Sample Bar List in Excel File

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 52

BAR - LIST

Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
APPROACH WALL

A=1,550
1 F1 D16 L=2.550 36 1.578 144.86
B=1,000
L=2,550
A=1,550
2 F1.1 D16 L=2.050 76 1.578 245.85
B=500
L=2,050

A=2,700
3 F2 D16 L=2.700 80 1.578 340.85
L=2,700

A=2,700
4 F3 D16 L=2.700 80 1.578 340.85
L=2,700

A=1,850
5 F4 D16 L=1.850 140 1.578 408.70

L=1,850
A=870
6 F5 D16 L=0.870 84 1.578 115.32

L=0,870
A=1,500
7 F6 D16 L=1.500 148 1.578 350.32
L=1,500
A=4,450
8 F7 D14 L=5.050 2 1.208 12.20 B=600
125˚
L=5,050
A=4,580
9 F8 D14 L=5.180 2 1.208 12.51 B=600
125˚
L=5,180
A=4,720
10 F9 D14 L=5.320 2 1.208 12.85 B=600
125˚
L=5,320
A=5,480
11 F10 D14 L=6.080 2 1.208 14.69 B=600
125˚
L=6,080
A=2,600
12 F11 D14 L=3.200 2 1.208 7.73 B=600
125˚
L=3,200

A=2,730
13 F12 D14 L=3.330 2 1.208 8.05 B=600
125˚
L=3,330

A=2,870
14 F13 D14 L=3.470 2 1.208 8.38 B=600
125˚
L=3,470
A=3,000
15 F14 D14 L=3.600 2 1.208 8.70 B=600
125˚
L=3,600
A=3,140
16 F15 D14 L=3.740 2 1.208 9.04 B=600
125˚
L=3,740
A=3,270
17 F16 D14 L=3.870 2 1.208 9.35 B=600
125˚
L=3,870
A=3,400
18 F17 D14 L=4.000 2 1.208 9.66 B=600
125˚
L=4,000
A=9,880
19 F18 D14 L=9.880 2 1.208 23.87
L=9,880
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=10,180
20 F19 D14 L=10.180 2 1.208 24.59

L=10,180

A=10,480
21 F20 D14 L=10.480 2 1.208 25.32

L=10,480

A=10,780
22 F21 D14 L=10.780 2 1.208 26.04

L=10,780

A=10,780
23 F22 D14 L=11.380 4 1.208 54.99 B=600
125˚
L=11,380

A=10,180
24 F23 D14 L=11.180 2 1.208 27.01 B=1,000
125˚
L=11,180

A=10,480
25 F24 D14 L=11.610 2 1.208 28.05 B=1,130
125˚
L=11,610

A=10,780
26 F25 D14 L=12.040 2 1.208 29.09 B=1,260
125˚
L=12,040

A=5,610
27 F26 D14 L=5.610 2 1.208 13.55

L=5,610

A=5,910
28 F27 D14 L=5.910 2 1.208 14.28

L=5,910

A=6,210
29 F28 D14 L=6.210 2 1.208 15.00

L=6,210

A=6,510
30 F29 D14 L=6.510 2 1.208 15.73

L=6,510

A=6,810
31 F30 D14 L=6.810 2 1.208 16.45

L=6,810

A=7,110
32 F31 D14 L=7.110 2 1.208 17.18

L=7,110

A=7,375
33 F32 D14 L=7.375 2 1.208 17.82
L=7,375
A=100

34 W1 D16 L=7.700 36 1.578 437.42 C=700


B=6,900
L=7,700
A=4,850
35 W2 D14 L=5.550 64 1.208 429.08 B=700
125˚
L=5,550
A=3,440
36 W3 D14 L=4.140 2 1.208 10.00 B=700
125˚
L=4,140
A=3,490
37 W4 D14 L=4.190 2 1.208 10.12 B=700
125˚
L=4,190

A=3,540
38 W5 D14 L=4.240 2 1.208 10.24 B=700
125˚
L=4,240
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=3,590
39 W6 D14 L=4.290 2 1.208 10.36 B=700
125˚
L=4,290

A=3,640
40 W7 D14 L=4.340 2 1.208 10.49 B=700
125˚
L=4,340
B= 6900 to 7400 A=100

41 W8 D16 L=7.950 76 1.578 953.43 C=700


B=7,150
L=7,950

A=10,800
42 W9 D14 L=11.500 52 1.208 722.38 B=700
125˚
L=11,500

A=7,000
43 W9.1 D14 L=7.000 2 1.208 16.91

L=7,000

A=10,840
44 W9.2 D14 L=11.540 12 1.208 167.28 B=700
125˚
L=11,540

A=8,200
45 W10 D14 L=8.900 2 1.208 21.50 B=700
125˚
L=8,900

A=8,300
46 W11 D14 L=9.000 2 1.208 21.74 B=700
125˚
L=9,000

A=8,400
47 W12 D14 L=9.100 2 1.208 21.99 B=700
125˚
L=9,100

A=8,500
48 W13 D14 L=9.200 2 1.208 22.23 B=700
125˚
L=9,200

A=8,600
49 W14 D14 L=9.300 2 1.208 22.47 B=700
125˚
L=9,300

A=8,820
50 S1 D16 L=8.820 105 1.578 1,461.39

L=8,820
A= 277 to 8,515

51 S1.1 D16 L=4.396 40 1.578 277.48 A=4,396

L=4,396

A=10,300
52 S2 D16 L=10.300 32 1.578 520.11
L=10,300
A= 8,240 to 12,000

53 S3 D16 L=10.120 21 1.578 335.36 A=10,120


L=10,120
B= 920 to 3000
54 S3.1 D16 L=13.960 11 1.578 242.32 A=12,000 650
B=1,960
L=13,960
B= 1000 to 7500
55 S4 D16 L=16.250 32 1.578 820.56 A=12,000 650
B=4,250
L=16,250
A=1,040
56 CW1 D16 L=1.340 38 1.578 80.35
B=300
L=1,340

A=5,408
57 CW2 D14 L=5.408 8 1.208 52.26
L=5,408

A=1,800
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
58 CW3 D16 L=2.100 148 1.578 490.44
B=300
L=2,100

