RA Erection of Pre-Engineered Steel Buildings (Structural Steel)
RA Erection of Pre-Engineered Steel Buildings (Structural Steel)
Date: 26-01-2019
KEY: L = Likelihood S = Severity R = Risk (Likelihood x Severity)
L = Low priority to be implemented M = Medium priority to be scheduled as H = High priority to be acted on
RISK RANKING:
when resources allow. soon as practicable. immediately.
Population at Risk Rating Revised Rating
Task/Element Potential Hazards
Risk Control Measures
L S R L S R
Good housekeeping in the area.
Remove all unwanted materials, tools and
equipments
A) Presence of unsuitable Proper Coordination with supervisor.
Area materials, tools and Workmen 3 3 M Check all tool & tackles before use, 1 3 L
preparation equipment’s Ensure all electrical tools must be inspected and
approved by competent person,
Ensure Proper illumination at night work
(1) Very (2) (3) Possible (4) Likely (5) Very Likely
Unlikely Unlikely
Operations but unusual not surprising no doubt
but possible though
under extreme conceivable
Personnel Asset damage Environmental Reputation circumstances
Downtime
(1)First Aid (1)Slight (<$1,000) (1) Slight (1)Local exposure 1 2 3 4 5
(< 1 Gallon)
(1) 8 hours
(3)Lost Time/ Rest. injury (3)Medium (<$100,000) (3) Medium (3) National exposure 3 6 9 12 15
(<420 Gallons)
(3)> 1 day
Personnel with competency and skills to perform the job have the authority to proceed after verbally discussing the job
1–6 Low Risk
requirements with anyone performing the work with them.
May be acceptable; however, review task to see if risk can be reduced further.
Job shall only proceed with appropriate authorization after consultation with HS&E personnel and assessment team. Where
7 – 15 Medium
possible, the job shall be redefined to take account of the hazards involved or the risk shall be reduced further prior starting the
Risk
job(TRA Section 4, RISK IDENTIFICATION, ASSESSMENT AND CONTROL). If applicable, a Permit-to-Work shall be
obtained in accordance with Permit to Work System.
The job must not proceed until it has been redefined or further control measures put in place to reduce risk. The controls shall
16 – 25 High Risk
be re-assessed for adequacy prior to starting the job.