Professional Documents
Culture Documents
A Study On The Proposed Construction of Poblacion-Libag Bridge PDF
A Study On The Proposed Construction of Poblacion-Libag Bridge PDF
Prepared by:
Jadee A. Daquioag
Leomar D. Juliano
Frenalyn G. Villano
College of Engineering
May 2018
APPROVAL SHEET
As members of the panel committee, we certify that we have examined this paper and
hereby recommended as a fulfilment for the degree Bachelor of Science in Civil Engineering.
The researchers would like to extend their utmost regards to the people and institutions that
made this endeavour possible.
Firstly, to our Almighty Father who gave us the strength and wisdom to pursue this study and
the people who helped us along the way.
Secondly, to our families who gave us undying support in every aspect of this experience and
motivated us to complete this study.
Thirdly, to our dear advisers who shared to us their broad knowledge with regards to our
objectives in the research and guidance in every phase and progress during the time the study was
conducted.
We also would like to thank our fellow classmates, who helped us acquire data that are
relevant in our study.
Lastly, is to our dear academe, The Cagayan State University – Carig Campus, specifically
the Department of Civil Engineering, for its vision and mission for the welfare of students like us.
TITLE PAGE i
APPROVAL SHEET ii
DEDICATION iii
ACKNOWLEDGEMENT iv
TABLE OF CONTENT v
LIST OF TABLES x
ABBREVIATIONS xiii
1. INTRODUCTION..................................................................................................................2
2.2.2 Geomorphology……………………….........................................................11
2.2.3 Population......................................................................................................12
2.4.1 The Feasibility Study on the Construction of a New Bridge across River Nile
at Jinja in the Republic of Uganda..................................................................17
4.3 Legal and Institutional Frameworks for Environmental and Social Impacts..............53
4.4 Recommendations........................................................................................................57
5.2.1 General...........................................................................................................60
5.2.4 Evaluation.......................................................................................................64
5.3.1 General................................................................................................................66
6.1 Conclusion...................................................................................................................68
6.2 Recommendations........................................................................................................69
APPENDICES......................................................................................................................................71
TABLE XV. PROJECTED TRAFFIC VOLUME CAPACITY RATIO PER YEAR (EXISTING
ROUTE)
REFERENCE.................................................................................................................................123
LETTERS.......................................................................................................................................124
PROFILES.....................................................................................................................................128
The Poblacion of Tuguegarao City is accessed through the Pinacanauan Overflow Bridge or
Capatan Overflow Bridge by residents of Capatan, LibagNorte, Peñablanca, and Northern
Areas of Isabela. The bridge is a shortcut made to access the city center where the hospital,
cathedral church, schools, and business establishments are found but availability of the bridge
is sometimes restricted because of flooding due to typhoons and heavy continuous raining. In
recent years, the bridge were closed off two to three times a year ranging from three days to a
week including the clean-ups after the storms. As a result, traffic is disrupted entirely thus,
giving inconvenience to the people especially during emergencies.
Large trucks are also not allowed to pass the overflow bridge due to its low load carrying
capacity. It usually takes about twenty seven minutes more to reach the city center using the
Cagayan valley Road and Cagayan-Apayao Road without traffic. However, that route is
already heavily congested. This causes delays in transportation of people and goods affecting
the economy of the city.
Moreover, the current road condition of the existing bypass route is considered mainly bad.
The length of the road along the Pan-Philippine Highway, also known as Maharlika Highway
or Cagayan Valley Road which conditions are considered good, fair, poor and bad are 1 km,
1.3 km,1.6 km, and 8.1 km, respectively. Such situations of the bridge and existing routes
cause constraint of the effective use of road assets and the difficulty of carrying machinery
and materials for rural development and local products. Thus, the bridge’s condition not only
causes a bottleneck for development but restricts the basic traffic demand of inhabitants.
In light of the foregoing, in order to cope with the situation, the team carried out a study on
the Construction of a New Poblacion-Libag bridge in Tuguegarao City.
The inhabitants utilize the project bridge in their daily lives. This project will provide safe and
easy means of access to social facilities such as markets, schools, clinics, etc., at all times.
The city serves as commercial and institutional hub. Thus, trade and service establishments
together with industrial and tourism-related activities mushroom in the area. The realization
of the project is needed because of the fast development rate of Tuguegarao City.
Since the proposed bridge with high load carrying capacity will be constructed, large vehicles
will be able to pass. Furthermore, the travel distance will be shortened because of elimination
Considering that the number of people and goods entering the city are remarkably increasing,
economic losses generated by the delays will also increase through the years. The bridge may
not be able to support the anticipated continuously increasing traffic in the future. That may
be a hindrance to the revitalization of the economy due to the increase of employment and
purchasing opportunities utilizing the development potential of Tuguegarao City.
The main objective of the study is to examine and evaluate the feasibility of the Project for
Construction of Poblacion-Capatan/Libag Bridge in Tuguegarao City, Cagayan. Specifically,
it aims to achieve the following objectives:
The Study commenced with the analysis of available data, the review of the foregoing study
reports and the generation of complementary data through field investigations including
traffic survey, road condition survey, topographic survey and the maximum flood level which
is 26.912 meters was obtained from DPWH-R02.
Future traffic volumes were forecasted based only on the flow data of vehicles from the traffic
surveys conducted by the team. The traffic growth rates used are shown in Table 3.2.2-7
obtained from the DPWH-R02. The vehicles passing the CVR and CAR-TS and the bridge
were assumed to enter and leave the city center.
Design standards, design criteria and other conditions necessary for the planning and design
of the road and bridge were discussed/consulted with relevant authorities and will be
established.
The Team will confirm laws, standards, procedures related to environmental impact
assessment and necessary licenses in the Philippines. The necessary land acquisition area and
approximate number of resettlement houses will be determined by site survey, aerial
photographs.
The preliminary project will be estimated based on collected data relating to linear meter cost
of different bridge type, slope protection and road.
Economic and financial evaluations were carried out based on the estimated construction cost
of the project, operation and maintenance costs, and economic benefits derived from savings
in Travel Time Cost, from the Vehicle Operating Cost Ratio and the implementation plan.
The study covers the areas directly affected by the proposed development. Figure 1.5-1 shows
the location of the proposed New Poblacion-Libag Bridge and its surrounding Area.
The traffic demand between Capatan-Libag Area and Centro of Tuguegarao city is made from
“Forecasted traffic”. The forecasted traffic is defined as the existing vehicle traffic which
would increase relatively with traffic growth rate.
Considering the converted traffic volume from the existing route, its level of service is
examined:
0.90
0.79
0.80
0.74
0.70
0.70
0.65
0.61
0.60 0.58
0.54
VOLUME CAPACITY RATIO
0.51
0.50 0.48
0.45
0.42
0.39
0.40 0.37
0.35
0.32
0.30
0.29
0.30 0.27
0.25
0.23
0.22
0.20
0.10
0.00
2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 2042 2044 2046 2048 2050 2052 2054 2056 2058
TIME
As a result, the estimated VCR value for 2018 to 2044 along the existing route is
between0.21 to 0.50 that correspond to Relatively Free Flowing or LOS B and it only reached
LOS D or Moderate to Heavy Traffic by 2055 with a value of 0.72. However, the VCR of 2050
reached 0.61 which is greater than 0.60 thus, requiring a four (4) lane highway.
Moderate to Heavy
0.71< VCR ≤ 0.85 D
Traffic
3) Natural Conditions
a) Topography and Geology
Tuguegarao City, the capital of the province of Cagayan and the Regional Center of Cagayan
Valley (Region 02), lies between latitude of 17°36’47.45” N and longitude of
121°43’37.27”E, is located approximately 480.7 km from Manila by the Pan-Philippine
Highway (Maharlika Highway).
The City is almost surrounded by the Cagayan River in the western side and Pincanauan
River, a tributary of Cagayan River, in eastern part. The Pinacanauan River passes through the
municipality of Penablanca and Tuguegarao City.
Period o f
1902-2016 1903-2016 1966-2016
Record
Source: Philippine Atmospheric, Geophysical and Astronomical Services Administration
The three alignment alternatives, which are the basis in formulating the comparative analysis
for selecting the optimum solution in the study, are shown in Figure iv and Table v hereunder.
At the
intersection
of
Approximat Aguinaldo-
ely Valenzuela
190 m near the
downstream new The route Approximately 6
from the Provincial length is residential building,
1 3400 None None Good
existing Museum shorter than 1 electric post and 2
bridge with and others streets lights
river width connecting
of 130 m with the
Provincial
Road near
Libag
Bridge
Along
Gonzaga
Approximat
Street near
ely
Centro 10
300 m The route
Barangay Approximately 15
upstream
Hall and crosses the residential building
2 3785 from the None Good
connecting existing and 7 commercial
existing
with the road. building
bridge with
Provincial
river width
Road near
of 110 m
Libag
Bridge
Approximat Connecting The
ely Rizal Street construction
910 m near cost is high Approximately 10
Difficult to
upstream Adrinel’s residential building,
construct due because Relatively large
from the and 20 commercial
3 4920 to relatively bridge length (more than 150 Very Bad
existing connecting building, 10 electric
large is longer than houses)
bridge with at the post, 8 light post and
resettlement. others and
river width intersection more than 20 trees.
of 95 m of Terisita resettlement
Boulevard – is large.
The following five bridge types were compared, and consideration was given to whether they
were applicable. As a result, it was found that the PC box girder bridge was able to meet the
subjective evaluation
i) Hybrid Cable-stayed
The maximum span length is 450m, this bridge type has never been constructed within the
region and reputable international contractors may have to be engaged
ii) PC Cable-stayed
The maximum span length is 240m, reputable international contractors may have to be
engaged
The maximum span length is 180m, No major technical problems will be encountered in
adopting this type of superstructure but theres potential risk on the river bank erosion during
construction
The maximum span length is 180m, and it satisfies the subjective evaluation.
v) Suspension Bridge
The maximum span length is 240m, reputable international contractors may have to be
engaged
The project is to construct an approximately 0.77 km bridge over the Pinacanuan River. The
main bridge is at elevation of 30.182m in height and 14.640m in width. The bridge approach
road connecting with Valenzuela Street and Maharlika Highway is proposed with 2% slopes.
The total project length including the main bridge, approach bridge and roads is
approximately 3.4km. As a result of the comparison of alternative bridges, PC Box Girder
Bridge was recommended. As the typical cross section, 4 lanes with a total width of 14.640
wide including together with 1.110m wide sidewalk at both side only.
1) Natural Environment
The project will not affect these protected areas since the project location is far from any and
that Tuguegarao City or any part of the city is not listed in the Protected Areas List.
