Professional Documents
Culture Documents
Compiled Variable Load Bsme5 10
Compiled Variable Load Bsme5 10
Compiled Variable Load Bsme5 10
A central station is supplying energy to a community through two substations. One substation feeds four
disturbing circuits, the other, six. The maximum daily recorded demands are:
TIME 12 3 6 8 10 11 12 1 3 4 5 6 7 9 12
LOAD,
kW x 95 60 60 150 175 180 175 150 200 250 310 170 140 160 105
10³
Plot the load curve to scales of 1 cm = 2 hr, 1 cm = 50,000 kW. Determine the load factor. What
is the daily load factor of the standby equipment that takes all the peak load over 200,000 kw?
SOLUTION:k+1
Note: Graph actually shown maybe not to scale. Need to redraw to scale.
𝑏 1
A = ∫𝑎 𝑓(𝑥)𝑑𝑥 = ∑𝑁
𝑘=1(𝑋k + 1 – 𝑋𝑘 )[𝑓(𝑋k + 1) + (f(Xk)]
2
1 1 1 1
A = 2 (103 )(95 + 60)(3) + 2 (103 )(60 + 60)(3) + 2 (103 )(60 + 150)(2) + 2 (103 )(150 +
1 1 1
175)(2) + (103 )(175 + 180)(1) + (103 )(180 + 175)(1) + (103 )(175 + 150)(1) +
2 2 2
1 1 1
(103 )(150 + 200)(2) + (103 )(200 + 250)(1) + (103 )(250 + 310)(1) +
2 2 2
1 1 1
(103 )(310 + 170)(1) + (103 )(170 + 140)(1) + (103 )(140 + 160)(2) +
2 2 2
1
(103 )(160 + 105)(3) = 3412.5𝑥10³ 𝑘𝑤ℎ𝑟
2
3412.5𝑥10³
Load factor = 310,000𝑥24 = 0.4587 (𝒂𝒏𝒔𝒘𝒆𝒓)
TIME 12 3 6 8 10 11 12 1 3 4 5 5.876 7 9 12
Load,
kW x 0 0 0 0 0 0 0 0 0 50 110 0 0 0 0
10⁻³
1 1 1
A = (103 )(0 + 50)(1) + ( 103 )(50 + 110)(1) + (103 )(110 + 0)(0.786) =
2 2 2
148.23𝑥103 𝑘𝑤ℎ𝑟
148.23𝑥10³
Daily load factor = 110,000𝑥 2.786= 0.4837 (answer)
PROBLEM3
3. A daily load curve is defined as follows:
Time 12 2 4 6 8 10 12 2 4 6 8 10 12
Load, 140 150 160 180 170 170 170 160 240 365 320 220 160
kW
Plot the load curve to scales of 1 cm = 2hr, 1 cm = 50 kW. Determine the load factor and energy
produced.
Solution:
Note: Graph actually shown maybe not to scale. Need to redraw to scale.
Energy Produced:
Use Trapezoidal Rule
𝑏 𝑏−𝑎
A = ∫𝑎 𝑓(𝑥)𝑑𝑥 = [𝑓(𝑥1 ) + 2 𝑓(𝑥2 ) + 2𝑓(𝑥3 ) + ⋯ 2𝑓(𝑥𝑁 ) + 𝑓(𝑥𝑁+1 )
2𝑁
b-a = 24 hrs
N = 12
24
Energy Produced = [140+2(150)+2(160)+2(180)+2(170)+2(170)+2(170)+2(160)+2(240)+2(365)
2(12)
+2(320)+2(220)+160]
Energy Produced = 4910 kW-hr
4910 𝑘𝑊−ℎ𝑟
Average load = 24 ℎ𝑟𝑠
= 204.58 kW
𝟐𝟎𝟒.𝟓𝟖 𝒌𝑾
Load Factor = 𝟑𝟔𝟓 𝒌𝑾
= 0.56 = 56%
PROBLEM4
MORSE4:
An investigation of the way of transformation daily load curves into
annual load duration curves may be made if one of the daily load curves
described in these problems is considered to be duplicated every other
day of the year. This untrue but simplifying assumption will eliminate
need for a mass of load data and the reader will learn the principle.
Solution:
Load Curves - the curve showing the variation of load on the power
station (power plant) with reference to time is known as load curve.
The curve thus obtained is known as daily load curve as it shows the
variations of load w.r.t. time during the day. Fig. 3.2. shows a typical
daily load curve of a power station. It is clear that load on the power
station is varying, being maximum at 6 P.M. in this case. It may be seen
that load curve indicates at a glance the general character of the load
that is being imposed on the plant. Such a clear representation cannot
be obtained from tabulated figures.
