPLES

The contractor shall furnish to the Engineer-in-Charge for approval when requested or if required by
the specifications, adequate samples of all materials and finishes to be used in the work. Such samples
shall be submitted before the work is commenced and in sample time to permit tests and examinations
thereof. All materials furnished and finishes applied in actual work shall be fully equal to the approved
samples.

21 MATERIALS OBTAINED FROM DISMANTLING

If the Contractor in the course of execution of the work is called upon to dismantle any part for reason
other than those stipulated in here-in-above, the materials obtained in the work of dismantling etc.,
will be considered as the KTL's property and will be disposed off to the best advantage of the KTL.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 136
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

22 ARTICLES OF VALUE FOUND

All gold, Silver and other minerals of any description and all precious stones, coins, treasure, relics,
antiquities and other similar things which shall be found in under or upon the site, shall be the property
of the KTL and the contractor shall duly preserve the same to the satisfaction of the Engineer-in-Charge
and shall from time to time deliver the same to such person or persons indicated by the KTL.

23 SECURITY ARRANGEMENTS

The contractor shall provide and maintain at his own expense all security personnel, other
arrangements including fencing, lighting etc., wherever necessary of the protection of the works and
for the safety convenience of those employed on the works at site.

24 CARE OF WORKS

From the commencement to completion of the works, the contractor shall take full responsibility for
the care of all works including all temporary works and in case any damage, loss or injury shall happen
to the works or to any part thereof or to any temporary works form any cause whatsoever, shall at his
own cost repair and make good the same so that at completion, the work shall be in good order and in
conformity in every respect with the requirements of the contract and the Engineer-in-charge's
instructions.

25 DRAWINGS TO BE SENT AT SITE

The Contractor shall take the following action with reference to drawings:

Detailed working drawings on the basis of which actual execution of the work shall be carried out, will
be furnished by the contractor to his site supervisor from time to time during the progress of the work.

Copies of all detailed working drawings, relating to the works shall be kept at the contractor's office on
the site and shall be made available to the Engineer-in-Charge at any time during the construction. The
drawings and other documents issued by the KTL shall be returned to the KTL on completion of the
works.

26 BILLING

The contractor will submit a bill in four copies to the Engineer-in-Charge of the work giving abstract and
detailed measurement for the various items executed during a month before the expiry of the first
week of succeeding month. The Engineer-in-Charge shall take or cause to be taken the requisite
measurements for the purpose of having the same verified and the claim, as far as admissible,
adjusted, if possible, before the expiry of 30 days from presentation of the bill.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 137
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

27 ALTERATIONS IN SPECIFICATIONS AND DESIGNS AND EXTRA WORK


INCLUDING SUPPLIES
The KTL shall have power to make any alternation/deletion/additions to or substitutions in the original
specifications, drawing, designs and instructions that may appear to them to be necessary or advisable
during the progress of the work, and the contractor shall be bound to carry out such
deletion/addition/alteration or substitution of work including supplies in accordance with any
instructions which may be given to them in writing signed by the KTL/Engineer-in-Charge, and such
alterations, deletions, additions or substitutions shall not invalidate the contract and any altered,
deleted, additional or substituted work, supplies which the contractor may be directed to do in the
manner above specified as part of the work shall be carried out by the contractor on the same
conditions in all respects on which he agreed to do the main work. The time of completion of work may
be extended for the part of the particular job at discretion of the Engineer-in-Charge for only such
alteration, deletions or substitutions of the work including supplies as he may consider as just and
reasonable. The rates for such additional deleted, altered or substituted supplied under this Para shall
be worked out in accordance with the following provisions:

If the rates for additional, deleted, altered or substituted supplied are specified in the contract, the
contractor is bound to carry out the additional, deleted altered or substituted supplies at the same
rates as are specified in the contract.

If the rates for the additional, deleted altered or substituted supplies are not specifically provided in
the contract, the rates will be derived from the rates for similar class of work/items as are specified in
the contract. The opinion of the Engineer-in-Charge as to whether or not the rates can be reasonably so
derived from the items in this contract will be final and binding on the contractor.

If the rates for the altered, additional, deleted or substituted work including supplies cannot be
determined in the manner, then the contractor shall within 7 days of the date of receipt of order,
inform the Engineer-in-Charge of the rate which it intends to charge for such class of work including
supplies, supported by analysis of the rate or rates claimed, and the Engineer-in-Charge shall determine
the rate or rates on the basis of the prevailing market rates labor cost at schedule of hourly/daily rates
plus 10% to cover contractors supervision overhead and profit and pay to recover from the contractor
accordingly. The opinion of the Engineer-in-Charge as to current market rates of materials and the
quantum of labor involved per unit of measurement will be final and binding on the contractor. The
Engineer-in-Charge will normally utilize the schedule of hourly/daily rates quoted by the contractor, to
arrive at the reasonable rate payable for such work and the above course be resorted to only if such
schedule of hourly/daily rates, in his opinion, cannot be applied in arriving at a reasonable rate.

KTL approval is required for any change by contractor.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 138
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

28 NOTICE OF CLAIMS FOR ADDITIONAL PAYMENT

Should the Contractor consider that he is entitled to any extra payment or compensation or to make
any claims whatsoever in respect of the work including supplies, he shall forthwith give notice in
writing to the Engineer-in-Charge that he claims extra payment and/or compensation. Such notice shall
be given to the Engineer-in-Charge within ten days from the ordering or happening of any event upon
which the contractor bases such claims and such notice shall contain full particulars of the nature of
such claims with full details and amount claimed. Failure on the part of the contractor to put forward
any claim with the necessary particulars as above within the time specified shall be an absolute waiver
thereof. No omission to reject any such claim and no delay in dealing therewith by the KTL shall be
waiver of any right in respect thereof.

29 ACTION WHERE NO SPECIFICATION IS ISSUED

In case of any class of item for which there is no such specification supplied by the KTL as is mentioned
in the contract, supplies will be made by the contractor in accordance with Indian Standard
Specification and where it does not cover the same, the same should be carried out as per standard
engineering practice with the approval of the Engineer-in-Charge.

30 LIABILITIES FOR DEFECTS, IMPERFECTIONS ETC. AND RECTIFICATION


THEREOF
If it shall appear to the Engineer-in-Charge that any supplies have been executed with unsound,
imperfect or unskilled workmanship, or with materials of any inferior description, or that any materials
or articles provided by the contractor for the execution of contractor are unsound or otherwise not in
accordance with the contract, the contractor shall on demand in writing form the Engineer-in-Charge of
his authorized representative specifying the item materials or articles complained of, notwithstanding
that the same may have been inadvertently passed. Certified and paid for forthwith rectify or remove
and replace that item so specified and provide other proper and suitable materials or articles at his
own charge and cost, and in the event of failure to do so within a period to be specified by the
Engineer-in-Charge in his demand aforesaid, the Engineer-in-Charge may on expiry of notice period
rectify or remove and re-execute the time or remove and replace with others, the materials or articles
complained of as the case may be at the risk and expense in all respects of the contractor. The
decisions of the Engineer-in-Charge as to any question arising under this Para shall be final and
conclusive.

Further the defect liability clause as per Technical specifications document shall be followed.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 139
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

31 TESTING

On completion of erection of the equipment and before start-up each item of the equipment shall be
thoroughly cleaned and then inspected jointly by KTL/Consultant and the Contractor for correctness
and completeness of installation and acceptability for startup. The Contractor shall test each,
equipment used for plant under prevailing weather condition to the full satisfaction of the KTL. The
mode of pre-commissioning tests, data to be recorded Format of test reports etc. shall have to be got
approved from the KTL well in advance. The Contractor shall provide all the necessary testing
appliances. Renowned third party certificate is required for PV panels.

Following the construction of solar PV plant and issuance of physical completion certificate by the
owner, following shall be the tests carried out jointly by EPC contractor and owner. It will be EPC
contractor’s responsibility for arranging all the consumables, instrumentation, material and human
resources as required for complete commissioning, start-up tests and performance ratio comparisons.

32 START-UP TESTS:

The start-up tests shall be the first step for provisional acceptance of plant. These tests shall essentially
include open circuit voltage, short circuit current and initial performance ratio test. The start-up test
shall be carried immediately after 7 days of physical completion of plant.

PERFORMANCE GUARANTEE TEST: The performance Guarantee test shall verify whether the solar PV
plant is performing at or above the agreed value and shall be conducted as specified in the PG concept
note technical document.

The PG measured on-site shall be compared with the guaranteed performance levels provided by EPC
contractor for the specified time period. Details of on-site measurement of PG and the procedure
thereon are provided in the PG concept note technical document:

If the Contractor fails to achieve the guaranteed performance levels, contractor shall at its own cost
rectify all the defects identified during the test and take necessary steps/efforts to pass the PG test
within the stipulated time span, the contractor will be liable to pay LD to the client as agreed within the
contract.

The Contractor before start of commissioning will submit the following documents.

The technical documents according to which the work was carried out.

As Built drawings, Approved method statement, Quality Plan, Technical Data sheets,MQP, FAT & SAT
documents

Completion certificate for embedded and covered up-works.

Certificate of tests performed for various works.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 140
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

During the start-up and commissioning, the required adaptation, adjustment and rise to normal
operation condition shall be performed.

Results of start-up tests and commissioning shall be recorded.

33 PAYMENT OF CONTRACTOR’S BILL

The KTL shall make payment due to the Contractor by crossed Account Payee cheque forwarding the
same to registered office or the notified office of the Contractor or through LC payment or through
RTGS transfer. In no case will KTL be responsible if the cheque is mislaid or misappropriated by
unauthorized person/persons. In all cases, the Contractor shall present his bill duly pre-receipted on
proper revenue stamp.

In case KTL decides to enter in to multiple contracts as stated above, the contractor shall raise separate
bills for each of the contracts.

All payments shall be made in Indian Currency.

34 RECEIPT FOR PAYMENT

Receipt for payment made on account of work when executed by the Contractor must be signed in the
name of the contractor by one of its principal officers or by some other persons having authority to
give effectual receipt for the Contractor.

35 CERTIFICATE AND PAYMENTS ARE NO EVIDENCE OF COMPLETION

Except the Final Certificate, no other certificates or payment against certificate or on general account
shall be taken to be an admission by the KTL of the due performance of the contract or any part thereof
or of occupancy or validity of any claim by the Contractor

36 PATENT, COPYRIGHT, AND TRADEMARK

The Contractor, if licensed under any patent covering equipment, machinery, materials or compositions
of material to be used or supplied or methods and process to be practiced or employed in the
performance of this contract or for copy right, trademarks or trade names or brands relating to any of
the Equipment’s and materials described in the contract, agrees to pay all royalties and license fees
which may be due with respect thereto. If any equipment, machinery, materials, composition of
matters to be used or supplied or methods and processes to be practices or employed in the
performance of this contract, is covered by a patent under which the contractor is not licensed, then
the Contractor before Supplying or using the equipment, machinery, materials, composition, method of
processes shall obtain such licenses and pay such royalties and license fee as may be necessary for
performance of this contract. In the event the contractor fails to pay

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 141
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

any such royalty or obtain any such license, any suit for infringement of such patents or copy right or
trademarks or trade names or brands relating to any of the equipment’s and materials described in the
contract, which is brought against the Contractor at his own expense and the contractor will pay any
damages and costs awarded in such suit. The Contractor shall promptly notify the KTL if the Contractor
has acquired knowledge of any plant under which a suit for infringement could be reasonably brought
because of the use by the KTL of any equipment, machinery, materials, process and methods to be
supplied hereunder. The Contractor agrees to and does hereby grant to KTL, together with the right to
extend the same to any of the subsidiaries of the KTL as irrevocable, royalty from license to use in any
country, any invention made by the Contractor or his employees or as a result of the Performance of
the work under the Contract.

The Contractor shall indemnify and save harmless the KTL from any loss on account or claims against
KTL for the Contributory infringement of patent rights arising out and based upon the claim that the
use by the Contractor of the process included in the design prepared by the KTL and used in the
operation of plant infringes on patent right. With respect to any sub-contract entered into by the
Contractor pursuant to the provisions of the relevant Para thereof, the Contractor shall obtain from the
Sub-Contractor and undertaking to provide the KTL with the same patent protection that Contractor is
required to provide under the provisions of this Para.

37 SUBLETTING / ASSIGNMENT

The Contractor shall not without the consent in writing of the KTL, assign, sublet or transfer the
contract or the benefits or obligations or any part thereof, directly or indirectly to any person, firm or
corporation. The Contractor shall not, without the consent in writing of the KTL, sublet with any person
or firm for supply of any major shall not apply to sub-Contractor shall also be in accordance with this
contract and the Contractor shall be solely responsible to the KTL for any act done by the Sub-
Contractor. If the KTL for any reason whatsoever subsequently rescinds the approval once given by the
KTL in favor of a Sub-Contractor, it shall be obligatory on the part of the Contractor to act upon it.

No part of the contract nor any share or interest therein shall in any manner or degree by transfer,
assigned or sublet by the Contractor directly or indirectly to any person, firm or Corporation whosoever
except as provided for in the succeeding Para, without the consent in writing of the KTL.

KTL may give written consent to sub-contract for the execution of any part of the works at site, being
entered into by the contractor provided each individual sub-contract is submitted to the Engineer-in-
Charge before being entered into and is approved by them.

At the commencement of every month, the Contractor shall furnish to the Engineer-in-Charge list of all
Sub-Contractor and working at the site during the previous months with particulars of the general
nature of the sub-contract or works.

If any Sub-Contractor engaged upon the works at the site executes any work which in the opinion of
the Engineer-in-Charge is not in accordance with the contract documents, the KTL may by written

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 142
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

notice to the Contractor request them to terminate such sub-contract and dismiss the Sub-Contractors
and the latter shall forthwith leave the works, failing which the KTL shall have the right to remove such
Contractors from the site.

No action taken by the KTL as stated above shall relieve the Contractor of any of his liabilities under the
contract or give rise to any right to compensation for extension of time or otherwise.

Not withstanding any sub-letting with such approval as aforesaid and notwithstanding that the KTL
shall have received copies of any Sub-Contracts. Contractor shall be and shall remain solely responsible
for the quality and proper and expeditious execution of the contract and the performance of all the
conditions of the contract in all respects as if such Sub-contractor or sub-letting had not taken place
and as if such work had been done directly by the Contractor.

38 ARBITRATION

If the dispute cannot be resolved within the said 30 (thirty) days by the mutual discussions, an arbitral
tribunal comprising of 3 arbitrators shall decide the same in accordance with the Arbitration &
Conciliation Act 1996 as in force. Each Party shall appoint one arbitrator and the arbitrators so
appointed shall appoint the third arbitrator who will act as the presiding arbitrator.

In case a Party fails to appoint an arbitrator within 30 (thirty) days from the receipt of the request to do
so by the other Party or the 2 (two) arbitrators so appointed fail to agree on the appointment of third
arbitrator within 30 (thirty) days from the date of their appointment upon request of a Party, the Chief
Justice of AP High court or any person or institution designated by them shall appoint the arbitrators’/
presiding arbitrator.

The arbitral tribunal shall give a reasoned award and the same shall be final, conclusive and binding on
the Parties.

The venue of the arbitration shall be at Kallam Textiles Cotton Ltd.NH-16, Chowdavaram, Guntur,
Andhra Pradesh.

The fees of the arbitrators shall be borne by the Party nominating them and the fee of the presiding
arbitrator, costs and other expenses incidental to the arbitration proceedings shall be borne equally by
the Parties.

The Agreement shall be governed by and construed in accordance with the laws of India.

The Bidder agrees that it shall not seek injunction from any court with respect to any claims, dispute or
differences against the Owner arising under this Agreement.

Notwithstanding the commencement of any arbitration proceeding, the Consultant agrees to discharge
its obligations arising under this Agreement.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 143
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

39 FORCE MAJEURE

If at any time during the subsistence of the Contract, the performance in whole or in part by either
party (Sub-Contracts excluded) of any obligation under this contract shall be prevented or delayed by
reasons of war hostility acts of public enemy, civil commotion, sabotage, fires, flood explosion,
epidemics, quarantine restrictions, non-performance due to illegal strikes and acts of God/natural
calamities such as fire, flood earthquake, hurricane or from compliance with any statue or regulation of
the Government (hereinafter referred to as „EVENT‟), then provided a notice of the happening of any
such event is given within twenty one days from the date of occurrence thereof, neither party shall be
reason of such days from the date of occurrence thereof, neither party shall be reason of such event be
entitled to terminate this contract nor shall either party have any claim for damages against the other
in respect of such non-performance, and completion and / or work under the contract shall be resumed
as soon as practicable after such event has come to an end or ceased to exist, and decision of KTL as to
whether deliveries and/ or the work have been so resumed shall be final and conclusive provided
further that if the performance in whole or in part is delayed by reasons of any such events or a period
exceeding 15(fifteen) days both parties shall meet immediately and decide the future course of action
or at the exclusive option of the KTL terminate the contract in which event the KTL shall be at liberty to
take over from the Contractor at a price to be fixed by mutual agreement, all unused, undamaged and
acceptable materials, bought-out components and stores in the possession of the Contractor at the
time of such termination or such portion thereof as the KTL may deem fit excepting such materials
bought-out components and stores as the Contractor may with the concurrence of the KTL elect to
retain.

40 POST COMMISSIONING SERVICES

The Contractor shall render Post Commissioning services up to a period of 5 years from the date of
conclusion of O&M period on the terms and conditions mutually agreed.

41 DOCUMENTS

The contractor shall furnish to the KTL and his Consultant, CPM/PERT oriented data-wise schedule for
all activities as per the contract.

Un-priced copies of Purchase Order placed by Contractor on Sub-Contractor in duplicate shall be


submitted by the Contractor to the KTL within 07 (seven) days after the placement of Order. Copies
must be thoroughly checked by the Contractor before submission. The purchase order copies shall be
complete with all enclosures as referred to in the Purchase Order.

However, before placement of order, approval of the KTL shall be obtained. In case any purchase order
is amended by the Contractor at the later date copies of the amended purchase order in duplicate shall
be submitted to the KTL.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 144
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Contractor shall obtain approval from Electrical Inspector’s for the electrical installations.

42 FIELD MANAGEMENT AND CO-ORDINATION OF WORK

The field management will be the responsibility of the Engineer-in-Charge, who will be nominated by
the KTL. The Engineer-in-Charge may also authorize his representative to perform his duties and
functions.

The co-ordination and inspection of the day-to-day work under the contract shall be the responsibility
of the Engineer-in-Charge or his authorized representative. A work order book will be maintained by
the Contractor for each sector in which the aforesaid written instructions will be entered. These will be
signed by the Contractors or his authorized representative by way of acknowledgement within 12
hours.

The Engineer-in-Charge shall co-ordinate the works of various agencies engaged at site to ensure
minimum disruption of work carried out by different agencies. It shall be the responsibility of the
Contractor to plan and execute the works strictly in accordance with site instructions to avoid
hindrance to the work being executed by other agencies. In this connection, instructions of the
Engineer-in-Charge shall be binding on the Contractor.

43 DEFECTS PRIOR TO TAKING OVER

If at any time before the work is taken over, the Engineer-in-Charge shall:

Decide that any work done or materials used by the Contractor or any Sub-Contractor is defective or
not in accordance with the contract, or that the works or any portion thereof are defective or do not
fulfill the requirements of contract (all such matters being hereinafter called „Defects‟ in this Para and

Notify the contractor as soon as reasonable and practicable, in writing of the said decision, specifying
particulars of the defects alleged to exist or to have occurred then the contractor shall at his own
expense and with all speed make good the defects so specified.

In case Contractor shall fail to do so, KTL may take at the cost of the Contractor such steps as may in all
circumstances be reasonable to make good such defects. The expenditure so incurred by the KTL will
be recovered from the amount due to the Contractor. The decision of the engineer-in-Charge with
regard to the amount to be recovered from the Contractor will be final and binding on the Contractor.
On completion of the works in accordance with the Contract (except in minor respects that do not
affect their use for the purpose for which they are intended and except for maintenance thereof) and
on having passed the tests on completion in accordance with contract, the Engineer-in-Charge shall
issue an Acceptance Certificate, in which he shall certify the date on which the works have been so
completed and have passed the said tests and works on the date so certified. If the works have been
divided into various groups in the contract, the KTL shall be entitled to take over any group or groups

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 145
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

before the other or others, without relieving the Contractor from his responsibility to fulfill all the
objectives under the Contract.

44 DEFECTS AFTER TAKING OVER

The Contractor shall make good with all possible speed any defect arising from the defective materials
supplied by the Contractor or workmanship or any act of omission of the contract or that may have
been noticed or developed, after the works or group of the works has been taken over, the period
allowed for carrying out such work will be normally one month. If any defect is not remedied within
such reasonable time, KTL may proceed to do the work at Contractors risk and expense and deduct
from the final bill such amount as may be decided by KTL. If by reason of any default on the part of the
Contractor, Acceptance Certificate has not been issued in respect of every portion of the works within
one month after the date fixed by the contract for the same, KTL shall be at liberty to use the works or
any portion thereof in respect of which Acceptance Certificate has not been issued, provided that the
works or the portion thereof so used as aforesaid shall be afforded reasonable opportunity for
completion of these works for the issue of Acceptance Certificate.