2) Social Environment
a) Centro Side
The proposed project site has commercial facilities along Rizal Street. Tuguegarao East
Central School, Rizal Park, Primark Mall, Tuguegarao City Cathedral, People’s Emergency
Hospital are located near the area. Also, beside the road is the rehabilitation of the former
Provincial Jail to a museum. The traffic volume of Rizal Street is not that heavy except during
Sundays. Therefore, it is necessary to consider appropriate measures to prevent the traffic
congestion and accidents. Further widening of the road networks might be required, hence
part of the structures, existing fences and shrubbery will be affected. Moreover, since the
proposed Bridge is a 4-lane highway, it is also necessary to study possible traffic problems
since Aguinaldo Street is a 2 lane road and without the provision of DPWH ROW.
b) Libag Side
-EIA study: Securing of ECC and EIA study for ECC application is required
-Tree cutting permit: Tree cutting permit inside construction site shall be acquired from
DENR
The proposed Poblacion-Libag Bridge which will be treated as a diversion route has a total
estimated cost of Php 2,151,178,000 (base cost), which is comprised of new construction of
2.63km road, 2.49km slope protection, 770m of pre-stresses concrete box girder
bridge(main bridge), and 47,559 sq.m. Right of Way Acquisition(ROW). Table vi shows the
cost summary of the proposed project.
Economic Evaluation:
Major quantifiable economic benefits derived from the proposed project are mainly composed
of savings in vehicle operating cost and travel time cost. The economic analysis is made
The sensitivity analysis of the economic analysis is considered for the following:
Combined
SENSITIVITY ANALYSIS
ECONOMIC Increase Decrease Cost
BASE
INDICATORS Project Cost Savings by Combined
by 20% 20%
Net Present Value Php Php Php (Php
(NPV) 1,145,249,898.17 677,673,746.33 448,623,766.69 18,952,385.15)
Benefit-Cost Ratio
1.489866685 1.241555571 1.191893348 0.993244457
(BCR)
Internal Rate of Return
15.73% 13.07% 12.49% 9.90%
(IRR)
Considering existing route, the project EIRR for the base case was estimated at 15.73%.
Sensitivity analysis, at increased project cost by 20 % and reduced traffic demand of 20 %,
resulted to an EIRR of 13.07% and 12.49% respectively and combined by 9.90% which
established the economic feasibility of the project.
SENSITIVITY ANALYSIS
ECONOMIC
BASE Increase Project Decrease Cost
INDICATORS Combined
Cost by 20% Savings by 20%
Net Present Value Php (Php (Php (Php
(NPV) 48,818,758.98 418,757,392.86) 428,521,144.66) 896,097,296.50)
Benefit-Cost Ratio
1.020881629 0.850734691 0.857598912 0.680587753
(BCR)
Internal Rate of Return
10.29% 7.66% 7.05% 4.03%
(IRR)
Considering Peñablanca route, the project EIRR for the base case was estimated at 10.29%.
Sensitivity analysis, at increased project cost by 20 % and reduced traffic demand of 20 %,
resulted to an EIRR of 7.66% and 7.05% respectively and combined by 4.03% which still
established the economic feasibility of the project.
The result of the traffic analysis along the existing route and the proposed route yielding
values that indicate that there is a need for the diversion, since the result met the threshold
value for IRR of 10%, Benefit-Cost ratio of greater than 1 and a positive value of NPV. And
along Peñablanca route and proposed route because the base cost result met the threshold
value for IRR of 10%, Benefit-Cost ratio of greater than 1 and a positive value of NPV.
3) Financial Evaluation:
The Proposed Bridge Project will not be tolled so financial cash flows are not to be
considered. However, in terms of funding, there are no restrictions. The Government of the
Philippines (GOP) thru Department of Public Works and Highway (DPWH) will fund the
project using the multi-year project contract.
1) Conclusion
Tuguegarao City is the main entry to the Province and is also a convergence area for the whole
province of Cagayan, Kalinga, Apayao and the northern part of Isabela [1]. The poblacion of
Tuguegarao City is accessed through the Pinacanauan Overflow Bridge or Capatan Overflow
Bridge by residents of Capatan, Libag, Peñablanca, and Northern Areas of Isabela. The bridge
is a shortcut made to access the city center where the hospital, cathedral church, schools, and
business establishments are found but availability of the bridge is sometimes restricted because
of flooding due to typhoons and continuous heavy raining. In recent years, the bridge were
closed off two to three times a year ranging from three days to a week including the clean-ups
after the storms. As a result, traffic is disrupted entirely thus, giving inconvenience to the
people especially during emergencies.
Large trucks are also not allowed to pass the overflow bridge due to its low load carrying
capacity. It usually takes about thirty minutes more to reach the city center using the Cagayan
valley Road and Cagayan-Apayao Road-Tuguegarao City without traffic. However, that route
is already heavily congested. This causes delays in transportation of people and goods hence,
affecting the economy of the city.
Moreover, the current road condition of the existing bypass route is considered mainly bad. The
length of the road along the Pan-Philippine Highway, also known as Maharlika Highway or
Cagayan Valley Road which conditions are considered good, fair, poor and bad are 1 km, 1.3
km,1.6 km, and 8.1 km, respectively [2]. Such bridge and existing road conditions provide for
the effective use of road assets and the difficulty in transporting machinery and materials for
rural development and local products. Thus, the condition of the bridge not only causes a
bottleneck for development but restricts the basic traffic needs of the inhabitants.
In the light of this, to cope with the situation, the team conducted a study on the Construction
of a New Poblacion-Libag bridge in Tuguegarao City.
The inhabitants use bridge projects in their daily lives. This project will provide a safe and easy
way to access social facilities such as markets, schools, clinics, etc., at all times.
The city serves as commercial and institutional hub. Thus, trade and service establishments
together with industrial and tourism-related activities mushroom in the area [3]. The realization
of the project is needed because of the fast development rate of Tuguegarao City.
Because the proposed bridge with high load carrying capacity will be built, large vehicles can
be passed. Additionally, the distance of travel has been shortened due to the removal of a turn.
Thus, travel time and transportation costs will be saved and the transportation efficiency of
people and goods will be improved.
Considering that the number of people and commodities entering the city is enormous, the
economic losses generated by delays will also grow over the years. The bridge cannot support
the expected steady increase in traffic in the future. This could be a barrier to economic
revitalization due to increased employment and buying opportunities with the potential
development of Tuguegarao City.
The main objective of the study is to examine and evaluate the feasibility of the Project for
Construction of Poblacion-Capatan/Libag Bridge in Tuguegarao City, Cagayan. Specifically, it
aims to achieve the following objectives:
The Study commenced with the analysis of available data, the review of the foregoing study
reports and the generation of complementary data through field investigations including traffic
survey, road condition survey, topographic survey and the maximum flood level which is
26.912 meters was obtained from DPWH-R02.
Future traffic volumes were forecasted based only on the flow data of vehicles from the traffic
surveys conducted by the team. The traffic growth rates used are shown in Table 3.2.2-7
obtained from the DPWH-R02. The vehicles passing the CVR and CAR-TS and the bridge
were assumed to enter and leave the city center.
Design standards, design criteria and other conditions necessary for the planning and design of
the road and bridge were discussed/consulted with relevant authorities and will be established.
The proposed location or route and alignment of the bridge was examined and decided by site
observation and using satellite images/aerial photographs and a structure type of the bridge is
proposed based on the comparison study. The Study will not include engineering design, only
typical designs obtained from DPWH-R02 based on minimum design standards.
The Team will confirm laws, standards, procedures related to environmental impact assessment
and necessary licenses in the Philippines. The necessary land acquisition area and approximate
number of resettlement houses will be determined by site survey, aerial photographs.
The preliminary project will be estimated based on collected data relating to linear meter cost
of different bridge type, slope protection and road.
Economic and financial evaluations were carried out based on the estimated construction cost
of the project, operation and maintenance costs, and economic benefits derived from savings in
Travel Time Cost, from the Vehicle Operating Cost Ratio and the implementation plan.
The study covers the areas directly affected by the proposed development. Figure 1.5-1 shows
the location of the proposed New Poblacion-Libag Bridge and its surrounding Area.
Data Collection
Cost Estimation
[Route]: This term delineates the general location of the bridge and the approach roads as
a combined stretch drawn with some margin to allow possible adjustments of alignments
within the space provided for the route.
[Bridge Location]: This term refers to a place where the bridge crosses the River Nile.
[Alignment]: This term defines the centreline of the approach road drawn on the basis of
the adopted design standard, existing land use, environmental conditions along the route,
and connecting a point along the bridge location.
[Bridge Type]: This term is used to discuss the structural types of the bridge to be
constructed along the bridge location.
[Level of Service]: This term is qualitative measure of the highway’s operating conditions
under a given demand within a traffic stream and their perception by motorists and/or
passengers.
[Average Annual Daily Traffic]: This term defines the number of vehicles crossing a road
section per day.
[Traffic]: This term refers to all vehicles that are moving along the roads in a particular
area.
[Existing Route]: This term refers to the route along the Pinacanauan Overflow Bridge.
[Peñablanca Route]: This term refers to the route along the CVR and CAS-TS.
[Existing Alternative Routes]: This term refers to the route along the Pinacanauan
Overflow Bridge and the route along the CVR and CAS-TS.
[Avenue]: It is a wide and straight road.
[Primary Road]: Directly connect to major cities (at least around 100000 people).
[Secondary Road]: Directly connects cities to Primary road, except Metropolitan Area.
[Tertiary Road]: Roads which are perform a local function
[Environmental Management Plan/Program]: It is a section in the EIS that details the
prevention, mitigation/management and monitoring measures to enhance positive impacts
and minimize negative impacts and risk of a proposed project undertaking. It also includes
contingency and compensation plan for environmental impacts and risks.
[Environmental Monitoring Plan]: it is a apart if EMP which indicates specific
parameters to the monitored for identified environmental aspects and impacts, the sampling
and measurement plan and the corresponding management scheme.
The main mode of transportation to and from the region is on land. With the increasing demand
for mobility and the number of goods sent within and outside the region, volume of vehicles
also increase which contributes to the current condition of road network. The road condition of
the region is far from ideal with the constant focus on rehabilitation. Road widening of major
roads had also been given priority in the past two years to accommodate the increasing volume
of vehicles. Relatedly, preventive maintenance was deprioritized due to the emphasis on road
widening.
Source: DPWH
Complementing the on-going rehabilitation of roads is the drainage and protection works
project that were also carried out along national roads and bridges. This reduces the
vulnerability of national roads from surface scouring, subgrade failure, deposition of soil and
rock materials due to erosion and landslide. It is also a response to the climate and disaster-
proofing of roads to increase its serviceability for the flow of people, goods and services to and
from the region.
Moreover, for the past three years, 6 bridges were translated into permanent bridges, 20 bridges
were rehabilitated, 14 bridges were maintained and 15 were new constructions along national
roads or in major locations needing access.
