Professional Documents
Culture Documents
Moxham Great Banks 2001 Prerequisities For SMED
Moxham Great Banks 2001 Prerequisities For SMED
IJQRM
18,4 Prerequisites for the
implementation of the SMED
methodology
404
A study in a textile processing
Received April 2000
Revised November 2000 environment
Claire Moxham and Richard Greatbanks
Manchester School of Management, UMIST, Manchester, UK
Keywords Textile industry, Teamwork, Process control, Single minute exchange of die
Abstract Discusses the practical application of the single minute exchange of die (SMED) within a
textile processing operation. First, the operational environment is presented, and the SMED
application is considered against a changing business requirement. The current approaches to
SMED are then discussed within the context of traditional textile manufacture. The prerequisite
requirements for successful SMED application, defined in this paper as SMED-ZERO, are then
presented and discussed. Concludes by suggesting that all of the SMED-ZERO attributes must be in
place before the traditional SMED techniques can be applied successfully.
Introduction
Shingo (1985) developed the single minute exchange of die (SMED) technique
over a period of 19 years, beginning in 1950. Shingo's technique refers to both
the theory, and the practice of simplifying and improving operational set-up
activities to under ten minutes' total duration. The requirement for SMED
stems from the difficulties encountered in manufacturing environments from
diversified, low volume production. These difficulties are essentially the
increased number of machinery set-ups required to produce a variety of goods
in small batch sizes. SMED theory (Shingo, 1985, p. 33) states that, even if the
frequency of the set-ups cannot be reduced, the actual downtime caused by
machinery specification changes can be greatly reduced, thus providing an
increase in available production capacity. Shingo therefore pronounces that:
SMED can be applied in any factory, to any machine, and that the first stage of
implementation is separating internal and external set-up (Shingo, 1985).
405
Figure 1.
SMED conceptual stages
other than accepted in its entirety. The research, upon which this paper reports,
sets out to challenge this accepted starting position that, in the words of
Shingo, the first stage of SMED is ``. . . the separating of internal and external
set-up'' (Shingo, 1985).
This study, undertaken within an industrial textile processing operation and
reported within this paper, suggests that there are a number of prerequisites
that need to be in place prior to Shingo's initial implementation phase.
Attempts to implement SMED within a traditional textile processing operation,
the focus of this study, support the view that the SMED technique, as it stands
in Shingo's method (Figure 1), can be ineffective due to cultural, procedural and
management barriers, and that overcoming such barriers may be classified as
the prerequisites to SMED.
This paper outlines and attempts to develop the SMED methodology to
incorporate the prerequisites that have been identified. Shingo's original technique
will be modified and the prerequisites included as an additional stage ± SMED-
ZERO.
Figure 2.
Ratio of production run
time to process set-up
time for residential and
commercial yarn
IJQRM 1998) have contributed to the development of process set-up and changeover.
18,4 Criticism that the terminology ``SMED'' restricts its use to press systems
involving the exchange of dies exists (McIntosh et al., 1996). Whilst it is
recognised that SMED was developed for such machinery, it is also recognised
that SMED is a concept and as such can be adapted to suit the purpose.
Figure 3.
Theoretical run-down
scenario for the twisting
process
Figure 4.
Actual run-down
scenario for the twisting
process
A further consideration is that of the weight of the finished order. If the raw Implementation
material cops are not divisible by the number of spindles, machinery utilisation of the SMED
must be considered. A number of systems are in place which aim to maximize methodology
machinery utilization, but the situation often arises in which a machine will be
running off a small number of cops, leaving the remainder of the machine
empty. For example, if an order consisted of 90 raw material cops, the initial 60
may be run to utilize the full machine. This then leaves 30 cops ``running down'' 409
which increases the set-up time and gives only 50 percent machinery utilisation
as shown in Figure 5.
The example in Figure 6 illustrates that the ``run-down'' time can add over 23
hours to the total set-up and changeover time.
Figure 5.
Twisting machine
utilization
Figure 6.
Run-down and set-up
tasks and timings
analysis
IJQRM Lemon, 1995), there are certain prerequisites that need to be in place before
18,4 Shingo's first stage ``separate set-up activities into internal and external'' can
commence. Prerequisites are not addressed by Shingo and, whilst authors have
cited SMED as a tool within a continuous improvement programme (Gilgeous and
Thomas, 1998; Regan and Dale, 1999), the research evidence from the study
described in this paper suggests that the effective implementation of SMED
410 necessitates a number of fundamental requirements. Adoption and implementation
of these fundamental requirements will be classified as SMED-ZERO.
In order to lay the foundations upon which SMED can be built within the
textile processing operation, this research suggests that the following pre-
requisites are required.
These prerequisites have been classified within four important areas, those of:
(1) teamwork approach to communication;
(2) visual factory control;
(3) performance measurement; and
(4) kaizen with a view to simplifying both assessment and measurement.
Performance measurement
Vision. The management team must define what is required to be achieved, and 411
the means by which they can achieve it. Without an analysis of the potential gain
it is impossible to understand the scope of the project. Performance measurement
will enable the company to have a snapshot of where they currently stand in
terms of the length of time taken to set up the machinery. Realistic targets can
then be developed which detail the required set-up and changeover times. If the
potential gain to the company from reduced set-up times is not understood or
communicated effectively, the SMED project will be seen as unnecessary and will
be given a low priority. Similarly external business pressure can quantify the
requirement for set-up time reduction. The SMED project requires a vision as to
how the set-up times will be reduced and the required outcome. This visioning
process must be communicated throughout the business.
Kaizen
Communication tools. SMED focuses upon problem solving and
experimentation, using the employees who are closest to the process. The
IJQRM understanding is that such people will have the best knowledge of the systems
18,4 and machinery. In order to fulfil this role, employees must be able to use a
variety of communication tools and techniques. If problem solving has not
previously been encouraged on the shopfloor, it is very difficult to break this
mould. It must be ascertained whether employees have the necessary
knowledge to undertake problem-solving tasks. Further training may be
412 appropriate.
Internal communication of SMED project progress. Dedicated notice-boards
need to be available, upon which the project can be communicated to all areas of
the operation. It is recognised that not all employees may have direct
involvement with the project from the outset, yet effective change management
must include the entire organisation.
Continued management support. It must be recognised that the SMED project
is not a ``quick fix''. The project group may not get it right first time. Management
must communicate their continuing support regularly.
Figure 7.
Incorporation of
SMED-ZERO to SMED
conceptual stages
Figure 8.
Incorporation of
SMED-ZERO to SMED
conceptual stages
IJQRM the application model or, if the prerequisites are in place, proceed with the
18,4 preliminary stage of the SMED conceptual stages.
SMED-ZERO is to be developed as a pre-SMED assessment tool. It can be
adapted within the range of industries in which SMED is applicable. The tool is
to be developed as a precursor to a SMED programme to ensure that an informed,
strategic and successful set-up time reduction project can then commence.
414 Figures 7 and 8 show the incorporation of SMED-ZERO to SMED conceptual
stages.
Note
1. The company name has been changed for confidentiality.