45 WAIVER OF DEFAULT

Any waiver by KTL of any breach of the terms condition of the Contract shall not constitute a waiver of
any subsequent breach of the same.

Any failure by KTL at any time or from time to time to enforce or require strict performance by the
Contractor of any of the terms and conditions of the contract shall not constitute a waiver by KTL of a
breach of any such terms or conditions and shall not affect or impair such terms conditions in any way
or the right at any time to avail themself of such remedies as he may have for any such breach or
breaches of such terms or conditions.

46 SUSPENSION OF WORK

The Contractor shall if ordered in writing by the KTL’s Engineer-in-Charge or his representative,
temporarily suspend the works or any part thereof for such period and such time as so ordered,
proceed with the work therein ordered to be suspended until he shall have received a written order to
proceed therewith. An extension of time for completion, corresponding with the delay cause by any
such suspension of the works as aforesaid will be granted to the Contractor. The Contractor should
apply for the same provided that the suspension was not consequent to any default or failure on the
part of the Contractor.

In case of suspension of entire work ordered in writing by the Engineer-in-Charge for a period of more
than four months the Contractor shall have the option to terminate the contract.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 146
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

47 POWER OF ENTRY

If the Contractor shall not commence the work in the manner described in the contract documents or if
he shall at any time in the opinion of the Engineer-in-Charge:

Fail to carry on the works in conformity with the contract documents, or

Fail to carry on the works in accordance with the contract schedule, or

Substantially suspend work or the works for the period of 7 (Seven) days with without authority from
the Engineer-in-Charge, or

Fail to carry on and execute the works to the satisfaction of the Engineer-in-Charge, or

Fail to supply sufficient or suitable constructional plant, temporary works, labor materials or things, or

Commit or suffer, or permit any other breach of any of the provision of the contract on his part to be
performed or observed or persists in any of the above mentioned breaches of the contract for 14
(fourteen) days after notice requiring such breach to be remedied, or

If the Contractor shall abandon the works, or

If the Contractor during the continuance of the contract shall become bankrupt make any arrangement
or composition with his creditors, or permit any execution to be levied or go into liquidation whether
compulsory or voluntary not being merely a voluntary liquidation for the purpose of amalgamation or
reconstruction.

Then in any such case, the KTL shall have the power to enter upon the works and take possession
thereof and of the materials, temporary works, constructional plant, and stock thereon, and to revoke
the Contractor’s license to use the same, and to complete the works by his agents, other Contractors or
workmen, or to relate the same upon any terms and to such other person. Firm or corporation as the
KTL in his absolute discretion may think proper to employ and for the purpose aforesaid to us or
authorize the use of any materials, temporary works, constructional plant, and stock as aforesaid,
without making payment or allowance to the Contractor for said materials other than such as may be
certified in writing by the Engineer-in-Charge to be reasonable, and without making any payment or
allowance to the Contractor (due account being taken of any such extra work or works which may be
omitted) then the amount of such excess as certified by the Engineer-in-Charge shall be under the
contract and not paid for.

Any deficiency shall forthwith be made good and paid to the KTL by the Contractor and the KTL shall
have power to sell in such a manner and for such prices as he may think fit all or any of the
constructional plant, materials etc. constructed or by belonging to and to recoup and retain the said
deficiency or any part thereof out of the proceeds of the sail.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 147
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

48 CONTRACTOR’S SUBORDINATE STAFF AND THEIR CONDUCT

The Contractor, on or after award of the work shall name and depute qualified engineers having
sufficient experience in carrying out work of similar nature to whom the equipment, materials, if any,
shall be issued and instructions for works given. The Contractor shall also provide to the satisfaction of
the Engineer-in-Charge sufficient and qualified staff to supervise the execution of the works competent
sub-agents. Foremen and leading hands including those specially qualified by previous experience to
supervise the types of works comprised in the contract in such a manner as will ensure work of the best
quality and. expeditious working. Wherever in the opinion of the Engineer-in-Charge. Additional
properly qualified supervisory staff is considered necessary; the Contractor shall employ them without
additional charge on account thereof. The Contractor shall ensure to the satisfaction of the Engineer-in-
Charge that Sub-Contractors, if any, shall provide competent and efficient supervision, over the work
entrusted to them.

If and whenever any of the contractor’s or Sub-Contractor’s agents, assistants, foremen or other
employees shall in the opinion of Engineer-in-Charge be guilty of any mis-conduct or be incompetent or
insufficiently qualified or negligent in the performance of their duties or that in the opinion of the KTL
or the Engineer-in-Charge, it is undesirable for administrative or any other reason for such person or
persons to be employed in the works, the Contractor, if so directed by Engineer-in-Charge shall at once
remove such person or persons from employment thereon. Any person or persons so removed from
the works shall not again be employed in connection with the works without the written permission of
the Engineer-in-Charge.

Any person removed from the works shall be immediately replaced at the expenses of the Contractor
by a qualified and competent substitute. Should the Contractor be requested to repatriate any person
removed from the works, he shall do so and shall bear all costs in connection therewith.

The Contractor shall be responsible for the proper behavior of all the staff, foremen, workmen etc. and
shall exercise a proper degree of control over them and in particular and without prejudice to the said
generality, the Contractor shall be bound to prohibit and prevent any employee(s) from trespassing or
acting in anyway detrimental or prejudicial to the interest of the community or of the properties or
occupiers of land and properties in the neighborhood and in the event of such employee so
trespassing, the Contract shall be responsible therefore and relieve the KTL of all consequent claims or
actions for damages or injury or any other grounds whatsoever. The decision of the Engineer-in-Charge
upon any matter arising under this Para shall be final.

If and when required by the KTL, all Contractor’s personnel entering upon the KTL’s premises shall be
properly identified by badges of a type acceptable to the KTL which must be worn at all times on KTL’s
premises.

Without repugnance to any other conditions it shall be the responsibility of the Contractor executing
the work of civil construction of work in close co-operation and coordinate in the works with the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 148
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

mechanical, electrical, air-conditioning and inter-communication contractors and other agencies or


their authorized representatives, in providing the necessary grooves. Recesses, cuts and opening etc. in
wall, slabs, beams, and columns etc. and making good the same to the desired finish as per
specifications for the placement of electrical and inter-communication cables, conduits, air-
conditioning inlets and outlets, grills and other equipment etc. where required. For the above said
requirements in the false ceiling and other partitions, the Contractor before starting up the work shall
in consultation with the electrical, mechanical, inter-communication, air-conditioning Contractors and
other agencies prepare and put up a joint scheme, showing the necessary openings, groves, recesses,
cuts, the methods of fixing required for the works of the aforesaid and the finishes scheme, with any
required modifications shall get the final agreement of all the agencies, which shall be binding.

No claim shall be entertained on account of the above. The contractor shall conform in all respects with
the provisions of statutory regulations, ordinances or by laws of any local or duly constituted
authorities or public bodies, which may be applicable, from time to time the works or any temporary
works. The Contractor shall keep the KTL indemnified against all penalties and liabilities of every kind,
arising out of non-adherence to such statues, ordinances, laws, rules, regulations etc.

The above is applicable to Contract’s scope of work and advised in time by the KTL.

Prior Erection contractors approved list to be provided to KTL.

49 AGENCIES AT SITE

The Contractor shall have to execute the work in such place and conditions where other agencies may
also be engaged for other works such as site grading, filling and leveling, electrical and mechanical
engineering works etc. No claim and/ or time extensions shall be entertained due to work being
executed in the above circumstances.

50 SUB CONTRACTS

The Contractor shall notify the Owner in writing of all sub contracts awarded under the contract if not
already specified in his offer. Such notification in his original offer or later shall not relieve the
Contractor from any liability or obligation under the contract

In case, the Contractor engages any Sub-Contractor to carry out a part of the work, the Sub-Contractor
should have requisite Government License for carrying out such part of the work.

51 SUPPLY OF THE MATERIAL

The contractor shall procure and provide the whole of the materials required for the construction
including building materials, tools, tackles, construction materials and equipment for the completion
and maintenance of the works. The KTL may give necessary recommendation to the respective
authority, if so desired by the Contractor and assumes no further responsibility of any nature. The KTL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 149
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

may insist on the procurement of materials which bare ISI stamp and/ or which are supplied by reputed
suppliers.

52 ASSISTANT TO THE ENGINEER

The Contractor shall make available to the Engineer-in-Charge free of cost all accessories, instruments
and assistance in checking of setting out of works and in the checking of any works made by the
Contractor for the purpose of setting out and taking measurements of work.

53 DISCREPANCIES BETWEEN INSTRUCTIONS

Should any discrepancy occur between the various instructions furnish to the contractor, his agents or
staff or if any doubt arises as to meaning of any such instructions or should there be any
misunderstanding between the contractor’s staff and Engineer-in-Charge staff the Contractor shall
refer the matter immediately in writing to the Engineer-in-Charge whose decisions thereon shall be
final and conclusive and no claim for losses alleged to have been caused by such discrepancies between
instruction, doubts, or misunderstanding shall in any event be admissible

54 POSSESSION PRIOR TO COMPLETION

The Engineer-in-Charge shall have the right to take possession of or use any completed or partially
completed work or part of the work. Such possession or use shall not be deemed to be an acceptance
of any work completed in accordance with the contract agreement. If such prior possession or use by
the Engineer-in-Charge delays the progress of work, equitable adjustment in the time of completion
will be made without any bearing on cost and the contract agreement shall be deemed to be modified
accordingly.

55 RIGHTS OF VARIOUS INTERESTS

The Contractor shall co-operate and afford other Contractors reasonable opportunity for access to the
works for the carriage and storage of materials and execution of their works.

Wherever the work being done by any department of the KTL or by other Contractors employed by the
KTL is contingent upon work covered by this bid, the respective rights of the various interest involved
shall be determined by the Engineer-in-Charge to secure the completion of the various portions of the
work in general harmony.

56 LABOUR LAWS AND SAFETY REGULATIONS

a) The Contractor shall adhere to the following labor laws.

b) No labor below the age of 18 (Eighteen) years shall be employed on the work.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 150
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

c) The Contractor shall not pay less than what is provided under law to laborers engaged
by them on the work.

d) The Contractor shall at his expense comply with all laws and keep the KTL indemnified in
respect thereof.

e) The Contractor shall pay equal wages for men and women in accordance with applicable
labor laws.

f) The Contractor shall be allowed to commence work at site only on production of


requisite license.

g) The Contractor shall be allowed to commence work at site only on production or


requisite license as required under the Contract Labor (Regulation & Abolition) Act,
1970 amended up to date.

h) Human Resource Management

Contractor shall make its own arrangements for the engagement of personnel, as may be required for
the proper and timely performance of the Services and shall use all diligence in arranging for a
sufficient and suitable supply of such personnel but all such arrangements shall be in accordance with
the general local usage and subject to the applicable laws. Contractor shall be responsible for making
all arrangements for the payment, feeding, housing, health, safety, sanitation and transport of all the
personnel engaged by it in the provision of the Services.

Contractor shall be solely responsible for timely payment of wages/salary/other reimbursements to the
personnel/ labours, as per the applicable law from time to time. Contractor undertake and agree to
deduct and remit, regularly, as required by applicable law, the requisite contribution towards
employees‟ provident fund and employees‟ state insurance in the state treasury, bank as the case may
be and produce the relevant challans, returns and receipts for inspection and records on monthly basis
to KTL.

a) Contractor shall also be responsible for making the payment of all benefits as
admissible under applicable law to the personnel/ labours, including but not limited to
weekly rest days, leave, national holidays, overtime if any, bonus/gratuity, if applicable,
from time to time. Payment of any overtime wages/ salary to the personnel/ labours
shall be Contractor’s sole responsibility and

KTL shall not be liable for the same. Contractor shall provide supporting documents to
substantiate disbursement of payment of bonus to its employees/ labours and also the
material consumed in carrying out the Services.

b) Contractor shall maintain all requisite records, registers, accounts books etc., which are
obligatory under applicable law and shall provide any information as may be required by
KTL in this regard from time to time.

c) Contractor shall hold and maintain, valid and effective, a license under the Contract
Labour (Regulation and Abolition) Act 1970 during and throughout the Work Order

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 151
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

term. If Contractor is the principal employer of all or any of the employees, temporary,
casual, contracted, or permanent performing the Services, Contractor shall obtain the
registration to this effect under the Contract Labour (Regulation and Abolition) Act 1970

d) In the employment of personnel for the performance of the Services, Contractor shall
comply without limitation, with all requirements of any applicable law relating to the
employment of workmen or any subsequent modification or re-enactment thereof
including but not limited to, matters relating to timely payment of wages and
allowances, payment of minimum wages, payment of overtime, grant of leave, payment
of workmen's compensation, working hours, safety, maternity benefits, holidays,
framing of standing orders, disciplinary action against employees, payment of provident
fund contributions, payment of gratuities and payment of bonuses. Contractor shall pay
the personnel employed directly / through sub-contractors, wages not less than the
minimum wages notified under the Minimum Wages Act. Contractor shall in respect of
all personnel employed by itself either directly or through sub-contractors comply with
or cause to be complied with the provisions of the Payment of Wages Act, 1936,
Minimum Wages Act 1948, Employers Liability Act, 1938, Workman's Compensation Act
1923, Maternity Benefit Act 1961, Contract Labour (Regulations and Abolition) Act 1970,
Employee's Provident Fund Act and all applicable laws as regards the terms and manner
of employment, terms of service, conditions of employment etc. including all applicable
labour laws. All amounts payable towards provident funds, employee state insurance,
welfare & assurance charges contributions etc. Including interest and penalties shall be
payable by Contractor. Contractor shall ensure that the disbursement of wages is done
in the presence of the authorized representative of KTL.

f) Contractor, at all times shall be solely responsible for the registration of all its workers/
personnel under the relevant provisions of Building and other Construction Workers Act, 1996
(the “BOCW Act”) (if applicable) during the tenure of the Services/ Work Order. Further,
Contractor as part of BOCW Act compliance shall be strictly required to supply to KTL, all
supporting documents such as photocopy of registration certificate(s) of each of the worker(s)/
personnel engaged in the aforesaid Services, within 30 (thirty) days of engaging the said
worker(s).

g) Contractor shall maintain accurate, up to date and complete records of its workers/ personnel
registered under the BOCW Act in accordance with the Applicable Law, and in a manner
acceptable to KTL and the relevant government authorities/ agencies. Contractor shall permit
authorized officers and representatives of KTL, or such agents appointed by KTL to have
complete access to the records of such registered workers, at any time during the tenure of the
Work Order.

h) Contractor shall indemnify, defend and hold harmless KTL and each of its directors, partners,
managers, officers, employees and agents (as the case may be) from and against any liabilities,
claims, damages, judgments, losses, demands and legal proceedings, which may be incurred by
or brought against them arising out of any non-compliance / non-adherence to any of the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 152
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

provisions of the BOCW Act on its part, including but not limited to, the failure on its part to get
its workers/ personnel registered under the BOCW Act.

i) On or before the date of final payment by the KTL under this Work Order, Contractor shall
deliver to KTL a statement stating that the personnel that has been employed/ deployed by
Contractor for performing the Services, have received all wages, salaries and emoluments due
to them in connection with such employment and that all dues under any applicable laws have
been paid

j) Contractor shall settle, at its own cost, all disputes and differences arising as to the rates of
wages to be paid or the terms/ conditions of employment. In the event any notice/ claims
pertaining to such/ related disputes is received by the KTL (through KTL Representative or
otherwise), KTL may make such payments of such claims to such person / relevant authority, as
it may deem appropriate, out of any monies at any time due to Contractor under this Work
Order and such payment shall be deemed to be a payment made to Contractor under and by
virtue of this Work Order towards the Work Order Sum. If KTL receives a request from the tax
authorities to pay on Contractor’s behalf and/or its employees, or to withhold payments from
it in order that the relevant authority may subsequently so pay, any of the abovementioned
taxes, fees, duties, fines, levies and assessments, Contractor hereby authorize KTL to comply
with the terms of the said request.

k) Contractor shall at all times save harmless and indemnify KTL from and against all claims,
liabilities, expenses, costs and losses suffered or incurred by the KTL which may arise out
of or in connection with the employment of any personnel for the performance of the
Services by Contractor or its (its employees, labours agents etc.) any act related to
provision of Services.

a. Compliance with Statutes and Statutory Declaration

l) Contractor shall comply with all applicable laws, rules and regulations of India, official
directive/ guideline of any governmental authority or any person acting under the
authority of any governmental authority or any statutory authority, including any
notification issued by the Reserve Bank of India or of any governmental authorities, as may
be in force and effect during the subsistence of this Work Order.

m) Contractor shall obtain requisite license from the licensing authority under Contract
Labour (R&A) Act.1970, according to employee or labour engaged by Contractor and get
the aforementioned license renewed from time to time as and when due from the
appropriate authority and shall keep valid and produce the same when called upon to do
so by KTL.

n) It is hereby declared by Contractor that it is covered under EPF & MP Act and ESI Act.
Contractor hereby undertake and agree to deduct and remit, regularly, as required by law,
the requisite contribution towards EPF & ESI in the state treasury, bank as the case may be
and produce the relevant challans, returns and receipts for inspection and records as and
when required by the KTL.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 153
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

o) Contractor hereby undertake to fully comply with the provision of Contract Labour (R&A)
Act 1970, and the rules made there under and EPF & MP Act 1951, ESI Act 1948, Minimum
Wages Act 1948 and such other applicable laws including laws applicable to the labour
employed by it for the completion of the Works.

Compliance with the Operation, Management and Development Agreement (OMDA)

Contractor to indemnify the KTL

The Contractor shall indemnify the KTL and every member, officer and employees of the KTL, also the
Engineer-in-Charge and his staff against all actions, Proceedings, claims, demands, costs and expenses
whatsoever arising out of or in connection with the matters referred to the damage to the property
and all actions, proceedings, claims, demands, costs and expenses which may be made against KTL for
or in respect of or arising out of any failure by the contractor in the performance of his obligation under
the contract documents. The KTL shall not be liable for or in respect of any demand or compensation
payable by law in respect or inconsequence of any accident or injury due to negligence or otherwise to
any workmen or other person in the employment of the Contractor or his sub-Contractor and
Contractor shall indemnify and keep indemnified the KTL against all such proceedings, costs-charges
and expenses whatsoever, in respect or in relation thereto. The liability in such cases including criminal
liability shall be to the Bidders account.

Should the KTL have to pay any money in respect of such claims or demands as aforesaid the amount
so paid and the costs incurred by the KTL shall be charged to and by the Contractor and the Contractor
shall not be at liberty to dispute or question the right of the KTL to make such payments
notwithstanding the same may have been made without his consent or authority or in law or otherwise
to the contrary.

57 HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS

In respect of all labor directly or indirectly employed in the works for the performance of Contractor’s
part of this agreement the Contractor shall comply with or cause to be complied with all rules and
regulation of the local sanitary and other authorities or as framed by GOAP form time to time for the
protection of health and sanitary arrangements for all workers.

58 SAFETY REGULATIONS

In respect of all labor, directly or indirectly employed in the work for the performance of Contractor’s
part of this agreement the Contractor shall at his own expense arrange for all the safety provisions as
per safety codes of CPWD. Indian Standards Institution, the Electricity Act, the Mines Act, Regulations,
Rules and Orders made there under and other acts as applicable.

The contractor shall observe and abide by all fire and safety regulations of the GOAP. Before starting
construction work, the Contractor shall consult with KTL’s Safety Engineer-in-Charge and must make
good to the satisfaction of the KTL’s Safety Engineer or Engineer-in-Charge any loss or damage due to

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 154
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

fine to any portion of the work done or to be done under this agreement or to any of the KTL’s existing
property.

Contractor shall adhere to safe construction practice and guard against hazardous and unsafe working
conditions and shall comply with necessary safety rules in this regard.

59 FIRST AID AND INDUSTRIAL INJURIES

Contractor shall maintain first aid facilities for his employees and those of his Sub-Contractors.

Contractor shall make outside arrangements for ambulance services and for the treatment of industrial
injuries. Names of those providing these services shall be furnished to KTL prior to start of
constructions and their telephone numbers shall be prominently pasted in Contractor’s office.

All critical industrial injuries shall be reported promptly to KTL and a copy of Contractor’s report
covering each personnel injury requiring the attention of a physician shall be furnished to the KTL.

60 SMOKING PROHIBITED IN NON-SMOKING AREAS

Smoking within non-smoking areas is strictly prohibited. Violators of the no-smoking rules shall be
discharged immediately.

61 BARRICADES

Contractor shall erect and maintain barricades required in connection with his operation to guard or
protect:

Excavations

Hoisting areas

Areas adjudged hazardous by Contractor’s or KTL’s Inspections

Rail/road unloading spots

Contractor’s employees and those of his Sub-Contractor shall become acquainted with KTL’s
barricading practice and shall respect the provisions thereof.

Red flashed lanterns shall mark barricades‟ and hazardous areas adjacent to but not located in normal
routes or travel at nights.

Construction power to be arranged by the KTL. KTL will only provide Testing and Commissioning power
and the required interconnection and cable to be arrange and installed by bidder/ sub-contractor

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 155
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

62 DAMAGE TO PROPERTY

Contractor shall be responsible for making good to the satisfaction of the KTL any loss or any damage
to all structures and properties belonging to the KTL or being not executed or procured or being
procured by the KTL or of other agencies within the premises of all the work of the KTL, if such loss or
damages due to fault and/ or the negligence or willful acts or omission of the contractor, his
employees, agents, representatives or Sub-Contractors.