PROBLEM5
MORSE 5
The daily load curve of a power plant is given by these coordinates.
Time 12 2 4 6 8 10 12 2 4 6 8 10 12
Load, Kw x 103 2 2.5 3 4 6 6.5 6.5 5 6 8 9 5 3
a.) Find the daily load factor. B.) All loads in excess of 4000 kw are carried by unit no. 3 rated at
6000 kw. Find its use factor.
Energy Produced:
Use Trapezoidal Rule
𝑏
𝑏−𝑎
𝐴 = ∫ 𝑓(𝑥)𝑑𝑥| = [𝑓(𝑥1 ) + 2𝑓(𝑥2 ) + 2𝑓𝑥3 )+. .2𝑓(𝑥𝑛 ) + 𝑓(𝑥𝑛 )]
𝑎 2𝑁
b-a = 24hrs
N = 12
24(103 ) 2+2(2.5)+2(3)+2(4)+2(6)+2(6.5)+2(6.5)
Energy produced = [ ] = 128,000𝐾𝑤 − ℎ𝑟
2(12) +2(5)+2(6)+2(8)+2(9)+2(5)+3
128,000
Average load = = 5333.33 Kw
24
128,000
Use factor = (4000)(6+1)+(4000+6000)(17) = 0.6465
PROBLEM6
6. The annual peak load on a 15000 kw power plant. Two substation are supplied by this plant. Annual
energy dispatched through substation A is 27,500,000 kwhr with peak at 8900kw, while 16,500,000 kwhr
are sent through B with a peak at 6650 kw. Neglect line losses. Find (a) diversity factor between
substation and (b) capacity factor of the power plant.
Solution:
SOLUTION:
Commercial 35 kW 35 kw × 0.6 = 21 kW
Total for Commercial lighting = 21 kW
Transformer No. 3
Commercial 15 kW 15 kW × 0.6 = 9 kW
Commercial 5 kW 5 kW × 0.6 = 3 kW
Power 4 kW (4 kW/0.72)( 0.75) = 4.17 kW
Commercial 15 kW 15 kW × 0.6 = 9 kW
Commercial 25 kW 25 kW × 0.6 = 15 kW
Total for Commercial lighting and Power = 40.17 kW
Transformer No. 4
Power 32 kW (32 kW/0.72)( 0.55) = 24.44 kW
Total for Power = 40.17 kW
Residence 24 kW 24 kW × 0.5 = 12 kW
Residence 35 kW 35 kW × 0.5 = 17.5 kW
Residence 18 kW 18 kW × 0.5 = 9 kW
Total for Residential lighting = 38.5 kW
Total Diversity Total Diversity Simultaneous
Residence Factor (Commercial and factor kW
power), kW
Transformer 27.5 3.5 7.86
1
Transformer 36.5 3.5 21 1.5 24.43
2
Transformer 40.17 1.5 26.78
3
Transformer 38.5 3.5 24.44 1.5 27.29
4
PROBLEM10
10. a certain distributing transformer has connected load as follows: residence no. 1, ¾ kw; no. 2, 2 ½
kw; no. 3, 500 w; no.4, 3 kw. Restaurant, 5 kw lighting and 11 kw motors. Store, 15 kw lighting and 3.7 kw
motors. Efficiency of motors, 70% calculate the maximum expected demand on the transformer.
Solution:
Residence lighting
Restaurant
Store
Solution:
Then,
P.M. 1:00 1:30 2:00 3:00 4:00 5:00 5:30 6:00 7:00 8:00 9:00 10:00 11:00 12:00
kW 500 590 620 670 760 1000 960 930 900 870 850 720 600 380
It is proposed to carry this load with a new Diesel engine power station. A certain
line of engines is offered in the following sizes, depending on the number of
cylinders: 360 kW, 480 Kw, 600 kW, 720 kW, 960 kW. Plot the load curve and fit it
with selection from the engine line mentioned so that there will be a good balance
between capacity factor and number of units installed. (a) Determine the capacity
factor of the plant. (b) Tabulate an “operating schedule”. (c) Determine the use
factor of each unit.
