Attention
The circuit-breaker may be filled only by
SF6 or under the supervision of qualified per-
3.1.6 SF6 sonnel, and in accordance with the SF6
filling curve (see under 3.1.6 Arc Quench-
ing Medium SF6).
Attention
SF6 IEC 60376 For filling the breaker with gas only use
SF6-gas which corresponds the demands
acc. IEC 60376.
WARNING
- High gas pressure - Danger of bursting!
Exceeding the permissible filling pressure
can cause the pole columns to burst,
resulting in severe personal injury and
damage to property.
0000126a
56 927-55511-001_0-
4 - Installation
1009378a
B4 B4 Density monitor
MA MA Pressure gauge
W1 W1 Filling flange
W2 SF6- W2 Test connection (SF6-density monitor)
11 11 Breaker base
927-55511-001_0- 57
4 - Installation
1007051a
W1 W1 Filling flange
1 1 Gas cylinder
2 2 Pressure reducer regulating valve
3 (0 9.0 bar) 3 Pressure gauge (0 up to 9.0 bar)
4 4 Safety valve
31 Fig. 31 Gas filling device connected
WARNING
Release the SF6-pressure before working
SF6 on the screw connections of the gas
chamber.
If a leak is discovered, undo the leaking connection
and check the sealing surface for damage or foreign
bodies. Then fit a new seal, remake the connection
and repeat the leak test.
58 927-55511-001_0-