Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Homework Solutions – Chapter 3

1. The following activities are part of a project to be scheduled using CPM:

Activity Immediate Predecessor Time (wks)


A - 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7

a. Draw the network


b. What is the critical path?
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?

Solution

a.

b. A-C-D-E-G, also shown in the network above as the bold path.


c. 26 weeks, 6+7+2+4+7.
d. 6 weeks, 15-9.
2. For the project with the following information,
a. Determine the critical path and the early completion time in weeks.
b. Reduce the project completion time by three weeks. Assume a linear cost per
week shortened, and show, step by step, how you arrived at your schedule.

Activity Imm. Pred. Normal time Normal cost Crash time Crash cost
A -- 5 7000 3 13000
B A 10 12000 7 18000
C A 8 5000 7 7000
D B 6 4000 5 5000
E C 7 3000 6 6000
F C 4 6000 3 7000
G D,E,F 4 7000 3 9000

Solution

a. A-B-D-G, 25 weeks, 5+10+6+4.


b.

Activity Normal Normal Cost Crash Time Crash Cost NT-CT Cost/week
Time (NT) (NC) (CT) (CC) to expedite
A 5 $7,000 3 $13,000 2 $3,000
B 10 12,000 7 18,000 3 2,000
C 8 5,000 7 7,000 1 2,000
D 6 4,000 5 5,000 1 1,000
E 7 3,000 6 6,000 1 3,000
F 4 6,000 3 7,000 1 1,000
G 4 7,000 3 9,000 1 2,000

First, reduce D (lowest cost activity on the critical path) by one week. This adds an additional
critical path with activities C and E in it. Second, crash activity G by one week. Critical paths
remain the same. Third, crash activity A by one week at a cost of $3,000, which is the least
expensive.

Summary of activities crashed:

Step Activity Cost to crash Weeks reduced


1 D $1,000 1
2 G 2,000 1
3 A 3,000 1
Total cost $6,000

You might also like