The Contractor shall indemnify and keep the KTL harmless of all claims for damage to property other
than KTL’s property arising under or by reason of this agreement if such claims result from the fault
and/ or negligence or willful acts or omissions of the contractor, agent representatives or Sub-
Contractors.

63 FINAL BILL WITH LETTER OF DISCHARGE

Contractor shall submit the final bill covering all his claims, on any account whatsoever, including the
extra work arising out of or under the contract. Once the final bill has been submitted, it shall be
deemed that Contractor has no other claims of any kind or nature whatsoever under or arising out of
or relating to the contract or the work or extra work done pursuant thereto and that the contract
including the arbitration agreement contained therein stands terminated and determined by mutual
agreement of the parties claims and disputes, if any, after the date of discharge letter shall only be
settle by suit in Court of Law and not through arbitration.

In case KTL decides to enter in to multiple contracts as stated above, the contractor shall raise separate
bills for each of the contracts.

64 INSURANCE

The Contractor shall be responsible and take an Insurance Policy for marine-cum-transit-cum-storage-
cum-erection for all the materials to cover all risks and liabilities for supply of materials at site, storage
of materials at site, erection, testing, commissioning, till handing over the Plant & Equipment to KTL
including third party indemnity valid from date of signing of the contract to the commissioning and
hand over of the plant. The Insurance policy should be taken from Reputed Insurance Company and in
consultation with KTL and it should be assigned in favour of KTL.

The Contractor shall also take insurance for Third Party Liability covering loss of human life engineers
and workmen not belonging to Contractor) and also covering the risks of damage of the other’s
material/equipment/properties during execution of the Contract. However, the value of third party
liability for compensation for loss of human life and damage of equipment/property shall be subject to
the approval of KTL/Consultant.

Before commencement of the work, the Contractor will ensure that all its employees and
representatives are covered by suitable insurance against and damage, loss, injury or death arising out

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 156
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

of the execution of the work or in carrying out the Contract. This insurance coverage should continue
till handing over of the Plant & Equipment to KTL.

Employees State Insurance act: The contractor shall accept full and exclusive liability for the compliance
with all obligations imposed by the Employees State Insurance Act 1948 and the Contractor shall
further defend, indemnify and hold KTL harmless from any liability or penalty which may be imposed by
the Central State or Local authority by the reasons of any asserted violation by Contractor or Sub-
Contractor of the Employees State Insurance Act, 1948 and also from all claims, suits or proceedings
that may be brought against the KTL arising under growing out of or by reasons of the work provided
for by this Contract whether brought by employees of the Contractor by third parties or by Central or
State Government Authority or any political sub-division thereof. The contractor shall fill-in with the
Employees State Insurance Corporation. The Declaration Forms and all forms which are required in
respect of the Contractor’s or Sub-Contractor’s employees, who are employed in the work provided for
or those covered under ESI from time to time under the Agreement. The contractor shall deduct and
secure the Agreement of the Sub-Contractor to deduct the employee’s contribution as per the First
Schedule of the Employees State insurance Act from wages and affix the employee’s contribution as
required by the Act. The contractor shall maintain all cards and records required under the Act in
respect of employees and payments of the Contractor shall secure the Agreement of the Sub-
Contractor to maintain such records. All expenses incurred for the contributions, making contributions
or maintain records shall be the Contractor’s or Sub-Contractor’s account. The KTL shall retain such
sum as may be necessary from the total Contract value until the Contractor shall furnish satisfactory
proof that all contribution as required by the Employees State Insurance Act. 1948 have been paid.

Workmen’s Compensation Act and Employer’s liability Insurance: Insurance shall be affected for all the
Contractor’s employees engaged in the performance of this contract in accordance with Workmen’s
Compensation Act &Employer’s liability. If any of the work is sub-let, the Contractor shall require the Sub-
Contractor to provide workmen’s compensation and Employer’s liability insurance for the latter’s
employees. If such employees are not covered under the Contractor’s Insurance.

Any other insurance required under law or regulations or by KTL: Contractor shall also carry and
maintain any and all other insurance which he may be required to have under any law or regulations
from time to time. He shall also carry and maintain any other insurance, which may be required by the
KTL.

Accident injury to workman: The KTL shall not be liable for or in respect of any demand or
compensation payable at law in respect of or in consequence of accident or injury to any workman or
other person in the employment of the Contractor or any Sub-Contractor and the Contractor shall
indemnify and keep indemnified the KTL against all such damages and compensation and against all
claims demands, proceedings, cost, charges and expense whatsoever or liability thereof.

It is expressly understood that the risk costs and consequence of the Contractor’s failure to arrange for
insurance coverage as specified above, shall be solely to Contractor’s cost and account and KTL shall
have no responsibility or liability thereof.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 157
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Contractor shall fulfil the necessary requirement/ obligations of the Insurance Company including
provisions of adequate firefighting facilities etc so that the claims are not rejected.

Welding, soldering or the use of an open flame in the vicinity of combustible material is permitted only
if at least one workman suitably equipped with extinguisher and trained in fire-fighting is present.

All inflammable material (such as shuttering material not used for concreting liter etc. and especially
and inflammable liquids and gases must be stored at a sufficiently large distance from the property
under construction or erection and any hot work.

The Contractor shall ensure that the insurance coverage is obtained to take care of future cost
escalations and variation in taxes & duties during the tenure of the Contract. The Contract shall, if
necessary, also enhance and extend the insurance coverage till completion of supplies.

The Contractor shall lodge, whenever required, the necessary claim with the Insurance Company and
shall settle the claims with Insurance Company thereafter. However, the Contractor shall proceed with
the repaid and /or replacement of the equipment/component without waiting for the settlement of
the claims.

The above insurance policy shall be kept valid during the tenure of the Contract (during EPC period as
well as O&M Period) and the Contractor shall pay necessary premiums as required under the terms of
the policy.

The insurance policy mentioned above is only illustrative, the contractor shall take necessary insurance
cover during EPC and O&M period, not only for covering the risk of equipment, material and other
properties relating to the project but also specific cover for third party claim, personal accident cover.
Notwithstanding such insurance coverage, any loss arising in respect of property of the project or third
party claims during the EPC or O&M period shall be on account of the contractor. In case any such
claims are met or paid by KTL, they shall be recoverable from the contractor.

The Contractor shall furnish to the KTL a photocopy of policy/policies of insurance and receipt for
payment of premium at regular intervals for reference.

65 LIQUIDATION, DEATH, BANKRUPTCY ETC.

If the Contractor shall die, dissolve or become Bankrupt or insolvent or cause or suffer any Receiver to
be appointed to his business or any assets thereof compound with his Creditors, or being a corporation
commence to be wound up for the purpose of amalgamation or reconstruction, or carry on its business
under a Receiver for the benefits of its Creditors or any of them, the KTL shall be at liberty:

to terminate the Contractor forthwith upon coming to know of the happening of any such event as
aforesaid by notice in writing to the Contractor or to the Receiver or Liquidator or to any person in
whom the Contract may become vested to or.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 158
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

to give such Receiver, Liquidator or other person the option of carrying out the Contract subject to his
providing guarantee up to an amount to be agreed for the due and faithful performance of the
Contract.

66 RESPONSIBILITY FOR PERFORMANCE OF CONTRACT

The contract shall be solely responsible for the entire supplies whether made by them directly or by his
Sub-Contractors with or without the approval of KTL/Consultant as the case may be. The Contractor
shall be responsible for the due and faithfully performance of the Contract in all respect according to
the intent and meaning of the drawings, specifications and all other documents referred to in this
contract. Any approval, which the KTL may have given in respect of the stores, materials, suppliers or
other particulars and the workmanship involved in the contract (whether with or without tests carried
out by the Contractor or the KTL/Consultant) shall not bind the KTL and notwithstanding any approval
or acceptance given by the Consultant, it shall be lawful for the KTL to reject the materials supplied are
not in conformity with the terms and conditions of the Contract in all respects.

The Contractor shall co-operate with the KTL’s other Contractors, if any, for any associated plant and
freely exchange all technical information with them to obtain the most efficient and economical design
and to avoid unnecessary duplication of equipment. No remuneration shall be claimed from the KTL for
such technical co-operation.

67 RESPONSIBILITY FOR COMPLETENESS

Any supplies which not have been specifically mentioned in this Contract but which are necessary for
the design, engineering, manufacture, supply & performance or completeness of the unit shall be
provided by the Contractor without any extra cost and within the time schedule for efficient and
smooth operation and maintenance of the unit under Indian conditions.

The approval by the KTL at any stage for any supplies by the Contractor shall not relieve them of his
obligations under the contract.

68 DISPATCH AND BILLING SCHEDULE

Within week of Effective Date, the Contractor shall prepare and submit detailed dispatch schedule and
corresponding billing schedule for the Plant and Equipment. The dispatch-cum-billing Schedule shall
indicate the breakdown of the complete plant into shipment units with approximate weights and
dimensions, respective dates upon which such units will be dispatched from the Contractor’s works
along with billing value. The Contractor shall arrange for supplies of the Plant, Machinery and
Equipment in the logical sequence required for erection within the overall delivery schedule of the
Contract. The dispatch cum billing Schedule shall be scrutinized and approved by the KTL. The
Contractor shall promptly give written notice to the KTL of any anticipated delay in maintaining such

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 159
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Schedule stating reasons and KTL measures, if any. This shall not absolve the Contractor from his
responsibilities for any delay.

69 PACKING, IDENTIFICATION AND MARKING

The Contractor shall include and provide for securely protecting and packing the materials so as to
avoid loss or damage during handling & transport by rail and road.

All packing shall allow for easy removal and checking at site. Special precaution shall be taken to
prevent rusting of steel and iron parts during transit. Gas seals or other methods proposed to be
adopted for protection against moisture during transit shall be subject to the prior approval of the KTL.

The number of each package in a shipment shall be shown in fraction, numerator-showing number of
the package and the denominator showing the total number of packages in a lot/consignment. The
packages number shall be generally prepared wherever possible in the sequence in which they will be
required for erection.

Each package delivered under the Contract shall be marked by and at the expense of the Contractor
and such marking must be distinct and in English language (all previous irrelevant markings being
carefully obliterated). Such marking shall show the description and quantity of contents, the name of
the Contractor with a distinctive number of marks sufficient for purpose of identification. All markings
shall be carried out with such material as to ensure quickness of drying, fastness and indelibility. Each
equipment or parts of equipment, when shipped or railed or otherwise dispatched shall be tagged with
reference to the assembly drawings and corresponding part numbers. Each bale or package shall
contain a packing note quoting specifically the name of the contractor, the number and date of
Contracts or orders and the name of the office placing the Contract, nomenclature of the stores and
include a schedule of parts for each complete equipment giving the part numbers with reference to the
assembly drawing and the quantity of each part, drawing Nos. and tag numbers.

All packing cases, containers, packing and other similar materials shall be new and supplied free by the
Contractor and same will not be returned unless otherwise stated in the Schedule hereto.

Notwithstanding anything stated in this clause, the Contractor shall be entirely responsible for loss,
damage or depreciation or deterioration to the materials and supplies due to faulty protective and
insecure packing.

Packing list to be provided by contractor.

70 TYPE QUALITY OF MATERIALS AND WORKMANSHIP

The design, engineering, manufacture, assembly inspection, testing and performance of the equipment
shall be in accordance with applicable codes and standards including the Technical document of this bid
and latest appropriate Indian Standards and Codes. Where appropriate Indian Standards and Codes are
not available, other suitable standards and codes as approved by the KTL shall be used.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 160
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Contractor shall be deemed to have carefully examined and to have knowledge of the equipment,
the general and other conditions, specifications, schedules, drawings, etc. forming part of the contract
and also to have satisfied themself as to the nature and character of the supplies to be made and the
type of equipment and duties required including wherever necessary of the site conditions and
relevant matters and details. Any information thus had or otherwise obtained from KTL/Consultant
shall not in any way relieve the Contractor from his responsibility and contractual obligations for
designing, manufacturing and supplying the Plant and Equipment at site in terms of the Contract. If the
Contractor shall have any doubt as to the meaning of any portion of the Contract, he shall, before
signing it, set forth the particulars thereof and submit to KTL in writing so that such doubt may be
removed.

The equipment under scope of supply shall be of the best quality and workmanship according to the
latest engineering practice and shall be manufactured from materials of best quality or highest class
considering strength and durability for their best performance and all materials shall be new.
Substitution of specified material or variation from the method of fabrication may be permitted with
the prior written approval of the KTL. Such approval shall be granted only if a compelling reason exists
for making a substitution.

The Contractor shall procure and/or fabricate all materials and equipment inaccordance with all
requirements of Central and State enactment's, rules and regulations governing such work in India and
at site. This shall not be construed as relieving the Contractor from complying with any requirement of
KTL as enumerated in the contract specifications which may be more rigid than and not contrary to the
above mentioned rules, nor providing such constriction as may be required by the above mentioned
rules and regulations. In case of variance of the contract specification from the laws, ordinance, rules
and regulations governing the contract, the contractor shall immediately notify the same to the KTL. It
is the sole responsibility of the Contractor, however, to determine that such variance exists. The
contractor shall also obtain the Statutory Authorities approval for the plant, machinery and equipment
to be supplied by the contractor.

Codes and standards referred in Contract documents shall be followed. Codes and standards of other
countries can be followed with the prior written approval of KTL/Consultant, provided materials,
supplies and equipment according to the standard are equal to or better than the corresponding
standards specified in the Contract.

All meters, gauges, recorders and other types of indicating, integrating or recording devices shall be
calibrated in metric system and degree Celsius. English system gearing must be changed to produce
result on a true decimal (metric basis) functional and instruction plate shall be in English language.

Brand names mentioned in the Contract documents are for the purpose of establishing the type and
quality of product to be used. The Contractor shall not change the brand name and qualities of the
bough-out items without the prior written approval of the KTL. All such products and equipment shall

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 161
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

be used or installed in strict accordance with original manufacturer's recommendations, unless


otherwise directed by the KTL.

71 CONTRACT DRAWINGS AND DOCUMENTS

The Contractor immediately after the award of the Contract shall provide the KTL consultant CPM/PERT
oriented data wise delivery schedule for all drawings and other design and engineering information.

Drawings, documents and other information to be supplied by the Contractor are also given in the
specification elsewhere.

The Contractor well in advance of commencement of supplies shall supply three sets of all computation
sheets and drawings as indicated above. The computation sheets shall be for the purpose of reference
and record only. Of the drawings, one copy shall be returned to the Contractor with the
KTL's/Consultant's approval or comments for amendments. In the latter case, further three copies of
the amended drawings shall be submitted again for approval, supported, necessary by amended
computation sheets in triplicate. On final approval, the Contractor shall supply one reproducible
plastic/mini-film tracing and six sets of ordinary prints of the finally completed drawings/documents.

Where approval of drawings before manufacture/construction/fabrication has been specified, it shall


be Contractor's responsibility to have these drawings prepared as per the direction of KTL and get
these approved before proceeding with manufacture/fabrication as the case maybe. Any changes that
may have become necessary in these drawings during the execution of the Contract shall have to be
carried out by the Contractor to the satisfaction of KTL, at no extra cost and time. All final drawings
shall bear the certification stamp duly signed by the Contractor.

Following literature and documents pertaining to the contract equipment shall be supplied by the
Contractor free of charge to the KTL in Six copies according to agreed schedule:

Drawing showing equipment details with illustrated parts catalogue

Instruction manuals for operation and maintenance

Complete erection instructions with details erection drawing. These shall be supplied to KTL as early as
possible, but not later than six weeks before the dispatch of the respective Plant and Equipment from
the Contractor's works

Spare parts list catalogues

Catalogues of bought out items

Detailed drawings for all wearing parts along with material specification, in enough details for local
manufacture

Reference resource including insolation data, temperature and wind.

Energy yield report.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 162
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Project implementation schedule

Indicative delivery schedule

Any other information document as may be required by the KTL will provide after contract award to
bidder. The Contractor shall furnish as soon as possible, general arrangement drawing to enable the
KTL/Consultant to examine the type and material of plant to be supplied and to propose any changes,
which they may think necessary. The Contractor shall not withhold any detailed drawings or
information necessary to enable the above examination to take place. The KTL/Consultant shall make
any comment or objection, which they may have within one month of the receipt of the various
drawings.

Any modification shall be subject to written approval of the KTL.

The supply of all contract drawings under this technical specifications document shall be completed in
accordance with the delivery schedule for the supply of drawings.

The Drawing number should be given in such a manner that the drawings pertaining to a particular
section are found together. Suitable cross-reference shall be given in the drawings, as required.

The supply of all drawing/documents as stated above shall form a part of the contract and the KTL will
withhold payment of the Contractor under the Contract until the drawing/documents have been
received in full, to the entire satisfaction of the KTL.

72 ERRORS AND OMISSIONS

The Contractor shall be responsible for any discrepancies errors and omissions in the drawings or other
information submitted by them irrespective of whether these have been approved, reviewed or
otherwise accepted by the KTL/consultant or not.

The Contractor, however, shall not be responsible, should the discrepancies, errors or omissions arise
out of incorrect or incomplete information or particulars furnished by the KTL unless correctness
completeness of such information or particulars should have been re-checked/re-confirmed by the
Contractor on his own as a sound design and engineering practice.

The Contractor shall take all corrective measures arising out of discrepancies, errors and omissions in
drawings and other information within the time schedule and without extra cost to the KTL.

The Contractor shall also be responsible for any delay and/or extra cost, if any, in carrying out
engineering and omissions as well as of any late revisions of drawings and information submitted by
the contractor.

73 APPROVAL BY THE KTL

Documents and drawings as per and Technical Specification shall be subject to the approval of the
KTL/consultant.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 163
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Drawings and documents as per of and given elsewhere, shall be submitted by the contractor for
review/reference.

Allchangesfromtheagreedspecifications/drawingsshallbesubjecttotheapproval of the KTL.

All sub-contracts for design and engineering, manufacture and supplies and any other work/services
covered under the contract shall be subject to the written approval of the KTL.

While the Contractor shall make supplies, in terms of the contract, KTL shall have the right to check and
approve designing, type, quality, quantity, materials and workmanship of any or all items of supplies,
where considered necessary by KTL, to ensure that supplies made by the contractor are in accordance
with the provisions of this contract.

This enable the KTL to accord approval and to review documents and drawings. The Contractor shall
submit back-up data/calculations assumptions as may be required by the KTL/consultant.

Where approval of the KTL is necessary or implied but is not specifically provided for elsewhere in this
contract, such approval shall also come within the purview of this schedule.

Approval by the KTL in terms of this Technical specifications document shall not relieve the contractor
of his obligations under this contract.

74 GENERAL SPECIFICATION ON QUALITY SYSTEM, INSPECTION AND


TEST OF PLANT AND EQUIPMENT AT MANUFACTURER'S PREMISES
Inspection & testing of material and equipment shall be carried out by KTL/consultant at the
works/principal of successful Bidder (contractor/sub-contractor) during manufacturing and on final
product to ensure conformity of the same with the acceptable criteria of technical specifications,
approved drawings, authenticated manufacturing drawings and reference national/international
standards, as brought in Technical Specifications document.

15 days advance notice shall be given by the Supplier to the KTL.

The supplier has to furnish type and routine test certificate of all major equipment as per relevant IS/
International Standard.

KTL will appoint third party inspector for testing of Solar modules during manufacturing, The contractor
to coordinate the manufacturing dates of solar modules from the manufacturer and intimate the dates
to KTL at least 15 days in advance. In case there is a delay in taking up of manufacturing the contractor
to pay for the idle time consultancy fees for the third party inspector.

KTL can appoint UL Certification team for rooftop solar at its cost.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 164
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

75 COMPLIANCE WITH LAWS AND REGULATIONS

The Contractor shall, throughout the performance of this contract comply with all laws, rules,
regulations and statutory requirements of Government of India, State Government and other statutory
bodies as far as such bodies have jurisdiction over the Contract or any part of the same.

76 SECRECY TITLES

All maps, plans, drawings, specifications, schemes and the subject matter contained therein and all
other information given to the contractor, by KTL /consultant in connection with the performance of
the contract shall be held confidential by the Contractor and shall remain the property of the KTL and
shall not be used or disclosed to third parties by the Contractor for any purpose other than for which
they have been supplied or prepared. The Contractor may disclose to third parties, upon execution of
secrecy agreements satisfactory to KTL, such part of the drawings, specifications or information if such
disclosure is necessary for the performance of the contract.

Maps, layouts and photographs of the unit/integrated plant including its surrounding region's showing
vital installation for national security shall not be published or disclosed to the third parties or taken
out of the country without prior written approval of the KTL and upon execution of secrecy agreements
satisfactory to the KTL with such third parties prior to disclosure.

Title to secret processes, if any, developed by the Contractor on an exclusive basis and employed in the
design of the unit shall remain with the Contractor. KTL shall hold in confidence such process and shall
not disclose such processes to the third parties without prior approval of the Contractor and execution
by such third parties of secrecy agreements satisfactory to the Contractor prior to disclosure.