Tuguegarao City is the main entry to the Province of Cagayan. Tuguegarao City is bounded by
Iguig, Cagayan on the north; by Peñablanca, Cagayan on the east; by the Province of Isabela
on the south; and by the Cagayan River on the southwest and west. Across the river, the towns
of Enrile and Solana are located to the southwest and west. Tuguegarao City is also a
convergence area for the whole province of Cagayan, Kalinga, Apayao and the northern part of
Isabela.
2.2.2 Geomorphology
The region’s topography is generally sloping. About 40 percent of the land is mountainous or
with slopes greater than 30 degrees. This is followed by undulating to hilly terrain (8 to 30
degrees slope) and lowlands (below 8 degrees slope) at 31 and 29 percent of total area
respectively. Lands with elevation from 0 to 500 m. above sea level (ASL) represent about 92
percent of the total area while only 8 percent have an elevation between 500 to 1000 m. ASL.
Figure 2.2.2-1 Elevation Map of Region 2 Figure 2.2.2-2 Slope Map of Region2
The trend on the population of the region is also a vital area in economic progress, this affecting
the economic activity, human resource capacity and extent of public services in the regional
economy.
From the period 2010 to 2015, the population of the region has been increasing by 1.27 percent
annually with more productive population at 64 percent of the total population. Growth and
expansion in the urban areas of the Cagayan Valley especially in its four cities (Tuguegarao
City, Ilagan City, Cauayan City and Santiago City) were registered over the years (see Table
2.2.4-1). The region contributes 3.4 percent of the country’s total population which is
significantly lower compared to other regions with higher population and correspondingly
greater GRDP contributions.
Table 2.2.3-1 Top Ten Most Populous Cities of Cagayan Valley Region
Rank City/Municipality Province Population
1 Tuguegarao City Cagayan 155,502
2 Ilagan City Isabela 145,568
3 City of Santiago Isabela 134,830
4 City of Cauayan Isabela 129,523
5 Baggao Cagayan 82,782
6 Solana Cagayan 82,502
7 Echague Isabela 79,094
8 Alicia Isabela 71,504
9 Tumauini Isabela 67,650
10 Aparri Cagayan 65,649
Source: Philippine Statistics Authority Region 02
The growing urban population, if appropriate development measures are in place, will support
the economic progress through more formal financial transactions, increased demand for goods
and services (consumption), increased labor force, hasten industry developments (i.e., tourism,
housing, and commercial trades). On the other hand, implementation of policies (i.e., human
capital development, utilization of resources, environment protection and conservation),
provision of infrastructure facilities, and efficiency of social services should be prioritized to
maximize opportunities brought by population growth. The only challenge is the strong
possibility of urban sprawl or unregulated development as demand for housing and commercial
development is increasing. The trend towards migration to urban centers is also growing
associated with economic opportunities that the urban centers provide in terms of livelihood
and employment.
(1) Overview
For 2010-2015, the region’s economy has sustained a positive though erratic growth pattern.
While it reflects a positive growth of 4.95 percent over the 5-year period, this is not enough to
change the position of the region as the fourth from the bottom in terms of contribution to the
total GDP. Location and physical attributes of the region are contributory factors to the current
economic performance of the region. The negative effects of climate change also pulls down
modest gains that have been achieved as production sectors especially those in agriculture are
very vulnerable to frequent weather disturbances such as typhoons, monsoon rains and drought.
Over the period, the structure of the regional economy is becoming more diversified as it slowly
shifts from the Agriculture Sector (more than half of the region’s GRDP in 2010 to 36.6% in
2015) to Services Sector. While there is already a significant shift in the share of the Services
Sector to the total economy, agriculture still remains as the major source of income and
livelihood to more than 50 percent of the population.
Table 2.2.4-1 Regional Shares to Total GDP (at Constant 2000 Prices, in Percent), 2014-2015
Region/Year 2014 2015 2014 Rank 2015 Rank
NCR 34.8 40.4 1 1
CAR 1.0 1.1 15 13
Ilocos 3.2 2.7 8 9
Cagayan Valley 2.1 1.1 12 14
Central Luzon 13.5 8.3 3 3
CALABARZON 14.3 17.3 2 2
MIMAROPA 2.2 0.5 10 16
Bicol 1.4 2.8 14 8
Western Visayas 3.3 5.5 7 4
Central Visayas 8.0 5.3 4 5
Eastern Visayas (0.9) 1.4 17 12
Zamboanga Peninsula 2.2 2.5 11 10
Northern Mindanao 4.3 3.5 6 7
Davao Region 5.7 5.3 5 6
SOCCSKSARGEN 2.7 1.5 9 11
CARAGA 1.9 0.9 13 15
ARMM 0.3 -0.1 16 17
Philippines 100 100
Source: Philippine Statistics Authority Region 02
While the growth of the Services Sector had been phenomenal – this is now the main contributor
to the domestic economy in the past six years, there was a slowdown in industry development
at the regional level, particularly in manufacturing. Its growth also cushioned the poor
performance of the Agriculture Sector primarily due to its vulnerability to climate change.
This emphasizes the need for the region to embrace and migrate to this new paradigm on
knowledge economy. However, the region still lacks the support infrastructure, facilities and
quality services to migrate and actively adapt to this trend. The region is still highly dependent
on its Agriculture Sector and the limited capability of farmers to understand and take advantage
of the benefits of new technologies in increasing productivity are among the concerns that have
to be dealt with. There is also the need for the processing sector to explore the use of modern
technology to improve product quality and production efficiency including the utilization of the
internet for product advertising and marketing.
Growth in the Services Sector was manifested through the increase in the number of malls,
banks, gasoline stations, fast food chains, and other similar establishments in fast growing urban
areas in the region. It is also a manifestation of increasing demand for service-related activities
and attract in-migration. It is for the same reason that the region remains steadfast in pursuing
processing industries under manufacturing sub-sector because of the potential domestic and
external trade. This will bring in opportunities for the region to attract investments, spur the
growth of small and medium scale industries and create a substantial number of quality jobs.
Department of Public Works and Highways (DPWH) Region II Director Melanio C. Briosos
said construction operation has started for the Tallang Bridge project located in Baggao, a town
located in the heart of Cagayan, “We are implementing the Php 182-million Tallang Bridge
along Baybayog-Baggao-Dalin-Sta. Margarita Road which will connect less developed
barangays of Baggao to nearby urban centers,” said Director Briosos. The bridge will be
completed and opened to the public by May 2018. It will be built to have nine (9) spans, with
a 7.32 meters carriageway width and with abutments, and eight (8) piers utilizing bored piles
as foundation.
The bridge will be an all-weather structure, meaning it can withstand such strong winds and
stream of water during typhoons.
The project will provide convenience in transporting agricultural and commercial products
from the countryside to major economic hubs in urban areas and other neighboring provinces
of Cagayan. It also aimed to promote peace and development in the area of Baggao by
improving its rural road connectivity.
The Department of Public Works and Highways (DPWH) is constructing a new bridge to
replaces a typhoon-ravaged bridge in Isabela that has long been closed to traffic.
The cost of the project is Php 482 million, with 10-span and approach spanning 450 lineal
meters with carriageway width of 7.32 meters both abutments and nine (9) piers rest on bored
piles.
“This is going to be a better, more durable bridge that will benefit those who have been risking
their lives and properties crossing the old ravaged bridge,” said Director Briosos. The
replacement of Pigaolo Bridge will shorten the travel time between barangays on both sides of
the town of Angadanan and San Guillermo, Isabela.
The Department of Public Works and Highways (DPWH) has been completed the 665-linear
meter bridge that is seen to support livelihood and tourism in the southern part of Ilocos Sur.
According to the DPWH Region I Director Ronnel M. Tan, the cost of the Sugpon Bridge is
Php 273 million along Alilem-Sugpon-Sudipen Road in the municipality of Sugpon and it was
opened to the motoring public in time for the Lenten Season.
“The newly-built Sugpon Bridge which is designed as an all-weather bridge now allows safer
and faster link between the town of Sugpon, Ilocos Sur and to the outer towns of La Union,
crossing Amburayan River. The local residents and tourists won’t have to resort to small boats
or rafts just to cross the river during rainy season’” said Director Tan.
The newly completed Lucban Bridge was opened on February 24, 2017 that serves as a
replacement to an old bridge along Manila North Road (MNR) in the municipality of Abulug,
Cagayan Province.
With a cost of Php 631 million, the 825-linear meter new Lucban Bridge crossing over the
Cagayan River is seen to boost trade and tourism in Region 2.
The new Lucban Bridge was constructed 15 meters upstream of the old Lucban Bridge to
guarantee that general public will have safer and more efficient access to and from the regions
of Cagayan Valley, Ilocos and the Cordilleras.
Other than the construction of the bridge replacement the project includes provision for
shoulders, guard rails, parapet walls, signages, pavement markings, and solar-powered
pavement studs in the approaches to ensure safety of commuters.
2.3.5 Study on the Project for Construction of Davao-Samal Bridge in Republic of the
Philippines
The cities of Davao and Island Garden of Samal are located near to each other where the
Pakiputan Strait is placed in between. The main means of transportation is by ferries and boats
but is limited by the operation schedules and weather which gives inconvenience to inhabitants
especially those on the island. Recently, waiting time for the ferry is too long at peak times
Past studies were carried out regarding the proposed construction of the bridge. “The Study on
the Davao Integrated Development Program (DIDP) Master Planning” in March 1999
commends to connect IGACOS and Davao due to the cities high potential for high-grade
residential development, environmental friendly industrial estate, and cultural and financial
centers under the BIMP-EAGA scheme as well as resort development due to its adjacency to
Davao City and well preserved environment. Also, “Davao Gulf Area Development Plan 2011-
2030” aimed at creating employment and wealth by direct effects generated from promotion of
trades and commercial activities to LGUs in Davao Gulf Area, a project (Davao City-Samal
Bridge) is listed in the Programs and Activities of the development plan. Furthermore,
“Comprehensive Land Use Plan 2008-2017” mentions Samal-Davao Bridge as an economic
development strategy, improvement of accessibility to enhance economic productivity.
The project is to construct an approximately 1km bridge over the Pakiputan Strait. The main
bridge is to clear the navigational height limit of 58.91m from the highest sea elevation of 1.55m
in height and 100m in width. Furthermore, aeronautical height limit because of Davao Airport
forces the main bridge structure to be lower than 74m in altitude. The bridge approach roads to
the main bridge need to be viaducts to connect with Davao-Panabo Road and Samal
Circumferential Road with 6% or less slopes. The total project road length including the main
bridge, approach viaducts and approach roads is approximately 4.4km. As a result of the
comparison of alternative schemes, 3-span steel truss main bridge and PC hollow slab bridge
and steel box girder bridge approach viaducts were proposed. As the typical cross section, 2
lanes of 3.5m wide travel way and 2.5m wide shoulders for slow speed vehicles and broken-
down vehicles are proposed together with 1.5m wide sidewalk at one side only.
