Department of Education

Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Description: Construction of flower boxes and Repair of bulletin board


Name of Recipients: Katidtuan Central Elementary School
Project Duration: 8 days
Date Started:
Date of Completion:
Project Cost:

Materials for Construction of Flower boxes

No. Unit Quantity Description of Materials Unit Cost Total

1 load 1 Sand and Gravel 2,700.00 2,700.00


2 pcs 20 Cement 230.00 4,600.00
3 length 18 Round Bar 9mm 140.00 2,520.00
4 pcs 1000 CHB 11.00 11,000.00
5 kl 1 Tire Wire 92.00 92.00

Sub. Total 20,912.00

B. Labor Cost: 5,000.00


C. Total Cost: 25,912.00

Materials for the Repair of Bulletin Board


No. Unit Quantity Description of Materials Unit Cost Total
1 length 1 Square Tube (2x2) 610.00 610.00
2 length 3 Tubular (2x3) 555.00 1,665.00
3 length 6 Tubular (1x2) 317.50 1,905.00
4 pcs 8 Corrogated Sheet 267.50 2,140.00
5 pcs 50 TEKS Screw 2.50 125.00
6 pcs 2 Plywood (Marine 10mm) 649.00 1,298.00
7 gal 1 Slating Paint 650.00 650.00

Sub. Total 8,393.00

B. Labor Cost: 2,000.00


C. Total Cost: 10,393.00

Prepared by: Noted by:

EVELYN E. BAREZ BERNARDINO R. AGUILAR


Principal I DepEd Project Engineer

Approved by:

Engr. NEMESIO R. JAROMAY


Division Engineer
Department of Education
Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Descripti Rewiring of Academic Building


Name of RecipienKatidtuan Central Elementary School
Project Duration:8 days
Date Started:
Date of Completion:
Project Cost:

Materials for Rewiring


No. Unit Quantity Description of Materials Unit Cost Total
1 pcs 5 Single Enclosure 150.00 750.00
2 pcs 5 Breaker 20 apms 350.00 1,750.00
3 pcs 1 Service Drop Wire #6 1,800.00 1,800.00
4 m 40 TW 38 black and white 63.00 2,520.00
5 pcs 5 Entrance cap 3/4 40.00 200.00
6 pcs 5 PVC Pipe 3/4 90.00 450.00
7 pcs 5 PVC Elbow 30.00 150.00
8 pcs 5 L-B 3/4 50.00 250.00
9 pcs 30 PVC Clamp 3/4 3.00 90.00
10 pcs 20 Wood Screw 3/4 1.00 20.00
11 pcs 5 Junction Box 40.00 200.00
12 pcs 100 PDX wire #14 40.00 4,000.00
13 pcs 5 Screw Insulator Big 35.00 175.00

14 set 2 Secondary Rock with Spool Single 130.00 260.00

15 box 5 Staple Wire #1 50.00 250.00


16 pcs 5 Receptague 4x4 35.00 175.00
17 pcs 5 Thunder Switch Ccon. Outlet 35.00 175.00
18 pcs 5 Con Outlet 3 gang 60.00 300.00
19 pcs 10 St. Connector 35.00 350.00
20 pcs 4 Electrical Tape Big 40.00 160.00
Sub. Total 14,025.00

B. Labor Cost: 7,000.00


C. Total Cost: 21, 025.00

Prepared by: Noted by:

EVELYN E. BAREZ Engr. BERNARDINO R. AGUILAR


Principal I DepEd Project Engineer

Approved by:

Engr. NEMESIO R. JAROMAY


Division Engineer
O R. AGUILAR
t Engineer
Department of Education
Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Description: INSTALLATION OF THE DENTAL CLINIC


Name of Recipients: Katidtuan Central Elementary School
Project Cost: 8,520.00

1. MASONRY
No. Unit Quantity Description of Materials Unit Cost Total
1 cubic 2 Sand and Gravel 450.00 900.00
2 pcs 100 CHB 15.00 1,500.00

Sub. Total 2,400.00

2. HARDWARE MATERIALS
No. Unit Quantity Description of Materials Unit Cost Total
3 bags 10 Cement 210.00 2,100.00
4 length 10 Round Bar (9mm) 96.00 960.00
5 kilo 1 Tire Wire 60.00 60.00

Sub -Total 3,120.00


Labor 3,000.00
TOTAL 8,520.00

Prepared by:

NOREEN M. DAPUN Noted by:


School Supply Officer
EVELYN E. BAREZ
Principal I
Department of Education
Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Description: TILE WORK OF THE FLOORING


Name of Recipients: Katidtuan Central Elementary School
Project Cost: 64,050.00

No. Unit Quantity Description of Materials Unit Cost Total


1 pcs 215 Tiles ( 60x60) 160.00 34,400.00

2 bags 10 Tile Adhesive 270.00 2,700.00

3 bags 20 Cement 210.00 4,200.00

4 kls 6 Tile Grout 75.00 450.00

5 pcs 5 Tile Cutter 480.00 2,400.00

6 cubic 2 Fine Sand 450.00 900.00

Sub -Total 45,050.00

Labor 19,000.00

Total 64,050.00

Prepared by:

NOREEN M. DAPUN Noted by:


School Supply Officer
EVELYN E. BAREZ
Principal I
Department of Education
Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Description: WINDOW AND DOOR GRILLING


Name of Recipients: Katidtuan Central Elementary School
Project Cost: 20,070.00

No. Unit Quantity Description of Materials Unit Cost Total


1 pcs 20 Square Tube (1x1) 310.00 6,200.00
2 pcs 25 Square Bar 1/4 150.00 3,750.00
3 box 1 Welding Rod 750.00 750.00
4 pcs 10 Steel Cutter 90.00 900.00
5 f 2 Sand Paper #60 65.00 130.00
6 gal 1 Acrylic Paint(Jet Black) 1,000.00 1,000.00
7 gal 2 Acrylic Paint Thinner 460.00 920.00
8 gal 1 Polytop 620.00 620.00
Sub Total 14,270.00
Labor 5,800.00
GRAND TOTAL 20,070.00

Prepared by:

NOREEN M. DAPUN Noted by:


School Supply Officer
EVELYN E. BAREZ
Principal I
Department of Education
Region XII
Cotabato Division
Katidtuan Central Elementary School
Katidtuan, Kabacan Cotabato

PROGRAM OF WORKS

Project Description: PURCHASE AND INSTALLATION OF AIRCON


Name of Recipients: Katidtuan Central Elementary School
Project Cost: 36,199.00

No. Unit Quantity Description of Materials Unit Cost Total

1 pcs 1 Aircon 23,849.00 23,849.00

2 pcs 1 Circuit Braker 1,500.00 1,500.00

3 Meter 5 Thin Wire 30.00 150.00

4 pcs 1 AC Outlet 200.00 200.00

Sub Total 25,699.00

Labor 10,500.00

GRAND TOTAL 36,199.00

Prepared by:

NOREEN M. DAPUN Noted by:


School Supply Officer
EVELYN E. BAREZ
Principal I