Solution:
Energy Produced =
1 1 1
(380 + 220)(1) + (220 + 200)(1) + (200 + 190)(1)
2 2 2
1 1 1
+ (190 + 180)(1) + (180 + 180)(1) + (180 + 200)(1)
2 2 2
1 1 1
+ (200 + 300)(1) + (300 + 410)(1) + (410 + 560)(1)
2 2 2
1 1 1
+ (560 + 590)(1) + (590 + 610)(1) + (610 + 605)(1)
2 2 2
1 1 1
+ (605 + 490)(1) + (490 + 500)(1) + (500 + 590)(1)
2 2 2
1 1 1
+ (590 + 620)(1) + (620 + 670)(1) + (670 + 760)(1)
2 2 2
1 1 1
+ (760 + 1000)(1) + (1000 + 960)(1) + (960 + 930)(1)
2 2 2
1 1 1
+ (930 + 900)(1) + (900 + 870)(1) + (870 + 850)(1)
2 2 2
1 1 1
+ (850 + 720)(1) + (720 + 600)(1) + (600 + 380)(1)
2 2 2
1:00 AM 220
2:00 AM 200
3:00 AM 190
4:00 AM 180
5:00 AM 180
6:00 AM 200
7:00 AM 300
8:00 AM 410
8:45 AM 480
3:45 PM 0
4:00 PM 40
5:00 PM 280
5:30 PM 240
6:00 PM 210
7:00 PM 180
8:00 PM 150
9:00 PM 130
10:00 PM 0
𝟐𝟗𝟒𝟖.𝟕𝟓
Unit No. 1 use factor = = 𝟎. 𝟒𝟐𝟑𝟕 Answer.
𝟔𝟗𝟔𝟎
Time Kw
8:15 AM 480
9:00 AM 560
10:00 AM 590
11:00 AM 610
12:00 NN 605
12:30 PM 490
1:00 PM 500
1:30 PM 590
2:00 PM 620
3:00 PM 670
3:45 PM 720
4:00 PM 720
5:00 PM 720
5:30 PM 720
6:00 PM 720
7:00 PM 720
8:00 PM 720
9:00 PM 720
10:00 PM 720
11:00 PM 600
12:00 PM 380
𝟏𝟎,𝟐𝟏𝟓
Unit No. 2 use factor = = 𝟎. 𝟗𝟎 Answer.
𝟏𝟏,𝟑𝟒𝟎
PROBLEM14
14 by Morse (Power Plant Engineering)
14. The load shown in fig. 2-11 goes to peak of 24000 kw. It is to be carried by one 10000 kw unit
and two 7500 kw units. Work out a use scheme similar to fig. 2-10 which will be best from the
standpoint of number of paralleling operations and plant use factor. What is the resulting daily
load factor for each unit?
Solution:
Tabulation:
Time Kw
12:00 MID 6968
1:00 AM 5419
2:00 AM 3871
3:00 AM 3097
4:00 AM 3097
5:00 AM 2323
6:00 AM 3484
7:00 AM 6581
8:00 AM 10,839
9:00 AM 14,710
10:00 AM 17,807
11:00 AM 17,419
12:00 NN 17,419
1:00 PM 12,774
2:00 PM 17,807
3:00 PM 18,194
4:00 PM 20,129
5:00 PM 24,000
6:00 PM 20,129
7:00 PM 18,196
8:00 PM 17,032
9:00 PM 14,323
10:00 PM 10,065
11:00 PM 6968
12:00 MID 5807
𝑏 1
𝐴 = ∫𝑎 𝑓(𝑥)dx=2 ∑𝑁
𝑘=1(𝑋𝑘+1 -𝑋𝑘 ){f(𝑋𝑘+1 )+f(𝑋𝑘 )}
Energyproduced=
1 1 1 1 1
(6968+5419)(1)+ 2(5419+3871)(1)+ 2(3871+3097)(1)+ 2(3097+3097)(1)+ 2(3097+2323)(1)+
2
1 1 1 1
(2323+3484)(1)+ (3484+6581)(1)+ (6581+10,839)(1)+ (10,839+14,710)(1)+
2 2 2 2
1 1 1 1
(14,710+17,807)(1)+ 2(17,807+17,419)(1)+ 2(17,419+17,419)(1)+ 2(17,419+12,774)(1)+
2
1 1 1 1
(12,774+17,807)(1)+ 2(17,17,807+18,194)(1)+ 2(18,194+20,129)(1) 2(20,129+24,000)(1)+
2
1 1 1 1
(24,000+20,129)(1)+ 2(20,129+18,196)(1)+ 2(18,196+17,032)(1)+ 2(17,032+14,323)(1)+
2
1 1 1
(14,323+10,065)(1)+ 2(10,065+6968)(1)+ 2(6968+5807)(1)= 292,070.5 kW-hr
2
Hours of Operation:
Unit No. 1 = 24 hrs
Unit No. 2 = 15.5 hrs
Unit No. 3 = 11.2 hrs
292,070.5
Plant use factor = 7500 𝑥 24+7500 𝑥 15.5+10,000 𝑥 11.2
Time Kw
12:00 MID 6968
1:00 AM 5419
