OJT DAILY ACTIVITIES REPORT

GROUP : STG GROUP 1


NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1. Learning about Circulating Water Sytem


1 3rd, June 2019 (KTG1-DECDI-C-PA-ME-PID-7003-R0-WP-CRS1)
OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

1. Knowing the flow process and the equipment of circulating


water system

2. Knowing the specification and configuration of circulating water


pump (during normal operation 3 pump start and 1 pump standby)

3. Knowing the flow process of make up water for cooling tower


system

4. Knowing the operation parameter of circulating water system


OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1. Learning about Circulating Water & Open Cooling Water System


1 4th, June 2019 (KTG1-DECDI-C-PA-ME-PID-2102-R0-WP-CRS1)
OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

1. Knowing the flow process and the equipment of open cooling


water system

2. Knowing the specification of each equipment in the circulating


water & open cooling water system (condenser, rubber ball device,
OCW strainer, CCCW heat exchanger, vacuum pump heat
exchanger, etc)
OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1. Walk down to power plant site


1 7th, June 2019 (learning the actual pipeline of circulating water and open cooling water
system)

2. Learning the circulating water system interlock checklist


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

Knowing the actual condition and placement of circulating water


system pipeline and eqiupment

Knowing all the equipment of circulating water system that should


be tested interlock before system start-up
OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 10th, June 2019 1. Learning about Turbine Lubricating Oil System

2. Learning about Circulating Water Pump


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

Knowing the flow process and the equipment of Turbine


Lubricating Oil System

Knowing the specification, installment, and arrangement of


Circulating Water Pump
OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1. Learning about Lube Oil Sytem


1 11th, June 2019 (KTG1-DECDI-C-MAV-ME-PID-2105-RB)

2. Walk down to power plant site


(Turbine lube oil system)
OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

Knowing the flow process, specification and the equipment of lube


oil system

Knowing the actual condition and placement of lube oil pipeline


and eqiupment
OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 12th, June 2019 1. Learning about Circulating Water Pump

2. Learning about Lube Oil Sytem


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

- Knowing each part of Circulating Water Pump


- Knowing the start-up and shutdown procedure of Circulating
Water Pump
- Knowing the step of dismantling and repairing the Circulating
Water Pump

- Make the scheme of turbine lube oil system


- Knowing about the system of turbine lube oil
OJT DAILY ACTIVITIES REPORT
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 13th, June 2019 1. Review about Circulating Water Pump

2.Review about Turbine Lube Oil System

3. Walkdown to site
OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

- Knowing the specification of Circulating Water Pump


- Make the scheme of Turbine Lube Oil System
- Knowing the specification of AC Lube Oil Pump and DC Lube Oil
Pump

- Knowing the actual condition and placement of lube oil pipeline


and equipment
OJT DAILY ACTIV
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 14th, June 2019 1. Review about lube oil system and lube oil treatment system

2. Review about Turbine Lube Oil System


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

Knowing the flow process and the equipment of Turbine


Lubricating Oil System and lube oil treatment system

Knowing lube oil parameter


OJT DAILY ACTIV
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 17th, June 2019 1. Review about Main Steam & By-pass System

2. Walk dow to site


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

1. Draw the main steam & by-pass system scheme

2. Knowing the flow process of the main steam from boiler to


turbine and the HP-LP bypass system

3. Knowing the working parameters of main steam and by-pass


steam

1. Knowing the working parameter of deaerator

2. Knowing the start-up procedure of deaerator


OJT DAILY ACTIV
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 18th, June 2019 1. Review about Main Steam & By-pass System

2. Learning about deaerator working principle


OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

1. Draw the main steam & by-pass system scheme

2. Knowing the flow process of the main steam from boiler to


turbine and the HP-LP bypass system

3. Knowing the working parameters of main steam and by-pass


steam

1. Knowing the actual condition and placement of auxiliary steam


pipeline and equipment

2. Knowing the actual condition and placement of deaerator


pipeline and equipment

3. Knowing the specification of auxiliary steam


OJT DAILY ACTIV
GROUP : STG GROUP 1
NAME : 1. OKTAVIANUS PASONGKA T.
2. ANDI TEGAR PRATAMA
3. BAGUS AMIN FAJARUDIN
4. IFFAN ROSYADI ALI
5. JAYA RACHMAT
6. MARSHELLA A. G

NO DATE ACTIVITIES

1 19th, June 2019 1. Walk down to Turbine Area (Deaerator and auxiliary steam)
OJT DAILY ACTIVITIES REPORT

ACHIEVEMENT REMARKS

Knowing all the pipe flow that installed in the deaerator and
auxiliary steam header

Knowing the instrument position of the deaerator and auxiliary


steam header