A=12,000 B=3,100
59 CW4 D14 L=15.100 8 1.208 145.93
600
L=15,100

A=10,300
60 CW5 D14 L=10.300 8 1.208 99.54

L=10,300
A=12,000 B=7,000
61 CW6 D14 L=19.000 8 1.208 183.62
600
L=19,000
D14 2,440.30
TOTAL
D16 7,565.59

TOTAL WEIGHT OF APPROACH WALL 10,005.89

REGULATION PART

A=2,850
62 F1 D16 L=3.350 67 1.578 354.18 RHS-W
B=500
L=3,350

A=1,850
63 F1.1 D16 L=2.350 7 1.578 25.96 LHS-W
B=500
L=2,350

A=2,050
(LHS & RHS)-
64 F2 D16 L=2.050 88 1.578 284.67 W

L=2,050

A=3,050
(LHS & RHS)-
65 F3 D16 L=3.050 88 1.578 423.54 W

L=3,050

A=1,500
(LHS & RHS)-
66 F4 D16 L=1.500 176 1.578 416.59 W

L=1,500

A=870
67 F5 D16 L=0.870 46 1.578 63.15 RHS-W

L=0,870

A=1,850
(LHS & RHS)-
68 F6 D16 L=1.850 176 1.578 513.80 W

L=1,850

A=12,000
B=1,400 (LHS & RHS)-
69 F7 D14 L=13.400 12 1.208 194.25 W
600
L=13,400

A=2,000
70 F8 D14 L=2.000 3 1.208 7.25 RHS-W

L=2,000
A=827
C=2,600
71 F8.1 D14 L=4.050 6 1.208 29.35 B=470 153˚ RHS-W

L=4,050

A=6,000
72 F8.2 D14 L=6.000 3 1.208 21.74 RHS-W

L=6,000

A=12,000
B=1,400 (LHS & RHS)-
73 F9 D14 L=13.400 14 1.208 226.62 W
600
L=13,400

A=1,000
74 F10 D14 L=1.000 3 1.208 3.62 RHS-W

L=1,000

A=1,250
75 F11 D16 L=1.250 4 1.578 7.89 RHS-W
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
75 F11 (mm)
D16 L=1.250 4 (kg/m)
1.578 7.89 RHS-W

L=1,250

A=1,120
76 F12 D14 L=1.120 58 1.208 78.47 LHS-W

L=1,120

A=2,170
77 F13 D14 L=2.170 3 1.208 7.86 LHS-W

L=2,170
C=628 A=650

78 F14 D14 L=4.248 3 1.208 15.39 R=400 LHS-W


B=2,970
L=4,248
A=1,450

79 F15 D14 L=2.150 3 1.208 7.79 C=700 LHS-W

L=2,150
A=5,000

80 F16 D14 L=8.963 4 1.208 43.31 166˚ C=3,963 LHS-W

L=8,963

A=3,650
81 F17 D16 L=3.650 67 1.578 385.90 LHS-W

L=3,650

A=1,550
82 F18 D16 L=1.550 18 1.578 44.03 LHS-W

L=1,550

A=3,050
83 F19 D16 L=3.050 14 1.578 67.38 LHS-W

L=3,050
A=500
84 F20 D16 L=0.850 4 1.578 5.37 C=350 LHS-W

L=0,850

A=650
85 F21 D16 L=0.650 8 1.578 8.21 RHS-W

L=0,650

A=1,400
86 F22 D16 L=1.400 3 1.578 6.63 RHS-W

L=1,400

A=12,000
B=1,400
87 F23 D16 L=13.400 29 1.578 613.21 PEIR-1
650
L=13,400
A=4,200
88 F24 D16 L=4.200 88 1.578 583.23 PEIR-1

L=4,200
A=2,100
89 F25 D16 L=2.100 6 1.578 19.88 PEIR-1

L=2,100
A=4,200
90 F26 D16 L=4.200 7 1.578 46.39 PEIR-1

L=4,200
A=1,620
91 F27 D16 L=1.620 40 1.578 102.25 PEIR-1

L=1,620
A=1,250
92 F27.1 D16 L=1.250 11 1.578 21.70 PEIR-1

L=1,250
A=2,170
93 F28 D16 L=2.170 5 1.578 17.12 PEIR-1

L=2,170
C=628 A=600

94 F29 D16 L=4.198 5 1.578 33.12 R=400 PEIR-1


B=2,970
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit1.578
Weight Weight
No.
94 BarF29
code D16 Length(m)
L=4.198 Quantity
5 33.12(kg) Detail of Bar Bending Remark
PEIR-1
(mm) (kg/m)
L=4,198
A=1,450
95 F30 D16 L=2.150 5 1.578 16.96 C=700 PEIR-1

L=2,150

A=5,000
96 F31 D16 L=8.963 5 1.578 70.72 166˚
C=3,963 PEIR-1

L=8,963

A=1,700
97 F32 D16 L=1.700 10 1.578 26.83 PEIR-1

L=1,700

A=3,100
98 F33 D16 L=3.100 5 1.578 24.46 PEIR-1

L=3,100

A=1,250
99 F34 D16 L=1.250 7 1.578 13.81 PEIR-1

L=1,250

A=2,000
100 F35 D16 L=2.000 3 1.578 9.47 PEIR-1

L=2,000

A=1,870
101 F36 D16 L=1.870 46 1.578 135.74 PIER-1

L=1,870
A=2,000
102 F37 D16 L=2.000 6 1.578 18.94 PIER-1

L=2,000
A=827
C=2,600
103 F38 D16 L=4.050 12 1.578 76.69 B=470 153˚ PIER-1

L=4,050

A=6,000
104 F39 D16 L=6.000 6 1.578 56.81 PIER-1

L=6,000

A=1,850
105 F40 D16 L=2.350 97 1.578 359.71 PIER-1
B=500
L=2,350

A=3,650
106 F41 D16 L=3.650 64 1.578 368.62 PIER-1

L=3,650

A=1,550
107 F42 D16 L=1.550 36 1.578 88.05 PIER-1

L=1,550
A=3,050
108 F43 D16 L=3.050 28 1.578 134.76 PIER-1

L=3,050
A=500
109 F44 D16 L=0.850 5 1.578 6.71 C=350 PIER-1

L=0,850

A=650
110 F45 D16 L=0.650 10 1.578 10.26 PIER-1

L=0,650

A=1,400
111 F46 D16 L=1.400 3 1.578 6.63 PIER-1

L=1,400

A=12,000
B=1,400
112 F47 D16 L=13.400 66 1.578 1,395.58 PIER-2,3
650
L=13,400

A=4,800
113 F48 D16 L=4.800 176 1.578 1,333.09 PIER-2,3

L=4,800
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)

A=4,800
114 F49 D16 L=4.800 14 1.578 106.04 PIER-2,3

L=4,800

A=2,100
115 F50 D16 L=2.100 14 1.578 46.39 PIER-2,3

L=2,100

A=1,620
116 F51 D16 L=1.620 160 1.578 409.02 PIER-2,3

L=1,620
A=1,250
117 F51.1 D16 L=1.250 44 1.578 86.79 PIER-2,3

L=1,250
A=2,170
118 F52 D16 L=2.170 20 1.578 68.49 PIER-2,3

L=2,170
C=628 A=650
119 F53 D16 L=4.248 20 1.578 134.07 R=400 PIER-2,3
B=2,970
L=4,248
A=1,450
120 F54 D16 L=2.150 20 1.578 67.85 C=700 PIER-2,3

L=2,150

A=5,000
121 F55 D16 L=8.963 20 1.578 282.87 166˚
C=3,963 PIER-2,3

L=8,963

A=3,100
122 F56 D16 L=3.100 20 1.578 97.84 PIER-2,3

L=3,100

A=2,800
123 F57 D16 L=2.800 20 1.578 88.37 PIER-2,3

L=2,800

A=1,850
124 F58 D16 L=2.350 66 1.578 244.75 PIER-2,3
B=500
L=2,350

A=3,650
125 F59 D16 L=3.650 252 1.578 1,451.44 PIER-2,3

L=3,650

A=1,550
126 F60 D16 L=1.550 144 1.578 352.21 PIER-2,3

L=1,550
A=3,150
127 F61 D16 L=3.150 96 1.578 477.19 PIER-2,3

L=3,150
A=500
128 F62 D16 L=0.850 20 1.578 26.83 C=350 PIER-2,3

L=0,850

A=650
129 F63 D16 L=0.650 40 1.578 41.03 PIER-2,3

L=0,650

A=1,400
130 F64 D16 L=1.400 12 1.578 26.51 PIER-2,3

L=1,400

A=12,000 B=1,400
131 F65 D16 L=13.400 59 1.578 1,247.57 WEIR
600
L=13,400

A=5,300
132 F66 D16 L=5.300 204 1.578 1,706.13 WEIR

L=5,300
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=5,800
133 F67 D16 L=5.800 102 1.578 933.54 WEIR