Technical specifications, drawings, flow sheets, norms calculations, diagrams, interpretations of the
test results, schematics, lay outs and such other information which the contractor has supplied to KTL
under the contract shall be passed on to KTL. KTL shall have the right to use these for construction
erection, start-up, commissioning, operation, maintenance, modifications and/or expansion of the unit
including for the manufacture of spare parts.

The provisions shall not apply to information:

Which at the time of disclosure are in the public domain or which later on become parts of public
domain through no fault of the party concerned;

Which were in the possession of the party concerned prior to disclosure to them by the other party, or

Which were received by the concerned party after the time of disclosure without restriction on
disclosure or use, from a third party who did not acquire such information directly or indirectly from
the other party;

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 165
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

77 REJECTION OF DEFECTIVE PLANT

If the completed equipment, machinery’s or any portion thereof, before it is accepted or taken over, be
defective or fails to fulfill the requirement of the contract, KTL shall give the Contractor notice setting
forth particulars of such defects or failure and the Contractor shall forthwith make the defective
equipment, machinery’s good or alter the same to make it comply with the requirements of the
contract. Should the Contractor fail to do so KTL may reject and replace at the risk and cost of the
Contractor, the whole or any portion of the same as the case may be which is defective or fails to fulfill
the requirements of the contract. However, such rejection/replacement by the KTL shall not absolve
the Contractor of his responsibilities under this contract.

In the event of such rejection, KTL shall be entitled to the use the equipment, machinery’s in a
reasonable and proper manner for a time reasonable sufficient to enable them to obtain other
replacement plant.

78 NEGLIGENCE

If the Contractor shall neglect to execute the supplies with due diligence of expeditions or shall refuse
or neglect to comply with any reasonable order given to them in writing by KTL in connection with the
supplies or shall contravene the provisions of contract, KTL may give notice in writing to the Contractor
calling upon them to make good the failure, neglect or contravention complained of within such time
as may be deemed reasonable and in default of this compliance with the said notice, KTL without
prejudice to his rights may rescind or cancel the contract holding the Contractor liable for the damages
that the KTL may sustain in his behalf.

Should the Contractor fail to comply with such notice within a reasonable period from the date of
serving thereof in the case of failure, neglect or contravention capable of being made good within that
time or otherwise within such time as may be reasonably necessary for the same making good, then
and in such case KTL shall have at his option the right to take the supplies wholly or in part out of the
Contractor's hands and may complete the supplies envisaged in the contract either departmentally or
by awarding fresh contract at a reasonable price with any other person to execute the same or any part
thereof and provide other materials, tools and tackles or labor for the purpose of completing the
supplies or any part thereof

In such event KTL shall, without being responsible to the Contractor for fair wear and tear of the same,
be entitled to seize and take possession and have free use of all materials, tools, tackles or other things
which may be on the site for use at any time in connection with the supplies to the exclusion of any
right of the Contractor over the same and KTL shall be entitled to retain and apply and Balance sum
which may otherwise be then due on the contract by them to the Contractor or such part thereof as
may be necessary to the payment of the cost of execution of such supplies as aforesaid.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 166
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

If the cost of executing the supplies as aforesaid shall exceed the Balance due to the Contractor and the
Contractor fails to make good the deficit, the said materials, tools, tackles, construction plant or other
things, the property of the Contractor as may not have been used up at site may be sold by KTL and the
proceeds applied towards the payment of such difference and the cost of and incidental to such sale,
any outstanding Balance existing after crediting the proceeds of such sale be paid by the Contractor on
the certificate of KTL, but when all expenses, cost and charges incurred in the completion of the
supplies are paid by the Contractor, all such materials, tools, tackles, construction plant or other things
not used and remaining unsold shall be removed by the Contractor.

79 PROGRESS REPORT

The Contractor shall submit the progress report daily, weekly and every month in the Format mutually
discussed and agreed between the KTL and the Contractor. The Contractor shall submit 3 (three) copies
of the progress report to KTL. KTL will have the right to depute his/their representatives to ascertain
the progress of contract at the premises of works of the Contractor or any of his sub-contractors.

80 MAINTENANCE AND GUARANTEE

For a period of five years for regular and reliable working of the plant commencing from the date of
issue of commissioning certificate, the Contractor shall be liable to replace any part that may fail or
show signs of defects in place of his own manufacture or those of his sub-contractor's under the
conditions as per the contract and under proper use and arising from faulty designs, materials or
workmanship or erection or from any act of omission of the Contractor.

All such replacements of defective parts mentioned above shall be made free of cost at site by the
Contractor and the return of the defective parts to the Contractor's works shall be Contractor's
responsibility and shall be made at his expense. KTL will however, render such assistance in this matter
as will expedite the same. In the case of defective parts not repairable at site but essential in the
meantime for the commercial use of the plant, the Contractor shall replace at site free of cost to KTL
the said defective parts, before the defective parts are removed to his works.

The issue of KTL's certificate shall in no way exempt the Contractor from the provisions of this
schedule.

The Contractor shall pass on manufacturer’s/sub-contractor’s guarantees to KTL.

81 FURTHER THE GUARANTEES AS SPECIFIED IN TECHNICAL


SPECIFICATION DOCUMENT
The Contractor warrants that the supplies shall be new and of most modern design based on best
engineering practices and employing up to date, proven and established technology.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 167
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Within the terms of the Warranty, the contractor shall be liable for any defect in design, material,
manufacture, packing, transport, shipment, construction, erection, installation and operation.

Up to expiry of the warranty period hereinafter defined, the contractor shall remain solely liable for
compliance of his supplies with contract provisions and with the best trade practice. He shall be held to
perform entirely at his expense any modification; adjustment and/or revision acknowledged to be
required to meet the conditions of the contract.

Upon detection of defects either by KTL or by the Contractor and/or notification thereof in writing to
the Contractor by KTL, the Contractor shall immediately take appropriate or efficient measures to
remove the defects at his cost by repair or replacement as may be approved by KTL.

If the Contractor does not commence the rectification either by repair or replacement of such defects
within 7 days from the date of notice by KTL or does not complete the said rectification with
reasonable diligence and within a reasonable time as may be mutually agreed, KTL may, at his option,
rectify the defects at the Contractor's expense. KTL shall, in such as case, deduct from payment due to
the Contractor the expenses incurred by KTL for remedy of such defects without prejudice to the other
rights of KTL under this contract.

If the Contractor on account of the defects repairs and/or replaces certain items by changing the design
or materials, such change shall not reduce the performance of the unit.

If any drawings/documents supplied by the Contractor are found to be incorrect or incomplete within
the tenure of this contract, the Contractor shall correct or complete such drawing/documents at his
cost within a reasonable time.

The issue of acceptance certificate/inspection certificate/approval by KTL/Consultant shall in no way


relieve the Contractor from the provisions of the contract.

82 FURTHER, THE WARRANTY DETAILS AS SPECIFIED TECHNICAL


SPECIFICATION DOCUMENT OF THIS BID SHALL BE APPLICABLE
Rights of KTL to Vary or Cancel the Contract

If any changes are required for completeness of the contract, the Contractor shall not be entitled to
extra price or time.

The Contractor shall not change any supplies to be made pursuant to this contract except as may
become necessary to enable them to meet his technical obligations under this contract, provided that
such changes shall be subject or prior written approval of KTL.

If any changes are required for completeness of the work, the Contractor shall not be entitled to extra
price of time.

If KTL requests a change of the schedule, which requires additional price.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 168
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

KTL shall have further power to cancel the contract if the Contractor fails to duly perform and complete
the contract or if it appears for valid reasons that he will fail to fulfill his obligations under the contract
for reasons other than those relieving them from his responsibility under any other provision of this
contract. In such an event, without prejudice to and claims under this contract of KTL, there shall be
and equitable settlement of his obligations arising out of this contract.

83 SAFETY CODE

The Contractor shall adhere to safe construction practice and guard against hazardous and unsafe
working conditions and shall comply with necessary safety rules in this regard.

84 GOVERNING LAW AND JURISDICTION

The Contract shall be governed by the construed according to the laws of the land. For the entire
dispute arising out of this contract, the jurisdiction shall lie with the courts in Maharashtra only. The
Indian law shall be applicable for both Indian and Foreign contractors/suppliers.

85 LANGUAGE

All documents, instructions, catalogues, brochures, pamphlets, design data, norms and calculations,
drawings, operation, maintenance and safety manuals, reports, labels, on deliveries and any other date
shall be in English Language.

The contract agreement and all correspondence between KTL/Consultant and the Contractor shall be in
English language.

86 STATUTORY REGULATIONS AND JURISDICTION

The Contractor shall comply with all the statutory regulation of Government of India/State Government
applicable at site and KTL shall not be liable for any action or the statutes applicable due to non-
fulfillment of statutory obligations by the Contractor.

For the purpose of litigation, if any, the courts at Maharashtra alone shall have exclusive jurisdiction to
hear & decide all matters pertaining thereto.

87 INDEMNITY

The Contractor shall at all times, indemnify and keep indemnified the KTL, including its employees,
authorized agents and the Engineer-in-Charge, its successors from any and all liability for damages
resulting from or arising out of or in any way connected with the operation covered by the contract and
he shall make good all losses and damages arising there from. In case KTL shall incur any cost or
expenses or suffer any loss on account of any claim demand or course of action brought against them
and arising out of the operations covered by the contract, KTL shall have the power (without being

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 169
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

bound to do so) to defend, contest or compromise any such claim, demand or cause of action. Any
amount that may become payable by KTL and any cost, expense etc that may be incurred by the KTL in
this behalf, shall also be recoverable from the Contractor.

All sums payable by way of compensation/s under any of these conditions shall be considered as
reasonable compensation to be applied to the use of the Company without reference to the actual loss
or damage sustained and whether or not any damage shall have been sustained.

Contractor shall also keep indemnified KTL against all claims of its staff under Industrial Disputes Act,
Payment of Wages Act, and Mines Act and other Acts/Rules applicable on the awarded work to the
Contractor.

88 OBSERVANCE BY SUB-CONTRACTOR

The Contractor shall also be responsible for the observance of all the above clauses by his Sub-
Contractors.

We accept above all terms and conditions and signed each page of this document.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 170
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SECTION - IV
SPECIAL CONDITIONS OF CONTRACT– COMMERCIAL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 171
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1 CONTRACT PRICE
The total price for the project in accordance with all terms, conditions, stipulations, specifications,
requirements and other conditions of the Contract as accepted by KTL and incorporated into the
Contract document, shall be treated as the Contract Price. The total contract price includes the price
quoted by the Bidder in the price schedule B and C - Schedule C-1 + Schedule C-2 + Schedule C-3

2 EPC CONTRACT PRICE


EPC Contract price shall be the total price quoted by bidder in Schedule C-1 and Schedule C- 2

The EPC Contract price shall be deemed inter-alia to include entire scope of work and cover the cost of
equipment, materials and suppliers, tools & tackles, templates, consumable, transport, handling,
approval, checking & testing, power evacuation facility up to interconnection facilities, stores,
appliances, insurance & safety by the Contractor and all other materials in connection with the
execution of the supplies or any portion thereof complete in every respect or as may be ordered in
writing during the tenure of the Contract.

The EPC Contract price shall be deemed to include and cover the cost of all royalty and fees for all
articles and processes protected by letters, patent or otherwise incorporated in or used in connection
with the supplies, also all royalties, rents and other payments in connection with obtaining all the
materials for the supplies and shall indemnify KTL and this indemnity is hereby given by the Contractor
against all actions, proceedings, claims, damages, costs and expenses arising from the incorporation in
or use of any such articles, processes or supplies.

The EPC Contract price is on lump sum turnkey basis and the Contractor is responsible for the total
scope of work starting from design & manufacture till the project is successfully commissioned.

The EPC Contract price shall remain firm and fixed and binding till completion of work. No escalation
will be granted on any reason whatsoever. Unless otherwise provided in the Contract, the contractor
shall not be entitled to claim any additional charges, even though it may be necessary to extend the
completion period under this Contract for any reasons whatsoever.

The EPC Contract price shall be inclusive of all taxes and duties, TDS, Building Cess etc. KTL is open for
tax planning and tax structuring of the contract in a tax efficient manner within the framework of law.
Accordingly, the contract can be structured in a tax efficient manner.

The EPC contract price shall be exclusive of O&M of the Solar Photovoltaic Power Plant for a period of
Five (5) years.

The Contractor shall not separately bill any accessories and items required for making the plant &
machinery workable and their price will be deemed to be included in the price of such components in
the price of machinery plant or equipment.

3 O&M CONTRACT PRICE


EPC Contract price shall be the total price quoted by bidder in Schedule C-3.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 172
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Operation & Maintenance of Solar Photovoltaic Power Plant would include wear, tear, overhauling,
machine break down, insurance, replacement of defective modules, inverters, spares, consumables &
other parts for a period of Five (5) years. The same shall be treated as O&M Contract Price.

The O&M Contract Price shall be deemed inter-alia to include entire scope of work and cover the cost
of all consumables, spares, insurance & deployment of manpower including security personal during
O&M period.

The O&M Contract Price shall remain firm & fixed and binding till completion of O&M period from date
for commercial operation of complete Solar Power Plant. No escalation will be granted on any reason
whatsoever, unless otherwise provided in the contract.

The O&M Contract Price shall be inclusive of all taxes, duties, royalty works tax etc.

The O&M charges are inclusive of insurance charges for the Solar Power Plant. In case any break down,
the Contractor shall take immediate steps to repair such breakdown with no loss to KTL. If the
insurance authorities do not agree these failures as machinery break-down and consider wear and tear
failures, then these failures will be considered covered under O&M scope of work of the contract and
no extra charges shall be payable by KTL to the Contractor.

All Bank charges and all other charges in connection with payment to be made to the Contractor and in
connection with Bank Guarantee shall be borne and paid by the Contractor.

The contract price shall be inclusive of all taxes, duties, etc. according to the legislation in effect as on
date of the bid submission.

In case of failure by the Contractor to include any taxes, duties and levies in the quoted price, KTL shall
not entertain any claim later on whatsoever except for the statutory variations and or imposition of
new taxes and duties. KTL shall be eligible to avail the benefit if any downwards revision in the taxes
and duties.

Whenever tax has been paid in excess or any benefit under the Taxation Laws, which were available,
but has not been availed of or refund/benefit would be available to the Contractor on account of
avoidance of double taxation, the same shall be diligently claimed by the contractor from the
authorities concerned and refunded.

4 ERECTION OF EQUIPMENT
The KTL shall not be liable to pay any taxes and duties on the erection of equipment supervision of
erection & commissioning and commissioning assistance to be rendered by the Contractor and/or any
taxes and duties that may be applicable on the erection work and commissioning services. The
Contractor will include in his price all such taxes and duties in his price separately on this account. The
Contractor shall be fully responsible to pay such taxes and duties.

5 PERFORMANCE AND O&M BANK GUARANTEE DEPOSIT


As security for the due and proper fulfillment of the obligation under the contract, the Contractor will
furnish to the KTL Performance Guarantee equal to 15% of the total EPC contract price in the form of a
Bank Guarantee in the Format appended here to as “Schedule I: Format for Bank Guarantee towards

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 173
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Performance Guarantee” from a Commercial Bank listed in “Schedule J: List of Acceptable Banks”
within Fifteen days from the date of receipt of work order/letter of Award. This Bank Guarantee shall
be valid until successful completion of PG Test and Additional Claim period for three (03) Months from
the date of scheduled completion of work. The Performance Bank Guarantee of 15% of the total EPC
contract price shall be released after successful “commissioning” of the solar plant with completion of
PG test and after submission of the O&M Bank Guarantee of 10 % of total O&M contract value.

The Successful Bidder shall submit a Bank Guarantee of 10 % of total O&M contract value within 7 days
of start of Operation and Maintenance Period after successful commissioning of solar plant with 30
days period. The validity of O&M Bank Guarantee shall be 63 months (60 months + 3 months) from the
successful completion of PG test and O&M Period of solar plant with demonstration of each year
minimum annual guaranteed generation. O&M period shall commence with PG Test after successful
commissioning of solar plant with clear of all punch points by bidder and approved by KTL. The bank
guarantee may be issued by a nationalized bank or KTL approved bank. Bank Guarantee shall be in
favour of "Kallam Textiles Limited".

KTL shall be at liberty to realize and enforce payment of the Performance Guarantee for non-
fulfillment and unsatisfactory performance of the Contract without any notice or reference to the
Contractor. PBG should be encashed only after expiry of cure period given to the Contractor and in case
of failure of the contractor to (a) rectify the breach or (b) to pay the amount of damages.

Upon such encashment and appropriation from the Performance Guarantee, the Contractor shall,
within 15 (fifteen) days thereof, replenish, in case of partial appropriation, the Performance Security to
its original level, and in case of appropriation of the entire Performance Security provide a fresh
Performance Security, as the case may be. PBG is to be replenished back to a value that is limited to the
liability of the contractor.

If, by any reason, it is required to extend the Bank Guarantee, bidder shall undertake to renew the Bank
Guarantee at least one month before the expiry of the validity failing which KTL will be at liberty to
encash the same. KTL shall notify the bidder for submission of renewal of bank guarantee.

The Bank Guarantee shall remain binding notwithstanding such variations, alterations or extensions of
completion time as may be made, agreed to between the Contractor and the KTL under these general
conditions otherwise.

The said Performance Guarantee deposit shall not in any way be construed as a limitation of the
Contractor's responsibilities or liability pertaining to its obligations and/or guarantees under the
contractor and shall be without prejudice and in addition to any other remedies available to KTL in
terms of the contract and/or the laws of the land.

If the Contractor/Sub-contractor or their employees shall break, deface or destroy the property
belonging to the KTL or others during the execution of the contract, the same shall be made good by
the Contractor at his own expense and in default thereof. KTL may cause the same to be made good by

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 174
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

other agencies and recover expenses from the Contractor for which the certificate of the KTL shall be
final.

All Bank charges and all other charges in connection with bank guarantee shall be borne by the
Contractor.

6 PAYMENT MILESTONES

a) Supply Payment Terms: For Supply of Modules /Inverter/ MMS with Lifeline, Walkway,
Module cleaning system, safety guard rail/ DC cable/ WMS & Data Monitoring system ( as
per Price breakup schedule C-1 items 1 to 5

Particulars Amount

Mobilization Advance 10% of the Purchase Order Sum against submission of the 15% of
Purchase order Performance Bank Guarantee (PBG) for an
equivalent amount from a commercial/nationalized bank, in the
format acceptable to KTL

1st Tranche 30% of the Purchase Order Sum shall be paid against dispatch of
Modules /Inverter/ MMS with Lifeline, Module cleaning system,
Walkway, safety guard rail/ DC cable/ WMS & Data Monitoring
system along with documentary evidence & quality certificate. The
payment will be done as per price breakup given the Price Bid
against individual items.

2nd Tranche 20% of the Purchase Order Sum shall be paid against receipt &
acceptance of Modules /Inverter/ MMS with Lifeline, Module
cleaning system, Walkway, safety guard rail/ DC cable/ WMS &
Data Monitoring system at Project Site

3rd Tranche 10% of the Purchase Order Sum shall be paid on completion of
testing on installation & issuance of mechanical completion
certificate

4th Tranche 10% of the Purchase Order Sum shall be paid on achieving
provisional acceptance of the completion of the commissioning of
the proposed project.

5th Tranche 10% of the Purchase Order Sum shall be paid on achieving PG test
pass certificate from KTL and UL Certification Report along with
supply of the requisite O&M spares. In case of PG Generation
shortfall amount will be deducted and excess generation incentive
will be paid.

6th Tranche 10% of the Purchase Order Sum shall be paid on completion of

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 175
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

defect liability period of the proposed project.

Note: Payment terms shall be same for Supply of material like Modules /Inverter/ MMS with
Lifeline, Walkway, safety guard rail/ DC cable/ WMS & Data Monitoring system.

b) Supply Payment Terms (Including Civil Works): For Supply of all other material, equipment
including civil material (Schedule C-1 Item No.6)

Particulars Amount

Mobilization Advance 10% of the Purchase Order Sum against submission of the 15% of
Purchase order Performance Bank Guarantee (PBG)for an
equivalent amount from a commercial/nationalized bank situated
in KTL, in the format acceptable to KTL

1st Tranche 50% of the Purchase Order Sum shall be paid against dispatch of all
other materials along with documentary evidence, quality
certificate and receipt & acceptance of Materials at Project Site

2nd Tranche 10% of the Purchase Order Sum shall be paid on completion of
testing on installation & issuance of mechanical completion
certificate

3rd Tranche 10% of the Purchase Order Sum shall be paid on achieving
provisional acceptance of the completion of the commissioning of
the proposed project

4th Tranche 10% of the Purchase Order Sum shall be paid on achieving PG test
pass certificate from KTL along with supply of the requisite O&M
spares. In case of PG Generation shortfall amount will be deducted
and excess generation incentive will be paid.

