Professional Documents
Culture Documents
01-02&03 Introduction To PMP 5th-MAO PDF
01-02&03 Introduction To PMP 5th-MAO PDF
01-02&03 Introduction To PMP 5th-MAO PDF
Project Planning
1
Project Planning Project Planning
Planning Inputs and Outputs
Planning Major steps
INPUTS OUTPUTS
Contract information Activities
Determination of Project Activities (WHAT)
Drawings Relationships among activities
Specifications Method statement
Establishment of Logic; Relationships and overlap (WHEN)
Available resources Responsibility
PLANNING Reporting levels
Bills of quantities Presentation (Table, Network, Chart, …)
Project network diagram
Site reports
Activities duration
Organizational data Estimate Activities’ Duration and Cost (HOW)
Activities cost
Construction methods
Project is divided into segments of work called activities Types of construction activities:
Activity: Time-consuming single work element Production: taken directly from drawings and/or specifications
Guidelines for project breakdown: by: area of responsibility, structural Management (Approvals, site establishment, …etc).
Level of details depends on: planning stage, size of the project, complexity
2
Project Planning Code
10
Description
Set-up site
Predecessors
---
14 Procure RFT ---
16 Procure P.C. Beams ---
20 Excavate left abutment 10
Activities Relationships 30 Excavate right abutment 10
40 Excavate central pier 10
50 Foundation left abutment 14, 20
60 Foundation right abutment 14, 30
70 Foundation central pier 14, 40
80 Construct left abutment 50
The order in which project activities are to be performed
90 Construct right abutment 60
100 Construct central pier 70
Which activity(ies) must be completed before an activity can start
110 Erect left P.C. Beams 16, 80, 100
120 Erect right P.C. Beams 16, 90, 100
Which activity(ies) can not start until activity completion
140 Fill left embankment 80
150 Fill right embankment 90
Which activity(ies) have no logical relations
155 Construct deck slab 110, 120
160 Left road base 140
Logic constraints: Physical, and Resources
170 Right road base 150
180 Road surface 155, 160, 170
190 Bridge railing 155
200 Clear site 180, 190
SS SF
3
Project Planning Project Planning
A B
5 1 1 B depends on A
Two Types: 0 5
Activity-On-Arrow; AOA (Arrow Networks).
A C
Activity-On-Node; AON (Precedence Networks): 5 10 15 C depends on A and B
B
5
AOA 15
B B depends on A
Activity represented as arrows with start and finish nodes called A C C depends on A
5 10 15
Events
5 15
A C B depends on A and B
D depends on A and B
Activity A B 10 D
i j 15
j>i 5
4
Project Planning Project Planning
Project networks: AON Project networks: Example
10 20
A B
B depends on A
10 30 40
Activity Predecessors
C depends on A and
A C D
B
D depends on C A -
20 B -
B
30 C A, B
C D C
10 20 B depends on A
A B
E C
C depends on B
D depends on B F D
40 G D, E
D
Project Planning
Project networks: Example (AOA) Check - List
5
Example of a check list
Bar Charts
Activity Start Finish
It is a graphical presentation that is organized so
Proceeding
Quantity
Duration
Remark
activities
that:
Unit
No. description Plan actual Plan actual
1. All activities are listed in a column at the left.
1 Mobilization LS LS 5 ----- 1/12 3/12 6/12 9/12 Delay 2. A horizontal time scale is at the top & extends to
the right.
2 Excavation 400 m3 10 1 7/12 7/12 17/12 17/12 On 3. Activities are presented in bars that extend from
time activity schedule starting time to the finishing
3 PC. 200 m3 4 2 18/12 18/12 22/12 24/12 Delay time.
4. For progress reporting & control, another bar is
4 drawn for each activity to show the actual
performance time.
6
Two Types Of Bar Charts Types Of Bar Chart
Simple graphical presentation results in easy Because of their broad planning nature, they
general comprehension. become very cumbersome as the number of line
activities, or bars increases.