2.4.1 The Feasibility Study on the Construction of a New Bridge across River Nile at Jinja in
the Republic of Uganda
Upon request from the Government of Republic of Uganda, the Government of Japan
conducted the Feasibility Study on the Construction of a New Bridge across River Nile at
Jinja and entrusted the Study to the Japan International Cooperation Agency (JICA).
The capital city of Uganda, Kapala, is known as the cargo traffic generating source and the
centre of distribution of goods and considered as the hub of the national road network. The
Northern Corridor route runs through Kampala in parallel with the northern coast of Lake
Victoria. This route constitutes a major strategic link from Uganda and other inland
The objectives of the Study were to conduct a feasibility study on the construction of A New
Bridge across River Nile at Jinja including the construction of approach roads on both sides of
the bridge and to transfer relevant expertise, skills and technologies to Ugandan personnel
concerned relative to the development of the Project.
The project was concluded technically and economically feasible and environmentally sound.
Hence, it is justified to implement the project for national and people’s benefits. It is
recommended to select Alignment A which is located close to Nytil Textile Factory. It is
recommended to adopt PC Cable-stayed bridge with inverted Y-shape Pylon and Single Plane
Stayed-Cable. Preparation and execution of RAP in adequate, fair and prompt manner is most
anticipated to expedited the land acquisition process. Introduction of Toll System to the
Project should be carefully examined again during the Detailed Design stage involving
stakeholders not only the service providers but also users.
The condition is determined through distress surveys or roughness surveys and the data from
the assessment are stored in the Roads and Bridges Inventory Application (RBIA) show in
Table 3.1-1 and Table 3.1-2 was done by subjective assessment.
Table 3.1-1 summarizes the 2018 road condition of the existing road segment, of the Cagayan
Valley Road (S04161LZ) and Cagayan-Apayao Road (S04170LZ) and Table 3.1-2 summarizes
the 2018 road condition of the existing road segment.
In order to grasp the traffic characteristics between Tuguegarao City Center, Capatan,
Libag, Peñablanca and Northern Isabela, the following surveys were conducted in this
study:
Traffic Count Survey for vehicles using the existing route: April 10, 2018
(Tuesday) 06:00 AM to 06:00 PM, continuous 12 hour survey, and using the
Peñablanca route: January 20, 2018 (Tuesday) 06:00 A.M. to 06:00 P.M.,
continuous 12 hour survey.
Travel Time Survey passing through the existing route (Tuguegarao City proper to
Capatan-Libag Area), and Peñablanca route (CVR and CAS-TS) on April 17, 2018
(Tuesday) 7:57 A.M. to 8.54 A.M., 10:35 A.M. to 11:35 P.M., 3:10 P.M. to 4:03
P.M., and 5:37 P.M. to 6:33 in the evening.
Road Condition Survey or Roughness Survey on April 27, 2018 (Friday) 4:13 P.M.
in the afternoon to 6:01 P.M in the evening.
The Traffic Count Survey was carried out at point 1.a which is the intersection at Batang Road
–Gonzaga Street and at point 1.b which is the intersection at Libag Norte.
Travel time Survey along the existing route (From Centro of Tuguegarao City to Libag Sur
and Vice Versa), and at Peñablanca route (CVR and CAS-TS, and Vice Versa).
The characteristics of vehicle traffic between Tuguegarao City Center and Capatan, Libag,
Peñablanca and Northern Isabela using the existing route and Peñablanca route are given
as follows, (assuming that all the vehicles surveyed crossing the Peñablanca route are going
to Centro of Tuguegarao City):
The illustrated definitions of vehicle types in Table 3.2-1 were adopted in the survey.
The definition of vehicle types were included in the traffic survey for projection of
AADT for 40 years.
Small Bus
(Capacity of
Motorcycle
30 to 40 seats
only)
Rigid Truck
Motorcycle
2-Axle
Large Bus
(Capacity of
Goods Utility
40 seats and
Above)
Articulated
Cargo
Passenger
Trucks/Rigid
Utility
Truck 4-5
Axle
The Average Annual Daily Traffic Data are shown in Table 3.2-2 and Table 3.2-3.
Table 3.2-2 Average Annual Daily Traffic crossing the Existing Route (Veh/day)
DIRECTION 1 DIRECTION 2
Capatan-Libag Centro of
Area to Centro of Tuguegarao City BOTH Percentage
TYPE
Tuguegarao City to Southern area DIRECTION (%)
(Crossing the (Crossing the
existing route) existing route)
Table 3.2.2-3 Average Annual Daily Traffic crossing the Peñablanca Route (Veh/day)
DIRECTION 2
DIRECTION 1
Centro of
Capatan – Libag
Tuguegarao City
Area to Centro of BOTH
TYPE to Capatan – Percentage
Tuguegarao City DIRECTION
Libag Area
(Peñablanca
(Peñablanca
route)
route)
The AADT for the existing route is 25631 veh/day and the Peñablanca route is 17585 veh/day.
25631
25000
20000 19239
17585
NYMBER OF VEHICLES
15000
11863
10000
5312
5000
3674 857
1190
803 278
0
TYPES OF VEHICLES
The AADT was computed using the data from Traffic Volume Survey (See Appendix A)
conducted on the two (2) routes (CVR and CAS-TS and Existing Route). The existing route
has a greater number of motorcycle/tricycle and passenger cars than the Peñablanca route
because it is a shortcut from Capatan-Libag Area to Centro of Tuguegarao City. While
passenger/goods utility/PUJ and big trucks/bus crossing the Peñablanca route is greater than
the existing overflow bridge because big trucks/bus are not allowed to cross the bridge.
Figure 3.2-4 Hourly Variation of Vehicle Traffic crossing the Peñablanca Route
(January 20, 2018)
PASSENGER/GOODS
TIME UTILITY/SMALL BUS/PUJ
1000
800 ARTICULATED CARGO TRUCK
600
400 RIGID TRUCK 3+axles
200
0 PASSENGER CAR
PASSENGER/GOODS
UTILITY/SMALL BUS/PUJ
MOTORCYCLE/TRICYCLE
TIME
Figure 3.2-5 Hourly Variation of Vehicle Traffic crossing the Existing Route (April 10, 2018)
1600 TRUCK
1400
1200 RIGID TRUCK 3+axles
1000
800
PASSENGER CAR
600
400
200 RIGID TRUCK 2axles
0
PASSENGER/GOODS
UTILITY/SMALL BUS/PUJ
MOTORCYCLE/TRICYCLE
TIME
1400
RIGID TRUCK 3+axles
1200
1000
800 PASSENGER CAR
600
400 RIGID TRUCK 2axles
200
0
PASSENGER/GOODS
UTILITY/SMALL
BUS/PUJ
MOTORCYCLE/TRICYCL
E
TIME
Figure 3.2-6 Composition of Vehicle Traffic crossing the Peñablanca Route (January 20,
2018)
PASSENGER/GOODS TRUCKS/BUS
UTILITY/PUJ/SMALL 6.77%
BUS
4.88%
PASSENGER
CARS
20.89%
MOTORCYCL
E/TRICYCLE
67.46%
Figure 3.2-7 Composition of Vehicle Traffic crossing the Existing Route (April 10, 2018)
PASSENGER/GOODS
UTILITY/PUJ/SMALL TRUCKS/BUS
BUS 1.08%
3.13%
PASSENGER
CARS
20.72%
MOTORCYCLE
/TRICYCLE
75.06%
To analyze further the traffic condition along the existing route, the Volume Capacity Ratio
(VCR) should be established which will reflect the corresponding Level-of-Service (LOS) or
the efficiency of the road.
Moderate to Heavy
0.71 < VCR ≤ 0.85 D
Traffic
.
VCR = Eq. 03.
.
Two lanes VCR = < 0.6
.
Four lanes VCR = > 0.6
The existing route is characterized by the VCR for the existing route with equivalent Level of
Service (LOS).
The total volume of traffic (in terms of PCU) is projected applying the corresponding Traffic
Growth Rate (TGR) form DPWH-R02 with the purpose of determining the Level of Service
for 40 years and the result is shown in Table 3.2-8.
As a result, the estimated VCR value for 2018 to 2044 along the existing route is between 0.21
to 0.50 that correspond to Relatively Free Flowing or LOS B and it only reached LOS D or
Moderate to Heavy Traffic by 2055 with a value of 0.72. However, the VCR of 2050 reached
0.61 which is greater than 0.60 thus, requiring a four (4) lane highway.
Where:
C1 – BHOC along the existing route; and
C2 – BHOC along the proposed Diversion.
In the graph:
P1 – traffic volume that will be left using the existing route; and
P2 – traffic volume that will use the proposed Diversion.
Table 3.2-9 shows the assumed probable diverted traffic based on Equation 04 and Figure 3.2-
8.
The future traffic demand was forecasted under differing road network conditions of “With”
and “Without” project cases. “With” case scenario, assumes that number of motorized vehicles
would use the Poblacion-Libag Bridge, while “Without” case scenario assumes that al; the
motorized vehicles would use the existing route and Peñablanca route (CVR and CAS-TS).
Table 3.2-9 shows the percentage assumptions for the Diverted Traffic Demand.
Tuguegarao City, the capital of the province of Cagayan and the Regional Center of Cagayan
Valley (Region 02), lies between latitude of 17°36’47.45” N and longitude of 121°43’37.27”E,
is located approximately 480.7 km from Manila by the Pan-Philippine Highway (Maharlika
Highway).
The City is almost surrounded by the Cagayan River in the western side and Pincanauan River,
a tributary of Cagayan River, in eastern part. The Pinacanauan River passes through the
municipality of Penablanca and Tuguegarao City.
The climate is tropical in Tuguegarao, with a dry season lasting only from one to three months,
either during period from December to February or from March to May. According to Köppen
and Gieger climate classification, it is classified as “Aw”( topical wet-dry ). With a
precipitation less than 60 mm in driest month, the average temperature in Tuguegarao City is
27.2 °C and about 1756 mm of precipitation falls annually.
Along with Regions 1, 3 and CAR in Northern Luzon, Region 2 is highly vulnerable to heavy
rains and strong typhoons due to its geographical location and topography. These regions lie
along the country’s “typhoon belt”, which makes the area highly vulnerable to the occurrence
of typhoons that visit Northern Luzon at an average of 5 to 8 typhoons in a year.
The following design specifications of DPWH are basically applied to the project. As necessary,
AASHTO (American Association of State Highway and Transportation Officials)
specifications are referred to and compared to establish the most suitable design standards and
criteria for the project.