5th Tranche 10% of the Purchase Order Sum shall be paid on completion of
defect liability period of the proposed project.

c) Services Payment Terms (Including Civil Works): For design, engineering, erection, testing &
commissioning and Civil Works: Schedule C-2

Particulars Amount

Mobilization Advance 10% of the Purchase Order Sum against submission 15% of
Purchase order of the Performance Bank Guarantee (PBG)for an
equivalent amount from a commercial/nationalized bank
situated in KTL, in the format acceptable to KTL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 176
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1st Tranche 30% of the Service Contract Price shall be paid on Completion
of the MMS, walkway, Safety lifeline, Safety guardrail works and
module installation, approval of all design works, project
schedule, Quality Assurance plans, Health and safety and
environment implementation plans

2nd Tranche 30% of the Service Contract Price shall be paid on completion of
inverter, DC/ AC, LT panel and all other plant material &
equipments with accessories erection, installation, testing and
up on receiving certificate of mechanical completion from the
Owner.

3rd Tranche 10% of the Service Contract Price shall be paid up on successful
commissioning of the plant with PG test and synchronizing with
grid and provisional acceptance letter from KTL. In case of PG
Generation shortfall amount will be deducted and excess
generation incentive will be paid.

4th Tranche 10% of the Service Contract Price shall be paid after completion
of the punch points ,submission of O&M manuals, complete
built drawings and handing over other documents as per the
contract

5th Tranche 10% of the Service Contract Price shall be paid after completion
of defect liability period of the proposed project.

The above said payment shall be released within 30 days from the date of submission of invoice along
with all necessary supporting documents. The EPC CONTRACTOR has to submit the tax invoice in the
approved format by KTL otherwise it will not consider.

7 PAYMENT PROCEDURE
The Bidder shall submit the bills for claim in four copies. The payment shall be made after the
verification and recommendation for payment from the Engineer-In-charge and appropriate authority.

It is expressly understood that the drawl of payment by the contractor in the manner specified will not
be construed as the fulfillment of the contractor's obligations either in part or whole under the
contract and that the contractor shall continue to remain responsible to KTL until all the obligations
under the agreement have been fulfilled.

8 COMPLETION PERIOD
The completion time is deemed to be of essence to the Contract and shall be firm and binding. The
Bidder shall complete the design, engineering, manufacture, supply, storage, civil work, erection,
testing & commissioning of 2.6 MWp within Four (04) months of date of issue of clear work
order/letter of Award.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 177
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

9 LIQUIDATED DAMAGES
Time is the essence of the contract. Should the contractor fail to commission the power plant/activity
within specified time (as per clause8) from the date of the work order/Letter of Award, KTL may allow
an extension in time of commissioning subject to recovery from the contractor as LD @ 0.5% per week
subject to maximum of 10% of the EPC contract price. LD subject to situation beyond EPC contractor’s
control should be replaced by standard force majeure conditions.

Contractor shall fail to achieve Guaranteed generation, based on deviation of actual versus guaranteed
Generation (PG) as per contract LD will be apply as mentioned in Performance Guarantee (PG)
document.

The Bidder shall maintain maximum plant availability factor for achieving Guarantee generation as per
contract during O&M period. For any shortfall in the annual targeted Guaranteed Generation due to
plant availability factor, LD will be levied as mentioned in Performance Guarantee (PG) document.

10 WARRANTY AND GUARANTEE

The Contractor shall warranty that the goods to be supplied under this contract are new and unused, of
the most recent or latest technology and incorporate all recent improvements in design and materials
unless provided otherwise in the contract.

The Contractor shall provide warrantee covering the rectification and replacement if required at their
own cost for all defects in the design of equipment, materials and workmanship including spares
consumables parts as specified in the technical document attached in Technical specification
document.

11 HANDING OVER –TAKING OVER

The work shall be taken over by KTL upon successful completion of all tasks to be performed at site(s)
on equipment supplied, installed, erected & commissioned by the Contractor in accordance with
provision of Tender. During handing over complete project work, the Contractor shall submit the
following for considering final payment.

All as- Built Drawings as per mutually agreed.

Detailed Engineering Document with detailed specification, schematic drawing, circuit drawing and test
results, manuals for all deliverable items, Operation, Maintenance & Safety Instruction Manual and
other information about the project.

Bill of material

Inventory of spares at projects site

Immediately after taking over of complete project(s), the same will be handed over to the Contractor
for Operation & Maintenance for a period of Five (5) year.

At the end of the contract period:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 178
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Contractor shall handover to the Owner, the project along with the site, free of cost and
consideration and clear of any liability, charge and/or Encumbrances. The Contractor shall also deliver
to the Owner any information as may be reasonably required to enable the Owner to continue the
Operation and Maintenance of the project.

All the sub-contracts of the Contractor shall specify the transfer date and its effect. Failure to specify
the transfer date and its effect shall not adversely affect the Owner and the Contractor shall be solely
responsible for the handover of the project along with the site at its own risk and cost.

The Contractor shall hand over full and peaceful possession of the project and the site to the Owner
and the Contractor, its sub-contractors, agents, employees or any other entity appointed by the
Contractor shall vacate the site.

The Contractor shall be responsible for the costs and expenses, including stamp duties, taxes, legal fee
and expenses incurred in connection with the handover of the project and site to the Owner. The
Contractor hereby undertakes to indemnify the Owner against any liability arising out of the any non-
payment of tax liability till the contract period that may be sought to be or imposed on a later date on
the Owner by the any Tax Authorities, in relation to the project.

12 CONTRACTOR AND OWNER OBLIGATIONS

Owner’s Basic Obligations

The OWNER shall be obliged to:

 Appoint quality assurance personnel to witness tests on the all necessary plant equipment’s
prior to the supply / procurement as mentioned in this agreement

 Appoint KTL’s engineer / independent technical consultant for reviewing project designs,
detailed engineering, drawings, equipment specifications and all project management
documents provided by bidder.

 Maintain cash flow of the project and make payments to the bidder on time after satisfactory
completion of its obligations as specified in other sections of this contract. The payment to the
EPC contractor shall be based on the pro rata basis or milestone basis as per agreed terms and
condition

Turnkey EPC Contractor’s Basic Obligations

A successful Bidder shall be referred as ‘Bidder or EPC Contractor’, who has won the contract. In
addition to obligations of Bidder specified elsewhere in other sections, the turnkey EPC contractor shall
be bounded by the following basic obligations.

a. Adherence to all the terms and specifications under various sections of this contract document
is essentially a key obligation of the EPC contractor.

b. Conducting site survey and soil investigation studies. Bidder has to familiarize themselves with
the existing Site Conditions, environment at the Facility Site

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 179
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

c. Unless otherwise agreed, the Bidder shall not be obliged to perform any Works other than
those required to be performed for successful erection, commissioning and smooth operation
of the facility to achieve agreed power generation as per performance parameter and specified
in the Scope of Work.

d. Bidder shall prepare all remaining Contract Documents (if any) in terms of and as per the
requirements of the Scope of Work and submit such Contract Documents to the Owner or to
the Bidder's Representative for its review and approval as per the Schedule of Program agreed
between the parties.

e. Bidder shall submit before starting manufacturing to Owner /Technical Consultant, the
drawings/ diagrams / documents / calculations, for approval by the Owner /Technical
Consultant.

f. Bidder shall be solely responsible for, and shall bear any fees, costs and expenses of obtaining
any Applicable Permits falling in their Scope of Work under the List of Approvals and
Clearances. However, the Bidder shall facilitate / assist the Owner in completing the tasks
excluded in Bidder’s scope.

g. The Bidder shall in performing its obligations under this Agreement, comply with all applicable
rules, regulation, Laws and the requirements of any Government Authority relating to
occupational health, safety and the environment.

h. Owner shall provide construction water and construction power at one point as per mutual
understanding.

i. All Bidder related approvals/ clearances, etc. shall be in the scope of Bidder. Bidder shall
comply with all the Codes and Standards as provided in this Agreement. However, the list is not
exhaustive and the bidder must refer to relevant Indian and International standards for
designing and executing the plan. Without generality of the foregoing, the Bidder shall ensure
that the Facility withstands 10 years of operation, given the nature of the Works carried out
under this Agreement.

j. The Bidder shall comply with the provisions of the applicable labour laws and in timely manner,
obtain and / or maintain the licenses, registrations, employment records, registers, certificates
and other records and file returns as are required under various Act/ Rules / Regulations of the
State/Center/Local Government in force or as amended from time to time and furnish the
proof of the same if requested by the Owner within a reasonable time. The Bidder shall abide
by and comply with the applicable statutory requirements under the existing Central, State and
local body regulations, laws or those made applicable from time to time.

k. Safety shall be the highest priority. Bidder shall be fully responsible for the safety of all
equipment and material supplied at Site and personnel deployed by them / their sub-Bidders
for the works and also for all the Site operations and the method of construction. Bidder shall
be responsible for the safe keeping for their tools and tackles, any work related equipment at

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 180
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Site by their personnel or by their sub-Bidders. The detailed activities to be carried out at the
Site should be provided by the client in form an HSE document which will be approved by the
Owner, and should be adhered to. Bidder shall adhere to all safety as well as first aid
requirements of their employees as well as of their Sub Bidders /Bidders. Safety Helmets,
safety shoes, safety goggles, dust mask, reflective jackets and gloves are the minimum
requirement which shall be provided by contract to workforce.

l. O&M Manuals & Design Documents: Bidder shall submit to Owner all the O&M manual
equipment wise, required for operation and for the smooth hand over of the Project Facility
before getting Final Acceptance Certificate

m. Bidder shall be required to comply with all applicable environmental laws and regulations upon
them during construction of the Facility. Detailed list of activities to be covered under Health,
Safety, Security and Environment is provided under contract.

Project Management

a. Bidder shall submit the Project Organogram for the review and approval of the Owner

b. Bidder shall submit the detailed billing schedule / breakup to the Owner

c. Bidder shall, within 1 week of receipt of Notice to Proceed, appoint a competent Project
Manager, to be stationed at Site for the supervision and progress of work, including the quality,
safety and health measures. The Project Manager appointed shall remain till the completion of
the Project

d. Bidder shall deploy full time QA/QC engineer at Site, who will prepare and maintain all
documents to be handed over to Owner/technical consultant at the completion of the works

e. Timely delivery of the Facility shall be of the essence of the contract. The Bidder shall so
organize its resources and perform the Scope of Works as to ensure that the Facility is
commissioned and ready for commercial operation within the Scheduled Commercial
Operation Date. The Bidder shall develop Base line detail level 2 project schedules within 10
Business Days of Notice to Proceed.

f. The Bidder shall submit to the Owner the inspection list and quality assurance plan for his
approval for them to organize factory inspection, witness tests at factory, / Bidders / sub-
vendors facility and provide dispatch clearances. Bidder within 1 week of the NTP, shall submit
and get the Quality Assurance Plan (QAP) and approved for manufacturing as well as site
construction activities, from the Owner /Technical Consultant. Bidder shall ensure the
Inspection and approval is taken from the Owner before dispatch of goods to Site. Dispatch
approval document by Owner/technical consultant shall form part of the invoice submitted for
payment by the Bidder.

g. The bidder shall submit labour, machinery and material schedule in line with the detailed work
schedule. The schedule will be approved by the Owner, and the mobilization will be deemed

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 181
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

complete when the bidder engages all men, material and machinery for first two weeks of work
at site along with sufficient power, water and lighting arrangements for day and night shift
work at site.

h. All equipment, accessories materials, civil construction and erection works shall comply with all
applicable statutory requirements and standards.

i. The entire responsibility and risk relating towards workforce working at site and compliance of
different statutory regulations shall solely lie with Bidder.

j. The Bidder shall submit the detailed ledger statements and balance confirmation at the end of
every quarter towards the Scope of Work carried out by them, to the Owner for completion of
their accounts / audit requirement. The Bidder shall also, as and when required by the Owner
or Owner’s Representative, submit details of the arrangements and methods which the Bidder
proposes to adopt for the execution of the balance Work.

k. If any permission required for cutting / felling of trees, removal or transplanting if any shall be
obtained by the Bidder from appropriate authorities.

l. Bidder shall be responsible for training of Operation & Maintenance personnel before the
receipt of Final Acceptance Certificate /Work Completion Certificate

m. Bidder shall so effectuate the Works that the Project is completed and commissioned on or
before agreed timelines.

n. Bidder shall independently conduct resource assessment and predict energy yields clearly
specifying losses and degradation over project lifecycle. KTL shall closely monitor these losses
and degradation, and shall link with project performance.

o. Wherever standard codes are provided in the document, stringent codes shall be followed by
the bidder; wherever codes are not mentioned, latest relevant IS, NEC and IEC codes shall be
followed.

p. The project being a turnkey EPC contract, scope shall include everything as required for
successful implementation, commissioning and operation & maintenance of the plant as per
the site conditions for five years. No variation shall be entertained on this account by the
OWNER.

q. Bidder shall perform works strictly adhering to technical documents and drawings approved by
the OWNER as well as requirements established by the applicable technical regulations.

r. Bidder shall follow and perform all works in accordance to technical document. Bidder shall
strictly follow the start-up and functional requirements of the project as presented in technical
document. This shall essentially include all the material and construction equipment supply,
implementation, testing and commissioning of the relevant systems as required for successful

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 182
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

completion, commissioning and 5 years of O&M along with DLP for years from the date of
Commissioning.

s. Owner shall provide site-specific list of approvals & bear all statutory type fees for approval
after signing of agreement.

13 SCOPE OF WORK AS PER THE TECHNICAL DOCUMENT

The Contractor shall arrange on his own cost, utility facilities such as construction and power & water
will be provide by KTL.

The Contractor in all matters arising out of the performance of the contract should comply in all respect
with relevant laws, Acts, by laws and rules and give all notices and pay all fees required by the provision
of any National or State Statute, or other law or any regulations or by laws of any constituted authority.
The Contractor shall also comply with all the applicable laws of the country of manufacture of the
equipment.

The Contractor shall indemnify KTL against all claims, infringement of any patent, registered design,
copyright remarks or other property right. For the avoidance of doubt, KTL shall be under no obligation
to make any payments by way of royalties or fee for the possession and use of any copyright /patent or
other intellectual property right in relation to the equipment provided by the Contractor.

The Contractor shall coordinate with KTL/Statutory Authority/other agencies for timely completions of
interconnection, protection scheme and provide the same including the metering facility as required.

The Contractor shall in connection with all works provide and maintain at his own cost, guards, fencing
and watch and ward when and where necessary or required.

The Contractor shall be responsible for the safety of the working personnel and shall take all necessary
precautions according to the existing laws and regulations as applicable.

The EPC cum O&M Contractor shall provide access for officials of KTL/GOI//MNRE/GOT or any other
nominated agencies to all project facilities at all reasonable time during construction and operation
phase and during O&M contract period.

The EPC cum O&M contractor shall be responsible for safe and uninterrupted operation of the plant
including undertaking planned maintenance programmed.

The contractor shall also provide all data, documents and information to GOI/KTL and its nominee as
desired during erection, operation and maintenance period.

The land will be acquired by KTL and will be handed over to Contractor for construction, commissioning
and thereafter for O & M purposes.

Bidder is responsible for solar data accuracy. For the performance of the plant, the Bidder is
responsible for obtaining authenticated solar data from any sources.

It is the responsibility of the O & M contractor to maintain high power factor to reduce VAR drawl in
these system. If any Statutory Authority penalizes KTL for lower power factor / VAR drawl from grid,
penalty at actual amount shall be deducted from the O & M contractor bills/outstanding contractor’s

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 183
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

credit amount. The Contractor shall also be liable for fulfillment of any other losses arises due to poor
performance of the Solar Photovoltaic Power Plant.

The O&M contractor shall strictly follow the gird code and metering code of CERC/CEA/KTL. In case any
Statutory Authority penalize KTL for any disturbance in transmission and distribution system the same
shall be recovered from the bills of O&M contractor or any amount outstanding with KTL or by any
legal means.

14 CONDITIONS FOR OPERATIONS & MAINTENANCE OF THE SOLAR


POWER PLANT
a) Term

The Contractor shall be responsible for operation and maintenance of the Solar Power Plant for a
period of Five (5) year from the date of commercial operations of the Solar Photovoltaic Power Plant as
a whole for O & M.

b) Extension of Term

This term may be extended for further period and such additional period on terms and conditions that
are mutually agreeable to the KTL and Contractor.

15 BATTERY LIMIT
The battery limit for Bidder during the period of O&M contract shall cover complete Solar Power Plant
and power evacuation system up to inter connection point.

The Bidder shall be responsible for the guaranteed performance ratio (PR) as offered by the Bidder for
Five (5) years. For any deviation in the guaranteed performance ratio (PR), the contractor will have to
compensate the Owner as defined herein this document.

The Bidder shall be responsible for supply of all spare parts as required from time to time, schedule and
preventive maintenance, major overhauling of the plant, replacement of defective, modules, inverters,
all spares, consumables, PCU’s etc. and maintaining log sheets for operation detail, deployment of staff
for continuous operations and qualified engineer for supervision of O&M work.

16 SCOPE OF WORK AS PER THE TECHNICAL DOCUMENT WHICH


SHALL BE FOLLOWED
Contractor shall provide all day-to-day operation and maintenance for the Power Plant as set forth
herein. Contractor shall perform the Work and supply all required spare parts in a prudent efficient
manner and in accordance with:

Manufacturers and systems designers‟ specifications, the Annual Operating Plan for the Plant and all
manuals, Operation and maintenance

All Indian applicable laws including environmental protection, pollution, sanitary, employment and
safety laws, (“Government Rules”).

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 184
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Prudent Utility Practice.

a) Contractor uses all reasonable and practical efforts-To maximize plant capacity utilization,

To reduce plant downtime, to optimize the useful life of the equipment of the power plant

b) The Contractor shall perform the following obligations prior to takeover of the O&M
activity:

 Prepare Mobilization plan in consultation with the KTL


 Provide the services and personnel set forth in the Mobilization Plan
 Prepare in consultation with the KTL, the initial Annual Operating Plan.

Develop and implement plans and procedures including those for firefighting, maintenance planning,
procuring and inventory control of stores and spares, plan to meet emergencies, plant safety and
security; and such other facilities and systems as may be necessary to commence of Contractor’s
ongoing responsibilities.

Provide in plant training to KTL personnel who will gain experience for the operation and maintenance
of the plant.

After taking over the activity of O&M for the power plant, the Contractor shall be responsible for the
operation and maintenance of the plant and shall perform all necessary services including applicable
services listed below:

 Provide all operations and maintenance services necessary or advisable to efficiently operate
and maintain the plant, including all associated and appurtenant mechanical and electrical
keeping in view the objectives set forth herein above.

 Maintain accurate and up-to-date operation logs, records and Monthly reports regarding the
operation and maintenance of the Plant which shall include detail of power output, other
operating data, repairs performed and status of equipment. Upon expiry of term, the
Contractor shall hand over such records to the Owner; however, KTL shall have access to all
such records at any time.
 Regularly update and implement equipment repair and preventive maintenance program that
meets the specifications of the equipment manufacturers and the recommendations of the
manufacturers.
 Perform periodic overhauls or preventive maintenance required for the Plant in accordance
with the recommendations of equipment manufacturers. Also attend break down and other
maintenance in the Plant.
 Provide technical & engineering support for solving operation and maintenance problems.
 Perform the service required to procure all spare parts, overhaul parts, tools and equipment,
required to operate and maintain the Plant in accordance with the recommendations of
individual original equipment manufacturer.
 Operate and maintain fire protection plant and safety equipment.
 Maintain with the assistance of the KTL, accounting records regarding the facility in accordance
with the generally acceptable accounting principles under the Laws of India.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 185
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

17 PERSONNEL

The Contractor shall employ only such personnel who are adequately qualified and experienced for
operating and maintaining the power generating sets. The Contractor shall ensure that such personnel
are on duty at the plant at all times, twenty-four (24) hours a day and seven (7) days a week
commencing from the Date of Commercial Operations.

18 INSURANCE

Contractor shall provide or obtain and maintain in force throughout the period of contract the
following insurance coverage:

Workmen compensation and / or group personal accidents Insurance policy covering all its employees
and works including of the sub-Contractor. Insurance to cover third party liability.

Insurance in respect of claims for personal injury to or death of any person in the employment of
Contractor and arising out of and in the course of such employment, which insurance shall comply with
all applicable Indian law and directives.

Transit Insurance for all the materials: In the Scope of the EPC contractor for all the material movement
until the delivery of goods at site.

Contractor shall provide insurance, which shall cover among other things, fire, earthquake, and flood
damage and deductibles thereon. Machinery breakdown insurance and deductibles / excess thereon
for modules, inverters, PCU’s, other auxiliaries and complete Solar Photovoltaic Power Plant.