2:00 AM 3871
3:00 AM 3097
4:00 AM 3097
5:00 AM 2323
6:00 AM 3484
7:00 AM 6581
8:00 AM 7500
9:00 AM 7500
10:00 AM 7500
11:00 AM 7500
12:00 NN 7500
1:00 PM 7500
2:00 PM 7500
3:00 PM 7500
4:00 PM 7500
5:00 PM 7500
6:00 PM 7500
7:00 PM 7500
8:00 PM 7500
9:00 PM 7500
10:45 PM 7500
11:00 PM 6968
12:00 MID 5807
Energy produce =
1 1 1 1 1
(6968+5419)(1)+ 2(5419+3871)(1)+ 2(3871+3097)(1)+ 2(3097+3097)(1)+ 2(3097+2323)(1)+
2
1 1 1 1 1
(2323+3484)(1)+ 2(3484+6581)(1)+ 2(6581+7500)(0.25)+(7500)(15.5)+ 2(7500+6968)(0.25)+ 2(6
2
968+5807)(1)= 154,271.6 kW-hr
154,271.6
Average load = = 6428 kW
24
Time kW
12:00 MID 0
1:00 AM 0
2:00 AM 0
3:00 AM 0
4:00 AM 0
5:00 AM 0
6:00 AM 0
7:00 AM 0
7:15 AM 0
8:00 AM 3339
9:00 AM 7210
9:05 AM 7500
10:00 AM 7500
11:00 AM 7500
12:00 NN 7500
12:45 PM 7500
1:00 PM 5274
1:15 PM 7500
2:00 PM 7500
3:00 PM 7500
4:00 PM 7500
5:00 PM 7500
6:00 PM 7500
7:00 PM 7500
8:00 PM 7500
8:45 PM 7500
9:00 PM 6823
10:00 PM 2565
10:45 PM 0
11:00 PM 0
12:00 MID 0
Energy produced =
1 1 5 1 1
(3339+7210)(1)+ (7210+7500)( )+(7500)(3.7)+ (7500+5274)(0.25)+ (5274+7500)(0.25)+(75
2 2 60 2 2
1 1 1
00)(7.5)+ 2(7500+6823)(0.25)+ 2(6823+2565)(1)+ 2(2565+0)(0.75) = 100, 527.2 kW – hr
100,527.2
Average load = = 4189 kW
24
Time Kw
12:00 MID 0
1:00 AM 0
2:00 AM 0
3:00 AM 0
4:00 AM 0
5:00 AM 0
6:00 AM 0
7:00 AM 0
7:15 AM 0
8:00 AM 0
9:00 AM 0
9:05 AM 0
10:00 AM 2,807
11:00 AM 2,419
12:00 NN 2,419
12:45 PM 0
1:00 PM 0
1:15 PM 0
2:00 PM 2,807
3:00 PM 3,194
4:00 PM 5,129
5:00 PM 9,000
6:00 PM 5,129
7:00 PM 3,196
8:00 PM 2,032
8:45 PM 0
9:00 PM 0
10:00 PM 0
10:45 PM 0
11:00 PM 0
12:00 MID 0
Energy produced =
1 1 1 1 1 1
(2807+2419)(1)+ 2(2419+2419)(1)+ 2(2419+0)(0.75)+ 2 (0+2807)(0.75)+ 2(2807+3194)(1)+ 2(319
2
1 1 1 1 1
4+5129)(1)+ 2(5129+9000)(1)+ 2(9000+5129)(1)+ 2(5129+3196)(1)+ 2(3196+2032)(1)+ 2(2032+0)
(0.75) = 35,821.3 kW - hr
35,821.3
Average load = = 1493 kW
24
A 50.000-kw steam plant delivers an annual output of 238,000,000 kw/hr with a peak load of
42,860 kw. (a) What is the annual load factor? (b) What is the capacity factor?
Solution:
𝑘𝑤
𝑜𝑢𝑡𝑝𝑢𝑡
ℎ𝑟
Average Load =
8,760 ℎ𝑟
238,000,000
Average Load = = 27,169 kw
8,760
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑
Load Factor =
𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑
27,169 𝑘𝑤
Load Factor = = 0.6339 kw
42,860 𝑘𝑤
27,169 𝑘𝑤
Capacity Factor = 50,000 𝑘𝑤 = 0.5434 kw
PROBLEM16
MORSE16. The load shown by data of Prob.13 is carried by one steam turbogenerator having the
following steam characteristics: Total steam= 907.2 + 4.99 kw kg per hour, where P= kw / Generator
efficiency = 96% Steam cost 67 cents per 500 kg to produce. What is the cost of the steam supplied to
this unit per day of 24 hr? What is the cost of steam used per kw hr?