Design Guidelines, Criteria and Standards for Public Works and Highways (DPWH)
Highway Safety Design Standards 2012 (DPWH)
A Policy on Geometric Design of Highways and Streets 2011, AASHTO
(c) Radius
A comparison of minimum radius for horizontal curves is shown in Table 3.4-2
(d) Gradient
A comparison of the specifications regarding maximum gradient is shown in Table 3.4-3
Hybrid Cable-stayed
Bridge Profile
Construction Risk This bridge type has never been constructed in Region 2. To ensure good
quality and completion schedule reputable international contractors may have
to be engaged
Maintenance Periodic inspection work will be required for the stay cables and anchorages.
Maintenance work might be required for the stay cables and anchorages for
possible corrosion and cable cut if found
PC Cable-stayed
Construction Risk To ensure good quality and completion schedule reputable international
contractors may have to be engaged
Maintenance Periodic inspection work is required for the structural steel deck, stay cables
and anchorages.
Maintenance work might be required for stay cables and anchorages for any
defects such as corrosion and cable cut if found.
Aesthetic Viewpoint It can be a symbol and landmark. However, it has the same bridge type as
Dondoyan Bridge.
Arch Bridge
Bridge Profile
Construction Risk No major technical problems will be encountered in adopting this type of
superstructure.
Construction Risk This type is commonly used nationwide. No major technical problems will be
encountered for adopting this type of superstructure.
Evaluation RECOMENDED
Suspension bridge
Bridge Profile
Construction Risk To ensure good quality and completion schedule reputable international
contractors may have to be engaged
Maintenance Periodic inspection work will be required for the cables and anchorages.
Maintenance work might be required for the stay cables and anchorages for
possible corrosion and cable cut if found
In Chapter 3, alternatives to the routes were evaluated from aspects of economic efficiency,
construction limit, site condition, and social impact. Eventually, the alternative route 1 in Figure
3.2.5-1 was determined as the best location was selected as the final proposed route considering
road alignment. In light of this, this chapter discusses environmental and social impacts
concerning the proposed project. Issues were identified in consideration of any adverse
environmental and social impacts that could be foreseen, should be examined further by
succeeding study.
The project will not affect these protected areas since the project location is far from any and
that Tuguegarao City or any part of the city is not listed in the Protected Areas List.
a) Centro Side
The proposed project site has commercial facilities along Aguinaldo and Rizal Street.
Tuguegarao East Central School, Rizal Park, Primark Mall, Tuguegarao City Cathedral,
People’s Emergency Hospital are located near the area. Also, beside the road is the
rehabilitation of the former Provincial Jail to a museum. The traffic volume of Rizal Street is
heavy during Sundays as the St. Peter and Paul Cathedral is nearby. Additionally, traffic is also
heavy every morning (7:00 – 8:00 am) and afternoon (4:00 – 5:00 pm). Therefore, it is
necessary to consider appropriate measures to prevent the traffic congestion and accidents.
Further widening of the road networks might be required, hence part of the structures, existing
fences and shrubbery will be affected. Moreover, since the proposed Bridge is a 4-lane
highway, it is also necessary to study possible traffic problems since Aguinaldo Street is a 2
lane road and without the provision of DPWH ROW.
In considering the current situation of the proposed project sites, an assessment has been
made of the impacts in case the project is not implemented (“without project scenario”). Both
positive and negative impacts are foreseen.
The resettlement and tree-cutting would not be required as land acquisition would not be
necessary.
The current landscape would be maintained.
The traffic condition in the existing route will not be improved. Moreover, the access to
medical and educational facilities during typhoons will be hindered.
Considering that the number of people and goods entering the city are remarkably
increasing, economic losses generated by the delays will also increase through the years.
The bridge may not be able to support the anticipated continuously increasing traffic in the
future. That may be a hindrance to the revitalization of the economy due to the increase of
employment and purchasing opportunities utilizing the development potential of
Tuguegarao City.
Large trucks are also not allowed to pass the overflow bridge due to its low load carrying
capacity. It usually takes about twenty seven minutes more to reach the city center using
the Cagayan valley Road and Cagayan-Apayao Road without traffic. However, that route
The result of comparative study from the environmental and social point of view are shown in
Table 4.2-1.
Eval
Capatan
Route Centro uatio
Libag
n
Approxima
No
tely 6
residents
residential
and less
buildings, 1
structures
electric
are
1 post and 2 Good
observed.
streets
Lands are
lights.
mainly
Some trees
agricultur
will also be
al
cut.
Approxima
tely 15
residential
building
and 7
No
commercial
residents
buildings.
and less
Many
structures
structures
are
2 will be Good
observed.
affected
Lands are
especially
mainly
businesses.
agricultur
Street
al
lights may
be affected
and some
trees may
be cut.
4.3 Legal and Institutional Frameworks for Environmental and Social Impacts
The establishment of the Philippine Environmental Statement System (PEISS) marked the
beginning of the realization of the importance of considering environmental concerns as early
as the project planning stage. Presidential Decree (PD) 1586, Establishing an Environmental
Impact Statement (EIS) System in 1978, states that under Section 4 of PD 1151, Philippines’
Environmental Code, all agencies and instrumentalities of the National Government, including
Government Owned and Controlled Corporations, as well as private corporations, firms and
entities, for every proposed project and undertaking which significantly affect the quality of
the environment.
The Department of Environment and Natural Resources (DENR) is the government unit
responsible for the environmental administration. Environmental Management Bureau,
Department of Environment and Natural Resources (DENR - EMB) is responsible for the
issuance of decision making documents such as Environmental Compliance Certificate (ECC)
and Certificate of Non-Coverage (CNC) for PEISS. EMB Regional Offices in respective
regions are primarily responsible for the consultation and supervision of development projects.
The Environment Impact Assessment (EIA) is used to enhance planning and guide decision
making. EIA is predominantly presented in the framework of a requirement to incorporate
environmental concerns in the planning process of projects at the feasibility stage. Through this
process, adverse environmental impacts of proposed projects are reduced by a review process
of project siting, design and other alternatives, and the succeeding preparation of environmental
management and monitoring plans. A positive determination by the DENR-EMB results to the
The Philippine EIA Process has six sequential stages 1) Screening, 2) Scoping, 3) EIA Study
and Report Preparation, 4) EIA Review and Evaluation, 5) Decision Making, and 6) Post
ECC Monitoring, Validation and Evaluation/Audit stage. The promoter initiates the first three
stages while Environmental Management Bureau (EMB) takes the lead in the last three
stages. A summary flowchart of the complete process is presented in Figure 4.3.2.1-1.
Projects which have been originally declared as Environmentally Critical Projects (ECPs) or
projects in Environmentally Critical Areas (ECAs) may pose significant impacts on the quality
of the environment are subject to PEISS. The four (4) ECP project types and twelve (12) ECA
categories have been declared through Proclamation No. 2146 (1981) and Proclamation No.
803 (1996), as shown in Table 4.3.2-1.
Table 4.3.1.1-1 Summary List of Environmentally Critical Project (ECP) Types and
Environmentally Critical Area (ECA) Categories
DPWH has the largest number of projects which require land acquisition among other
departments. Therefore, DPWH makes its own stipulation regarding the procedure of land
acquisition by following Department Order and manuals.
Preparation of RAP and land acquisition procedure shall be implemented according to the legal
framework of the Philippines described in Department Order and guidelines/manuals of
Compensation and assistance guideline of this project compiling type of loss, entitlement and
compensation package shall be formulated at the succeeding study based on the population
census survey covering all PAPs in project site, asset inventory and socioeconomic survey.
The basic policy for compensation is intended for direct loss caused by the project.
Compensation for income loss would be basically provided for the decrease of income directly
caused by the resettlement and it shall be considered case to case.
4.4 Recommendations
It is recommended that in the succeeding studies, the documents necessary should be prepared
and submitted to Environmental Impact Assessment Division of the EMB regional Offices. The
outcome of the EIA Process within PEISS administered by the EMB - DENR is the issuance of
decision documents.
EMP and EMoP shall be prepared after enough consultation with the residents and communities
at the EIA study in order to address residents’ concerns over environmental conservation and
avoid negative impact to the environment caused by the bridge construction.
Cutting or transplanting of trees inside the project sites are required before commencement of
the construction and tree cutting permit shall be acquired from DENR. The planting of
seedlings/ saplings is required as replacement for every tree cut within or along the ROW of all
DPWH-administered infrastructure projects with regards to National Greening Program
(Executive Order No. 26, 2011). Therefore, planting activities for replacement for those trees
that were cut shall be consistently implemented.
RAP shall be prepared since the proposed project requires land acquisition. In preparing a RAP,
consultations must be held with the affected people and their communities based on sufficient
DPWH shall secure the budget for RAP implementation based on the prepared RAP, then
appropriately implement and monitor the land acquisition and resettlement procedures with
cooperation of local government. The grievance process shall also be formulated.
Close coordination with utility companies is necessary for the relocation of utilities in project
site. It is desirable to relocate the utilities with enough ROW considering the implementation
of the Project.
The proposed Poblacion-Libag Bridge which will be treated as a diversion route has a total
estimated cost of Php 2,151,178,000 (base cost), which is comprised of new construction of
2.63km road, 2.49km slope protection, 770m of prestressed concrete box girder bridge(main
bridge), and 47,559 sq.m. Right of Way Acquisition (ROW). Table 5.1.1 shows the cost
summary of the proposed project.
The primary objective of the economic analysis is to examine the effects of the project
investment. The economic analysis was done to evaluate whether or not the project investment
will be beneficial for the national economy by analyzing the required expenditure of the
national economy resources. Table 5.2.1 shows the key assumptions that were explicitly made
to conduct the economic analysis.
By implementing the proposed bridge, a variety of benefits in the short and long term is
expected. Among these, the following tangible benefits are considered in this study as shown
in Table 5.2.2.
Construction of
Items of Benefits Notes
Bridge
Savings in Vehicle Operation Cost (VOC) ●
Savings in Travel Time Cost (TTC) ●
Direct
Savings in Transportation Cost ●
Benefit
Comfort and Convenience (Punctuality,
X
Flexibility, etc.)