L=5,800
A=2,170
134 F68 D16 L=2.170 59 1.578 202.03 WEIR

L=2,170
C=628 A=650
135 F69 D16 L=4.248 59 1.578 395.50 R=400 WEIR
B=2,970
L=4,248
A=1,450
136 F70 D16 L=2.150 59 1.578 200.17 C=700 WEIR

L=2,150

A=5,000
137 F71 D16 L=8.963 59 1.578 834.47 166˚
C=3,963 WEIR

L=8,963
A=500
138 F72 D16 L=0.800 59 1.578 74.48 C=300 WEIR

L=0,800

A=650
139 F73 D16 L=0.650 118 1.578 121.03 WEIR

L=0,650
A=1,500
140 F74 D16 L=1.500 288 1.578 681.70 WEIR

L=1,500
A=800
141 F75 D16 L=0.800 576 1.578 727.14 WEIR

L=0,800

B=150
142 F76 D16 L=0.450 384 1.578 272.68 A=300
WEIR

L=0,450
C=280
100
100
143 F77 D16 L=1.120 144 1.578 254.50 A=180 B=180 WEIR

D=280 L=1,120
A=1,000

144 W1 D16 L=8.600 22 1.578 298.56 C=1,200 RSW


B=6,400
L=8,600

A=7,400
145 W2 D16 L=7.400 26 1.578 303.61 RSW

L=7,400

A=12,000
B=1,400
146 W3 D14 L=13.400 30 1.208 485.62 RSW
600
L=13,400

A=3,464
147 W4 D14 L=3.914 26 1.208 122.93 RSW
B=450
L=3,914

A=3,400
148 W4.1 D14 L=3.400 4 1.208 16.43 RSW

L=3,400

A=8,168
149 W5 D14 L=8.618 24 1.208 249.85 RSW
B=450
L=8,618

A=8,168
150 W5.1 D14 L=8.168 4 1.208 39.47 RSW

L=8,168

A=1,468
151 W6 D14 L=1.918 3 1.208 6.95 RSW
B=450
L=1,918
A=1,000
RSW
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
152 W7 D16 L=6.850 19 1.578 205.38 RSW
B=5,850
L=6,850
A=400

153 W8 D16 L=7.700 19 1.578 230.86 B=7,300 RSW

L=7,700
A=100

154 W9 D16 L=2.100 19 1.578 62.96 C=800 RSW


B=1,200
L=2,100
A=6,031

155 W10 D14 L=8.431 3 1.208 30.55 B=1,200 C=1,200 RSW

L=8,431

A=6,200
156 W11 D14 L=6.200 4 1.208 29.96 RSW

L=6,200
A=1,100

157 W12 D14 L=3.500 4 1.208 16.91 B=1,200 C=1,200 RSW

L=3,500

A=6,200
158 W13 D14 L=6.200 3 1.208 22.47 RSW

L=6,200
A=800
159 W14 D16 L=8.400 4 1.578 53.02 C=1,200 RSW
B=6,400
L=8,400
A=7,500
160 W15 D16 L=7.500 8 1.578 94.68 LSW

L=7,500
A=3,050
161 W15.1 D16 L=3.050 8 1.578 38.50 LSW

L=3,050
A=3,700
162 W16 D16 L=3.700 22 1.578 128.45 LSW

L=3,700

A=7,216
163 W17 D16 L=7.216 44 1.578 501.02 LSW

L=7,216

A=12,000
B=1,400
164 W18 D14 L=13.400 30 1.208 485.62 LSW
600
L=13,400

A=6,130
165 W19 D14 L=6.130 10 1.208 74.05 LSW

L=6,130

A=4,600
166 W20 D14 L=5.150 14 1.208 87.10 LSW
B=550
L=5,150

A=3,680
167 W20.1 D14 L=3.980 14 1.208 67.31 LSW
B= 300
L=3,980

A=1,050
168 W21 D14 L=1.350 5 1.208 8.15 C=300 LSW

L=1,350

A=7,500
169 W22 D16 L=7.500 20 1.578 236.70 LSW

L=7,500

A=1,400
170 W23 D16 L=2.000 10 1.578 31.56 B=300 C=300 LSW

L=2,000
A=400

171 W24 D16 L=7.560 19 1.578 226.66 LSW


BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
171 W24 D16 L=7.560 19 1.578 226.66 B=7,160 LSW

L=7,560
A=1,150

172 W25 D16 L=5.450 19 1.578 163.40 LSW


B=4,300
L=5,450
A=100

173 W26 D16 L=2.500 19 1.578 74.96 C=1,000 LSW


B=1,400
L=2,500

A=6,200
174 W27 D14 L=6.200 6 1.208 44.94 LSW

L=6,200
A= 3510 to 5360
A=4,435
175 W28 D14 L=5.085 14 1.208 86.00 LSW
B=650
L=5,085

A=3,400
176 W28.1 D14 L=3.400 12 1.208 49.29 LSW

L=3,400
A= 6640 to 8800
A=7,720
177 W29 D14 L=8.170 17 1.208 167.78 LSW
B=450
L=8,170

A=4,300
178 W29.1 D14 L=4.300 4 1.208 20.78 LSW

L=4,300
A=1,150

179 W30 D16 L=7.350 5 1.578 57.99 C=1,200 LSW


B=5,000
L=7,350
A=1,100

180 W31 D14 L=3.500 6 1.208 25.37 B=1,200 C=1,200 LSW

L=3,500
A=2,480

181 W32 D14 L=3.080 3 1.208 11.16 B=300 C=300 LSW

L=3,080
A=250

182 W33 D16 L=0.850 10 1.578 13.41 B=300 C=300 LSW

L=0,850
A=150
183 W34 D16 L=0.750 10 1.578 11.84 B=300 C=300 LSW

L=0,750

A=3,500
184 W35 D16 L=3.500 6 1.578 33.14 LSW

L=3,500

A=3,700
185 W36 D16 L=3.700 2 1.578 11.68 LSW

L=3,700
A=1,400
186 W37 D14 L=2.000 14 1.208 33.82 B=300 C=300 LSW

L=2,000
A=1,250
187 W38 D14 L=1.850 12 1.208 26.82 B=300 C=300 LSW

L=1,850
A=1,200
188 W39 D16 L=1.960 2 1.578 6.19 LSW
60˚ B=700
L=1,960
A=4,040
189 W40 D14 L=4.040 2 1.208 9.76 LSW

L=4,040
A= 770 to 3900
A=2,335
190 W41 D16 L=2.735 8 1.578 34.53 B=400
LSW
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
190 W41 (mm)
D16 L=2.735 8 (kg/m)
1.578 34.53 LSW
B=400
L=2,735
A= 3250 to 6680
A=4,965
191 W42 D16 L=5.365 8 1.578 67.73 B=400
LSW

