TECHNICAL ASSIGNMENT
for construction and erection works for the lot:
Bank strengthening (04UPC), Rooppur NPP
Moscow
2017
1
TABLE OF CONTENTS
2
SECTION 1. DESCRIPTION OF THE WORKS TO BE PERFORMED
1.1 Construction and erection works for the lot: Bank strengthening (04UPC), Rooppur NPP.
3
products. Designs for various climatic regions. Categories, conditions of operation, storage and
transportation as regards to impacts of ambient climatic factors” is also tropical humid (sub-equatorial
monsoon climate).
Site fencing
The temporary fence around the site shall be constructed using temporary materials. Fence
around the work execution areas is made of steel mesh with a height of at least 1.6 m. After
completion of works, the Subcontractor shall dismantle the fence.
Outdoor lighting
Temporary lighting of the territory provided for the construction works shall be performed in
the scope required and sufficient for safe execution of construction and erection works. The lighting
system, number and capacity of spotlights, layout of masts, cable routes shall be specified in a WEP.
Upon completion of work, the outdoor temporary lighting system shall be dismantled by a
Subcontractor.
Earthworks
Soil, materials, products and structures used while building the underground structures and
foundations shall meet the requirements of the Working documentation and the corresponding
standards. Replacement of soil, materials, products and structures required for construction of the
building or its foundation shall be allowed upon approval of the design organization and the Customer
only.
Surface preparation for the slope strengthening:
- slope slicing;
- removal of the grass and moor vegetation;
- removal of top soil, peaty soil, silty and other types of soil containing organic substances;
- removal of top decompressed (soupy) soil layer.
- slope arrangement;
Concealed Works Acceptance Statement/Certificate shall be formalized for all concealed
works.
The requirements of the Construction Management Plan shall be taken into consideration while
planning of the sequence of civil and erection works as well as environmental conditions of the
Rooppur NPP site, including meteorological and hydrological conditions.
Formwork installation
For the purpose of the formwork installation for plane surfaces and curved surfaces of
structures to be concreted, the demountable plywood and metal formwork made of unified components
shall be mainly applied.
Deviations of installed formworks from the design position shall not exceed construction
tolerances, the surface projections at joints of panels shall not exceed 2 mm.
Concrete curing
Purpose of concrete curing is creation of favorable temperature and humidity conditions for the
hydration of cement during concrete strength development, to avoid overheating, drying and cracking
of surfaces and formation of shrinkage cracks in concrete structures. It is to be provided with the
continuous damping of concrete surface or outer sides of formworks until its removal by watering or
water spraying. Wet cloth (i.e. Tarpaulin, mats, canvas) shall be placed on the open surfaces for their
protection.
Damping of open horizontal, vertical or sloping concrete surfaces after early (after 1-2 days)
removal of formworks by spraying water from hoses, is not permitted within 2 days from the date of
placement or removal of formwork.
All construction and erection works shall be performed in accordance with the engineering
solutions specified in the Working Documentation, WEP and Process Charts and also in strict
compliance with the requirements of the RF RTD, including as follows:
- SP 48.13330.2011. Organization of construction. Revised edition of SNiP 12-01-2004;
- SP 126.13330.2012. Geodetic works in construction. Revised edition of SNiP 3.01.03-84;
- SNiP 3.01.04-87. Acceptance of the completed facilities for operation. General Provisions;
- SP 45.13330.2012. Earth structures, basements and foundations. Revised edition of SNiP
3.02.01-87;
- SP 16.13330.2011. Steel structures. Revised edition of SNiP II-23-81;
- SP 70.13330.2012. Bearing and enclosing structures;
- SP 71.13330.2011. Insulation and finishing coatings;
- SP 34.13330.2012. Motorways;
- SNiP 3.05.06-85. Electrical devices;
- RF Government Decree on Fire Prevention Activities in the RF No. 390 of 25.04.2012
(together with the Fire Prevention Rules in the RF);
Geodetic works
Geodetic instruments shall be verified and adjusted.
The geodetic works shall be performed with involvement of the trained personnel whose
qualification shall be proved with the documents.
6
Geotechnical monitoring
Geotechnical monitoring is carried out from the start of the excavation works in compliance
with geotechnical monitoring program and RD 34 15.073-91 “Guidance on geotechnical monitoring
over the preparation of grounds and erection of soil structures in power engineering”.
As-built Documentation
The as-built documentation shall be executed in compliance with the requirements of
applicable standards, SNiPs, RTD and "Regulation for execution of the as-built documentation".
