CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

FIRE FIGHTING SYSTEM


1 Check the piping supports are fixed as per the specified distance
2 Ensure all joints are properly completed
3 Check all pipe line are laid as per drawing
4 Check support verticality and clamp must to be rested on pipe with proper tightness
5 Ensure the sprinkler installation (Rigid / Flexible hose) completed
6 Ensure that valves are installed as per the drawing
7 Verify that BOP of pipes are installed as per the drawing
8 Ensure Wall / Partition through pipes are closed
verify pipe painting work completed & ensure that DFT measurement reading
9 observed
verify pipeaspainting
per specification
work completed & ensure that DFT measurement reading
10 observed as per specification
11 Verify the installation checklist completion
12 Verify the hydro test completion report

13 Ensure Drain Zone control Valve Installed with Proper Slope and connected to the
Shaft Header

14 Ensure Zone control Valve Install with correct Direction connected with the Header
Pipes In Shafts.
15 Ensure Civil Opening is don arround the FPS Lines in FPS Shafts
Clearance given for false ceiling work by FPS team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE

HVAC SYSTEM
1 Check the supports are fixed as per the specified distance
2 Ensure all duct's hanging supports are in vertical condition
3 Ensure that all duct's are laid as per drawing
4 Verify the all branch connection are done as per the approved drawing
5 Ensure that all VCD,FD,VAV installation works are completed
a Fire damper Installtion and ceiling fire damper without airgaps
b Enusre VCD installation/Provision
Ensure VAV Installation for Installation later date if any materials not
c avilablity.
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

6 Provision for grill/diffuser are completed


7 Ensure B.O.D installed as per approved drawings
8 Ensure unwanted hanging supports are removed
9 Ensure the duct pressure test completion and report attached
10 Ensure all opened ducts are closed properly
11 Ensure that duct & TDF insulation are done properly
12 Ensure Return Air CTS Ducts Installed as per approved Drawing in the Directions as per
approved drawing in the Directional of air flow of AHU Room.
Ensure Return air Opening is made in the partion wall above false ceiling as per
13 drawing to closed Return air circuits to AHU room

Ensure Trapdoor arrangments made in fire damper /VAV/VCD/in Gypsum falseceiling


14 area
15 Ensure Service Man hole Provide for Butterfly Dampers in Gypasum
Clearance given for false ceiling work by HVAC team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE

ELECTRICAL SYSTEM
1 Ensure that raceway, tray & Conduit are laid as per the drawing power
2 Ensure raceway / tray supports are in vertical condition
3 Ensure raceway / tray clamp support should be approved colour
4 Ensure ceiling power socket for other (Third Party power)services work are completed

5 Ensure raceway, tray,Earthing & back box connection with conduit is done with check
nut
6 Ensure all wall / partition crossing / connection works completed properly
7 Ensure point wiring drop work completed
8 Ensure the cable dressing are properly done
9 Ensure that identification done for above false ceiling power points
10 Ensure the cable dressing are properly done
11 Ensure that raceway, tray & Conduit are laid as per the drawing DATA/WIFI
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

12 Ensure that raceway, tray & Conduit are laid as per the drawing /AV Requirements
Ensure that raceway, tray & Conduit are laid as per the drawing /IBMS Requirements
13
14 Ensure all wall / partition crossing / connection works completed Fire Selent properly

15 Ensure The Lighting Circuits/Sensors works complted as per the approved Drawings
Ensure that Lighting Trunking Supports ,Trunkings installed as per the approved
16 drawings.
Clearance given for false ceiling work by Electrical team
From: MICRON Through : SPCPL MEP Through : SPCPL Civil Through : TCE

IBMS SYSTEM
1 Ensure that FAS/PA/ACS Cables,cable tray & conduit are installed as per the drawings
2 Ensure that back box fixing completed at ceiling for FAS /PA
3 Ensure thatFAS/PA/ACS cable drop work completed
4 Ensure CCTV provision had been completed
5 Ensure ACS control provision had been completed
6 Ensure third party BMS cabling Connectivity works
Clearance given for false ceiling work by IBMS team
From: IBMS Through : SPCPL MEP Through : SPCPL Civil Through : TCE
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES NO
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