L=5,365
A=1,650
192 W43 D16 L=1.650 9 1.578 23.43 LSW

L=1,650
A=1,300
193 W44 D14 L=1.300 15 1.208 23.56 LSW

L=1,300
A=800
194 W45 D16 L=0.800 13 1.578 16.41 LSW

L=0,800
A=1,100
195 W46 D14 L=1.700 3 1.208 6.16 B=300 C=300 LSW

L=1,700
A=6,700
196 C1 D16 L=6.700 28 1.578 296.03 LSW

L=6,700

B=300 C=300
197 C2 D14 L=1.800 45 1.208 97.85 LSW
A=1,200
L=1,800

A=1,050
198 C3 D14 L=1.050 45 1.208 57.08 LSW

L=1,050
A=300

199 C4 D14 L=0.880 90 1.208 95.67 C=100 E=90 D=90 LSW

B=300
L=0,880
B=100 C=100
200 C5 D14 L=0.650 45 1.208 35.33 LSW
A=450
L=0,650
A=2,820
201 C6 D16 L=2.820 28 1.578 124.60 LSW

L=2,820
A=7,490
202 C7 D16 L=7.490 50 1.578 590.96 LSW

L=7,490

B=300 C=300
203 C8 D14 L=2.000 70 1.208 169.12 LSW
A=1,400
L=2,000

A=3,100
204 C9 D14 L=3.100 90 1.208 337.03 LSW

L=3,100

B=120 C=120
205 S1 D16 L=3.160 22 1.578 109.70 LSW
A=2,920
L=3,160
B=120 C=120
206 S2 D16 L=0.460 8 1.578 5.81 LSW
A=220
L=0,460
B=120 C=120
207 S3 D16 L=0.380 8 1.578 4.80 LSW
A=140
L=0,380

B=120 C=120
208 S4 D16 L=2.280 6 1.578 21.59 LSW
A=2,040
L=2,280

B=120
209 S5 D16 L=1.690 4 1.578 10.67 LSW
A=1,450
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3

209
Diameter Unit1.578
Weight Weight
No. BarS5
code D16 L=1.690
Length(m) 4
Quantity 10.67(kg) Detail of Bar Bending Remark
LSW
(mm) (kg/m)
L=1,690

B=120
210 S6 D16 L=1.130 4 1.578 7.13 LSW
A=890
L=1,130

B=120 C=120
211 S7 D16 L=0.780 34 1.578 41.85 LSW
A=540
L=0,780

B=120 C=120
212 S8 D16 L=0.680 34 1.578 36.48 LSW
A=440
L=0,680

B=120 C=120
213 S9 D16 L=0.380 34 1.578 20.39 LSW
A=140
L=0,380

A=3,650
214 P1 D16 L=3.650 65 1.578 374.38 PEIR-1

L=3,650

A=6,900
215 P2 D16 L=6.900 128 1.578 1,393.69 PEIR-1

L=6,900
A= 6680 to 3250
A=4,965
216 P3 D16 L=5.365 18 1.578 152.39 PEIR-1
B=400
L=5,365
A= 237 to 4000
A=2,119
217 P3.1 D16 L=2.519 14 1.578 55.64 PEIR-1
B=400
L=2,519

A=4,300
218 P4 D16 L=4.300 49 1.578 332.48 PEIR-1

L=4,300

A=6,700
219 P4.1 D16 L=6.700 33 1.578 348.90 PEIR-1

L=6,700

A=2,250
220 P5 D16 L=2.250 10 1.578 35.51 PEIR-1

L=2,250

B=450
221 P6 D16 L=4.655 12 1.578 88.15 PEIR-1
A=3,755
L=4,655
A= 2633 to 4640
222 P7 D16 L=4.937 12 1.578 93.48 B=650 PEIR-1
A=3,637
L=4,937
A= 4960 to 7212
223 P8 D16 L=6.986 14 1.578 154.33 B=450 PEIR-1
A=6,086
L=6,986

A=6,750
224 P8.1 D16 L=6.750 1 1.578 10.65 PEIR-1

L=6,750

A=2,050
225 P8.2 D16 L=2.050 3 1.578 9.70 PEIR-1

L=2,050

226 P9 D16 L=7.592 23 1.578 275.54 B=550 PEIR-1


A=6,492
L=7,592

227 P9.1 D16 L=2.018 12 1.578 38.21 C=550 PEIR-1


A=1,468
L=2,018

228 P9.2 D16 L=6.400 3 1.578 30.30 PEIR-1


A=6,400
L=6,400
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)

229 P10 D16 L=3.513 34 1.578 188.48 B=450 PEIR-1


A=2,613
L=3,513

230 P10.1 D16 L=2.450 3 1.578 11.60 PEIR-1


A=2,450
L=2,450

A=600
231 P11 D16 L=3.870 34 1.578 207.63 R=850 B=2,670 PEIR-1
C=600
L=3,870

A=600
232 P12 D16 L=3.478 23 1.578 126.23 R=725 B=2,278 PEIR-1
C=600
L=3,478

A=3,100
233 P13 D16 L=3.100 74 1.578 361.99 PEIR-1

L=3,100

A=1,550
234 P14 D16 L=1.550 58 1.578 141.86 PEIR-1

L=1,550

A=1,250
235 P15 D16 L=1.250 31 1.578 61.15 PEIR-1

L=1,250

A=950
236 P16 D16 L=0.950 31 1.578 46.47 PEIR-1

L=0,950
A=450
C=100
237 P17 D16 L=1.000 31 1.578 48.92 PEIR-1
B=450
L=1,000

A=3,500
238 P18 D16 L=3.500 9 1.578 49.71 PEIR-1

L=3,500

A=3,700
239 P18.1 D16 L=3.700 2 1.578 11.68 PEIR-1

L=3,700

A=1,726
240 P18.2 D16 L=2.176 12 1.578 41.20 PEIR-1
B=450
L=2,176

A=6,050
241 P19 D16 L=6.350 9 1.578 90.18 C=300 PEIR-1

L=6,350

A=1,450
242 P20 D16 L=2.050 35 1.578 113.22 B=300 C=300 PEIR-1

L=2,050

A=2,481
243 P21 D16 L=3.081 9 1.578 43.76 B=300 C=300 PEIR-1

L=3,081

A=1,700
244 P22 D16 L=2.300 8 1.578 29.04 B=300 C=300 PEIR-1

L=2,300
A=1,050
245 P23 D16 L=1.650 6 1.578 15.62 B=300 C=300 PEIR-1

L=1,650
A=4,200
246 P24 D16 L=4.800 1 1.578 7.57 B=300 C=300 PEIR-1

L=4,800
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=5,783
247 P25 D16 L=4.050 1 1.578 6.39 B=300 C=300 PEIR-1