SOLUTION:
Total Steam= 907.2 + 4.99 kw kg per hr, where P= kw / Generator efficiency = 96%
Tabulation
𝑏 1
A ∫𝑎 𝑓(𝑥)𝑑𝑥 = ∑𝑁
𝑘=1(𝑥𝑘−1 − 𝑥𝑘 )(𝑓(𝑥𝑘−1 ) + 𝑓(𝑥𝑘 ))
2
Energy Produced=
1 1 1 1 1
. (380 + 220)(1) + (220 + 200)(1) + (200 + 190)(1) + (190 + 180)(1) + (180 +
2 2 2 2 2
1 1 1 1
200)(1) + 2 (200 + 300)(1) + 2 (300 + 410)(1) + 2 (410 + 560)(1) + 2 (560 + 590)(1) +
1 1 1 1 1
(590 + 610)(1) + (610 + 605)(1) + 2 (605 + 490)(1) + 2 (490 + 500)(1) + 2 (500 + 590)(1) +
2 2
1 1 1 1 1
(590 + 620)(1) + (620 + 670)(1) + 2 (670 + 760) + 2 (760 + 1000)(1) + 2 (1000 + 960)(1) +
2 2
1 1 1 1 1
(960 + 930)(1) + (930 + 900)(1) + 2 (900 + 870)(1) + 2 (870 + 850)(1) + 2 (850 + 720)(1) +
2 2
1 1
(720 + 600)(1) + (600 + 380)(1) = 𝟏𝟑, 𝟎𝟐𝟔, 𝟐𝟓 𝒌𝑾 − 𝒉𝒓
2 2
TOTAL SIMULTANEOUS
Transformer 1 0.6(3x) = 1.8x 1.8x/3.5 = 0.5143x
Transformer 2 0.6x 0.6x/3.5 = 0.1714x
Transformer 3 0.6(3x) = 1.8x 1.8x/3.5 = 0.5143x
Transformer 4 0.6x 0.6x/3.5 = 0.1714x
Transformer 5 0.6(4x) = 2.4x 2.4x/3.5 = 0.6857x
Transformer 6 0.6(3x) = 1.8x 1.8x/3.5 = 0.5143x
Operating Schedule:
Hours of Operation:
Unit No. 1 = 24 hrs
Unit No. 2 = 22 hrs
Unit No. 3 = 5 hrs
4910
Plant use factor = 150𝑥24+100𝑥22+150𝑥2
This load is supplied by a steam plant whose fuel consumption is tabulated as follows:
Assume that you are the purchasing agent and you want to contract in advance for the year's supply of coal
to be delivered in equal semimonthly deliveries. How many tonnes would you specify per delivery?
Solution:
Tabulation:
Coal determined by interpolation:
In tonnes. 1 tonne = 1000 kg = 2205 lb
Per delivery for semi-monthly = (1/24)(2.83 x 108lb)(1tonnes / 2205 lb)
Per delivery for semi-monthly =5348 tonnes per delivery (answer)
PROBLEM21
MORSE21. The system shown in Fig. 2-7 consists in part of a transformer serving
customers e, f and g. Estimate the peak load on the transformer.
a.) Store building with 5 kW lighting, 25-Kw small motor power.
b.) Store building with 18 kW lighting, 35-Kw small motor power.
c.) Office building with 55 kW lighting, 80-Kw large motor power.
Solution:
Customer e:
Store building with 5 kW lighting, 25-Kw small motor power
Customer f:
Store building with 18 kW lighting, 35-Kw small motor power
Customer g:
Office building with 55 kW lighting, 80-Kw large motor power
Problem 22: Assume that the maximum feeder loads of the system shown in Fig. 2-7 are (1) 18 kw, (2)
255 kw, (3) 115 kw, (4) 95 kw, (5) 37 kw, (6) 45 kw. Predict the peak load for the power plant.
Solutions.
23. A city is supplied by a 15,000 kw plant whose duration curve is defined by the following data:
The plant has one 15,000 kw unit supplied with steam by one boiler. Auxiliaries are electrically driven.
Draw the coal consumption duration curve from the load duration curve with intermediate graphical
modification from three plant characteristic.
Assume straight line variation between no load and full load condition. Determine annual coal
consumption, tons.