Good for of communication in the building
Logic sequence, interconnections and constrains
industry with basic understanding usually founds of various activities in the project is not
at all levels of management. expressed in the diagram.
Require less revision and updating than more It is difficult to be used for forecasting the
sophisticated system. effects that changes in a particular activity will
It is especially helpful in turbulent early stage of have on the overall schedule, or even to project
an engineering and construction project when the progress of an individual activity.
frequent changes and revisions are a fact of life. It is therefore limited as a control tool.
7
Progress Curves (S – Curves) Scheduled Cumulative Progress
100
15%
It shows measures of cumulative progress 90
0 1 2 3 4 5 6 7 8 9 10
25% 50% 25% Time (weeks)
8
Example:
750/15900
20% 70%
60%
15% 40%
15900 Lab-hrs
9
Peak Financing
10
% Delay
Delay
Lead
Project Scheduling
Scheduling = Planning + time
Project Scheduling Making corrective actions if schedule shows that the plan will result
in late completion
11
Project Scheduling Project Scheduling
The Critical Path Method (CPM) 1. CPM for Activity on Arrows
LTj
Most Widely used method for project scheduling ETi LTi ETj
x
Calculates the minimum completion time for a project
i dx j
Calculates activities timings
Forward path Backward path
Computer programs use CPM , handle large projects
ET for the first node = 0 LT for the last node = its ET
Forward path
ETj = ETi + dx LTi = LTj - dx
Backward path
ESx = ETi LFx = LTj
Float calculations
EFx = ESx + dx LSx = LFx - dx
Critical activates
Total time available for the activity = LF - ES the critical path is a continuous path of critical activities
TF = LF – EF = LS – ES
The critical path is the longest one in the network
FF = ETj – ETi – d
More than critical path can be formed
= smallest ES (of succeeding act.) – EF (of current act.)
12
Project Scheduling Project Scheduling
Example
ESi EFi ESj EFj
overlapij
i (di) j (dj)
LSi LFi LSj LFj
5
B d1
3
Forward path Backward path
A C E
1 3 9 11
d=3 4 5 ES for the first Activity = 0 LF for the last activity = its EF
D d2
6 EFi = ESi + di LSj = LFj - dj
7 ESj = EFi - overlapij
LFi = LSj + overlapij
1 2 3 4 5
6 7
B
3 1
D (6) A C
3 4
13
Project Scheduling Project Scheduling
3. Time-Scaled Diagram Bar Chart (Gantt Chart)
A (3 days) has no predecessor Time versus activity chart
B (3 days), C (4 days), & D (6 days) depend on A Simple representation and easy to read
E ((5 days) depends on B, C, and D Early bar chart
1 2 3 4 5 6 7 8 9 10 11 Activity
12 13 14 d=3
B
A
ES = 0 d=3 TF=3
ES=3
B d=4 TF=2
A C E
4 ES=3
3 C
5 d=6
D ES=3
D
3
6 Ed=5
ES=9
0 1 2 3 4 5 6 7 8 9 10 11 12 13
14 Time
Ed=5
LF=14
0 1 2 3 4 5 6 7 8 9 10 11 12 13
14 Time
14
Contractual Relationships Traditional
Owner
There are numerous alternative contractual approaches
(Delivery Methods) to bring together a team for the General
design and construction of a project. Designer
Contractor
The principle categories include:
1. The traditional approach.
Own Forces
2. The owner-builder. Subcontractors
Work
3. Turnkey. Separate Designer.
Single General Contractors.
4. Professional Construction management Numerous Subcontractors.
5. Project Management Fixed price, unit price, guaranteed maximum, or cost
plus fixed fee construction contract
Negotiated professional fee for design services.
Turnkey
Owner – Builder Design–Build Design–Manage
Owner Owner
Owner
Engineer
Contractor/ Engineer/ Construction
Design Construction DB Firm Manager
Department Department
General Design Construction
Design
Contractor Manager
15
Professional Construction Manager
General Contractor Construction Manager
Owner Owner
General
Design Contractor acting Construction
Design
as construction Manager
manager
A number of independent
Subcontractors contractors
16