L=6,383
A=3,750
248 P26 D16 L=4.050 3 1.578 19.17 C=300 PEIR-1

L=4,050
A=3,545
249 P27 D16 L=3.845 1 1.578 6.07 C=300 PEIR-1

L=3,845
A=450
250 P28 D16 L=1.050 8 1.578 13.26 B=300 C=300 PEIR-1

L=1,050
A=250
251 P29 D16 L=0.850 8 1.578 10.73 B=300 C=300 PEIR-1

L=0,850
A=3,650
252 P30 D16 L=3.650 66 1.578 380.14 PEIR-2,3

L=3,650
A=6,900
253 P31 D16 L=6.900 318 1.578 3,462.45 PEIR-2,3

L=6,900
A=2,590
254 P32 D16 L=2.590 40 1.578 163.48 PEIR-2,3

L=2,590
A= 2633 to 4540
A=3,587
255 P33 D16 L=4.237 48 1.578 320.89 PEIR-2,3
B=650
L=4,237
A=3,100
256 P34 D16 L=3.100 296 1.578 1,447.97 PEIR-2,3

L=3,100
A=3,760
257 P35 D16 L=4.210 48 1.578 318.88 PEIR-2,3
B= 450
L=4,210
A= 3200 to 6685
A=4,943
258 P36 D16 L=5.343 72 1.578 606.99 PEIR-2,3
B=400
L=5,343
A= 771 to 4000
A=2,386
259 P37 D16 L=2.786 56 1.578 246.15 PEIR-2,3
B=400
L=2,786
A=4,300
260 P38 D16 L=4.300 178 1.578 1,207.80 PEIR-2,3

L=4,300
A= 4535 to 6787
A=5,661
261 P39 D16 L=5.961 56 1.578 526.76 PEIR-2,3
B=300
L=5,961
A=6,750
262 P39.1 D16 L=6.750 4 1.578 42.61 PEIR-2,3

L=6,750
A=2,000
263 P39.2 D16 L=2.000 12 1.578 37.87 PEIR-2,3

L=2,000
A=2,800
264 P40 D16 L=2.800 58 1.578 256.27 PEIR-2,3

L=2,800
A=2,710
264 P40.1 D16 L=2.710 58 1.578 248.03 PEIR-2,3

L=2,710

A=600
265 P41 D16 L=5.598 68 1.578 600.69 R=1,400 B=4,398 PEIR-2,3
C=600
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


265 P41 Diameter
D16 L=5.598 68 Unit1.578 600.69
Weight Weight PEIR-2,3
No. Bar code Length(m) Quantity (kg) Detail of Bar Bending Remark
(mm) (kg/m)
L=5,598

A=600
266 P42 D16 L=4.813 36 1.578 273.42 R=1,150 B=3,613 PEIR-2,3
C=600
L=4,813

A=3,600
267 P43 D16 L=3.600 30 1.578 170.42 PEIR-2,3

L=3,600

A=3,700
268 P43.1 D16 L=3.700 8 1.578 46.71 PEIR-2,3

L=3,700

A=6,050
269 P44 D16 L=6.350 34 1.578 340.69 PEIR-2,3
B=300
L=6,350
A=2,300

270 P45 D16 L=2.900 70 1.578 320.33 B=300 C=300 PEIR-2,3

L=2,900

A=2,480
271 P46 D16 L=3.080 24 1.578 116.65 B=300 C=300 PEIR-2,3

L=3,080
A=2,800

272 P47 D16 L=3.400 16 1.578 85.84 B=300 C=300 PEIR-2,3

L=3,400
A=250

273 P48 D16 L=0.850 32 1.578 42.92 B=300 C=300 PEIR-2,3

L=0,850
A=300

274 P49 D16 L=0.900 16 1.578 22.72 B=300 C=300 PEIR-2,3

L=0,900

A=3,783
275 P50 D16 L=4.383 4 1.578 27.67 B=300 C=300 PEIR-2,3

L=4,383

A=5,430
276 P51 D16 L=6.030 4 1.578 38.06 B=300 C=300 PEIR-2,3

L=6,030

A=576
277 P52 D16 L=1.176 4 1.578 7.42 B=300 C=300 PEIR-2,3

L=1,176

A=723
278 P53 D16 L=1.323 4 1.578 8.35 B=300 C=300 PEIR-2,3

L=1,323

A=833
279 P54 D16 L=1.433 4 1.578 9.05 B=300 C=300 PEIR-2,3

L=1,433

A=915
280 P55 D16 L=1.515 4 1.578 9.56 B=300 C=300 PEIR-2,3

L=1,515

A=976
281 P56 D16 L=1.576 4 1.578 9.95 B=300 C=300 PEIR-2,3

L=1,576

A=1,015
282 P57 D16 L=1.615 4 1.578 10.19 B=300 C=300 PEIR-2,3

L=1,615
A=6,000
283 P58 D16 L=6.600 6 1.578 62.49 B=300 C=300 PEIR-2,3

L=6,600
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)

A=1,200
284 P59 D16 L=1.960 10 1.578 30.93 PEIR-2,3
60˚ B=700
L=1,960

A=4,040
285 P60 D16 L=4.040 10 1.578 63.75 PEIR-2,3

L=4,040

A=800
286 P61 D16 L=0.800 65 1.578 82.06 PEIR-2,3

L=0,800

A=1,650
287 P62 D16 L=1.650 80 1.578 208.30 PEIR-2,3

L=1,650

A=1,300
288 P63 D16 L=1.300 60 1.578 123.08 PEIR-2,3

L=1,300

A=800
289 B1 D16 L=0.800 120 1.578 151.49 BEARING

L=0,800

A=800
290 B2 D16 L=0.800 120 1.578 151.49 BEARING

L=0,800
A=1,250

291 BR1 D22 L=2.070 60 2.984 370.61 C=120 BRACKET


B=700
L=2,070

A=120 116˚
292 BR2 D22 L=1.518 60 2.984 271.78 B=1,398 BRACKET

L=1,518
B= 100 to 500
A=800
293 BR3 D22 L=1.400 96 2.984 401.05 B= A=300 B= A=300 BRACKET

L=1,400

A=100
294 BR4 D14 L=0.627 12 1.208 9.09 B=427 BRACKET
C=100
L=0,627

A=100
295 BR5 D14 L=0.477 12 1.208 6.91 B=277 BRACKET
C=100
L=0,477

A=3,100
296 BW1 D16 L=3.100 46 1.578 225.02 BRAST WALL

L=3,100

B=100 C=100
297 BW2 D16 L=3.500 26 1.578 143.60 BRAST WALL
A=3,300
L=3,500
D14 3,692.55

TOTAL D16 41,747.73

D22 1,043.45

TOTAL WEIGHT OF REGULATION 46,483.73

CHUT WAY

A=1,550
298 F1 D16 L=2.050 134 1.578 433.48
B=500
L=2,050
A=1,550
299 F1.1 D16 L=2.550 70 1.578 281.67
B=1,000
L=2,550
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
B= 1,550 to 3,000
A=2,275
300 F1A D16 L=3.025 30 1.578 143.20
B=750
L=3,025
A=1,550
301 F1B D16 L=2.300 106 1.578 384.72
B=750
L=2,300
A=2,700
302 F2 D16 L=2.700 320 1.578 1,363.39
L=2,700
A=2,700
303 F3 D16 L=2.700 320 1.578 1,363.39
L=2,700
A=2,350
304 F4 D16 L=2.350 100 1.578 370.83
L=2,350
A=10,350
305 F5 D14 L=10.350 4 1.208 50.01
L=10,350
A=10,550
306 F5.1 D14 L=10.550 4 1.208 50.98
L=10,550
A=10,350
307 F6 D14 L=10.350 9 1.208 112.53
L=10,350