“The Regulation for execution of the as-built documentation” is based on application of RD-
11-02-2006 “Requirements for the contents and procedure for maintenance of the as-built
documentation in the course of construction, reconstruction, overhaul repair of capital construction
facilities and the requirements applying to the acts of inspection of works, structures, utility network
sections”.
Changes in the documents at all stages shall be introduced on the basis of the notifications
according to the requirements of RD 210.002-89, GOST R 21.1101-2013, GOST 2.503-2013.
3.2 Requirements for finalizing and content of the Work Execution Plan (WEP)
3.2.1 The Subcontractor shall agree upon all the WEPs with the Contractor and the Customer
and, if necessary, with the organizations, which issued the technical specifications.
3.2.2 The WEP shall be developed for erection of the facility on the whole and (or) of its
constituent parts, for the works of the preparatory period, as well as for performance of separate types
of construction and erection works or demolishing (dismantling) works.
As part of the WEP for the facility as a whole and (or) for its constituent parts, the following
shall be developed: the calendar work execution plan for the facility; the construction general plan or
the plan for the works area and of adjacent territories; the schedule for delivery of building structures,
goods and materials to the facility or removal of the demounting waste from the facility; labor staff
demand schedule; main machines demand schedule; geotechnical monitoring program; process charts
for separate types of works; maps (schemes) for work quality control; labor protection and safety
measures; the explanatory note.
3.2.3 The work execution calendar plan for the facility determines the sequence and deadlines
for performance of construction and erection works. According to the data of the calendar plan, the
demand in construction machines, workers shall be determined, as well as the deadlines for delivery of
building structures, products, materials and process equipment.
3.2.4 The general construction plan shall be developed in the part necessary for work execution
at the facility. The plan shall specify the location of permanent and temporary transport routes,
temporary water supply networks, sewerage, power supply, heat supply, cargo lifting cranes,
storehouses, temporary inventory buildings, structures and devices to be used for providing
construction or demolition (dismantling) works.
3.2.5 It is necessary to develop the schedule of delivery of building structures, products and
materials to the facility for construction works, as well as the labor staff demand schedule, the main
construction machines and mechanisms demand schedule, in compliance with the requirements
specified in MDS12-46.2008.
3.2.6 Geotechnical monitoring program shall be developed with the consideration of
SP 47.13330.2012 (revised edition of SNiP11-02-96: Engineering survey for construction purposes.
General provisions), SP 11-105-97: Engineering geological survey for construction purposes. Part I.
7
General rules for performing the surveys, RD 34 15.073-91: Manual for geotechnical monitoring of
foundation preparation and erection of soil structures in power engineering.
3.2.7 During elaboration of the WEP it is necessary to be guided by the following requirements
of the applied regulatory technical documentation, including as follows:
- RF Decree on Fire Prevention Activities in the RF No. 390 of 25.04.2012 (together with the
Fire Prevention Rules in the Russian Federation);
- SNiP 12-03-2001, SNiP 12-04-2002. Safety on labor conditions in construction. General
requirements. Part 1.2;
- SP 34.13330.2012. Motorways;
- SP 48.13330-2011. Revised edition of SNiP 12.01-2004. Organization of construction;
- PB 13-407-01. Uniform safety rules for blasting operations;
- GOST 12.3.009-76*. Loading and unloading works.
General safety requirements;
- GOST 12.1.046-2014. Occupational Safety Standards System. Construction. Norms of
construction site lighting;
- GOST 23407-78. Fencings for building sites. Specifications;
- 1040-10-OOS NIMB-project LLC (List of environmental protection measures);
- SP 45.13330-2012, revised edition of SNiP 3.02.01-87. Earthworks, Grounds and Footings;
- POT R M-016-2001. Interindustry labor safety rules for operation of electrical installations;
- PTE EP (Rules for the technical operation of consumer power plants)
- Federal Law on Environmental Protection No. 7-FZ of 10.01.2012;
-SP 126.13330. 2012 revised edition of SNiP 3.01.03-84 Geodetic works in construction;
- SNiP 3.05.06-85. Electrical devices;
- Fire Safety Rules in the Russian Federation;
- MDS 12-46.2008. Methodical recommendations for development and execution of the
construction management plan, plan for arrangement of demolition (dismantling) works, work
execution plan.
8
9
SECTION 6. LIST OF DESIGN AND WORKING DOCUMENTATION
6.1. The List of the Design documents for performance of construction and erection works on
the facilities specified in Sub-clause 2.2 hereof is provided in Table 1.