Induced Benefits ▲
Indirect Impact to the Environment ▲
Benefits Regional Development X
Tourism Development X
Note: ● : Tangible benefit
▲ : Not included in this study
X: Not included items due to intangible benefits
Table 5.2.3-1 Travel Times for the ‘Without Project’ and ‘With Project’ Cases
Item Value
‘Without Project’ Case: Going to City Center Away from City Center
Using the Peñablanca Route 28 min and 19sec 28min and 15sec
1 A.M. Peak Hour 31min and 4sec 29min and 10sec
2 A.M. Off-peak Hour 29min and 12sec 27min and 14sec
3 P.M. Off-peak Hour 25min and 36sec 27min and 27sec
4 P.M. Peak Hour 27min and 22sec 29min and 10sec
Using the Existing Route 7min and 33sec 9min and 40sec
1 A.M. Peak Hour 8min and 30sec 9min and 55sec
2 A.M. Off-peak Hour 8min and 10sec 9min and 43sec
3 P.M. Off-peak Hour 7min and 3sec 9min and 29sec
GOODS UTILITY/
RIGID TRUCK 3+
SMALL BUS/ PUJ
ARTICULA-TED
MOTORCYCLE/
CARGO TRUCK
RIGID TRUCK -
PASSENGER/
LARGE BUS
TRICYCLE
2AXLE
AXLE
Using the Existing Route
C1 373335.08 334239.33 47343.88 0.00 18204.28 4516.14 1868.75
C2 657417.53 605211.01 88338.02 0.00 27689.37 6870.89 2843.13
C2/C1 1.76 1.81 1.87 0.00 1.52 1.52 1.52
Using the Peñablanca Route
C1 230202.92 231173.82 50527.65 58743.01 30340.47 60111.43 19466.14
C2 1240790.91 1279041.51 286237.81 336323.81 146813.91 290925.47 94211.62
C2/C1 5.39 5.53 5.66 5.73 4.84 4.84 4.84
5.2.4 Evaluation
The evaluation procedure for the Poblacion-Libag Bridge was done by assessing the project’s
computed Net Present Value (NPV), Benefit-Cost Ratio (BCR) and Internal Rate of
Return(IRR). These values were evaluated considering the Road Condition, Travel Time and
Running costs.
2) Economic Evaluation
The Net Present Value (NPV), Benefit-Cost Ratio (BCR) and Economic Internal Rate of
Return (EIRR) are the economic indicators to be established. In Table 5.2.4-1, the results
of the normal evaluation and sensitivity analysis are shown. From the normal evaluation,
the IRR produced met the requirement of 10% to merit feasibility of the proposed diversion.
Given that the result of the normal evaluation is feasible, sensitivity analysis was performed
for the following conditions:
And as indicated from the results in the Table 5.2.4-1, values are above the hurdle rate even
on the best case scenario, thus the given conditions were concluded feasible.
SENSITIVITY ANALYSIS
ECONOMIC Increase Decrease Cost
BASE
INDICATORS Project Cost Savings by Combined
by 20% 20%
Net Present Value Php Php Php (Php
(NPV) 1,145,249,898.17 677,673,746.33 448,623,766.69 18,952,385.15)
Benefit-Cost Ratio
1.489866685 1.241555571 1.191893348 0.993244457
(BCR)
Internal Rate of Return
15.73% 13.07% 12.49% 9.90%
(IRR)
Considering existing route, the project EIRR for the base case was estimated at 15.73%.
Sensitivity analysis, at increased project cost by 20 % and reduced traffic demand of 20 %,
resulted to an EIRR of 13.07% and 12.49% respectively and combined by 9.9% which
established the economic feasibility of the project.
And as indicated from the results in the Table 5.2.4-2, values are below the hurdle rate even on
the best case scenario, thus the given conditions were concluded not feasible.
SENSITIVITY ANALYSIS
ECONOMIC Increase Decrease Cost
BASE
INDICATORS Project Cost Savings by Combined
by 20% 20%
(Php (Php (Php
Net Present Value Php
418,757,392. 428,521,144.6 896,097,296.
(NPV) 48,818,758.98
86) 6) 50)
Benefit-Cost Ratio
1.020881629 0.850734691 0.857598912 0.680587753
(BCR)
Internal Rate of
10.29% 7.66% 7.05% 4.03%
Return (IRR)
Considering Peñablanca route, the project EIRR for the base case was estimated at 10.29%.
Sensitivity analysis, at increased project cost by 20 % and reduced traffic demand of 20 %,
The result of the traffic analysis along the existing route and the proposed route yielding values
that indicate that there is a need for the diversion, since the result met the threshold value for
IRR of 10%, Benefit-Cost ratio of greater than 1 and a positive value of NPV. And along
Peñablanca route and proposed route because the base cost result met the threshold value for
IRR of 10%, Benefit-Cost ratio of greater than 1 and a positive value of NPV.
The purpose of the financial analysis is to examine the financial viability of the investment for
the “Construction of Poblacion-Libag Bridge” from the viewpoint of the implementation body.
The financial performance of the proposed bridge project is usually examined based on the
financial cash flow of the project implementation. The major works for the financial evaluation
involve the preparation of the input data for the financial statements and other necessary
external variables such as construction costs, operation/maintenance costs, revenues and
financial parameters. Financial statements usually include cash flow statement, which consist
of cash-inflow and cash-outflow to estimate the annual surplus or deficit including loan and
application of funds. The major input data for the financial evaluation is shown in Table5.3.1.
The Proposed Bridge Project will not be tolled so financial cash flows are not to be considered.
However, in terms of funding, there are no restrictions. The Government of the Philippines
(GOP) thru Department of Public Works and Highway(DPWH) will fund the project using the
multi-year project contract.
6.1 Conclusion
(1) Based on the evaluation made in Chapter 3 Section 3.6, Route 1, which begins and runs along
Aguinaldo Street, passes Batang Road before crossing the river and extends to Libag Sur, is
considered the best alternative because it has the shortest length of the three and has the most
minimal number of resettlement.
(2) The new bridge with its approach roads will require four lanes, as resulted from the Traffic
analysis in Chapter 3 Section 3.2.
(3) The proposed bridge type for the main bridge is a Prestressed Concrete Box Girder Bridge
which is approximately 0.77 km long and 16.86 m wide with a centreline elevation of 30.182
m.
(1) Based on the result of economic evaluation made, it is concluded that the proposed bridge
project is economically feasible in considering both the existing overflow bridge route and
Peñablanca route.
(2) Based on the results of financial evaluation made, it is concluded that the proposed bridge
project is financially viable. The Proposed Bridge Project will not be tolled so financial cash
flows are not to be considered. There are no restrictions in terms of funding. The Government
of the Philippines (GOP) thru Department of Public Works and Highway (DPWH) will fund
the project using the multi-year project contract.
(3) In view therefore, the government thru DPWH shall carry out detailed feasibility study for
Poblacion-Libag Bridge Project.
(1) As bicycle riders and joggers were observed at the existing bridge, the team recommends that
further study must be conducted for the pedestrian/bicycle lane/s.
(2) Traffic issues were expected at the city center side since the road connecting to the proposed
route is only two lanes. It is suggested to determine whether a road widening or diversion roads
are required.
(1) The Study Team suggests to further analyze the savings in vehicle operating cost for “with
project” and “without project” case to determine in Pesos the savings of VOC.
(2) The Study Team separately considered the two existing alternative routes, existing route and
Peñablanca route, for the analysis of the diverted traffic. Future researchers must try to consider
the combined diverted traffic of both existing alternative routes to see if the economic values
will be higher or lower than the attained result.
(3) For future study, Origin and Destination Survey must be conducted for accurate diverted traffic
data and Household Survey (expenditures by tourist in Tuguegarao City) for induced benefit
data.
It is recommended that in the succeeding studies, the documents necessary should be prepared
and submitted to Environmental Impact Assessment Division of the EMB regional Offices. The
outcome of the EIA Process within PEISS administered by the EMB - DENR is the issuance of
decision documents.
EMP and EMoP shall be prepared after enough consultation with the residents and communities
at the EIA study in order to address residents’ concerns over environmental conservation and
avoid negative impact to the environment caused by the bridge construction.
Cutting or transplanting of trees inside the project sites are required before commencement of
the construction and tree cutting permit shall be acquired from DENR. The planting of
seedlings/ saplings is required as replacement for every tree cut within or along the ROW of all
DPWH-administered infrastructure projects with regards to National Greening Program
RAP shall be prepared since the proposed project requires land acquisition. In preparing a RAP,
consultations must be held with the affected people and their communities based on sufficient
information made available to them in advance. In addition, due consideration shall be given
for not only the PAPs directly affected by the project but also related persons who were not
affected negatively at the preparation of compensation policy.
DPWH shall secure the budget for RAP implementation based on the prepared RAP, then
appropriately implement and monitor the land acquisition and resettlement procedures with
cooperation of local government. The grievance process shall also be formulated.
Close coordination with utility companies is necessary for the relocation of utilities in project
site. It is desirable to relocate the utilities with enough ROW considering the implementation
of the Project.
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
UTILITY VAN/PICK-
CARGO TRUCK
MOTORCYCLE
ARTICULATED
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
UP
TIME
5:00 - 6:00
9 207 100 44 4 4 2 0 0 2 2 0 0 0 374
A.M.
6:00-7:00
23 427 243 126 9 17 9 0 0 0 0 0 0 0 854
A.M.
7:00-8:00
1 573 278 153 8 32 23 0 0 3 0 0 0 0 1071
A.M.
8:00-9:00
13 323 256 187 4 20 37 0 0 0 0 0 2 1 843
A.M.
9:00-10:00
2 199 205 144 4 22 22 0 0 6 1 0 1 4 610
A.M.
10:00-
11:00 1 144 184 140 1 23 18 0 0 4 0 0 0 2 517
A.M.
11:00-
12:00 3 180 166 129 0 23 16 0 0 0 0 0 0 0 517
NOON
12:00-1:00
0 98 147 107 2 13 17 0 0 5 0 0 0 0 389
P.M.
1:00-2:00
0 115 183 135 2 19 36 0 0 1 0 0 0 0 491
P.M.
2:00-3:00
0 171 199 108 0 16 28 0 0 4 0 0 0 1 527
P.M.
3:00-4:00
1 207 163 123 0 18 0 0 0 12 0 0 0 3 527
P.M.
4:00-5:00
3 219 151 131 3 12 23 0 0 7 0 1 0 0 550
P.M.
5:00-6:00
14 331 155 172 6 0 15 0 0 1 0 0 0 2 696
P.M.
6:00 - 7:00
1 303 123 124 2 12 15 0 2 5 0 0 0 1 588
P.M.
TOTAL 71 3497 2553 1823 45 231 261 0 2 50 3 1 3 14 8554
UTILITY VAN/PICK-UP
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
CARGO TRUCK
ARTICULATED
MOTORCYCLE
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
TIME
5:00 - 6:00
7 106 78 44 0 2 4 0 0 1 0 0 0 0 242
A.M.
6:00-7:00
7 240 99 83 1 11 12 0 0 3 2 0 1 0 459
A.M.
7:00-8:00
3 280 175 165 4 10 20 0 0 6 0 0 0 0 663
A.M.
8:00-9:00
1 153 187 117 0 12 26 0 0 7 2 0 0 0 505
A.M.
