FOR APPROVAL

A 19.12.2018 D.N.Duc H.S.Lee I.B.Wee FOR APPROVAL


Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier

CONSTRUCTION CORPORATION NO.1

Project

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT

Title

INSPECTION & TEST PLAN FOR PC SHEET PILE WORK

Document No. Rev. Page-No.


NS2-DH01-P0ZEN- A 4
ID NO: NS-DH01-P0ZEN-169256

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT REV: A

INSPECTION & TEST PLAN FOR PC SHEET PILE WORK


Participation by
Description of Inspection & Codes & Standard
No. Acceptance Criteria Record format Sampling Frequency
Test Proceduce Sub. Cont.
Employer/
WSP
1 Delivery
Factory inspection & test
1.1
before delivery
Performance JIS A 5373:2010 Not over 0.05 mm crack’s Factory & Laboratory
2 arbitrary numbers/lot must
a - Compressive strength test Annex C width at cracking moment format H S S
conform to acceptance criteria
- Bending test
Free from flaw, chip,
JIS A 5373:2010 camber, torsion and must
Each pile. All checked
Annex C be smooth as practically Factory check
b Apperance H R R samples must conform to
TCVN 10401:2015 acceptable.
acceptance criteria
Crack width not exceeding
0.2 mm
Submit document of: Factory
quality certificate, Result of JIS A 5373:2010 As per approved MAR Factory and
c H R R Each lot
compressive strength test, laboratory form
Result of Bending test
JIS A 5373:2010 Width: +7 & -2 mm
Annex C Height: +7 & -2 mm
Each pile must conforms to
d Shape & Dimension Approved MAR Thickness: +7 & -2 mm Factory check H R R
acceptance criteria
NS2-DE00-P0ZEN- Length: ± 30 mm
169211
1.2 Delivery Inspection
Free from flaw, chip,
JIS A 5373:2010 camber, torsion and must
Each pile. All checked
Annex C be smooth as practically Form 01
a Apperance H W W samples must conform to
TCVN 10401:2015 acceptable.
acceptance criteria
Crack width not exceeding
0.2 mm
JIS A 5373:2010 Width: +7 & -2 mm
Annex C Height: +7 & -2 mm
Each pile must conform to
b Shape & Dimension Approved MAR Thickness: +7 & -2 mm Form 01 H W W
acceptance criteria
NS2-DE00-P0ZEN- Length: ± 30 mm
169211
2 Equipment
Driving machine (crane with Approved Method Stamped
H W R Before execution of work
hammer, generator, trailer…) statement

1
ID NO: NS-DH01-P0ZEN-169256

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT REV: A

INSPECTION & TEST PLAN FOR PC SHEET PILE WORK


Participation by
Description of Inspection & Codes & Standard
No. Acceptance Criteria Record format Sampling Frequency
Test Proceduce Sub. Cont.
Employer/
WSP
3 Sheet pile driving

3.1 Setting out checklist

a Bench mark TCVN 9394:2012 At least 10m from structure Form 02 H W R Before driving

b Calibration of equipment TCVN 9394:2012 Form 02 H W R Before driving


TCVN 9394:2012 Deviation not exceeding
c Marking center line Form 02 Before driving
1cm/100m in length
TCVN 9394:2012 Inclination not exceeding
3.2 Vertical check (Plumbness) Form 02 H W R Each pile/During driving
1/100
Deviation of centerline not
3.3 Pile location check TCVN 9394:2012 exceeding 0.2t ~ 2.4 cm Form 02 H H W Each pile
(t – thickness of pile)
3.4 Pile top elev. TCVN 10401-2015 ± 5 cm Form 02 H H W Each pile
Approved ITP NS2- Follow approved ITP
(Form 01, 04, 05, 06,
3.5 Concreting work DH01-P0ZEN- No: NS2-DH01-P0ZEN-
07, 08, 09)
169028 169028
Abbreviation: S: Surveillance R: Report review RW: Random Witness Inspection W: Witness Inspection H: Hold Point

Page 2
ITP No. NS2-DH01-P0ZEN-169256
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT Rev.: A
Date: 2019.12.19
Format no.: Form 01
PC SHEET PILE DELIVERY INSPECTION
Date:
Sub-contractor: CC1 Start Time:
Work Title: Finish Time:
Inspected item:
Structure/Location:
Reference drawings/ documents:
Method of Inspection
□ Visual □ Laboratory test □ Measurement □ Survey □ Others

Inspection content Assessment


No.
Sheet Production Surface
Type Height Width Length Thickness Remark Accept Reject
pile code date condition
1
2
3

10
11
12
13
14
15
16
17
18
Comments:

Conclusion: Accepted the above inspected work and agreed to carry out the next civil works.

Owner Contractor Sub-contractor

Position

Signature

Full Name

3
ITP No. NS2-DH01-P0ZEN-169256
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT Rev.: A
Date: 2019.12.19
Format no.: Form 02
PC SHEET PILE DRIVING INSPECTION
Date:
Sub-contractor: CC1 Start Time:
Work Title: Finish Time:
Inspected item:
Structure/Location:
Reference drawings/ documents:

Sheet pile No.: Sheet pile type:

Finished sheet pile top elev: Actual sheet pile length:

Hammer type: Hammer weight:

No. Inspected properties Acceptance criteria Assessed by

1 Setting out checklist

Permit to work (PTW) ☐ OK ☐ Not OK

Calibration of equipment ☐ OK ☐ Not OK

Bench mark installation At least 10m from structure ☐ OK ☐ Not OK

Deviation not exceeding


Center line marking ☐ OK ☐ Not OK
1cm/100m in length

Inclination not exceeding


2 Vertical check (Plumbness) ☐ OK ☐ Not OK
1/100

Not exceeding 0.2t~2.4cm


3 Sheet pile location check ☐ OK ☐ Not OK
(t – thickness of pile)

4 Sheet pile top elev. ± 5 cm ☐ OK ☐ Not OK

Conclusion:
Approved Not approved

Conclusion: Accepted the above inspected work and agreed to carry out the next civil works.

Owner Contractor Sub-contractor

Position

Signature

Full Name

Page 4