Procedure for placing indents in SAP
1. Go to SAP Logon and login with your ID.
2. Enter the T-Code “IW31” for placing indents. ( note: for O&M works)
3. Enter the “order type” as ‘PM08’ for O&M material.
4. Enter “Priority” as ‘high’ or ‘medium’ depending of necessity of material.
5. Go to “Functional Location” and search for ‘location list’.
6. Go to ‘location data’ and enter “Maintenance plant” as 3312.
7. Enter “Plant section” as ‘MNB’ and then press ‘execute’.
8. Now select corresponding feeder bay ID or substation ID.(eg: SS-400KV-MNB)
9. Now click on “Header data”.
10. Enter “text”.
11. Now go to “components” tab.
12. Now enter the “Part No”.
13. Now enter “quantity”.
14. Save. (It will fetch “order number”)
Now the indent is in created status.
1. Enter T-code “IW32” from EE ID.
2. Enter the “order number” and press ‘execute’.
3. Select ‘green flag’ and then save.
4. Now indent status will go to ‘released state’.
After the allotment go to “IW32” and then go to “enhancement tab” and select “
Outbound delivery ” and copy the allotment number and then go to T-code
“ZMM_PRINT” and enter ‘ OBD number’ and press ‘ enter’ to take print of
allotment slip .
Note:-After the material drawn from stores physically, the material will be
transferred to virtual stores of concerned ID (employee ID on whom the material
was drawn).
3
Procedure for placing indents in SAP (for capital works)
1. Go to SAP Logon and login with your ID.
2. Enter the T-Code “IW31” for placing indents. (note: for RMI works)
3. Enter the “order type” as ‘PM06’ for RMI or capital works.
4. Enter “Priority” as ‘high’ or ‘medium’ depending of necessity of material.
5. Go to “Functional Location” and type as ‘SS-400KV-MNBL’ & press enter.
10. Enter “text” ( eg: indent for fuses ).
11. Now enter WBS Id in ‘additional data’ tab.
It will ask as ‘should dates be copied’ then press “YES”.
12. Now enter the “Part No” and “quantity” in “components” tab
13. Now enter “quantity”.
It will ask as ‘should PR be created’ then press as “NO”
14. Save. (It will fetch “order number”)
Now the indent is in created status.
1. Enter T-code “IW32” from EE ID.
2. Enter the “order number” and press ‘execute’.
3. Select ‘green flag’ and then save.
4. Now indent status will go to ‘released state’.
After the allotment go to “IW32” and then go to “enhancement tab” and select “
Outbound delivery ” and copy the allotment number and then go to T-code
“ZMM_PRINT” and enter ‘ OBD number’ and press ‘ enter’ to take print of
allotment slip .
4
Procedure for creating Purchase Requisition in SAP
(Note: Purchase Requisition should be created for materials such as computer
equipment only)
1. Go to SAP Logon and then login with your ID.
2. Enter the T-code “ME51N”.
3. Select “Document Overview ON” field.
4. Select “Document type” field as “Material Indent”
5. Select “Header” and then write the details of the indent in the box.
6. Select the “Item Overview” tab and then give “ Account Assignment (A) ” as “Q”
and “Item Category (I)” as “U”.
7. Enter the “Material Number” field by search or type the number as per P.O.
8. Enter the “Quantity” field, “Plant” field as 3312 ( your circle code) .
9. Enter the “Storage location” field with your substation code (e.g.: B401 for
400KVSS MNBL) and “PGR” field from the list. (e.g. : 445 for AET/ MNBL)
10. Enter the “supply plant” field with your stores ID ( e.g. 1040 for Gunadala)
11. Select the “Item Detail” tab and enter ‘WBS element’ in “Account Assignment”
tab.
12. Select the “Contact Person” tab and give “MRP controller” as ‘Z02’.
13. Select the “check” symbol on the top and verify for errors if any.
14. If there are no errors, then enter another item in “Item overview” tab.
15. Repeat the same procedure for all items and then “Save”.
16. It will fetch the ‘Purchase Requisition’ number which is to be forwarded to the
circle office.
Procedure to see the allotment number
1. Enter the T-code “ME23N”. ( Query for PR Number)
2. Select the “Item” tab.
3. Select the “purchase order history” tab and copy allotment number from the
“Material Document” field.
5. Enter the T-Code “ZMR_ PRINT” and enter the “material document” number
It will fetch the issue slip which is to be circulated to the stores.
5
Procedure for devolution of scrap in SAP
1. Go to SAP Logon and login with your ID.
2. Enter the T-Code “IW31” for devolution of scrap.
3. Enter the “order type” as ‘DV01’.
4. Enter “Priority” as ‘high’ or ‘medium’ depending of necessity of material.
5. Go to “Functional Location” and search for ‘location list’.
6. Go to ‘location data’ and enter “Maintenance plant” as 3312.
7. Enter “Plant section” as ‘MNB’ and then press ‘execute’.
8. Now select corresponding feeder bay ID or substation ID. (eg: SS-400KV-MNB)
9. Now click on “Header data”.
10. Enter “text”.
11. Now go to “components” tab.
12. Now enter the “Part No”.
13. Now enter “quantity”. ( quantity to be entered in negative for devolution)
14. Save. (It will fetch “material order number”)
Now the indent is in created status.
1. Enter T-code “IW32” from EE ID.
2. Enter the “material order number” and press ‘execute’.
3. Select ‘green flag’ and then save.
4. Now devolution status will go to ‘released state’.
5. Now enter the T-code “MIGO”.
6. Now Select “Goods Issue” from first scroll bar and select goods movement
number “262” and enter material order number and press ‘execute’.