19 MEASUREMENT OF ENERGY AND METERING

a) Metering Systems

The Contractor shall maintain the Metering System (which shall include energy meter, current
and potential transformers and tele-metering equipment) as per metering code and CEA
guidelines. Solar meter shall place near to KTL LT panel as per KTL/ Consultant approved
location. Solar meter shall be bidirectional type for measuring import and export energy at
metering point. Metering point will be the Delivery Point and shall have calibrated trivector
meters 0.5s Class with suitable 0.5s Class CT at 400V at Evacuvation Point. The Energy Meters
to be integrated with SCADA with suitable communication system. The cumulative of all the
trivector meters energy delivered is considered as delivered energy. The specification of items
mentioned above and installation thereof shall be subject to prior written approval of the
KTL. Meter reading shall be done jointly on a monthly basis or at a mutually agreed time
interval. Such measurement will be recorded in the measurement book by the Engineer-in-
charge or his authorized representative and signed in token of acceptance by the Contractor
or his authorized representative

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 186
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

b) Testing of Meters

i. The KTL shall have the right to carry out surprise inspections of the Metering Systems from
time to time to check for their accuracy.
ii. All testing equipment shall conform to the relevant IS/IEC/KTL standards.
iii. If either the Contractor or the KTL find any inaccuracy in the Metering System, the
Contractor or the KTL, as the case may be, shall notify the other party in writing within 24
hours for a joint inspection and testing from KTL/ or other agreed agency.

c) Sealing and Maintenance of Meters

The Metering System shall be sealed in the presence of both parties and representative of
any Statutory Authority, if required. When the Metering System and/or any component
thereof is found to be outside the acceptable limits of accuracy or otherwise not
functioning properly, it shall be repaired, re-calibrated or replaced by the Contractor as
soon as possible. If the meters are found tampered during the entire O&M period, the
responsibility of any charges recoverable by Statutory Authority / KTL on this account shall
be borne by the O&M Contractor.

20 PAYMENTS FOR O&M

The payment of O&M charges shall be made on quarterly basis after deduction of leviable taxes and
adjustment of dues payable to KTL. KTL will be billed by the Contractor promptly following the end of
each year of O&M period. For the purpose of payment, the first year shall be reckoned from the date of
hand over of Solar Photovoltaic Power Plant to the contractor for O& M purpose. Shortfall in O&M PG
will be deducted and incentive will be added while paying the bill.

21 HANDING OVER THE PLANT AFTER EXPIRY OF O&M TERM

After the expiry of term & extension of term as the case may be, contractor shall hand over the plant to
the KTL in excellent condition. The contractor shall demonstrate performance test of all the major &
critical equipment to ensure Generation from the Solar Photovoltaic Power Plant. While handing over
the plant contractor shall hand over all technical documents, literature, instruction manuals, lists of
spare part & tools & tackles. Contractor will also hand over all the relevant record/documents, spares
and consumable required for Five (5) years of Operation & Maintenance. On completion of O&M term
the Contractor will apply to the Engineer in-charge for the issue of Handing Over Certificate and the
same will be issued within 1 month of the Handing Over in all respects, after verifying from the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 187
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

documents & tests and satisfying themself that the Operation & Maintenance has been completed in
accordance with details set out in the control documents & Prudent Utility Practices.

All the aforesaid safeguards / rights provided for the company shall not prejudice its other rights /
remedies elsewhere provided herein and / or under law.

22 FINAL PAYMENT

Whenever, in the opinion of the Engineering-in-charge the Contractor has completely performed the
contract on his part, the Engineer in-charge will so certify in writing to the Contractor.

The final payment to the Contractor shall be made after accounting for all the previous
payments/advances/adjustments of dues, provided always that Contractor furnishes a “NO further
claim – No dues certificate”. “No Claim Certificate” should be printed in Rs 100/- stamp paper and
“Release & certificate of final payment” will be on Contractor’s letter head. The release of final
payments does not relieve the Contractor from his any other obligations as provided for in the
contract.

The company shall be deducting statutory taxes at source as per prevailing rates from bills of the
Contractor.

23 FAILURE OF THE CONTRACTOR TO COMPLY WITH THE


PROVISIONS OF THE CONTRACT
If, the Contractor refuses or fails to execute the work or any separable part thereof with such diligence
or fails to perform any of his obligations under the contract or in any manner commits a breach of any
of the provisions of the contract, it shall be open to the company, to adopt following course of action at
its option, by written notice to the Contractor.

To determine the contract in which event the contract shall stand terminated and shall cease to be in
force and effect on and from the date the decision is announced by the company. The Contractor shall
stop forthwith any of the Contractors work, then in progress and hand-over the work to the company.
The company shall be entitled for recovery of cost / compensation to complete the unfinished
obligations.

Without determining the contract, to take over the work of the Contractor or any part thereof and
complete the same through a fresh contractor or by other means at the risk and cost of the Contractor

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 188
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

In the event that the company proceeds in the manner given in the above clause then Bank Guarantee
furnished by the Contractor is liable to be forfeited without prejudice to the other rights of the
company. The company shall also have the right of taking possession and utilizing such materials,
equipment and plant, belonging to the Contractor, as may be at the site of the work in order to
complete the unfinished work

The amount that may have become due to the Contractor on account of work already executed by
them shall not be payable to them until after the expiry of six (06) months reckoned form the date of
the determination of contract of from the taking over of the work or part thereof by the company as
the case may be. Further during this period of six months the responsibility for faulty workmanship in
respect of such completed work shall, under the contract, rest exclusively with the Contractor

Termination of the contract shall not prejudice or affect the rights of the company which may have
accrued up to the date of such termination.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 189
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SPECIAL CONDITIONS OF CONTRACT - TECHNICAL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 190
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

1 THE BIDDER
1.1 General Obligations

n. All approvals required to be given by the KTL and/or KTL’s Personnel and/or KTL’s
Representatives with respect to this Contract have to be provided within 7 days from the
date of submission of the documents by the Bidder.

o. The KTL shall provide the Bidder with an access road to the Site and the clearance of the
Site to the extent necessary for the construction and erection activities.

p. The Bidder shall execute the Works in accordance with the Works Completion Schedule
and shall complete the Works on or prior to the Date for Commissioning and for this
purpose the Bidder shall provide necessary resources, services, Materials, Bidder's
Equipment, personnel with the requisite experience and all other things, whether of a
temporary or permanent nature required in and for the execution of the Works.

q. The Bidder shall execute the Works in accordance with the Contract and applicable local
/ statutory Laws. Where the Technical Specifications describe portions of the Work in
general terms, but not in complete detail, it is understood that, subject to Bidder
meeting the requirements of this Contract (including the Technical Specifications), Good
Industry Practices shall prevail. The Works shall be fit for the purposes for which they are
intended, as defined in the Contract. The Works shall include any work as implied by the
Contract, or arises from any obligation of the Bidder and all works not mentioned in the
Contract but which are necessary for safe and reliable operation of the Works should
have been performed in accordance with Good Industry Practice, unless it is excluded
elsewhere in the Contract.

r. The Bidder agrees and acknowledges that it shall perform all of its obligations and
responsibilities under the Contract at its own risk, cost and expense. The KTL shall have
no obligation or responsibility whatsoever with respect to the completion of the Works
or the fulfillment of other obligations of the Bidder under the Contract, except as
expressly provided in the Contract.

s. The Bidder shall take full responsibility for the methods of execution of the Works,
adequacy, stability and safety of the operations carried out at the Site relating the
execution of the Works, all Bidder's Documents, Plant and Materials and Bidder's
Equipment, irrespective of any approval or consent by the KTL's Representative.

t. Without prejudice to the provisions of the Contract and notwithstanding any testing or
certification pursuant to this Contract, the KTL shall at any time during the subsistence of
this Contract, have the right (but not the obligation) to notify the Bidder, with reason in
writing, on any part of the Works, the Plant, Materials, or the Bidder's Equipment, which
is found not to be in compliance with the Technical Specifications.

In such a situation, the KTL may instruct the Bidder to:


t. repair and/or replace the notified Plant, Materials or Bidder's Equipment or re-
instate the Works; or

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 191
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

u. execute any work which is urgently required for the safety of the Works, whether
because of an accident, unforeseeable event or otherwise;

In accordance with the requirements of this Contract, the cost of which shall be to the
sole account of the Bidder. The Bidder shall comply with the instruction within a
reasonable time, which shall be the time (if any) specified in the instruction, or
immediately if urgency is specified under paragraph (b).

If the Bidder fails to within the time specified in the notice, which shall be not less than
15 days (i) specifies the KTL with reasons in writing that the KTL's instructions are not
required to be performed; or (ii) proceed promptly with the repair or replacement of
the notified item of the Works, the KTL may, by contract with third Persons or
otherwise, repair or replace such part of the Works and the Bidder shall be liable to
reimburse the KTL upon demand for all costs and damages incurred by the KTL relating
to such repair or replacement by a third party. Such repair or replacement carried out
by a third party shall not in any manner affect any of the Bidder’s obligations,
representations or warranties under this Contract subject to such repair or replacement
being carried out by third party as per this Contract.

1.2 Right of Access to Site

The KTL shall give the Bidder right of access (motorable) to the site prior to issuance of Notice
to Proceed.
The Bidder shall not demolish, remove or alter any structures or other facilities on the Site
without the prior written approval of the KTL's Representative. The Bidder shall further ensure
that all waste materials resulting from the execution of the Works is burnt or removed and
disposed of, in accordance with Applicable Laws and that the Site is kept clean at all times
during the execution of the Works.

1.3 Permits, Licenses and Approvals

The Bidder shall be responsible for applying to and obtaining permission from State
Transmission Utility for connection of the Facility to the Grid. The Bidder shall provide
alldocuments as may be required by the KTLfor liaisoning permits and approval. The Bidder
shall be available at the Site during any inspection of the Facility by any government authority.
The KTL Shall be responsible for applying to and obtain permission. The Bidder shall provide all
technical documents and drawings as may required by KTL to make an application to APSPDCL
for the commissioning certificate. The Bidder shall be available at the site during any inspection
of the facility by APSPDCL, CEIGAP and Others.
Bidder shall obtain all the necessary permission from the respected statutory authorities
before commencement of work at site. All fees to obtain passes needs to be paid by the KTL to
issuing Authority. Bidder will facilitate the KTL for the obtaining the pass.

1.4 Bidder's Representative

The Bidder shall, within 7 days of the Commencement Date, appoint the Bidder's
Representative with the prior notification to the KTL (and vest in them the authority to act on
behalf of the Bidder for all purposes of the Contract. If the appointed person fails to act as the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 192
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Bidder's Representative, the Bidder shall provide the name and particulars of another suitable
person for such appointment.
The Bidder shall not, without giving prior written notice to the KTL, revoke the appointment of
the Bidder's Representative or appoint a replacement.
The Bidder's Representative shall give his whole time to directing the preparation of the
Bidders Documents, the execution of the Works and performance of the Bidder's obligations
under the Contract. Except as otherwise stated in the Contract, the Bidder's Representative
shall receive (on behalf of the Bidder) all notices, instruction, consents, approvals, certificates,
determinations and other communications from the KTL or the KTL's Representative.
Whenever the Bidder's Representative is not available, a suitable replacement person shall be
appointed, and the KTL's Representative shall be notified accordingly.

The Bidder's Representative may delegate any of his powers, functions and authorities to any
competent person, and may at any time revoke any such delegation. Any such delegation or
revocation shall be in writing and shall not take effect until the KTL's Representative has
received prior notice signed by the Bidder's Representative, specifying the powers, functions
and authorities being delegated or revoked. The Bidder's Representative and such competent
persons shall be fluent in English.

1.5 Sub-Bidders

1.5.1 The Bidder shall not subcontract whole of the Works.


The Bidder may sub-contract any part of the Works. The Bidder shall give written
Notification to the KTL about the Sub-Bidders engaged for the Works and takeprior
approval from the KTL.
1.5.2 The Bidder shall be solely responsible for the payments to be made to the Sub-Bidders in
accordance with their respective Subcontracts and ensure proper and uninterrupted
execution of the Works. The KTL shall, under no circumstances be liable to any Sub-
Bidder and the Bidder shall indemnify and keep indemnified the KTL against all liabilities,
costs, claims and demands of whatsoever nature by any Sub-Bidders.

1.6 Quality Assurance

The Bidder shall institute a quality assurance system to demonstrate compliance with the
requirements of the Contract.
Details of all procedures and compliance documents shall be submitted to the KTL's
Representative for information before each design and execution stage is commenced. When
any document is issued to the KTL's Representative, it shall be accompanied by the signed
quality statements for such document. The KTL's Representative shall be entitled to audit any
aspect of the system and require corrective action to be taken.
Compliance with the quality assurance system shall not relieve the Bidder of any of its duties,
obligations or responsibilities under the Contract.

1.7 Protection of Environment

Bidder shall in performance of the Works take all necessary steps and comply with all

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 193
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

applicable Laws, relevant permits, consents and approvals to protect the environment (both
on and off the Site) and to limit damage and nuisance to people and property resulting from
pollution, noise and other results of his operations.
Bidder shall ensure that emissions, surface discharges and effluent from Bidder's activities
shall not exceed the values indicated in the Technical Specifications and KTL's Requirements,
and in any event shall not exceed the values prescribed by applicable Laws and relevant
permits, consents and approvals.

Bidder shall indemnify and hold KTL harmless against and from all damages, losses and
expenses (including legal fees and expenses) resulting from Bidder's failure to comply with its
obligations under this Clause 1.7

1.8 Delivery of Plant and Materials

Unless otherwise stated in the Contract:


1.1 Bidder shall give the KTL not less than 7 days’ notice of the date on which major Plant and
Material and/or any other major item of equipment will be delivered to the Site;

Bidder shall be responsible for packing, loading, transporting, receiving, unloading, storing
and protecting all Plant, Materials and other things required for the Works; and

Bidder shall indemnify and hold the KTL indemnified and harmless against and from all
damages, losses and expenses (including legal fees and expenses) resulting from the
transport of, Materials and other things required for execution of the Works.

Bidder shall store the material and save guard the same at the KTL pre-defined location.
The Bidder will be the sole responsible of all it man, material and machinery till the time of
Handing Over of the Project.

1.9 Progress Reports

Daily, Weekly and Monthly reports shall be prepared by the Bidder and submitted to the
KTL's Representative on the agreed date of week and month. Activity chart to be included for
all the progress reports. The first progress report shall cover the period up to the end of the
calendar month immediately following the month in which the Works commenced and the
obligation to submit monthly progress reports shall continue until the Bidder has fulfilled all
its obligations under the Contract.

Each monthly progress report shall include:


1.6. Detailed descriptions of progress, including each stage of design, procurement,
manufacture, construction, erection, testing and Commissioning

1.7. Charts showing the status of Bidder's Documents, manufacture, supply and construction;
and for the manufacture of each main item of Plant and Materials, the name of
manufacturer, location, percentage progress, and the actual or expected dates of
commencement of manufacture, Bidder's inspections, tests and delivery at the Site;

1.10 Bidder's Equipment

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 194
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Bidder shall provide all Bidders Equipment necessary to complete the Works. Bidder shall
be responsible for and bear risk of loss and damage to all Bidder's Equipment. All Bidder's
Equipment shall, when brought to the Site, be deemed to be exclusively intended for the
execution of the Works and the Bidder shall be entitled to remove such Bidder’s Equipment
as and when the intended use of such Bidder’s Equipment is completed.

1.11 Safety Precautions

The Bidder shall throughout the execution of the Works:


b. Safety training should be imparted to every workman by Bidder.
c. Take full responsibility for the adequacy, stability, safety and security of the Works,
Plant and Materials, Bidder's Equipment, operations on the Site and methods of
manufacture, construction and transportation;
d. Have full regard for the safety of all persons on the Site (including persons to whom
access to the Site has been allowed by the Bidder), comply with all relevant safety
regulations, including provision of safety gear. Insofar as the Bidder is in occupation or
otherwise is using areas of the Site, the Bidder shall keep the Site and the Works (so
far as the Site and Works are not completed and occupied by the KTL) in an orderly
state appropriate for the avoidance of injury or accident to all persons on the Site and
shall keep the KTL indemnified against all costs, charges, losses and damages that may
be suffered by the KTL in any manner whatsoever as a result of any injury or accident
to any person on the Site in connection with the execution of the Works for reasons
solely attributable to the Bidder;
e. Provide and maintain all lights, guards, fences and warning signs and watchmen when
and where necessary for the protection of the Works and for the safety and
convenience of the public and all persons on the Site;
f. Where any part of the Works would otherwise be carried out in darkness, ensure that
all parts of the Site where such part of the Works is being carried out are so lighted as
to ensure the safety of all persons on the Site and of such part of the Works;
g. The Bidder shall ensure that its employees and the employees of the Sub-Bidders wear
identification badges (cards), uniforms, helmets, gum boots and other safety or
protection wear as directed by the KTL's Representative, and to be provided by the
Bidder.
h. The Bidder shall comply with all applicable safety regulations in his design, access
arrangements and operations on Site. The Bidder shall, from the commencement of
work on Site until taking-over by the KTL provide lighting, guarding and watching of
the Works.
i. The execution of the Works shall not be carried out in weather conditions that may
adversely affect the execution of the Works or damage the Works (or any part
thereof) unless proper protection is provided in consultation with the KTL's
Representative.
j. The Bidder shall submit a detailed and comprehensive contract specific Site safety
plan and system safety assurance plan.
k. Necessary safety permits to be taken from KTL.

1.12 Electricity, Water and Gas

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 195
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Bidder shall be responsible for the provision of all power, water, utilities and other
services it may require for execution of the Works. All necessary arrangement for
interconnection of electricity during Testing and Commissioning needs to be done by Bidder.

1.13 Clearance of Site

During the execution of the Works, the Bidder shall keep the Site free from all unnecessary
obstruction, and shall store or dispose of any Bidder's Equipment or surplus materials. The
Bidder shall clear away and remove from the Site any wreckage, rubbish or temporary works
no longer required.

Upon the issue of a Taking-over Certificate, the Bidder shall clear away and remove, from that
part of the Site and Works to which such Taking-over Certificate refers, all Bidder's
Equipment, surplus material, wreckage, rubbish and temporary works. The Bidder shall leave
such part of the Site and the works in a clean and safe condition to the satisfaction of the
KTL's Representative. Notwithstanding anything contained in this Clause, the Bidder shall be
entitled to retain on Site, until the issuance of the Taking-over Certificate, such Bidder's
Equipment, Materials and temporary works as may be required by it for the purpose of
fulfilling its outstanding obligations under the Contract.

1.14 Security of the Site

The Bidder shall be responsible for Site safety and for keeping unauthorized persons off the
Site. Authorized persons shall be limited to the employees of the Bidder, authorized
employees of its Sub-Bidders, governmental authorities who come for site visit or inspection
and KTL's personnel necessary for the execution of the Works.

1.15 Bidder's Operations on Site

The Bidder shall confine his operations to the Site, and to any additional areas which may be
provided and agreed by the KTL as working areas. The Bidder shall take all necessary
precautions to keep its personnel and equipment within the Site and such additional areas,
and to keep and prohibit them from encroaching on adjacent land.

2 DESIGN & DRAWINGS


2.1 General Obligations

The Bidder shall carry out and be responsible for the design of the Works in accordance with
the Technical Specifications, the KTL's Requirements, the terms and conditions of this Contract
and applicable Laws.

2.2 Bidder's Documents

The Bidder shall prepare Bidder's Documents in sufficient detail to satisfy all requirements
under applicable Laws, regulatory approvals to provide suppliers and construction personnel
sufficient instructions to execute the Works in accordance with this Contract and to describe
the operation of the completed Works.
Unless otherwise stated in the KTL's Requirements, Bidder's Documents shall be written in

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 196
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

English.
Each of the Bidder's Documents shall, when considered ready for use, be submitted to the
KTL's Representative for Approval prior to commencement of procurement, installation,
construction & Testing and commissioning. Based on the approved document only, work
should be proceed.

For each part of the Works, and except to the extent that the prior consent of the KTL's
Representative shall have been obtained:
1 Construction shall be in accordance with the Bidder's Documents

2 If the Bidder wishes to modify any Bidder's Document which has previously been
submitted for such approval, the Bidder shall immediately notify the KTL's Representative,
and shall subsequently submit revised documents to the KTL's Representative for
approval. Based on the approved document only, work should be proceeded.

Notwithstanding any review of the Bidder's Document by the KTL's Representative or any
failure to review the Bidder's Documents, the Bidder shall be fully responsible for the
adequacy of the Bidder's Documents for the execution of the Works to achieve the Date for
Commissioning, any failure of the Bidder to comply with the Contract, or otherwise, for any
ambiguity, inconsistency, deficiency, lack of fitness for purpose, errors and/ or omissions in the
Bidder's Documents.

2.3 Technical Standard and Regulations

The design, the Bidder's Documents, the execution and completion of the Work's shall comply
with all applicable technical standards and specifications, Laws applicable to the product being
produced from the Works, building, construction and environmental Laws and the standards
specified in the Technical Specifications, applicable to the Works or defined by the applicable
Laws and relevant permits, consents and approvals. Reference in the Contract to such
specifications and other matters shall be understood to be references to the edition applicable
on the Base Date, unless stated otherwise.

If substantially changed or new applicable specifications, technical standards or regulations


come into force after the Base Date, the Bidder shall give notice to the KTL's Representative
and (if appropriate) submit proposals for compliance to the KTL's Representative. In the event
that the KTL's Representative determines that:

2.1. Compliance is required; and

2.2. Such proposal constitute a Variation,

The KTL's Representative shall initiate a Variation in accordance with Clause

2.4 As-Built Drawings

The Bidder shall prepare, and keep up-to-date, a complete set of "as built" records of the
execution of the Works, showing the exact "as built" locations, sizes and details of the work as
executed, with cross reference to relevant specifications and data sheets. These records shall
be kept on the Site and shall be used exclusively for the purposes of this Clause.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 197
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

As a condition precedent to and in addition to other requirements mentioned under this


Contract, before the issuance of Taking over Certificate, the Bidder shall submit to the KTL's
Representative "as built drawings", and any further Bidder's Documents specified in the
Contract. The Works shall not be considered to be completed until such documents have been
submitted to the KTL's Representative.

