STANDARD OPERATING
PROCEDURE
FOR
BA SEAL WATER PUMP
List of Contents
1. Objective
2. Scope
3. Responsibility
4. Safety PPE’s
5. Safety Precaution During operation
6. Description of the system
7. Prechecks and Action By Field Engineer
8. Operating Procedure
9. Abbreviations / Notations
10. Point to be checked by operator in every shift
11. Checking of system after shut down
1. Objective:
2. Scope:
3. Responsibility:
4. Safety PPE’s:
Ear Plugs, Safety Goggles & Hand Gloves.
5. Safety Precaution During operation:
Ensure no permit to work is pending on regarding this system by checking with EE/FE.
6. Description of the system:
Seal water is required for gland sealing of Vacuum pumps, clinker grinders, BA Overflow pumps etc.
So whenever Bottom Ash system, Esp Deashing system started then seal water pumps to be started
beforehand. The seal water pumps will run from main PLC HMI. One no. pressure indicator is
provided to monitor the pressure locally. For interlocking purpose one pressure switch is also
provided at the common header. There are two seal water pumps out of which one will be working at
a time.
TECHNICAL DETAILS
8. Operating Procedure:
9. Abbreviations / Notations:
EQUIPMENT CLEANING
FIRST ENSURE SLURRY AND ASH WATER SUMP CLEANING AND THEN FILL
THE SUMP.
CHECK THE LINE VACUUM AND SHUT OFF VACUUM OF ALL PASSES.