PROJECT:

Labours productivity

Material Req'd
GROUP Working Nos. of days
S# Activities Trade Quantity done Unit Available this Material Next Productivity
NUM hours to Complete
Week Week

Dry Partition
Wall partition
1 Partition suspension Finshing C/P 3 8 40 M.2 13.3

2 Board installation Finshing C/P 3 8 60 M.2 20.0


False ceiling
1 Ceiling suspension Finshing C/P 3 8 20 M.2 6.7

2 Board installation Finshing C/P 3 8 30 M.2 10.0

Moulding cornice works

1 Moulding fabrication Finshing C/P 3 8 35 L.M 11.7

2 Moulding installation Finshing C/P 3 8 25 M.2 8.3

Block works
Hollow and thermal block
1 Hollow & thermal block works Mason 2 8 110 Nos 55.0
Solid bolck
1 Solid block works Mason 2 8 80 Nos 40.0

Plaster works

1 Plaster works by plaster machine Mason 2 8 9 M.2 4.5

2 Plaster works by hand mixing Mason 2 8 8 M.2 4.0

Marble tiles works


Flooring tiles
1 Flooring Marble tiles installing Mason 2 8 7 M.2 3.5
Wall tiles
1 Wall Marble installing Mason 2 8 6 M.2 3.0

Paint works

1 Basecoat painter 1 8 10 M.2 10.0

1 Paint primer painter 1 8 100 M.2 100.0

2 Paint stucco painter 1 8 30 M.2 30.0

3 Paint final painter 1 8 60 M.2 60.0