3 MATERIALS AND WORKMANSHIP


3.1 Manner of Execution

Bidder shall carry out the manufacture and supply of Plant, the production and manufacture of
Materials, and all other execution of the Works:
in the manner specified in the Contract (including Technical Specifications and KTL's
Requirements);

in a proper workmanlike and careful manner;

with properly equipped facilities and non-hazardous Materials, except as otherwise


specified in the Contract;

in accordance with all applicable Laws, permits, consents, approvals, codes and standards;

diligently and efficiently so as to achieve Commissioning by the Date for Commissioning;


and

So as to achieve the Initial Guaranteed PR and Annual Guaranteed PR.

3.2 Delivery

The Bidder shall be responsible for procurement, transport, receiving, Custom Clearance
unloading and safe keeping of the Plant, and Materials in scope of Bidder and required for the
completion of the Works.

3.3 Inspection

The KTL's Personnel shall at all reasonable times be entitled, during manufacture, construction
and fabrication (whether at the Site or at any other location where the Works are being
carried out), be entitled to inspect, examine, measure and test the major Materials and
workmanship, and to check the progress of manufacture, of the Plant and Materials to be
supplied under the Contract

The Bidder shall give the KTL's Personnel full opportunity to carry out such activities, including
providing access, facilities, permissions and safety equipment. No such activity shall relieve
Bidder of any obligation or responsibility.
In respect of the Works which the KTL's Personnel are entitled to examine, inspect, measure
and/or test, the Bidder shall give due notice to the KTL's Representative whenever such work
is ready, before packing, covering up or putting out of view. The KTL's Representative shall
then either carry out the inspection, examination, measurement or testing without
unreasonable delay, or promptly give notice to the Bidder that the KTL's Representative does

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 198
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

not require to do so. Third party inspection can be done by KTL.

3.4 Remedy

If as a result of inspection, examination or testing, any Plant, Materials, design or workmanship


is found to be defective or otherwise not in accordance with the Contract, the KTL's
Representative shall have a right to notify the Bidder to immediately repair or remedy such
defective Plant, Materials, design or workmanship which is not as per this Contract by giving
notice to the Bidder, with reasons. The Bidder shall then promptly, at its cost, make good the
Defect and ensure that the repaired or remedied item complies with the Contract.

3.5 Remedy Work

Notwithstanding any previous test or certification, the KTL may instruct and give notice to the
Bidder to:
a. repair or remedy any defective Plant or Materials which are not in accordance with the
Contract;

b. remedy and re-execute any Works which is not in accordance with the Contract; and

c. execute any work which is urgently required for the safety of the Works, whether because
of an accident, unforeseeable event or otherwise.

If the Bidder fails to within the time specified in the notice, which shall be not less than 45
days (i) writes to the KTL with reasons that the KTL's instructions are not required to be
performed; or (ii) proceed promptly with the repair or replacement of the notified item of the
Works, the KTL may, by contract with third Persons or otherwise, repair or replace such part of
the Works and the Bidder shall be liable to reimburse the KTL upon demand for all costs
incurred by the KTL relating to such repair or replacement by a third party. Such repair or
replacement carried out by a third party shall not in any manner affect any of the Bidder’s
obligations, representations or warranties under this

Contract subject to such repair or replacement being carried out by third party as per this
Contract and Good Industrial Practice

3.6 Ownership of Plant & Materials

Title to each item of Plant and Materials and all other things to be supplied by the Bidder
under the Contract and incorporated into the Facility shall pass to the KTL, free from liens and
other encumbrances upon:

3.1. The date of delivery of such item of Plant, Materials or any other item forming a part of
the Works at the Site; and

3.2. The date of receipt of payment by the Bidder for such item of Plant, Materials or any other
item forming part of the Works.

Where, prior to delivery to the Site, the title to Plant, Materials or any other item forming a
part of the Works passes to the KTL, the Bidder shall ensure that such Plant, Materials or other
items are set aside and marked as the KTL's property in a manner reasonably required by the

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 199
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

KTL. Notwithstanding the transfer of ownership of any item of the Plant, or Material, the
Bidder shall to the extent that it has not completely paid for any plant or material the
ownership of which has been transferred to the KTL have a lien on unpaid portion of such item
of Plant and Material.

Despite the transfer of ownership of any item of the Plant or Materials, the responsibility for
the care and custody together with the risk of loss or damage to such Plant or Materials shall
remain with the Bidder until the KTL has issued (or is deemed to have issued) the Taking-over
Certificate.

4 WORK PROGRAM
4.1 Works Program

The Bidder shall submit a detailed Works Program to the KTL's Representative within 10 days
after receiving the Award for approval. Each Works Program shall include:

The order in which the Bidder intends to carry out the Works, including the anticipated
timing of each stage of design, preparation and delivery of Bidder's Documents,
procurement, manufacture, inspection delivery to Site of the Plant and Materials,
construction, erection, testing, Commissioning and trial operation of the Facility;

The sequence and timing of inspections and tests specified in the Contract; and

A supporting report which includes a general description of the methods which the Bidder
intends to adopt, and of the major stages, in the execution of the Works.

If, at any time, the KTL's Representative gives notice to the Bidder that the progress of the
Works fail to comply with the Works Program submitted by the Bidder under this Clause, the
Bidder shall submit a revised Works Program to the KTL's Representative in accordance with
this Clause for approval.

4.2 Rate of Progress

For reasons solely attributable to the Bidder, if, at any time, the Bidder's actual progress falls
behind the Works Program or it becomes apparent that it will so fall behind, the Bidder shall
submit to the KTL's Representative a revised Works Program taking into account the prevailing
circumstances for approval. The Bidder shall, at the same time, notify the KTL's Representative
of the steps being taken to expedite progress, so as to achieve Commissioning on or prior to
the Date for Commissioning. It is clarified for avoidance of doubt that such submission of
revised Works Program or notification by Bidder of steps taken to expedite progress shall not
entitle the Bidder to any extension of time for the achieving Commissioning on or prior to the
Date for Commissioning.

5 PERFORMANCE TESTS
5.1 Tests on Commissioning

The Bidder shall give the KTL at least 7 days advanced final written notice, of the date on which

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 200
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

it intends to carry out the Tests on Commissioning.


The Bidder shall, at its sole cost and expense, carry out the Tests on Commissioning in
accordance to the Technical Specifications. The Tests on Commissioning shall be carried out to
ascertain (among other things) whether the Facility conforms to the Technical Specifications
and all applicable Laws. The KTL shall be entitled at all times to witness and monitor the
conduct of the Tests on Commissioning.

Immediately following any Test on Commissioning, Bidder shall forward to the KTL duly
certified copies of the results of such Test on Commissioning. Within two (2) days of receipt of
the test reports, the KTL shall, after evaluating the test reports, decide whether the Facility
complies with the required parameters or not.

5.2 Tests on Completion

The bidder should carry out all completion activities in presence of the owner or the owner’s
representative. The test shall be deemed accepted and closed only after approval of the owner
and/or owner’s representative. In case during the final acceptance test any defect or failure is
noticed the bidder at its own expense rectify the same and ensure its smooth running
thereafter.

5.3 Initial Guaranteed PR and Annual Guaranteed PR

5.3.1 Initial Guaranteed PR

The Bidder Guarantees the Facility shall achieve Initial Guaranteed PR as set forth PR Concept
Note.

5.3.2 Annual Guaranteed PR

In addition to Initial Guaranteed PR, the Bidder warrants that at the end of year one from the
Date of Actual Commissioning or commercial operation date whichever is later, the Facility
shall meet the Annual Guaranteed PR as set forth in Technical Document. The Bidder at all
times will have right to continually collect and analyze applicable data required to test the
performance of the works and its meeting of Initial Guaranteed PR and Annual Guaranteed PR.
Further the Bidder will have the right to undertake necessary action to rectify repair the Works
in order to ensure that the Facility meets the Initial Guaranteed PR and Annual Guaranteed PR.
The Bidder will set out to the KTL the intended work plan and dates. The Bidder shall ensure
such rectification will not lead to a reduction in Facilities output.

6 DEFECTS LIABILITY
6.1 Completion of Outstanding work and Remedying Defects

The Bidder shall, within a reasonable time as instructed by the KTL, complete any work which is
outstanding as at the Time of Completion.

If notified to Bidder in writing during the Defects Liability Period, Bidder shall at its cost and for
reasons solely attributable to the Bidder, in a manner which causes as little disruption to the
operation of the Works as reasonably possible, promptly repair, replace or otherwise make good

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 201
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

any Defects in the Works.

The Bidder's obligation in relation to Initial Guaranteed PR and Annual Guaranteed PR shall be
continuing warranties applying throughout the duration of their respective periods.

6.2 Cost of remedying Defects

During the Defects Liability Period all remedy KTL work for the Defect shall be executed at the risk
and cost of Bidder, if and to the extent that the Defect is attributable to:
3.6. the design of the Works; or

3.7. Plant, Materials or workmanship not being in accordance with the Contract;

If and to the extent that such remedy KTL work is attributable to any other cause, the KTL shall give
notice to Bidder accordingly and Clause 3 shall apply to all rectification and remedy KTL work to be
performed by the Bidder in accordance with the KTL's notice.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 202
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SECTION - V
SCHEDULES

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 203
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE A: FORMAT FOR BANK GUARANTEE TOWARDS EMD

From:

Bank’s Name & address

To

Kallam Textiles Limited (KTL),


NH-16, Chowdavaram, Guntur, Andhra Pradesh

Sirs,

Guarantee No. ________________

Amount of Guarantee ___________

Guarantee cover from __________ to ____________

1. In consideration of a bid document issued by Kallam Textiles Limited , having its registered office at
___________________, (hereinafter referred to as “KTL” for brevity) for undertaking ________
works, our constituents submitted its proposal for undertaking the Works. As per the said
Document, M/s. _________________ having its registered office at ____________________
(hereinafter referred to as “Constituents”) agreed to submit a Bank Guarantee towards EMD.

2. Our said Constituent has undertaken to furnish to KTL an unconditional and irrevocable Bank
Guarantee towards EMD. As per the said understanding accepted by our Constituents, we, the
______ Bank, _________ Branch, _________ (hereinafter for sake of brevity referred to as “Bank”)
as also our successors and assignees, do hereby bind ourselves unconditionally and irrevocably and
Guarantee the payment of all sums of money that may be liable to be paid to KTL to the extent of
Rs ________/- (Rupees _________ only) against being the value of this Bank Guarantee payable by
the said constituent of the Bank, towards EMD.

3. We, ________ Bank, __________ Branch, _________ hereby undertake to indemnify KTL to the
extent of Rs. _______/- (Rupees __________ only) against any loss or damage caused to KTL at any
time during the period of this Guarantee due to the failure, default, neglect or refusal of our
Constituent fails to pay KTL up to the value of Rs. ________/- (Rupees _________ only)

4. We, the ________ Bank, _______ Branch, further confirm and agree that we shall on the first
demand from KTL without any protest, hesitation or demur and unconditionally and without any
references to the said Constituent and notwithstanding and contestation by the Constituent of the
existence of any dispute whatsoever between KTL and the Constituents, shall pay forthwith to KTL

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 204
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

or to their successors and assignees any sum or sums not exceeding Rs. _______/- (Rupees
________ only).

5. We, ________ Bank, __________ Branch, _________ also agree that a communication from the
authorized signatory of Kallam Textiles Limited (KTL), Chowadavaram,Guntur-522019, Andhra
Pradesh, India to the effect that there has been a failure, default on the part of the Constituent,
shall be final, conclusive and binding on us.

6. We further declare that this Bank Guarantee is an irrevocable, unconditional and continuing
Guarantee and shall not be affected by (a) any indulgence shown by KTL to the Constituent (b) any
change in the constitution of KTL (c) any changes, additions, deletions or modifications in the terms
and conditions of the Agreement between KTL and the Constituent.

7. This Bank Guarantee shall not be revoked without KTL’s express written consent and shall not be
affected by:

(i) extension of time; or


(ii) any other indulgence to the Constituent by KTL, which shall include but not be limited
to postponement from time to time of the exercise of any powers vested in KTL; or
(iii) any right which KTL may have against the Constituent and to exercise the same in any
manner at any time,
and the Bank shall not be released from its obligations under this Guarantee by the
exercise of any of KTL’s rights with reference to matters aforesaid or any of them or by
whatsoever reason which under law would, but for this provision, have the effect of
relieving the Bank from its obligations under this Guarantee.

8. This Guarantee shall not be affected by any change in the constitution of the Bank or the
Constituent or for any other reason whatsoever.

9. This Guarantee shall remain in full force and effective all the time until all the dues of the
constituent to KTL have been fully paid and all KTL’s claims against the constituent are satisfied as
stipulated by KTL under the terms and conditions of the Bid, to the extent of Rs. _______/- (Rupees
___________ only) as specified herein above.

10. Notwithstanding anything contained in the foregoing clauses, the Bank’s liability under this
Guarantee shall be restricted to Rs _______/- (Rupees __________ only). This irrevocable and
continuing Guarantee shall remain in force for a period from dt. _______ to ______.The Bank shall
be discharged from all liabilities hereunder unless a claim under this Guarantee is lodged and / or
made by KTL within three months from the date of expiry i.e., on or before dt ______.

11. That the expressions the Constituents, the Bank, and KTL used herein shall, unless repugnant to the
subject or context include their respective successors and assignees.

12.1 Any demand, notice or other communication given in connection with or required by this
Guarantee shall be made in writing (entirely in the English language) shall be delivered to, or sent
by pre-paid registered post, or facsimile transmission to:

#address
#contact number

For the attention of:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 205
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

The Guarantor

(Name & Address of the Bank) at: __________________________

Attention of the: Branch Manager

or such other address as may be notified in writing from time to time.

12.2 Any such demand, notice or communication shall be deemed to have been duly served:

(i) if delivered by hand, when left at the property address for service;

(ii) if given or made by pre-paid registered post or facsimile transmission, when received,

provided in each case that if the time of such deemed service is either after 5.00 p.m. on a Business
Day (being a day other than a Sunday or a public holiday on which banks are open for domestic
business in the city of KTL or other than on a Business Day service shall be deemed to occur instead
at 9.00 a.m. on the next following Business Day.

13. We acknowledge and agree that the benefits of this Guarantee may not be transferred or
assigned by us. The benefits of this Guarantee may however be assigned in full by KTL to any person to
whom all the benefits of the Agreement are transferred, and to the lenders or to any agent,
representative or trustee acting on their behalf, their assignees and successors in title which will
include the right to make second or subsequent assignments. We undertake following receipt of a
notice of any such assignment to make any payments made hereunder in accordance with the
directions of such assignee.

14. This Guarantee shall be governed by and construed in accordance with the laws of the Republic
of India and the parties to this Guarantee hereby submit to the jurisdiction of the Courts of Andhra
Pradesh for the purposes of settling any disputes or differences which may arise out of or in connection
with this Guarantee, and for the purposes of enforcement under this Guarantee.

Date:

Place: Signed for and on behalf of the Bank

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 206
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE B: PRICE BID

(To be submitted on Bidder’s Letter Head)

Price in
Price
S.No. Particulars Rs. (In
(Rs.)
Words)

1 Design, Engineering, testing at manufacturers works, supply,


packing and forwarding, transportation, unloading, storage at
site, erection/installation, testing, commissioning of 2.6
MWp/2.0 MW grid connected Solar PV power project with
Captive mechanism at Chowdavaram village, Guntur District
in Andhra Pradesh on Turnkey EPC Basis

2 Operation and Maintenance (O & M) of the solar power project


from the completion of project to the end of 5 years including
arrangement of spares, consumables, tools, tackles, Testing
equipment & instruments, manpower, insurances,
fees/charges, charges payable to all government agencies,
liaison with all government agencies, all administrative work,
maintaining records and submissions to all Concerned
authorities.

Notes:

a. Any item of work not mentioned in the above particulars but written elsewhere in the scope
of work or in Technical Specification or essentially required for completion of works, proper
operation and maintenance of Solar farm, safety of equipment and operating personnel
shall be deemed to have been included in the above particulars.

b. The prices should be written in both figures and words.

c. Price quoted shall be inclusive of all taxes. However, breakup of tax components,
considered by bidders, shall be clearly provided in the bids.

d. Breakup of the following components shall be provided by bidders separately along with the
price bid for evaluation purpose:

e. Break up of all taxes/duties components, considered in the bid

f. Breakup of all fees/charges towards application, approvals, clearances, security deposit etc.

g. Break up for the supply and construction components of the project may be provided by the
bidders.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 207
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

h. Breakup of Insurance components.

The prices mentioned at this page shall be taken into consideration for evaluation of bids.
Any variation observed elsewhere in the bids shall be ignored while evaluation the bids.

Bidder should provide name & address of the proposed site in the priced Bid as well as
technical bid. In case of discrepancy in the site address given in the price bid & technical bid,
the details provided in technical bid shall prevail

Conditional bids are liable to rejection.

Date: ………………………..

Place: ……………………….

(Signature of the Authorized Representative of Bidder)

Name …………………………

Designation ……………………

Seal of Company……………

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 208
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE C: BREAK UP OF PRICE BID


(To be submitted on Bidder’s Letter Head)

SCHEDULE C1: BREAKUP FOR SUPPLY OF EQUIPMENT, MATERIAL, AND OTHERS CIVIL MATERIAL
REQUIRED FOR PROJECT

Price in Rs. Total Price


Sr. No. Particulars Price (Rs.) Tax
( in words) (Rs.)

Total Price for supply of PV


1 modules with 2% spare modules of
the total modules

2 Total Price for supply of Inverters

Total Price for supply of Module


mounting structure including
3
walkway, life line, Module cleaning
system, safety guard rail
Total Price for supply of DC Cable,
4 string monitoring boxes if any,
Earthing.
Total Price for supply of WMS &
5
Data monitoring system
Total Price for all other material
BOS (like remaining civil material,
6
earthing and all other materials
required for the Solar Project
Total Price of supply of equipment,
material, and others civil material

SCHEDULE C2: BREAKUP FOR CONSTRUCTION, ERECTION, TESTING, AND COMMISSIONING, CIVIL
WORK, TRANSPORTATION, UNLOADING, STORAGE AT SITE AND OTHER SERVICES OF THE SOLAR
PROJECT

Price in Rs. Total


Sr. No. Particulars Price (Rs.) Tax
( in words) Price

Total Price for Design, Engineering,


Erection ,Construction, Testing,
1 Commissioning, Civil
works, transportation, unloading, storage
at site and other Services of 2.6 MWp

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 209
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Solar project

SCHEDULE C3: BREAKUP FOR O & M COSTS

Price in Rs. Total


Sr. No. Particulars Price (Rs.) Tax
( in words) Price

Price for Operation & Maintenance for


1
first year

Price for Operation & Maintenance for


2
Second year

Price for Operation & Maintenance for


3
Third year

Price for Operation & Maintenance for


4
forth year

Price for Operation & Maintenance for


5
fifth year

Total Price for Operation and Maintenance

Notes:

a. Any item of work not mentioned in the above particulars but written elsewhere in the scope
of work or in Technical Specification or essentially required for completion of works, proper
operation and maintenance of Solar farm, safety of equipment and operating personnel
shall be deemed to have been included in the above particulars.

b. The prices should be written in both figures and words.

c. Break up of all taxes/duties components, considered in the bid

d. Breakup of all fees/charges towards application, approvals, clearances, security deposit etc.

e. Break up for the supply and construction components of the project may be provided by the
bidders.

f. Breakup of Insurance components.

The prices mentioned at this page shall be taken into consideration for evaluation of bids.
Any variation observed elsewhere in the bids shall be ignored while evaluation the bids.
Bidder should provide name & address of the proposed site in the priced Bid as well as technical
bid. In case of discrepancy in the site address given in the price bid & technical bid, the details
provided in technical bid shall prevail conditional bids are liable to rejection.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 210
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Date: ………………………..

Place: ……………………….