A=10,550
308 F6.1 D14 L=10.550 9 1.208 114.70
L=10,550

A=1,500
309 F7 D16 L=1.500 268 1.578 634.36

L=1,500
A=1,850
310 F8 D16 L=1.850 118 1.578 344.48

L=1,850
A=870
311 F9 D16 L=0.870 134 1.578 183.96
L=0,870
A=5,580
C=3,062
312 F10 D14 L=8.642 13 1.208 135.71 166˚

L=8,642
A=5,795
C=3,088
313 F11 D14 L=8.883 14 1.208 150.23 172˚

L=8,883
A=5,580
C=3,062
314 F12 D14 L=8.642 3 1.208 31.32 166˚

L=8,642
A=1,750
315 F13 D16 L=1.750 268 1.578 740.08
L=1,750
A=1,120
316 F14 D16 L=1.120 134 1.578 236.83
L=1,120

A=8,813
317 F15 D14 L=8.813 4 1.208 42.58

L=8,813

A=1,550
318 F16 D16 L=1.550 386 1.578 944.12

L=1,550

A=4,430
319 F17 D14 L=4.430 13 1.208 69.57
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
319 F17 (mm)
D14 L=4.430 13 (kg/m)
1.208 69.57

L=4,430
A=1,400
C=2,900
320 F18 D14 L=4.300 12 1.208 62.33 166˚

L=4,300

A=4,430
321 F19 D14 L=4.430 7 1.208 37.46

L=4,430

A=4,350
322 F20 D14 L=4.350 13 1.208 68.31

L=4,350

A=4,240
323 F21 D14 L=4.240 12 1.208 61.46

L=4,240

A=4,350
324 F22 D14 L=4.350 7 1.208 36.78

L=4,350

A=12,000 B=10,900
325 F23 D14 L=22.900 13 1.208 359.62
600
L=22,900

A=12,000 B=10,900
326 F24 D14 L=22.900 7 1.208 193.64
600
L=22,900

A=12,000 B=9,000
327 F25 D14 L=21.000 12 1.208 304.42
600
L=21,000

A=1,050
328 CW1 D16 L=1.350 72 1.578 153.38
B=300
L=1,350

A=10,550
329 CW2R D14 L=10.550 5 1.208 63.72

L=10,550

A=10,300
330 CW2L D14 L=10.300 5 1.208 62.21

L=10,300
A=1,800
331 CW3 D16 L=2.100 106 1.578 351.26
B=300
L=2,100

A=8,300
332 CW4 D14 L=8.300 7 1.208 70.18
L=8,300

A=10,300
333 CW5 D14 L=10.300 7 1.208 87.10

L=10,300
A=12,000 B=1,000
334 CW6 D14 L=13.000 7 1.208 109.93
600
L=13,000
A=12,000 B=1,000
335 S1 D16 L=13.000 115 1.578 2,359.11 SLAB
650
L=13,000
D= 200 to 1390
B=700 C=10,700
336 S1A D16 L=13.695 19 1.578 410.60 SLAB
A=1,500 D=795
L=13,695
A=8,810
337 S2 D16 L=8.810 101 1.578 1,404.12 SLAB

L=8,810
A=5,568
338 S2A D16 L=8.643 6 1.578 81.83 166˚ C=3,075 SLAB
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit1.578
Weight Weight
No.
338 BarS2A
code D16 Length(m)
L=8.643 Quantity
6 81.83(kg) Detail of Bar Bending Remark
SLAB
(mm) (kg/m)
L=8,643
A=4,438
339 S3 D16 L=4.438 107 1.578 749.34 SLAB

L=4,438
A=4,353
340 S4 D16 L=4.353 107 1.578 734.99 SLAB

L=4,353

A=12,000 B=12,000
341 S5 D16 L=24.000 107 1.578 4,052.30 SLAB
650
L=24,000

A=10,300
342 S6 D16 L=10.300 134 1.578 2,177.96 SLAB

L=10,300

A=8,300
343 S7 D16 L=8.300 134 1.578 1,755.05 SLAB

L=8,300

A=9,900
344 S8 D16 L=9.900 41 1.578 640.51 SLAB

L=9,900

A=12,000
345 S9 D16 L=12.000 34 1.578 643.82 SLAB

L=12,000
A=100

346 W1 D16 L=6.500 68 1.578 697.48 C=700


B=5,700
L=6,500

A=9,800
347 W2 D14 L=10.550 54 1.208 688.20
B=750
L=10,550

A=7,656
348 W3 D14 L=8.406 2 1.208 20.31
B=750
L=8,406

A=7,750
349 W4 D14 L=8.500 2 1.208 20.54
B=750
L=8,500

A=7,840
350 W5 D14 L=8.590 2 1.208 20.75
B=750
L=8,590

A=7,935
351 W6 D14 L=8.685 2 1.208 20.98
B=750
L=8,685

A=8,030
352 W7 D14 L=8.780 2 1.208 21.21
B=750
L=8,780
B= 5,100 to 4,700
A=100
353 W8 D16 L=5.700 11 1.578 98.94 C=700
B=4,900
L=5,700
B= 5,200 to 7,400
A=100
354 W8.1 D16 L=7.100 19 1.578 212.87 C=700
B=6,300
L=7,100

A=9,210
355 W9 D14 L=9.210 44 1.208 489.53

L=9,210
B= 530 to 5,430
A=600
356 W10 D14 L=3.580 9 1.208 38.92
B=2,980 174˚
L=3,580
A=5,580
C=3,075
357 W10.1 D14 L=8.655 2 1.208 20.91 166˚
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3

357 W10.1
Diameter
D14 L=8.655 2 Unit1.208
Weight Weight
20.91(kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
L=8,655
A=5,640
C=3,000
358 W11 D14 L=8.640 10 1.208 104.37 174˚

L=8,640
B= 4,686 to 5,968
A=100
359 W12 D16 L=6.127 30 1.578 290.05 C=700
B=5,327
L=6,127
A=1,950
C=600
360 W13 D14 L=2.550 1 1.208 3.08 166˚

L=2,550
A=3,670
C=600
361 W13.1 D14 L=4.270 1 1.208 5.16
166˚
L=4,270
A=5,380
C=600
362 W13.2 D14 L=5.980 1 1.208 7.22 166˚

L=5,980
A=7,100
C=600
363 W13.3 D14 L=7.700 1 1.208 9.30 166˚

L=7,700

A=8,810
364 W13.4 D14 L=8.810 1 1.208 10.64

L=8,810
B= 6,470 to 4,600
A=100
365 W14 D16 L=6.335 32 1.578 319.89 C=700
B=5,535
L=6,335

A=4,430
366 W15 D14 L=4.430 34 1.208 181.95

L=4,430
A=1,400
C=3,130
367 W16 D14 L=4.530 14 1.208 76.61 158˚

L=4,530

A=4,430
368 W17 D14 L=4.430 10 1.208 53.51
L=4,430
B= 4,600 to 5,600
A=100
369 W18 D16 L=5.900 32 1.578 297.93 C=700
B=5,100
L=5,900
A=850
370 W19 D14 L=1.450 1 1.208 1.75 166˚ B=600
L=1,450
A=1,850
371 W19.1 D14 L=2.450 1 1.208 2.96 166˚ B=600
L=2,450
A=2,850
372 W19.2 D14 L=3.450 1 1.208 4.17 166˚ B=600