9:00-10:00
5 215 187 101 0 19 23 0 0 4 2 0 1 0 557
A.M.
10:00-
11:00 1 201 228 165 2 16 23 0 0 5 1 0 0 0 642
A.M.
11:00-
12:00 2 108 228 135 10 12 28 0 0 10 1 0 0 0 534
NOON
12:00-1:00
0 129 189 113 4 20 19 0 0 3 0 0 0 0 477
P.M.
1:00-2:00
3 149 171 141 1 12 20 0 0 11 4 0 1 2 515
P.M.
2:00-3:00
7 190 171 129 2 19 32 0 0 20 2 0 1 0 573
P.M.
3:00-4:00
3 220 238 133 1 17 32 0 0 7 1 4 0 2 658
P.M.
4:00-5:00
12 374 236 134 3 23 20 0 0 1 0 0 0 0 803
P.M.
5:00-6:00
18 628 291 201 6 16 20 0 0 7 0 0 0 0 1187
P.M.
6:00 - 7:00
4 448 239 151 2 112 8 0 0 3 0 0 0 0 967
P.M.
TOTAL 73 3441 2717 1812 36 301 287 0 0 88 15 4 4 4 8782
UTILITY VAN/PICK-UP
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
CARGO TRUCK
ARTICULATED
MOTORCYCLE
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
TIME
5:00 - 6:00
16 313 178 88 4 6 6 0 0 3 2 0 0 0 616
A.M.
6:00-7:00
30 667 342 209 10 28 21 0 0 3 2 0 1 0 1313
A.M.
7:00-8:00
4 853 453 318 12 42 43 0 0 9 0 0 0 0 1734
A.M.
8:00-9:00
14 476 443 304 4 32 63 0 0 7 2 0 2 1 1348
A.M.
9:00-10:00
7 414 392 245 4 41 45 0 0 10 3 0 2 4 1167
A.M.
10:00-
11:00 2 345 412 305 3 39 41 0 0 9 1 0 0 2 1159
A.M.
11:00-
12:00 5 288 394 264 10 35 44 0 0 10 1 0 0 0 1051
NOON
12:00-1:00
0 227 336 220 6 33 36 0 0 8 0 0 0 0 866
P.M.
1:00-2:00
3 264 354 276 3 31 56 0 0 12 4 0 1 2 1006
P.M.
2:00-3:00
7 361 370 237 2 35 60 0 0 24 2 0 1 1 1100
P.M.
3:00-4:00
4 427 401 256 1 35 32 0 0 19 1 4 0 5 1185
P.M.
4:00-5:00
15 593 387 265 6 35 43 0 0 8 0 1 0 0 1353
P.M.
5:00-6:00
32 959 446 373 12 16 35 0 0 8 0 0 0 2 1883
P.M.
6:00 - 7:00
5 751 362 275 4 124 23 0 2 8 0 0 0 1 1555
P.M.
TOTAL 144 6938 5270 3635 81 532 548 0 2 138 18 5 7 18 17336
TRAILER 4axles
MOTORCYCLE
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
/TRICYCLE
TRAILER
UTILITY
UTILITY
TRUCK
TRUCK
GOODS
TOTAL
3+axles
5+axles
2axles
CAR
TIME
TRAILER 5+axles
TRAILER 4axles
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
RICYCLE
GOODS U
UTILITY
TRUCK
TRUCK
TILITY
TOTAL
3+axles
2axles
CAR
TIME
MOTORCYCLE/TR
PASSENGER CAR
TRUCK TRAILER
TRUCK TRAILER
GOODS UTILITY
RIGID TRUCK
RIGID TRUCK
PASSENGER
SMALL BUS
LARGE BUS
UTILITY
ICYCLE
TOTAL
3+axles
5+axles
2axles
4axles
TIME
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
UTILITY VAN/PICK-
CARGO TRUCK
MOTORCYCLE
ARTICULATED
EXPRESS)/FX
LARGE BUS
TRICYCLE
3-AXLE.35
BICYCLE
KALESA
HOV(UV
2-AXLE
TOTAL
PUJ
UP
UP
TIME
5:00 - 6:00
9 575 278 162 15 15 7 0 0 3 3 0 0 0 1067
A.M.
6:00-7:00
23 822 468 257 18 35 17 0 0 0 0 0 0 0 1639
A.M.
7:00-8:00
1 918 445 209 11 44 32 0 0 5 0 0 0 0 1665
A.M.
8:00-9:00
13 562 445 255 5 27 47 0 0 0 0 0 2 1 1359
A.M.
9:00-10:00
2 332 342 197 5 30 27 0 0 11 2 0 1 4 954
A.M.
10:00-11:00
1 253 323 198 1 33 23 0 0 8 0 0 0 2 842
A.M.
11:00-12:00
3 383 353 183 0 33 22 0 0 0 0 0 0 0 977
NOON
12:00-1:00
0 205 307 161 3 20 25 0 0 9 0 0 0 0 728
P.M.
1:00-2:00
0 257 409 203 3 29 50 0 0 2 0 0 0 0 952
P.M.
2:00-3:00
0 351 408 160 0 24 36 0 0 7 0 0 0 1 987
P.M.
3:00-4:00
1 409 322 181 0 27 0 0 0 23 0 0 0 3 967
P.M.
4:00-5:00
3 382 263 182 4 17 30 0 0 13 0 2 0 0 896
P.M.
5:00-6:00
14 489 229 215 8 0 20 0 0 3 0 0 0 2 978
P.M.
6:00 - 7:00
1 487 198 170 3 16 23 0 4 16 0 0 0 1 920
P.M.
TOTAL 71 6425 4792 2733 77 347 358 0 4 100 5 2 3 14 14931
UTILITY VAN/PICK-UP
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
CARGO TRUCK
ARTICULATED
MOTORCYCLE
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
TIME
5:00 - 6:00
7 295 217 162 0 7 13 0 0 2 0 0 0 0 703
A.M.
6:00-7:00
7 462 191 169 2 22 23 0 0 5 5 0 1 0 887
A.M.
7:00-8:00
3 449 280 225 5 14 28 0 0 11 0 0 0 0 1015
A.M.
8:00-9:00
1 266 325 160 0 16 33 0 0 12 6 0 0 0 819
A.M.
9:00-10:00
5 359 312 138 0 26 28 0 0 8 4 0 1 0 881
A.M.
10:00-11:00
1 353 401 234 3 23 29 0 0 10 2 0 0 0 1054
A.M.
11:00-12:00
2 230 485 192 14 17 38 0 0 19 1 0 0 0 998
NOON
12:00-1:00
0 269 395 170 6 30 28 0 0 5 0 0 0 0 903
P.M.
1:00-2:00
3 333 382 212 2 18 28 0 0 20 6 0 1 2 1006
P.M.
2:00-3:00
7 390 351 192 3 28 41 0 0 34 3 0 1 0 1049
P.M.
3:00-4:00
3 435 471 196 1 25 40 0 0 14 1 10 0 2 1198
P.M.
4:00-5:00
12 653 412 186 4 32 26 0 0 2 0 0 0 0 1326
P.M.
5:00-6:00
18 927 430 251 8 20 27 0 0 18 0 0 0 0 1698
P.M.
6:00 - 7:00
4 721 384 207 3 153 13 0 0 10 0 0 0 0 1494
P.M.
TOTAL 73 6141 5035 2692 51 432 394 0 0 168 27 10 4 4 15031
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
UTILITY VAN/PICK-
CARGO TRUCK
MOTORCYCLE
ARTICULATED
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
UP
TIME
5:00 - 6:00
16 870 495 325 15 22 20 0 0 5 3 0 0 0 1770
A.M.
6:00-7:00
30 1283 658 426 20 57 41 0 0 5 5 0 1 0 2526
A.M.
7:00-8:00
4 1367 726 435 16 57 59 0 0 16 0 0 0 0 2681
A.M.
8:00-9:00
14 828 771 415 5 44 81 0 0 12 6 0 2 1 2178
A.M.
9:00-10:00
7 691 654 335 5 56 55 0 0 19 6 0 2 4 1835
A.M.
10:00-11:00
2 606 724 432 4 55 51 0 0 17 2 0 0 2 1896
A.M.
11:00-12:00
5 613 838 375 14 50 59 0 0 19 1 0 0 0 1975
NOON
12:00-1:00
0 474 702 330 9 50 52 0 0 14 0 0 0 0 1631
P.M.
1:00-2:00
3 590 791 414 5 47 77 0 0 22 6 0 1 2 1958
P.M.
2:00-3:00
7 741 759 352 3 52 77 0 0 41 3 0 1 1 2037
P.M.
3:00-4:00
4 844 793 377 1 52 40 0 0 37 1 10 0 5 2165
P.M.
4:00-5:00
15 1035 675 368 8 49 56 0 0 15 0 2 0 0 2222
P.M.
5:00-6:00
32 1416 658 466 15 20 46 0 0 21 0 0 0 2 2676
P.M.
6:00 - 7:00
5 1208 582 376 5 170 36 0 4 26 0 0 0 1 2414
P.M.
TOTAL 144 12566 9827 5425 128 779 752 0 4 268 32 12 7 18 29962
GOODS UTILITY
TRAILER 5+axles
MOTORCYCLE/
TRAILER 4axles
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
TRICYCLE
UTILITY
TRUCK
TRUCK
TOTAL
3+axles
2axles
CAR
TIME
TRAILER 5+axles
MOTORCYCLE/
TRAILER 4axles
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
TRICYCLE
UTILITY
TRUCK
TRUCK
TOTAL
3+axles
2axles
CAR
TIME
TRAILER 5+axles
MOTORCYCLE/
TRAILER 4axles
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
TRICYCLE
UTILITY
UTILITY
TRUCK
TRUCK
GOODS
TOTAL
3+axles
2axles
CAR
TIME
UTILITY VAN/PICK-UP
HOV(UV EXPRESS)/FX
HEAVY EQUIPMENT
CAR/SUV VAN/PICK-
CARGO TRUCK
MOTORCYCLE
ARTICULATED
LARGE BUS
TRICYCLE
BICYCLE
KALESA
2-AXLE
3-AXLE
TOTAL
PUJ
UP
TIME
5:00 - 6:00
16 2174 1237 325 22 22 30 0 0 10 8 0 0 0 3844
A.M.
6:00-7:00
30 3209 1645 426 31 57 61 0 0 10 12 0 1 0 5481
A.M.
7:00-8:00
4 3417 1815 435 25 57 89 0 0 33 0 0 0 0 5874
A.M.
8:00-9:00
14 2070 1927 415 8 44 121 0 0 24 14 0 2 1 4639
A.M.
9:00-10:00
7 1727 1636 335 8 56 82 0 0 38 14 0 2 4 3910
A.M.
10:00-
11:00 2 1516 1810 432 6 55 77 0 0 34 4 0 0 2 3939
A.M.