(Signature of the Authorized Representative of Bidder)

Name …………………………

Designation ……………………

Seal of Company……………

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 211
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE D: DIRECT AND INDIRECT TAXES


Direct Tax: Tax deduction at source

Notwithstanding anything contained elsewhere in the Contract, KTL shall have the
right to withhold taxes on income, excess profits, royalty and other taxes from
payments due to Contractor under this Contract to the extent that such withholding
may be required by the government of India or any relevant authority thereof and
payment by KTL to the respective governmental office of the amount of money so
withheld will relieve KTL from any further obligation to Contractor with respect to
the amount so withheld.
KTL shall, at the time of its payments due to the Contractor, withhold the necessary
taxes at such rate as is required by any Government Authority, unless and to the
extent that the Contractor shall produce to the Purchaser any certificate issued by a
Government Authority (having authority to issue such certificate) entitling the
Contractor to receive the payments under the Contract for a prescribed period
without deduction of any tax or deduction at a lower rate
KTL shall provide the necessary withholding tax certificates to the Contractor within
the time stipulated by the relevant law to enable the Contractor to file the same with
the Government Authority as a proof of payment of such taxes
All taxes levied on Contractor’s corporate income or profits shall be for the account
of Contractor and shall not be reimbursed by KTL. Contractor shall also be
responsible for payment of income taxes of its personnel levied in India
Applicable Indirect Taxes

The applicable indirect taxes on execution of solar power contract are summarized
below. The Bidders are requested to check and confirm the applicability of indirect
taxes on execution of above contract. However, the Bidders are requested to
recheck and confirm the same and in any circumstances, KTL will not be liable to
compensate, increase, pay, incur or reimburse on account of non-eligibility of the
above benefits to Bidder.
Customs Duty

Goods imported into India are subject to applicable customs duty. Accordingly, the
Bidders are advised to check the applicable rates of customs duty on respective
goods proposed to be imported in relation to the execution of the above project.
An overview of the applicable customs duty exemption / benefits available to Solar
Power Plant are as follows:
Import of solar panel (photovoltaic cells/modules classified under CTH 8541 or latest)
is currently not subject to customs duty.
Vide Notification No 01/2011 dated 06/01/2011 the Central Government has
prescribed that goods imported for setting up the power plant would be exempt
from basic customs duty as in excess of 5% ad valroem or as applicable at the time of
submission of bid and from the additional duty of customs leviable under section 3

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 212
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

of Customs Tariff Act subject to fulfillment of prescribed conditions stipulated in the


above Notification.
GST:

The Contractors shall be responsible to pay all statutory levies imposed by the State
and Central Government. However the rates quoted in the tender shall allow for All
but including GST. No reimbursement whatsoever shall be made to the contractors
on account of any taxes or duties or increase in the taxes/duties by act of any
legislation except GST which should be mentioned separately as per applicable rate
of GST at the time of bill. The rates quoted are inclusive of all taxes, transportation
charges, loading and unloading at all points, transit insurance, other incidentals
charges and GST.
Deduction at source of Income Tax and any other statutory deductions shall be made
by KTL as per the provisions prevailing from time to time from the Running Account
or Final Bills and remitted to the concerned Taxation Authorities/State Government
on behalf of the contractor.
Variation

In the event of introduction of new legislation or any change or amendment or


enforcement of any Act or Law, rules or regulations, policies of the Government or
Public Body which becomes applicable or effective after the date of submission of
Price Bid or revised price bid, if any, and which results in increase to the Price Bid
through increased liability of taxes (other than personnel taxes), the Bidder shall be
indemnified for any such increased cost by KTL subject to production of
documentary proof to, the satisfaction of KTL, to the extent which is directly
attributable to such introduction of new legislation or change or amendment as
mentioned above.
Similarly, if introduction of a new legislation or any change or amendment or
enforcement of any Act or Law, rules or regulation, policies of the Government or
Public Body which becomes applicable or effective after the date of submission of
Price Bid or revised price bid, if any, and which results in reduction to the Price Bid
through reduced liability of taxes (other than personnel taxes), the Bidder shall pass
on such benefits of such reduced taxes, duties or fees to KTL to the extent, which is
directly attributable to such introduction of new legislation or change or
amendment as mentioned above In the event of any change in the current status of
the project after the date of submission of Price Bid and which results in increase to
the Price Bid through reduction of any considered available benefit, drawback or
concession directly resulting in increased liability of taxes (other than personnel
taxes), the Bidder shall be indemnified for any such increased cost by KTL subject to
production of documentary proof to, the satisfaction of KTL, to the extent which is
directly attributable to such change in status.
Similarly, in the event of any change in the current status of the project after the
date of submission of Price Bid and which results in reduction to the Price Bid
through addition/ extension of any available benefit, drawback or concession
directly resulting in reduction of liability of taxes (other than personnel taxes), the
Bidder shall pass on such benefits to KTL to the extent which is directly attributable
to such change in status.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 213
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

In case of introduction of new legislation or change or amendment in any act or law


after the Schedule/extended Completion Date, but which comes into force or
becomes effective retrospectively from a date on or before the Scheduled/extended
Completion Date and which results in any increase / decrease in the duties, taxes
and fees under the Contract, then such increase/decrease, subject to the stipulated
conditions shall be to KTL account.
All duties, taxes, fees (except where otherwise expressly provided in the contract) as
may be levied / imposed in consequence of execution of the Works or in relation
thereto or in connection therewith as per the Acts, Laws, Rules, Regulations in force
on the date of submission of Price Bid or revised price bid, if any, for this Contract
shall be to Bidder’s account and should be included in the price bid.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 214
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE E: QUALIFICATION CHECKLIST OF THE BIDDER


(To be submitted on Lead Member of Consortiums / Bidder’s Letter Head)

Name and Address of the Bidder:


Phone:
Email:
Fax:
Sr. No. Requirement Enclosed / Comments

1 Company Registration Documents (Certificate of


Incorporation, Memorandum of Association and
Article of Association, etc.) with reference to clause
no. 4.1 of ITB

In case of JV/ Consortium, Both Member should


provide Company Registration Documents.

2 Details of Earnest Money Deposit (EMD)

3 Details of Bid Processing Fee

4 Bidder is not Black Listed by any Public and Private


Companies/ group/ bodies/ agencies/ Government
offices

5 Bidder should have provide copy of work order


along with Work Completion Certificate issued from
client along with completion date and executed
amount of work with reference to clause no. 4.2 of
ITB

6 Bidder should provide audited annual report of FY


2014-15, FY 2015-16, FY 2016-17, FY 2017-18 and
FY 2018-19 with reference to clause no. 4.3 of ITB

In case of JV / Consortium, Both Member should


provide audited annual report of FY 2014-15, FY
2015-16, FY 2016-17, FY 2017-18 and FY 2018-19

7 Bidder’s should provide Certificate showing net


worth of last Financial Year (Year 2018-19) from
Chartered Accountants with reference to clause no.
4.3 of ITB

In case of JV / Consortium, Both Member should


provide Certificate showing net worth of last
Financial Year (Year 2018-19) from Chartered

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 215
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

Accountants

8 Client Certified track record of the units generated


along with Solar Radiation pattern for last
12months of the proposed SPV panels and System.

Date:………………………..

Place:……………………….
(Signature of the Authorized Representative of Bidder)
Name:
Designation:
Seal of Company:

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 216
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE F: LIST OF SIMILAR WORKS HANDLED


(To be submitted inLead Member of Consortiums / Bidder’s Letterhead)

Contact
Capacity
person
of Actual
Clients Name name & Date of Amount Date of
S.No. Rooftop completion
&Address number Commencement of Work Commissioning
Plant Time
with
(AC/DC)
designation

10

Note: Use additional sheets of the same format, if required.

Note :

The Bidder shall furnish a performance certificate in English issued by Competent Authority; clearly
mentioning that the Contractor has designed, engineered, supplied, installed, tested, commissioned
and operated and maintained the project for a minimum period of one year.
The bidder shall submit project completion certificate issued by respective client to KTL as per project
mentioned in above year wise table.
Date:………………………..

Place:………………………

(Signature of the Authorized Representative of Bidder)

Name …………………………

Designation ……………………

Seal of Company……………

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 217
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE G: FORMAT FOR SPARES AND CONSUMABLES / SPECIAL


TOOLS AND TACKLES
(To be submitted on Lead Member of Consortiums / Bidder’s Letter Head)

Comprehensive Operation and Maintenance (O & M) charges of the Solar Photovoltaic


Power Plant for a period of 5 year including arrangement of spares, consumables,
tools, tackles, testing equipment & instruments, manpower, insurances, fees/charges,
charges payable to all government agencies, liaisoning with all government agencies,
all administrative work, maintenance of records and submissions to all concerned
authorities. Give year wise prices, as follows

Note: The O & M charges should be quoted in INR i.e. rupees on “Firm Basis‟. The total of the
Break-up of should match with thetotal price.

Date: ………………………..

Place: ……………………….

(Signature of the Authorized Representative of Bidder)

Name …………………………

Designation ……………………

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 218
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE H: DEVIATION SCHEDULE


(To be submitted on Lead Member of Cosortium / Bidder’s Letter Head)

Bidder's Proposal Ref. No. and Date:

Bidder's name and address:

To,

C/ O Mr G.V.Krishnareddy,

Kallam Textiles Limited (KTL),

NH-16, Chowdavaram, Guntur, Andhra Pradesh Dear

Sir,

We declare that the following are the only deviations and variations from and exception to the
specifications contained in bid Document No. …………….dated………….. for setting up of 2.6
MWp Solar Photovoltaic projectinGuntur, Andhra Pradesh. The schedule has been filled,
except these deviations subject to the approval and acceptance by KTL. The entire work shall
be performance as per your specifications and documents. Further we agree that additional
conditions if any found elsewhere in our offer other than those stated below, other than
pertaining to any rebates offered, shall not be given effect to.

Statement of Variations and


Clause No. Reason Page
Deviations

Note: Use additional sheets of the same format, if required.

Date: ………………………..

Place: ……………………….

(Signature of the Authorized Representative of Bidder)

Name …………………………

Designation ……………………

Seal of Company……………

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 219
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE I: FORMAT FOR BANK GUARANTEE TOWARDS


PERFORMANCE GUARANTEE

(On non-judicial stamp paper of appropriate value)

(to be executed by scheduled bank)

From:

Bank’s Name & address

To

Kallam Textiles Limited (KTL),


NH-16, Chowdavaram, Guntur, Andhra Pradesh

Sirs,

Guarantee No. ________________

Amount of Guarantee ___________

Guarantee cover from __________ to ____________

1. In consideration of an Agreement dated ________ executed between KTL, having its registered
office at KTL, NH-16, Chowdavaram, Guntur, Andhra Pradesh(hereinafter referred to as “KTL” for
brevity) to our constituents M/s. _______________ [Please Insert Name of the Concessionaire]
having its registered office at [_____________________] (hereinafter referred to as “Constituent”)
wherein our said Constituent has agreed to comply certain obligations as per the terms and
conditions of the Agreement (herein after referred to as ‘Contractual Obligations’)

2. Our said Constituent has undertaken to furnish to KTL an unconditional and irrevocable Bank
Guarantee for the due performance of its obligations under the aforementioned Agreement and
against any future claims, damages/expenses incurred by KTL by virtue of action initiated by any
statutory or regulatory authorities for non-adherence or non observance of the obligations by the
Constituent as per the terms and conditions agreed in the Agreement.

3. As per the terms of the Agreement executed between KTL andour Constituents, we, the ______
Bank, _________ Branch, _________ (hereinafter for sake of brevity referred to as “Bank”) as also
our successors and assignees, do hereby bind ourselves unconditionally and irrevocably and
Guarantee the payment of all sums of money that may be liable to be paid to KTL to the extent of
Rs ________ (Rupees _________ only) against being the value of this Bank Guarantee payable by
the said constituent of the Bank, against any future claims, damages/expenses incurred by KTL by

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 220
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

virtue of non performance of the obligations under the Agreement by the Constituent or for an
action initiated by any statutory or regulatory authorities for non-adherence or non-observance of
the contractual obligations by the Constituent.

4. We, ________ Bank, __________ Branch, _________ hereby undertake to indemnify KTL to the
extent of Rs. __________ (Rupees __________ only) against any loss or damage caused to KTL at
any time during the period of this Guarantee due to the failure, default, neglect or refusal of our
Constituent to pay KTL up to the value of Rs. ____________ /- (Rupees _______ only)

5. We, the ________ Bank, _______ Branch, _________ further confirm and agree that we shall on
the first demand from KTL without any protest, hesitation or demur and unconditionally and
without any references to the said Constituent and notwithstanding and contestation by the
Constituent of the existence of any dispute whatsoever between KTL and the Constituents, shall
pay forthwith to KTL or to their successors and assignees any sum or sums not exceeding Rs.
__________ (Rupees ____________ only).

6. We, ________ Bank, __________ Branch, _________ also agree that a communication from any
authorized signatory of KTL, #location to the effect that there has been a failure, default on the
part of the Constituent, shall be final, conclusive and binding on us.

7. We further declare that this Bank Guarantee is an irrevocable, unconditional and continuing
Guarantee and shall not be affected by (a) any indulgence shown by KTL to the Constituent (b) any
change in the constitution of KTL (c) any changes, additions, deletions or modifications in the terms
and conditions of the Agreement between KTL and the Constituent.

8. This Bank Guarantee shall not be revoked without KTL’s express written consent and shall not be
affected by:

(i) extension of time; or


(ii) any other indulgence to the Constituent by KTL, which shall include but not be limited
to postponement from time to time of the exercise of any powers vested in KTL; or
(iii) any right which KTL may have against the Constituent and to exercise the same in any
manner at any time, and the Bank shall not be released from its obligations under this
Guarantee by the exercise of any of KTL’s rights with reference to matters aforesaid or
any of them or by whatsoever reason which under law would, but for this provision,
have the effect of relieving the Bank from its obligations under this Guarantee.

9. This Guarantee shall not be affected by any change in the constitution of the Bank or the
Constituent or for any other reason whatsoever.

10. This Guarantee shall remain in full force and effective all the time until all the dues of the
constituent to KTL have been fully paid and all KTL’s claims against the constituent are satisfied as
stipulated by KTL under the terms and conditions of the Agreement, to the extent of Rs. _______/-
(Rupees _________ only) as specified herein above.

11. Notwithstanding anything contained in the foregoing clauses, the Bank’s liability under this
Guarantee shall be restricted to Rs _________ (Rupees ________ only). This irrevocable and
continuing Guarantee shall remain in force for a period from dt. _______ to ______ (include three
months claim period also). The Bank shall be discharged from all liabilities hereunder unless a

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 221
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

claim under this Guarantee is lodged and / or made by KTL within three months from the date of
expiry i.e., on or before dt ______.

12. That the expressions the Constituents, the Bank, and KTL used herein shall, unless repugnant to the
subject or context include their respective successors and assignees.

13.1 Any demand, notice or other communication given in connection with or required by this
Guarantee shall be made in writing (entirely in the English language) and shall be delivered to, or
sent by pre-paid registered post, or facsimile transmission to:

The Guarantor

(Name & Address of the Bank) at: __________________________

Attention of the: Branch Manager

or such other address as may be notified in writing from time to time.

13.2 Any such demand, notice or communication shall be deemed to have been duly served:

(i) if delivered by hand, when left at the property address for service;

(ii) if given or made by pre-paid registered post or facsimile transmission, when received,

provided in each case that if the time of such deemed service is either after 5.00 p.m. on a
Business Day (being a day other than a Sunday or a public holiday on which banks are open
for domestic business in the city of KTL or other than on a Business Day service shall be
deemed to occur instead at 9.00 a.m. on the next following Business Day.

14. We acknowledge and agree that the benefits of this Guarantee may not be transferred or
assigned by us. The benefits of this Guarantee may however be assigned in full by KTL to any
person to whom all the benefits of the Agreement are transferred, and to the lenders or to any
agent, representative or trustee acting on their behalf, their assignees and successors in title
which will include the right to make second or subsequent assignments. We undertake
following receipt of a notice of any such assignment to make any payments made hereunder in
accordance with the directions of such assignee.

15. This Guarantee shall be governed by and construed in accordance with the laws of the Republic
of India and the parties to this Guarantee hereby submit to the jurisdiction of the Courts of
Andhra Pradesh for the purposes of settling any disputes or differences which may arise out of
or in connection with this Guarantee, and for the purposes of enforcement under this
Guarantee.

Date:

Place: Signed for and on behalf of the Bank

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 222
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE J: LIST OF ACCEPTABLE BANKS


Scheduled Commercial Banks

 State Bank of India


 Allahabad Bank
 andhra Bank
 Bank of India
 Bank of Andhra Pradesh
 Canara Bank
 Central Bank of India
 Corporation Bank
 Indian Bank
 Indian Overseas Bank
 Oriental Bank of Commerce
 Punjab National Bank
 Punjab & Sind Bank
 Syndicate Bank
 Union Bank of India
 United Bank of India
 UCO Bank of India
 Bank of Baroda
Scheduled Private Banks (India Banks)

 Bharat Overseas bank Ltd.


 Karur Vysya Bank Ltd.
 Axis Bank
 INDUSIND Bank Ltd.
 ICICI Bank
 HDFC Bank Ltd.
 Development Credit Bank Ltd.
 IDBI Bank Ltd.
 Yes Bank

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 223
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE K: FORMAT FOR LETTER OF DISCHARGE


(To be submitted on Bidder’s Letter Head)

No. Dated:

Head-

Sub: - Contract No…………………………………. dated ………….. for………………………….

Ref: - Our final bill dated ………………………

Dear Sir,

This has reference to our above final bill against the above contract and all
subsequent discussions and communications ending with or/your letter / tele / fax
No. …………. dated ……………..

We hereby write and agree that the amount of Rs. …………… received by us is in full and
final settlement of our above final bill. We further agree and confirm that the payment of
Rs. ……………… so received is in full and final settlement of all our claims and demands
arising out of or relating to the contract or the work or extra work done pursuant thereto
and all claims under the contract have been included in the final bill and as such arbitration
clause in the contract stands determined/terminated.

Thanking you,

Yours faithfully,

For and on behalf of Bidder

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 224
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE L: FORMAT FOR POWER OF ATTORNEY


(to be provided by the Bidding Company / All Member of JV/Consortium in favor of its representative
as Evidence of Authorized Signatory’s Authority)

(To be on non-judicial stamp paper of minimum Rs 100/-. Foreign companies submitting


bids are required to follow the applicable law in their country)

KNOW ALL MEN BY THESE PRESENTS, that we, _________(Name of the Bidder/Lead
Member of consortium), a Company/ Corporation/ Firm organized and existing
under and by virtue of the laws of _________(Name of Bidder’s country) and having
its registered office and principal office at ____________ (address of the Bidder) do
hereby irrevocably constitute, appoint, and authorize ____________(Name and
residential address) who is presently employed with us and holding the position of
____________________

___________________, as our true and lawful attorneys to do in our name and on


our behalf prepare, make, sign and submit the bid proposals and other documents,
certificates, undertakings and papers to be executed and delivered by us, and to do
all such acts, deeds and things as are necessary or required in relation to the tender
issued by KTL. for setting-up of a Solar Power Project of 2.6 MWp capacity on
turnkey basis in Guntur, Andhra Pradesh.

AND we hereby agree to ratify and confirm and do hereby ratify and confirm all acts,
deeds and things lawfully done or caused to be done by our said attorneys pursuant
to and in exercise of the powers conferred by this power of attorney and that all
acts, deeds and things done by our said attorneys in exercise of the powers hereby
conferred shall and shall always be deemed to have been done by us.

Signed by the within named

_____________________[Insert the name of the executant company]


through the hand of

Mr. ……………………………………….

duly authorized by the Board to issue such Power of Attorney Dated


this ………………………. day of ………

Accepted

Signature of Attorney

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 225
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

(Name, designation and address of the Attorney)

Attested

(Signature of the Executant)

(Name, designation and Address of the Executant)

Signature and stamp of Notary of the place of execution

Common seal of ……………… has been affixed in my/our presence pursuant


to Board of Director’s Resolution dated……

WITNESS

1. ______________

2. ______________

Note:

The mode of execution of the power of attorney should be in accordance with the
procedure, if any, laid down by the applicable law and the charter documents of the
executant(s) and the same should be under common seal of the executant affixed in
accordance with the applicable procedure. Further, the person whose signatures are
to be provided on the power of attorney shall be duly authorized by the
executant(s) in this regard.
Also, wherever required, the executant(s) should submit for verification the extract
of the chartered documents and documents such as a Board resolution

/ power of attorney, in favour of the Person executing this power of attorney for
delegation of power hereunder on behalf of the executant(s).

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 226
2.6 MWp SOLAR PLANT FOR TURNKEY EPC CONTRACTOR

SCHEDULE M: FORMAT FOR AFFIDAVIT

(TO BE STAMPED IN ACCORDANCE WITH THE STAMP ACT)

(TO BE NOTARIZED BY A NOTARY PUBLIC)

Affidavit of Shri ________________________S/O ___________________Aged


about ______ R/O _______________

I, the above named deponent do hereby solemnly affirm and declare as under:-

That I am working as______________(Designation) in (name and address of the


Bidder) since ________

That I am duly authorized by (name of the Bidder) to submit this affidavit of its
behalf.

That Bidder is submitting a bid in response to invitation for bid for design,
engineering, manufacture, supply, erection, testing and commissioning of 2.6 MWp
Rooftop Solar PV power plant in Guntur, Andhra Pradesh on turnkey basis including
5 years of Operation and Maintenance.

That Bidder is not Black listed or Banned, as on due date of submission of bids, for
participation in tenders issued by any of the power/ steel/ cement utilities/
Government/ Semi Government companies in any country.

That Bidder has successfully fulfilled all the contractual obligations in all
organizations, in terms of time, quantity and quality.

That if at any point of time the declarations given above are found to be incorrect,
KTL shall have the full right to terminate the contract and take any action as per
applicable laws for breach of contract including forfeiture of EMD/Performance
Bank Guarantee.

DEPONENT

Verification:

Verified at on day of___2019that the contents of my above affidavit are true to best of my
knowledge. No part of it is false and nothing material or relevant has been concealed there
from.

Doc.No:- Rev
2.6 MWp/2.0 MW SOLAR PV POWER PROJECT, ANDHRA GEPL/19/KTL/2.6MWp/RFP R0
Project: PRADESH
Date: 28-08-2019 Page 227