FIRE FIGHTING SYSTEM


1 Check the piping supports are fixed as per the specified distance
2 Ensure all joints are properly completed
3 Check all pipe line are laid as per drawing
4 Check support verticality and clamp must to be rested on pipe with proper tightness
5 Ensure the sprinkler installation (Rigid / Flexible hose) completed
6 Ensure that valves are installed as per the drawing
7 Verify that BOP of pipes are installed as per the drawing
8 Ensure Wall / Partition through pipes are closed
verify pipe painting work completed & ensure that DFT measurement reading
9 observed
verify pipeaspainting
per specification
work completed & ensure that DFT measurement reading
10 observed as per specification
11 Verify the installation checklist completion
12 Verify the hydro test completion report

13 Ensure Drain Zone control Valve Installed with Proper Slope and connected to the
Shaft Header

14 Ensure Zone control Valve Install with correct Direction connected with the Header
Pipes In Shafts.
15 Ensure Civil Opening is don arround the FPS Lines in FPS Shafts
Clearance given for false ceiling work by FPS team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE

HVAC SYSTEM
1 Check the supports are fixed as per the specified distance
2 Ensure all duct's hanging supports are in vertical condition
3 Ensure that all duct's are laid as per drawing
4 Verify the all branch connection are done as per the approved drawing
5 Ensure that all VCD,FD,VAV installation works are completed
a Fire damper Installtion and ceiling fire damper without airgaps
b Enusre VCD installation/Provision
Ensure VAV Installation for Installation later date if any materials not
c avilablity.
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES NO
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

6 Provision for grill/diffuser are completed


7 Ensure B.O.D installed as per approved drawings
8 Ensure unwanted hanging supports are removed
9 Ensure the duct pressure test completion and report attached
10 Ensure all opened ducts are closed properly
11 Ensure that duct & TDF insulation are done properly
12 Ensure Return Air CTS Ducts Installed as per approved Drawing in the Directions as per
approved drawing in the Directional of air flow of AHU Room.
Ensure Return air Opening is made in the partion wall above false ceiling as per
13 drawing to closed Return air circuits to AHU room

Ensure Trapdoor arrangments made in fire damper /VAV/VCD/in Gypsum falseceiling


14 area
15 Ensure Service Man hole Provide for Butterfly Dampers in Gypasum
Clearance given for false ceiling work by HVAC team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE

ELECTRICAL SYSTEM
1 Ensure that raceway, tray & Conduit are laid as per the drawing power
2 Ensure raceway / tray supports are in vertical condition
3 Ensure raceway / tray clamp support should be approved colour
4 Ensure ceiling power socket for other (Third Party power)services work are completed

5 Ensure raceway, tray,Earthing & back box connection with conduit is done with check
nut
6 Ensure all wall / partition crossing / connection works completed properly
7 Ensure point wiring drop work completed
8 Ensure the cable dressing are properly done
9 Ensure that identification done for above false ceiling power points
10 Ensure the cable dressing are properly done
11 Ensure that raceway, tray & Conduit are laid as per the drawing DATA/WIFI
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV

PROJECT : WIPRO CDC - 5 PROJECTS


Block Ref. :
Drawing Ref :
Location Name. :
Date :
Floor AREA/ODC
Sl. Items for Inspection YES NO
1 Ensure all the services install as per the approved Coordination Drawing with out any
Clashes
Clearance given for false ceiling work by SPCL
From: SPCPL Civil Through : SPCPL MEP Through :TCE TO :NSC Team

12 Ensure that raceway, tray & Conduit are laid as per the drawing /AV Requirements
Ensure that raceway, tray & Conduit are laid as per the drawing /IBMS Requirements
13
14 Ensure all wall / partition crossing / connection works completed Fire Selent properly

15 Ensure The Lighting Circuits/Sensors works complted as per the approved Drawings
Ensure that Lighting Trunking Supports ,Trunkings installed as per the approved
16 drawings.
Clearance given for false ceiling work by Electrical team
From: MICRON Through : SPCPL MEP Through : SPCPL Civil Through : TCE

IBMS SYSTEM
1 Ensure that FAS/PA/ACS Cables,cable tray & conduit are installed as per the drawings
2 Ensure that back box fixing completed at ceiling for FAS /PA
3 Ensure thatFAS/PA/ACS cable drop work completed
4 Ensure CCTV provision had been completed
5 Ensure ACS control provision had been completed
6 Ensure third party BMS cabling Connectivity works
Clearance given for false ceiling work by IBMS team
From: IBMS Through : SPCPL MEP Through : SPCPL Civil Through : TCE