L=3,450
A=3,850
373 W19.3 D14 L=4.450 1 1.208 5.38 166˚ B=600

L=4,450

A=4,350
374 W19.4 D14 L=4.350 1 1.208 5.25

L=4,350
A=4,220
375 W20 D14 L=4.220 44 1.208 224.30
L=4,220
A=4,350
376 W21 D14 L=4.350 10 1.208 52.55
L=4,350
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=100
377 W22 D16 L=6.500 150 1.578 1,538.55 B=5,700 C=700
L=6,500
A=11,250 B=11,650
378 W23 D14 L=23.650 54 1.208 1,542.74
C=750 600
L=23,650
A=11,250 B=6,620
379 W24 D14 L=18.620 2 1.208 44.99
C=750 600
L=18,620
A=11,250 B=6,720
380 W25 D14 L=18.720 2 1.208 45.23
C=750 600
L=18,720
A=11,250 B=6,820
381 W26 D14 L=18.820 2 1.208 45.47
C=750 600
L=18,820
A=11,250 B=6,920
382 W27 D14 L=18.920 2 1.208 45.71
C=750 600
L=18,920
A=11,250 B=7,020
383 W28 D14 L=19.020 2 1.208 45.95
C=750 600
L=19,020
END SILL

A=2,200
384 E1 D16 L=2.560 107 1.578 432.25
B=360
L=2,560
A=360
135˚ B=2,604
385 E2 D16 L=3.324 107 1.578 561.24
135˚
C=360
L=3,324
A=8,300
386 E3 D14 L=8.300 17 1.208 170.45
L=8,300
A=10,300
387 E4 D14 L=10.300 12 1.208 149.31
L=10,300
A=2,245
388 E4R D14 L=2.245 5 1.208 13.56
L=2,245
A=6,075
389 E4L D14 L=6.075 5 1.208 36.69
L=6,075
A=12,000 B=1,200
390 E5 D14 L=13.200 17 1.208 271.08
600
L=13,200
A=360
391 E6 D14 L=1.460 107 1.208 188.71 B=550 135˚ C=550
L=1,460
D14 6,964.25
TOTAL
D16 27,387.99

TOTAL WEIGHT OF CKUTE WAY 34,352.24

OVER BRIDGE

A=2,510
392 S1 D25 L=2.810 39 3.853 422.25
B=300
L=2,810
A=12,000 B=12,000
393 S2 D25 L=24.000 39 3.853 3,606.41
1200
L=24,000
A=11,500
394 S3 D25 L=12.000 39 3.853 1,803.20 B=500
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit3.853
Weight Weight
No.
394 BarS3
code D25 Length(m)
L=12.000 Quantity
39 (kg)
1,803.20 Detail of Bar Bending Remark
(mm) (kg/m)
L=12,000
A=11,700
395 S4 D22 L=12.000 39 2.984 1,396.51
B=300
L=12,000
A=12,000 B=12,000
396 S5 D22 L=24.000 39 2.984 2,793.02
1200
L=24,000

397 S6 D22 L=2.810 39 2.984 327.02 B=300


A=2,510
L=2,810

B=1,060 162˚ 162˚ C=1,060


398 H1 D22 L=2.801 38 2.984 317.61
A=681
L=2,801

B=1,060 162˚ 162˚ C=1,060


399 H2 D25 L=2.801 19 3.853 205.05
A=681
L=2,801
162˚
400 H3 D25 L=2.180 19 3.853 159.59 B=1,060 C=500
A=620
L=2,180
A=4,860
401 B1 D16 L=5.260 230 1.578 1,909.06 B=200 C=200
L=5,260
130 130
B=367 R=240 R=240 C=367
402 B2 D16 L=5.394 216 1.578 1,838.53
A=4,400
L=5,394

403 B3 D16 L=3.040 19 1.578 91.15 B=450 C=450


A=2,140
L=3,040
A=356
404 D1 D14 L=1.756 230 1.208 487.89 B=700 96˚ C=700
L=1,756
A=12,000 B=12,000 C=12,000
405 D2 D14 L=36.000 10 1.208 434.88
650 650
L=36,000

406 D3 D14 L=0.670 115 1.208 93.08 B=150 C=150


A=370
L=0,670
A=430
E=200 F=200
407 G1 D14 L=2.120 108 1.208 276.58 C=430 D=430
B=430
L=2,120
A=4,860
408 G2 D25 L=5.260 18 3.853 364.80 B=200 C=200
L=5,260

409 G3 D25 L=5.180 18 3.853 359.25 B=450 C=450


A=4,280
L=5,180
A=600
E=200 F=200
410 G4 D14 L=2.460 19 1.208 56.46 C=430 D=430
B=600
L=2,460
A=4,860
411 G5 D20 L=5.260 18 2.466 233.48 B=200 C=200
L=5,260

412 G6 D20 L=5.180 18 2.466 229.93 B=450 C=450


A=4,280
L=5,180

413 T1 D14 L=0.570 684 1.208 470.98 B=150 C=150


A=270
L=0,570

415 T2 D14 L=0.700 54 1.208 45.66 B=150 C=150


A=400
L=0,700
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
D14 1,865.53

D16 3,838.74

TOTAL D20 463.41

D22 4,834.16

D25 6,920.56

TOTALWEIGHT OFOVER BRIDGE 17,922.41

CHAIR BAR OF APPROACH WALL


A=1,200
416 CH1 D14 L=3.200 16 1.208 61.85 B=800 C=800
200 200
L=3,200
A=600
417 CH2 D14 L=2.600 16 1.208 50.25 B=800 C=800
200 200
L=2,600
A=300
418 CH3 D14 L=1.500 188 1.208 340.66 B=400 C=400
200 200
L=1,500
A=1,200
419 SU1 D14 L=1.200 16 1.208 23.19
L=1,200
A=3,200
420 SU2 D14 L=10.200 8 1.208 98.57 C=7,000
125˚
L=10,200
CHAIR BAR OF REGULATION PART
A=1,200
B=1,100 C=1,100
421 CH1 D16 L=3.800 34 1.578 203.88
200 200
L=3,800
A=600
B=1,100 C=1,100
422 CH2 D16 L=3.200 30 1.578 151.49
200 200
L=3,200
A=1,200
423 SU1 D14 L=1.200 30 1.208 43.49
L=1,200
A=12,000 B=1,400
424 SU2 D14 L=13.400 8 1.208 129.50
600
L=13,400
A=600
425 CH3 D16 L=5.570 18 1.578 158.21 B=2,285 C=2,285
200 200
L=5,570
A=600
426 CH4 D16 L=4.600 8 1.578 58.07 B=1,800 C=1,800
200 200
L=4,600
A=600
427 CH5 D16 L=3.640 14 1.578 80.41 B=1,320 C=1,320
200 200
L=3,640
CHAIR BAR OF CHUTE WAY PART
A=500
B=800 C=800
428 CH1 D14 L=2.500 24 1.208 72.48
200 200
L=2,500
A=1,200
B=800 C=800
429 CH2 D14 L=3.200 66 1.208 255.13
200 200
L=3,200
A=600
B=800 C=800
430 CH3 D14 L=2.600 60 1.208 188.45
200 200
L=2,600
A=300
B=400 C=400
431 CH4 D14 L=1.500 792 1.208 1,435.10
200 200
L=1,500
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remark
(mm) (kg/m)
A=300
B=660 C=660
432 CH5 D14 L=2.020 24 1.208 58.56
200 200
L=2,020
A=300
433 CH6 D14 L=2.620 24 1.208 75.96 B=960 C=960
200 200
L=2,620
A=300
434 CH7 D14 L=3.230 24 1.208 93.64 B=1,265 C=1,265
200 200
L=3,230
A=300
B=1,565 C=1,565
435 CH8 D14 L=3.830 24 1.208 111.04
200 200
L=3,830
A=300
B=1,790 C=1,790
436 CH9 D14 L=4.280 24 1.208 124.09
200 200
L=4,280
A=1,200
437 SU1 D14 L=1.200 66 1.208 95.67
L=1,200
A=5,568
438 SU2 D14 L=8.643 8 1.208 83.53 C=3,075
166˚
L=8,643
A=4,432
439 SU3 D14 L=4.432 8 1.208 42.83
L=4,432
A=4,347
440 SU4 D14 L=4.347 8 1.208 42.01
L=4,347