Solution:
Tabulation:
𝑏 𝑁
1
𝐴 = ∫ 𝑓(𝑥)𝑑𝑥 = ∑(𝑥𝑘+1 − 𝑥𝑘) [𝑓 (𝑥𝑘+1 ) + 𝑓(𝑥𝑘 )]
𝑎 2
𝑘−1
In tons:
Solution:
Total Kw hr sent =
½ (100)(114.5+91.6)(1000)+1/2(100)(91.6+81.0)(1000)+1/2(100)(81.0+74.5)(1000)
+1/2(100)(74.5+69.4)(1000)+1/2(100)(69.4+62.0)(1000)+1/2(100)(62.0+52.0)(1000)
+1/2(100)(52.0+40.8)(1000)+1/2(40.8+29.8)(1760)
Solution:
(26,260 − 3400)(15)
= 95.25 𝑘𝑔
3600
W= weight of water in the tank when fully charged to 3.2 kg/cm2 ga.
W= 95.25 + weight of water remaining when fully discharged at 2.5 kg/cm2 ga.
At 3.2 kg/cm2 ga., h=2739.3 kJ/kg
At 2.5 kg/cm2 ga., h=2731.2 kJ/kg
Average, h= 0.5(2739.3 + 2731.2)= 2735.3 kJ/kg
W = 7399 kg
At 3.2 kg/cm2 ga, vg=0.4464 m3/kg, vf = 1.085 x 10-3 m3/kg
At 2.5 kg/cm2 ga, vg=0.5291 m3/kg, vf = 1.0785 x 10-3 m3/kg
Average, vg=0.5(0.4464 + 0.5291) = 0.4878 m3/kg
vf = 0.5(1.085 + 1.0785) x 10-3 m3/kg = 1.08175 x 10-3 m3/kg
1
(26,260−3400)( )(0.4878)
3600
Surface Area = 0.305
𝑉 𝜋 16.12
= 𝐷=
𝐴 4 10.16
D=1.59m (answer)
10.16
L= 1.59 = 6.39m (answer)
PROBLEM26
PROBLEM 26
26.) A horizontal steam accumulator tank is 152 cm diameter by 6.1 m long. When fully charged the
water level is 144 cm above the bottom, and the pressure is 7 kg/cm2 ga. During a test for maximum
discharge it was found that the pressure could be dropped to 6.33 kg/cm2 ga in 10 sec without throwing
water into the discharging steam. Calculate the average rate of steam discharge from the accumulator in
kg per hr.
SOLUTION:
𝑉 = 𝐴𝐿
𝑅2 𝜋
𝐴= ( 𝐶 − sin 𝐶)
2 180
ℎ−𝑅
𝐶 = 180 + 𝐴𝑟𝑐𝑠𝑖𝑛
𝑅
ℎ = 114𝑐𝑚 = 1.14𝑚
152
𝑅= = 76𝑐𝑚 = 0.76𝑚
2
1.14 − 0.76
𝐶 = 180 + 2𝐴𝑟𝑐𝑠𝑖𝑛 = 240°
0.76
(0.76)2 𝜋
𝐴= [ (240) − sin(240)] = 1.4598𝑚2
2 180
𝑉 = 𝐴𝐿 = (1.4598)(6.1) = 8.9048𝑚3
At 7 kg/cm2 ga, hf = 718.14 kJ/kg
hg=2766.84 kJ/kg
vg=0.2438 m3/kg
𝑘𝑔 𝑉 8.9048
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 𝑖𝑛 𝑡ℎ𝑒 𝑡𝑎𝑛𝑘 𝑤ℎ𝑒𝑛 𝑡ℎ𝑒𝑦 𝑎𝑟𝑒 𝑓𝑢𝑙𝑙𝑦 𝑐ℎ𝑎𝑟𝑔𝑒𝑑 𝑡𝑜 7 2
𝑔𝑎 = =
𝑐𝑚 𝑣𝑓 1.1142 × 10−3
= 𝟕𝟗𝟗𝟐 𝒌𝒈
𝑇ℎ𝑒𝑛, 7992 𝑘𝑔 = 𝑊 + 𝑊𝑒𝑖𝑔ℎ𝑡 𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤ℎ𝑒𝑛 𝑓𝑢𝑙𝑙𝑦 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒𝑑 𝑎𝑡 6.33 𝑘𝑔/𝑐𝑚2
Initially, the water had an enthalpy of 718.14 kJ/kg, finally 702.54 kJ/kg.