11:00-
12:00 5 1532 2095 375 21 50 89 0 0 38 4 0 0 0 4209
NOON
12:00-1:00
0 1185 1754 330 14 50 79 0 0 27 0 0 0 0 3439
P.M.
1:00-2:00
3 1476 1979 414 7 47 116 0 0 44 15 0 1 2 4102
P.M.
2:00-3:00
7 1852 1899 352 4 52 116 0 0 82 6 0 1 1 4372
P.M.
3:00-4:00
4 2111 1982 377 2 52 60 0 0 74 4 24 0 5 4695
P.M.
4:00-5:00
15 2587 1688 368 13 49 83 0 0 30 0 5 0 0 4838
P.M.
5:00-6:00
32 3540 1646 466 23 20 70 0 0 41 0 0 0 2 5839
P.M.
6:00 - 7:00
5 3020 1456 376 8 170 54 0 8 52 0 0 0 1 5150
P.M.
GOODS UTILITY
TRAILER 5+axles
MOTORCYCLE/
TRAILER 4axles
RIGID TRUCK
RIGID TRUCK
PASSENGER
PASSENGER
SMALL BUS
LARGE BUS
TRICYCLE
UTILITY
TRUCK
TRUCK
TOTAL
3+axles
2axles
CAR
TIME
Project Component Length Width Unit Cost Financial Cost Economic Cost
Slope Protection 2.49 KM. 15 M Php 405,000,000.00 Php 1,008,450,000.00 Php 826,929,000.00
Main Bridge 0.77 KM. 15 M Php 1,200,000,000.00 Php 924,000,000.00 Php 757,680,000.00
Road 2.63 KM. 15 M Php 47,000,000.00 Php 123,610,000.00 Php 101,360,200.00
Road Right of Way 47,559.00 SQ.M. 19.1 M Php 2,000.00 Php 95,118,000.00 Php 95,118,000.00
Total Php 2,151,178,000.00 Php 1,781,087,200.00
Semi-
Public Rigid Rigid
Motor Motor Passenger Goods Small Large Trailer
Utility Truck 2- Truck 3-
Tricycle cycle Cars Utility Bus Buses Truck
Jeepney axle axle
4+axle
Running
Economic P/km 2.346 1.467 8.220 6.719 7.185 15.957 21.996 16.759 27.847 33.961
BVOC 2008 Time
Price Level P/min 1.418 1.374 6.807 7.443 2.569 12.589 27.820 1.024 1.456 2.095
S Pavement Type
CON & Condition Total Vehicle Operating Cost (P/km)
1 Paved Good 4.473 2.841 14.503 13.590 9.556 27.578 47.676 17.705 29.191 35.895
Paved
2 Good/Fair 4.590 3.039 15.438 14.498 10.113 29.344 50.916 18.621 30.695 37.754
3 Paved Fair 5.175 3.365 17.043 15.981 11.209 32.403 56.085 20.726 34.169 42.020
4 Paved Fair/Bad 5.862 19.680 37.864
5 Paved Bad 7.609 6.219 25.368 24.495 15.413 47.997 87.095 26.014 42.733 52.754
Paved Bad/Very
6 Bad 9.378 7.812 29.324 28.480 17.518 55.426 101.522 28.938 47.492 58.686
7 Paved Very Bad 12.942 11.015 35.956 35.029 21.287 67.926 125.033 34.747 56.998 70.471
8 Gravel Good 5.457 3.541 17.411 16.111 11.838 33.174 56.195 22.644 37.378 45.905
Gravel
9 Good/Fair 5.738 3.900 19.016 17.594 12.933 36.233 61.364 24.748 40.852 50.171
10 Gravel Fair 6.589 4.407 21.320 19.682 14.579 40.639 68.578 28.044 46.302 56.852
Gravel
11 Fair/Bad 7.438 5.270 24.349 22.722 16.212 46.330 79.563 30.362 50.080 61.556
12 Gravel Bad 8.641 6.864 28.985 27.451 18.574 55.018 96.773 33.388 54.985 67.697
Gravel
13 Bad/Very Bad 10.387 8.443 32.859 31.369 20.608 62.288 110.980 36.144 59.466 73.290
Gravel Very
14 Bad 13.669 11.469 38.505 37.112 23.514 72.873 131.852 39.943 65.631 80.999
Very Bad stone
15 pavement 23.421 20.489 63.282 63.003 35.030 119.097 226.970 51.897 84.757 105.284
16 Earth Bad 13.669 11.469 38.505 37.112 23.514 72.873 131.852 39.943 65.631 80.999
17 Earth Very Bad 23.022 20.239 61.885 61.861 33.809 116.384 223.230 49.048 80.023 99.510
18 Impassable
Semi-
Public Rigid Rigid
Motor Motor Passenge Goods Small Large Trailer
Utility Truck Truck 3-
Tricycle cycle r Cars Utility Bus Buses Truck
Jeepney 2-axle axle
4+axle
Running
P/km 3.045 1.904 10.672 8.723 9.328 20.718 28.558 21.759 36.154 44.092
Economic BVOC 2008
Price Level Time P/min 1.841 1.784 8.838 9.664 3.336 16.344 36.119 1.329 1.890 2.720
S Pavement Type &
CON Condition Total Vehicle Operating Cost (P/km)
1 Paved Good 5.81 3.69 18.83 17.64 12.41 35.80 61.90 22.99 37.90 46.60
2 Paved Good/Fair 5.96 3.95 20.04 18.82 13.13 38.10 66.11 24.18 39.85 49.02
3 Paved Fair 6.72 4.37 22.13 20.75 14.55 42.07 72.82 26.91 44.36 54.56
4 Paved Fair/Bad 7.61 6.02 25.55 24.14 16.48 48.52 85.00 29.84 49.16 60.51
5 Paved Bad 9.88 8.07 32.94 31.80 20.01 62.32 113.08 33.77 55.48 68.49
6 Paved Bad/Very Bad 12.18 10.14 38.07 36.98 22.74 71.96 131.81 37.57 61.66 76.19
7 Paved Very Bad 16.80 14.30 46.68 45.48 27.64 88.19 162.33 45.11 74.00 91.49
8 Gravel Good 7.08 4.60 22.60 20.92 15.37 43.07 72.96 29.40 48.53 59.60
9 Gravel Good/Fair 7.45 5.06 24.69 22.84 16.79 47.04 79.67 32.13 53.04 65.14
10 Gravel Fair 8.55 5.72 27.68 25.55 18.93 52.76 89.04 36.41 60.11 73.81
11 Gravel Fair/Bad 9.66 6.84 31.61 29.50 21.05 60.15 103.30 39.42 65.02 79.92
13 Gravel Bad/Very Bad 13.49 10.96 42.66 40.73 26.76 80.87 144.09 46.93 77.21 95.15
14 Gravel Very Bad 17.75 14.89 49.99 48.18 30.53 94.61 171.19 51.86 85.21 105.16
15 Very Bad stone pavement 30.41 26.60 82.16 81.80 45.48 154.63 294.68 67.38 110.04 136.69
16 Earth Bad 17.75 14.89 49.99 48.18 30.53 94.61 171.19 51.86 85.21 105.16
17 Earth Very Bad 29.89 26.28 80.35 80.32 43.89 151.10 289.82 63.68 103.90 129.20
18 Impassable
FORCASTED TRAFFIC
PASSENGER/
GOODS RIGID RIGID ARTICULATED TOTAL
MOTORCYCLE/ PASSENGER LARGE
YEAR UTILITY/ TRUCK - TRUCK - CARGO
TRICYCLE CAR BUS
SMALL 2AXLE 3+AXLE TRUCK
BUS/PUJ
1 2019 9620 5206 787 0 232 28 12 15885
2 2020 9909 5388 818 0 239 29 12 16395
3 2021 10206 5577 851 0 246 30 13 16922
4 2022 10512 5772 885 0 254 31 13 17467
5 2023 10827 5974 921 0 261 32 14 18028
6 2024 11152 6183 958 0 269 32 14 18608
7 2025 11487 6400 996 0 277 33 14 19207
8 2026 11831 6623 1036 0 285 34 15 19825
9 2027 12186 6855 1077 0 294 35 15 20463
10 2028 12552 7095 1120 0 303 37 16 21122
11 2029 12928 7344 1165 0 312 38 16 21803
12 2030 13316 7601 1212 0 321 39 17 22505
13 2031 13716 7867 1260 0 331 40 17 23230
14 2032 14127 8142 1310 0 341 41 18 23979
15 2033 14551 8427 1363 0 351 42 18 24752
16 2034 14988 8722 1417 0 361 44 19 25551
17 2035 15437 9027 1474 0 372 45 19 26375
18 2036 15900 9343 1533 0 383 46 20 27226
Total Survey
Total Survey
3.73 Length 3.73
Length (km.):
(km.):
STATION STATION
Travel Travel Ave. Est.
Number of From To From To
Traffic Condition Time Time Time
Run
Tuguegarao City Difference Tuguegarao Difference (minutes)
Libag Sur Libag Sur
Center City Center
AM PEAK 1 7:47:51 7:57:34 0:09:43 8:58:11 9:06:41 0:08:30 0:09:07
Travel Time per Direction 0:09:07
PM PEAK 1 5:27:54 5:37:23 0:09:29 6:37:27 6:45:36 0:08:09 0:08:49
Travel Time per Direction 0:08:49
Average Travel Time (AM and PM Peak): Directional Flow = Decreasing Chainage 0:08:58
say 9
Total Survey
Total Survey
3.73 Length 3.73
Length (km.):
(km.):
PASSENGER/
ARTICULA
YEAR MOTOR- GOODS RIGID RIGID TOTAL
PASSENGER LARGE TED
CYCLE/ UTILITY/ TRUCK - TRUCK -
CAR BUS CARGO
TRICYCLE SMALL 2AXLE 3+AXLE
TRUCK
BUS/PUJ
FORCASTED TRAFFIC
PASSENGER/
YEAR MOTOR- RIGID RIGID TOTAL
PASSENGER GOODS LARGE ARTICULATED
CYCLE/ TRUCK - TRUCK -
CAR UTILITY/ BUS CARGO TRUCK
TRICYCLE 2AXLE 3+AXLE
SMALL BUS/PUJ
[7] R. D. C. 02, Cagayan Valley Regional Development Plan 2011-2016, March 2018.
[9] N. E. C. C. L. N. S. &. S. M. C. Katahira & Engineers International, Study on the Project for
Construction of davao-Samal Bridge in Republic of the Philippines, Febrary 2016.
[10] O. C. C. L. E.-J. E. C. I. Japan International Cooperation Agency, The Feasibility Study on the
Construction of a New Bridge across River Nile at Jinja The Republic of Uganda, October 2009.