A=12,000 B=10,900
441 SU5 D14 L=22.900 8 1.208 221.31
600
L=22,900
D14 3,647.31
TOTAL
D16 652.06

TOTAL WEIGHT OF CHAIR BAR 4,299.37

DOWEL BAR OF CONTRACTION JOINT

A=500
442 DOWEL BAR D25 L=0.500 2296 3.853 4,423.24
L=0,500
D14 18,609.94
D16 81,192.12
TOTAL D20 463.41
D22 5,877.61
D25 11,343.81
TOTAL WEIGHT OF REINFOERCING BAR 117,486.88
ADD 3% 3,524.61

GRAND TOTAL 121,011


Remark
Remark
Remark
Remark

RHS-W

LHS-W

LHS & RHS)-


W

LHS & RHS)-


W

LHS & RHS)-


W

RHS-W

LHS & RHS)-


W

LHS & RHS)-


W

RHS-W

RHS-W

RHS-W

LHS & RHS)-


W

RHS-W

RHS-W
Remark
RHS-W

LHS-W

LHS-W

LHS-W

LHS-W

LHS-W

LHS-W

LHS-W

LHS-W

LHS-W

RHS-W

RHS-W

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1
Remark
PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-1

PIER-2,3

PIER-2,3
Remark

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

PIER-2,3

WEIR

WEIR
Remark

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

WEIR

RSW

RSW

RSW

RSW

RSW

RSW

RSW

RSW

RSW
Remark
RSW

RSW

RSW

RSW

RSW

RSW

RSW

RSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW
Remark
LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW
Remark
LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW

LSW
Remark
LSW

LSW

LSW

LSW

LSW

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1
Remark

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1
Remark

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-1

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3
PEIR-2,3
Remark

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3
Remark

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

PEIR-2,3

BEARING

BEARING

BRACKET

BRACKET

BRACKET

BRACKET

BRACKET

BRAST WALL

BRAST WALL
Remark
Remark

SLAB

SLAB

SLAB

SLAB
Remark
SLAB

SLAB

SLAB

SLAB

SLAB

SLAB

SLAB

SLAB
Remark
Remark
Remark
Remark
Remark
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remar
(mm) (kg/m)
CHAIR BAR OF APPROACH WALL
A=1,200
B=800 C=800
1 CH1 D14 L=3.200 16 1.208 61.85
200 200
L=3,200
A=600
B=800 C=800
2 CH2 D14 L=2.600 16 1.208 50.25
200 200
L=2,600
A=300
B=400 C=400
3 CH3 D14 L=1.500 188 1.208 340.66
200 200
L=1,500

A=1,200
4 SU1 D14 L=1.200 16 1.208 23.19

L=1,200

A=3,200
5 SU2 D14 L=10.200 8 1.208 98.57 C=7,000
125˚
L=10,200
CHAIR BAR OF REGULATION PART
A=1,200
B=1,100 C=1,100
6 CH1 D16 L=3.800 34 1.578 203.88
200 200
L=3,800
A=600
B=1,100 C=1,100
7 CH2 D16 L=3.200 30 1.578 151.49
200 200
L=3,200

A=1,200
8 SU1 D14 L=1.200 30 1.208 43.49

L=1,200

A=12,000 B=1,400
9 SU2 D14 L=13.400 8 1.208 129.50
600
L=13,400
A=600
B=2,285 C=2,285
10 CH3 D16 L=5.570 18 1.578 158.21
200 200
L=5,570
A=600
B=1,800 C=1,800
11 CH4 D16 L=4.600 8 1.578 58.07
200 200
L=4,600
A=600
B=1,320 C=1,320
12 CH5 D16 L=3.640 14 1.578 80.41
200 200
L=3,640
CHAIR BAR OF CHUTE WAY PART
A=500
B=800 C=800
13 CH1 D14 L=2.500 24 1.208 72.48
200 200
L=2,500
A=1,200
B=800 C=800
14 CH2 D14 L=3.200 66 1.208 255.13
200 200
L=3,200
A=600
B=800 C=800
15 CH3 D14 L=2.600 60 1.208 188.45
200 200
L=2,600
BAR - LIST
Project: Krang Ponley Water Resources Development P/J(Anlong Chrey Dam)

Location Structure No.3


Diameter Unit Weight Weight (kg)
No. Bar code Length(m) Quantity Detail of Bar Bending Remar
(mm) (kg/m)
A=300
B=400 C=400
16 CH4 D14 L=1.500 792 1.208 1,435.10
200 200
L=1,500
A=300
B=660 C=660
17 CH5 D14 L=2.020 24 1.208 58.56
200 200
L=2,020
A=300
B=960 C=960
18 CH6 D14 L=2.620 24 1.208 75.96
200 200
L=2,620
A=300
B=1,265 C=1,265
19 CH7 D14 L=3.230 24 1.208 93.64
200 200
L=3,230
A=300
B=1,565 C=1,565
20 CH8 D14 L=3.830 24 1.208 111.04
200 200
L=3,830
A=300
B=1,790 C=1,790
21 CH9 D14 L=4.280 24 1.208 124.09
200 200
L=4,280

A=1,200
22 SU1 D14 L=1.200 66 1.208 95.67

L=1,200

A=5,568
23 SU2 D14 L=8.643 8 1.208 83.53 C=3,075
166˚
L=8,643

A=4,432
24 SU3 D14 L=4.432 8 1.208 42.83

L=4,432

A=4,347
25 SU4 D14 L=4.347 8 1.208 42.01

L=4,347

A=12,000 B=10,900
26 SU5 D14 L=22.900 8 1.208 221.31
600
L=22,900
D14 3,647.31
TOTAL
D16 652.06

TOTAL WEIGHT OF CHAIR BAR 4,299.37

TOTAL WEIGHT OF REINFOERCING BAR 128.98

ADD 3% 4,428.35
Remark