𝑊 = 60.45 𝑘𝑔
PROBLEM27
MORSE. 27
The medium demand upon a steam accumulator ( i.e., one of the sectional areas in figure 2-14)
is 29,500 kg steam. Maximum charging pressure is 25 kg/cm2 ab. dry and saturated steam. The
delivery pressure, beyond valve B, is 2 kg/cm2 ab. Assuming that the accumulator is fully charged
just previous to the period of maximum demand, calculate the kg water the accumulator must
contain if this maximum demand is to be only 75% of the accumulators steam capacity.
SOLUTION:
0.75(29,500) = 22,125 kg
W = weight of water in the tank when fully charged to 25 kg/cm2 ab.
W = 22,125 + weight of water remaining when fully discharge at 2 kg/cm2 ab.
Solution:
𝑒𝑔𝑒𝑛 =0.96
𝑒𝑡 = .80
𝑒𝑝 = .75
𝐻𝑔 = 30𝑚
𝐻𝑓 = .3𝐻𝑔
Q = 907𝑚3
NE
H = Hg – Hf
H = 30 – 0.3(30)= 21m
Wt = (9.81)(Q1)(21)(.96)(.80)=1400(3600)
Q1= 31,855𝑚3
PUMP
H = Hg – Hf
H = 30 + .3(30) =39m
(9.81)(907)(39)
Wp = 0.96(.75)
= 481,957 KJ
Find the hydraulic impoundment volume necessary to meet a peak of 15,000 kw-hr with pump
storage. Yurbogenerator efficiency= 82%, head=70m. Neglect fiction and evaporation losses.
Solution:
W QHtg
15000(3600) (9.81)(Q)(70)(0.82)
Q 95,899m3
PROBLEM30
PROBLEM # 30
The Boiler load curve shown in fig. 2-11 is to be smoothed out by operating an hydraulic
accumulator unit in parallel. The accumulator plant will have an average head of 76m. Neglect
pipe friction and evaporation losses. Assume the steam turbine driving the accumulator pump
operatres as part of the plant characteristics shown and that the over-all efficiency of hydraulic
storage from steam turbine shaft back to hydro turbogenerator output is 65%.
(a) What steam plantbase load capacity is needed?
(b) What boiler capacity is needed?
(c) What is the capacity of the accumulator turbine?
(d) How much more steam is generated per 24 hr than would have been used without the
accumulator?
SOLUTION:
a.) Steam plant base load capacity = 1805.4 x 24 = 43,329.6 kg/day (answer)
b.) Boiler capacity = 86867 kg/day (answer)
c.) Capacity of the accumulator turbine = (1/2)(86867 - 1805.4 x 24)
= 21,768.7 kg/day (answer)
d.) Extra steam generated per 24 hr than would have been used without the accumulator
= 86867 – 1805.4 x 24
= 43,537.4 kg/day (answer)
PROBLEM31
1. A 50 MW Power Plant has an average load of 31,500 KW and a load factor of 70% .
Find the reserve over peak.
A. 4 MW C. 5 MW
B. 3 MW D. 6 MW
SOLUTION :
𝐴𝑣𝑒. 𝐿𝑜𝑎𝑑
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 =
Peak Load
31,500
0.70 =
Peak Load
Peak Load = 45,00 KW
Peak Load = 45 MW
Reserve Over Peak = 50 – 45
Reserve Over Peak = 5 MW
PROBLEM32
ALCORCON 2
The daily energy produced in a certain power is 480,000 kW-hrs. What is the daily average load?
Solution:
𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑑
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑 =
𝑁𝑜. 𝑜𝑓 ℎ𝑟𝑠.
480,000 𝑘𝑊 − ℎ𝑟
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑 =
24ℎ𝑟𝑠
𝑨𝒗𝒆𝒓𝒂𝒈𝒆 𝑳𝒐𝒂𝒅 = 𝟐𝟎, 𝟎𝟎𝟎 𝒌𝑾
PROBLEM33
ALCORCON 3
The annual energy produced in a 100 MW power plant is 438,000,000
KW-hrs. What is the annual capacity factor of the plant?
A. 40 % C. 35%
B. 50% D. 60%
Solution:
AnnualEnergyProduced
Annual Capacity Factor =
PlantCapacityx8760
438,000,000
Annual Capacity Factor =
100,000X8760
Solution:
𝐴𝑛𝑛𝑢𝑎𝑙 𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑑
Annual Capacity Factor = 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 ×8760
𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑑
0.50 = 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 ×𝑡
6,000 + 9,000
= 12,000
Thus;
Diversity Factor = 1.25
PROBLEM36
PRIME2
A 75 MW power plant has an average load of 35,000 KW and a load factor of 65%. Find
the reserve over peak.