Table 1
Section/
Title of the section/ book KKS Code
Volume
Section 6 Construction management plan and commissioning
6. 1. Organization of construction
6.1.1 Text part
Volume 1 General RPR-P06010101-BAA0001
6.1.2 Graphic part
Volume 1 Drawings RPR-P06010201-BAA0001
10
6.2. List of the Working Documentation for performance of construction and erection works on the facilities specified in Sub-clause 2.2 hereof is provided in Table 2.
Table 2
Note:
*Code of works as per the Contract with the Customer
11
SECTION 7. REQUIREMENTS AND CONDITIONS FOR DEVELOPMENT OF
ENVIRONMENTAL PROTECTION MEASURES AND ACTIVITIES
Process engineering solutions providing limitation of hazardous releases into the
atmosphere
Potential sources of environmental pollution can be the following sources:
concrete mixing facility (dusting of concrete, sand, broken stone);
mechanization base;
vehicle roads (dusting in dry weather).
In order to eliminate or mitigate negative impacts on the environment, the following process
solutions are stipulated:
concrete and mineral powder receipt and supply by pneumatic transport, with storage in
silos equipped with special filters;
supply of inert materials by closed conveyor galleries; adjustment of engines;
solid coating of motorways, watering in dry weather.
12
Fire prevention measures shall be envisaged by primary means, such as: sand, water, manual
foamy, carbon-dioxide and powder fire extinguishers.
It is not allowed to perform works without agreed and approved work execution plans, which
include labor safety solutions.
Arrangement of rainstorm and other water discharge from the area of the sites and
foundation pits
In the course of execution of works, the surface wastewater shall be discharged from the
Rooppur NPP site in a controlled way, which is preceded by construction of the drain ditch system.
Prior to construction of the drainage ditch, water shall be discharged from the excavated pits
under the structures from the open pit, using water discharge pumps with the subsequent discharge into
the temporary water drainage ditch through the drainage system.
13
SECTION 8. DEADLINES (INTERVAL) FOR PERFORMANCE OF WORKS
All construction and erection works on the facilities specified in Sub-clause 2.2 hereof shall be performed within the time limits specified in the
Works Performance Schedule, Table 3:
Work Performance Schedule
Table 3
Note:
*Code of works as per the General Contract with the Customer
14
SECTION 9. REQUIREMENTS FOR QUALITY OF THE WORKS TO BE
PERFORMED
Control of quality of the construction and erection works to be performed by the Subcontractor,
includes the following requirements:
- incoming inspection of the design and working documentation submitted by the Contractor;
- acceptance of geodetic control network;
- incoming inspection of the materials and products to be applied;
- operational inspection in the course of implementation and upon completion of operations;
- acceptance inspection.
In the course of performance of the Works the Subcontractor shall be guided by the
Subcontractor's quality management system documentation developed according to the requirements
of ISO 9000 standards and the legislation of the People’s Republic of Bangladesh;
The Subcontractor shall have a certified quality management system in line with the
requirements of GOST R ISO 9001-2008 (ISO 9001:2008), with submission of the corresponding
certificate.
15
- GOST 12.1.046-85. Lighting of building sites;
- RF Decree on Fire Prevention Activities in the RF No. 390 of 25.04.2012 (together with the
Fire Prevention Rules in the Russian Federation);
- WD-11-02-2006. Requirements for the contents and procedure for maintenance of the as-built
documentation in the course of construction, reconstruction, major repair of capital construction
facilities and the requirements applied to the acts of inspection of the works, structures and utility
network sections;
- POT R M-016-2001. Interindustry labor safety rules for operation of electrical installations;
- PTE EP (Rules for technical operation of power installations for loads);
- Federal Law on Environmental Protection No. 7-FZ of 10.01.2012;
- SNIP 3.05.06-85. Electrical devices.
16
SECTION 16. LIST OF ADOPTED ABBREVIATIONS
Item
Abbreviation Interpretation of abbreviation
No.
1. CEW Construction and Erection Works
2. CMP Construction Management Plan
3. ETP Engineering and Technical Personnel
4. GOST State Standard
5. NPP Nuclear Power Plant
6. PPB Fire Safety Rules
7. RD Guideline Documents
8. RTD Regulatory Technical Documentation
9. SNiP Construction Norms and Rules
10. SP Code of Rules
11. TA Technical Assignment
12. WEP Work Execution Plan
17
SECTION 17. LIST OF APPENDICES
Берегоукрепление. Ведомость
объемов работ/
1. RPR.0130.04UPC.0.KZ.TB0001.V0001 A-183233 C01
Shore protection. List of work
scopes.