7. Now enter ‘plant’ and ‘storage location’ for all the items.
8. Now select “Check” for any errors and then select “Post” and save.
9. Now Enter T-Code “ZMM_STO”.
10. Now enter the ‘material document No.’, ‘year’, ‘purchase group’ and enter the
plant to delivery. ( eg: 1040 or 1050) and press ‘execute’.
11. Now check all the items in display and then press “Create PO”.
12. It will fetch ‘Purchase order’ number.
13. Now enter the T-Code “MIGO”.
14. Now Select “Goods Issue” from first scroll bar and select goods movement
number “351” and enter ‘purchase order’ number and press ‘execute’.
15. Now also enter ‘plant’ and ‘storage location’ for all the items.
16. Now select “Check” for any errors and then select “Post” and save.
6
Procedure for creating Delivery Order in SAP
(Note: Delivery order should be created after creating customer order for materials which are
auctioned)
Now take the print and submit this delivery order to stores along with T-Note for
further regularisation.
7
Procedure for checking stock in transit
1. Go to SAP logon and login with your ID.
2. Enter the T-code “ZMB5T” for checking stock in transit.
3. Now enter your “plant” and enter
4. Now select ‘detailed list’ icon to have excel view of material.
Procedure to clear the “Stock in transit” (after the material drawn from stores)
1. Enter the T-code “MIGO” from the ID (ID for which stock to be cleared).
2. Select “Goods receipt” in first scroll bar and then enter “OBD No.”.
3. Press “Execute” (tick mark)
4. Now select the ‘Item ok’ for all the items in the list.
5. Press ‘check’ button for any errors.
6. Press ‘Post’ button and then press ok.
Now the material is transferred to concerned EE ID.
1. Enter the T-code “MIGO” from the ID (ID for which stock to be cleared).
2. Enter “Goods Issue” in first scroll bar and then enter “Order No.”
3. Press “Execute” (tick mark)
4. Now select the ‘Item ok’ for all the items in the list.
5. Press ‘check’ button for any errors.
6. Press ‘Post’ button and then press ok.
Now the material was transferred to the SS ID.
8
Procedure for searching Purchase Orders in SAP
1. GO to SAP Logon and login with your ID.
2. Enter the T-Code “ME23N” to see Purchase orders.
3. Now go to the left pane of the screen and then select “Select variant”
( Tricolour symbol).
4. Now select the “purchase orders” in the list.
5. Now query by “plant” location or by “purchase group”in the new screen
slide to see the purchase orders.
9
Procedure for Service Entry in SAP
1. Go to SAP Logon and login with your ID.
2. Enter the T-Code “ML81N” for creating service entry. (E.g. for vehicle, manning)
3. Select the required “PO Number” from the list on the left pane of screen
4. Now select “create” icon on top.
5. Enter ‘short text’. (Free text) (Eg: CC 1 N part)
6. Enter “Document date” (Month end date for vehicle and manning bills)
7. Enter “Reference”. (Free text)(eg: vehicle bill of EE/O&M)
8. Enter “document text”. (free text)(Eg: vehicle bill of EE/O&M for aug-18)
9. Click on “service selection” icon and then press ‘Ok’.
10.Select the required ‘PO lines’ and then do RMB(Right click) and select
“Adopt services”.
11. Now enter “quantity”. (Eg: 1) (days/month as per PO lines)
12. Now select the ‘green flag’ and then ‘save’.
13. Now bill status will change to “accepted”.
14.It will fetch “Service entry number”.
To print the bill Enter T-code “ZMM_ Work Bill”.
1. Enter “PO number” and then “service entry number”.
2. Enter “Recoveries”.
3. Now press “Execute”.
It will fetch the bill now type as “pdf!” on top searchbar to save the bill in pdf
format.
10
SAP Procedure for Stock transfer from one WBS ID to other
(This procedure is necessary if material is directly received to field site).
11
Procedure for Form-13 in SAP
1. Go to SAP Logon and login with your ID. (AE/M ID)
2. Enter the T-Code “ME23N” to display the required PO.
3. Select the required “PO Number” from the list on the left pane of screen
4. Now go to confirmations tab and copy inbound delivery number from PO.
5. Now go to the T-Code “MIGO” and select ‘goods receipt’ in first scroll bar,
‘inbound delivery’ in second scroll bar and movement type 103.
6. Now paste inbound delivery no which was copied from PO and press execute.
7. Enter Invoice no. of the bill and goods delivery date in ‘delivery note’ field and material
received date in ‘posting date’ field.
8. Tick mark the ‘Item OK’ in the bottom and then save.
9. It will fetch the order number.
10. Now Login with ADE/Maintenance Id (for check measurement)
11. Now enter T-code “QA32”. And select dynamic selection symbol.
12. Now go to ‘procurement’ and then ‘purchasing document’.
13. Now enter the PO No. and make all the fields empty and enter plant (3312).
14. Now press “Execute”.
15. It will fetch all the items and now select required line
16. Now select ‘Results’ tab and select ‘calendar button’ and enter date and time of check
measurement.
17. Enter ‘code’ as 01and ‘Non-conf’ as zero.
18. Now login with AE/M id and repeat steps 11 to 14.
19. Now select ‘Usage decision’ tab and enter ‘UO code’ as zero.
20. Now enter “Storage location’ (Substation location) and save.
21. To generate Form-13 enter T-code “ZMM_ Form13”.
22. Enter “material document no”, ‘plant’ (3312), ‘year’ and press execute.
23. Now Tick mark the check measurement box and enter “condition of material” as
GOOD, “material received as per specification” as YES, “material received at” as FIELD
SITE and press execute.
24. To take Form-13 print go to T-code “ZMM_FORM13PRINT”and repeat Step 22.
25. Enter ‘print no’ field ( No. of copies) and take print.