SOLUTION
Reserve over peak = Plant Capacity – Peak Load
Average Load
Load Factor = Peak load
35,000 𝐾𝑊
0.65 = 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑
Solution:
𝑆𝑢𝑚 𝑜𝑓 𝑖𝑛𝑑𝑖𝑣𝑖𝑑𝑢𝑎𝑙 𝑀𝑎𝑥. 𝐷𝑒𝑚𝑎𝑛𝑑𝑠
Diversity factor between substation = 𝑀𝑎𝑥. 𝐷𝑒𝑚𝑎𝑛𝑑 𝑜𝑓 𝑃𝑜𝑤𝑒𝑟𝑆𝑡𝑎𝑡𝑖𝑜𝑛
8900+6650
= 10,500
= 1.48
𝐴𝑐𝑡𝑢𝑎𝑙 𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒 𝐴𝑛𝑛𝑢𝑎𝑙𝑙𝑦
Capacity Factor of the Power Plant = 𝑀𝑎𝑥. 𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑑 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑠𝑎𝑚𝑒 𝑝𝑒𝑟𝑖𝑜𝑑
𝑘𝑊−ℎ𝑟 𝑘𝑊−ℎ𝑟
27,500 +16,500,000
𝑦𝑟 𝑦𝑟
= ℎ𝑟
15,000 𝑘𝑊 (8760 )
𝑦𝑟
= 0.335
PROBLEM38
4.) What is the daily average load in a certain power plant if the daily energy produced is 500, 000 kW-hrs.
A. 28.29 MW
B. 30.26 MW
C. 19.61 MW
D. 20.83 MW
Solutions:
𝑘𝑊 − ℎ𝑟𝑠 𝐸𝑛𝑒𝑟𝑔𝑦
𝐴𝑣𝑒. 𝑙𝑜𝑎𝑑 =
𝑛𝑜. 𝑜𝑓 ℎ𝑜𝑢𝑟𝑠
500,000𝑘𝑊 − ℎ𝑟𝑠
𝐴𝑣𝑒. 𝑙𝑜𝑎𝑑 =
24ℎ𝑟𝑠
𝐴𝑣𝑒. 𝑙𝑜𝑎𝑑 = 20,833.33𝑘𝑊 𝑜𝑟 20.83𝑀𝑊
PROBLEM39
PRIME#5. A distribution transformer supplies a group of general power customers have a connected
load of 186 kW. Demand factor and diversity factor are 0.75 and 1.5 respectively. If the load factor for the
group will average 45% and the energy sells 3 1/2 cents per kW-hr, what will be the monthly income (30-
day) from energy delivered through this transformer? Assume average motor efficiency is 75%
Solution:
= 0.75 ( 186 )
= 139.50 kW
139.50
=
1.5
= 93 kw
= 124 kW
Average Load on transformer
= 0.45 ( 124 )
= 55.8 kW
Thus;
Annuual Capacity Factor = Annual Energy Produced/ KW plant capacity x 8760 hrs
= 500,000,00/ 150,000(8760)
Solution:
𝐴𝑛𝑛𝑢𝑎𝑙 𝑘𝑊 − ℎ𝑟𝑠
Plant Use Factor =
𝑘𝑊 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦𝑥𝑁𝑜. 𝑜𝑓 ℎ𝑟𝑠 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛
𝐴𝑛𝑛𝑢𝑎𝑙 𝐸𝑛𝑒𝑟𝑔𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑑
Plant Capacity Factor =
𝑘𝑊 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦𝑥8760 ℎ𝑟𝑜𝑠
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟
No. of hrs. Operation = 8760( )
𝑈𝑠𝑒 𝐹𝑎𝑐𝑡𝑜𝑟
0.424
No. of hrs. Operation = 8760( )
0.485
A central station has an annual factors as follows: Load factor58.5%, capacity factor 40.9%, use
factor 45.2%. The reversed carried over and above the peak load is 8,900 kW. Find the no. Of
hous per year not in service.
Solution:
Where:
Then,
LoadFactor PeakLoad
Capacity Factor =
PeakLoad Re serve
0.585 PeakLoad
0.409
PeakLoad 8900
PeakLoad 20,682.38kW
hrs
AnnualkW hrs 12,099.19kW 8760
yr
hrs
AnnualkW hrs 105,988,924.5kW
yr
From,
AnnualkW hrs
Use factor=
InstalledC apacity No.ofhrsopeartion
AnnualkW hrs
0.452
InstalledC apacity No.ofhrsopeartion
hrs
No.ofhrsopeartion 7926.63
yr
Then,
Hrs per year not in service = 8760-929.63 hrs/year
Thus,