PSR-2 REJUVENATION PROJECT

PHASE 3
SITE ACCEPTANCE TEST (SAT) AND COMMISSIONING
PROCEDURE FOR 93 UNITS OF BFI FLAME SCANNER

Tag No.:

No. Description Remarks


1 Mechanical Installation
a) Appearance of BFI FLAME SCANNER – Visual
b) Appearance on Termination - Visual
c) Mounting Screw and Support bracket

2 Cabling Works
a) Instrument and power cable routes Installation
b) Cable glanding, cable ties, etc

3 Purge Panel and Tubing Works


a) Purge Panel Installation
b) Tubing Installation
c) Leakage inspection

4 Electrical
a) Cable terminations and tagging
b) Termination work
c) Power Supply

5 Performance Testing

a) Power Supply Functional test


b) Scanner Power On test
c) Flame Simulation Test
d) Flame Contact Functional Test

Flame Scanner System were both tested and commissioned on ……………………2019.

Prepared by: Verify by:

Wan Nurul Shazwani Wan Abdullah Malaysian Refining Company Sdn Bhd
LC Tech Engineering Sdn Bhd Instrument Representative