BCEG’s response to 
EME’s first site visit 
Deficiencies 

Commissioning issues. 
 

Royal Commission Headquarters,  
Yanbu Al Sinayah, Kingdom of Saudi Arabia 

Submitted by: 
 
Muhammad Sajjad. 
Mechanical Engineer.  
MEP department, BCEG. 
sajjad.bceg@gmail.com 
053‐2022676. 
 
Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

11. Deficiencies – Not Directly Related to Commissioning Effort


EME’s role on this project is the commissioning authority for basic commissioning as delineated for LEED compliance.
During EME’s site inspection, several issues were observed that are unrelated to the commissioning process. These are
noted below as a courtesy to the project team for resolution. These do not directly affect the LEED based
commissioning on this project. Resolution of these issues is beyond EME’s scope of work. Parsons shared that the
project is intended to conform to the International Family of Codes (IBC, IMC, IPC – see www.iccsafe.org). As
the project was designed in approximately 2013, it is assumed the 2012 edition governs.

Issue # Description of Issue


1 The International Mechanical Code (IMC) requires fire dampers (FD), smoke dampers (SD)
and fire smoke dampers (FSD) to conform to UL 555 and UL 555S. UL requires
manufacturers to issue installation instructions based on how the dampers were tested. The
installation instructions from the manufacturer (IGC) was transmitted to Parsons under
separate cover.

The FSD sleeves at the wall penetrations are required to have a gap around them. The gap
is generally 1/8 inch per foot of duct, with a minimum of 1/4" per the instructions. The gap
is required to permit expansion of the damper during a fire and alleviate the damper from
racking due to expansion. The masonry walls appear to be mortared solid to all damper
sleeves.

The retaining angles are fastened to the sleeve by pop rivets. It is unclear if the pop rivets
are aluminum or steel. The only loose pop rivets on the project that EME observed were
aluminum. EME did not remove and test any pop rivets. The installation instructions
permits fastening with 3/8" steel pop rivets.
BCEG’s Response. 
All duct work and dampers installation is as per approved RFC drawing. Nothing mentioned in 
spec section 15050 section 2.3.T sleeves. 
Dampers are UL approved. Retaining angles are used with Aluminum rivets. BCEG will work on 
changing the Aluminum rivets with St. Steel rivets.  

 
Non Commissioning Issues Page 1 of 2
Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

2 It is assumed that the kitchen hood is a type I hood (serves grease laden vapors, not just
moisture). The kitchen design is not yet available. A FD was observed in the Kitchen
hood at the top of the shaft. The damper is installed per construction drawing. The shaft
that encloses the kitchen hood exhaust duct serves other ducts. 506.3.11 of the IMC
prohibits installing fire or smoke dampers in this duct and requires the duct to be in its own
shaft.
BCEG’s Response. 
All duct work and damper installation is as per approved RFC drawing. Nothing 
mentioned in spec section 15840 section 2.3.1, C. Low Pressure Duct (Above Ground). 
  The black steel duct riser installation in the same shaft that serves other ducts is as per 
site condition. 

       
 
3 It is assumed that the kitchen hood is a type I hood (serves grease laden vapors, not just
moisture). The duct serving the kitchen hood has no access doors in it, or in the shaft that
encloses it. 506.3.8 of the IMC essentially requires access doors every 20 feet (6.1m) and
every 10 feet (3.05m) at changes of direction greater than 45 degrees. Specification
158403.2 requires access panels at 2-meter intervals and at changes of direction.
BCEG’s Response. 
Access doors are shown on duct penetration. BCEG will coordinate with site for AD installation. 
Further AD can be installed on horizontal duct in kitchen area at every 20 ft. 

Non Commissioning Issues Page 2 of 2


Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

 
4 There is no FSD at the exhaust duct penetration of the shaft to the heat recovery units. It
appears that the IMC would require the FSD.
BCEG’s Response. 
  No FSD is shown on any EAD throughout the building. For HRU a FD is shown on the 
EAD penetration from riser to HRU. 
 

     
   
  PMT’s reply against RFI‐842 says that no FSD is required for general Exhaust duct for the 
building. 
 
5 Dirt and dust have penetrated the ductwork, AHUs, heat recovery units, etc. throughout the
building. The project team may want to pursue cleaning the ductwork and AHUs in
accordance with the Assessment, Cleaning and Restoration of HVAC Systems (ACR)
standard developed as an international standard by the National Air Duct Cleaners
Association. ACR was previously transmitted to Parsons for review.

BCEG’s Response. 
BCEG has performed a thorough cleaning of all the duct work and removed the dust 
and dirt from HVAC duct, machines and all associated equipment. 
 
BCEG also using the MERV 8 temporary filters recommended by PMT for temporary use 
for startup and pre‐commissioning activities.

Non Commissioning Issues Page 3 of 2


Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

 
 
 

   
 
   
 
 
 
 
 
  A picture through access door. This shows the quality of duct cleanliness from inside. 
 

   
 
  MERV 8 filter installed inside AHU to trap the dust and dirt from system. 
  BCEG cleans the temporary filter every 2 weeks and changes the filter every 2 months. 

6 Specification 16050 2.2 C, D requires rigid (RGS) conduit in wet or damp locations and at
locations exterior to the building. Cable tray and EMT is used in the open area where the
cooling towers are located.

BCEG’s Response. 
 
BCEG will paint the EMT conduits with weather proof paints (Primer, intermediate coat 
and top coat) to close this issue. The proposal to paint the steel surfaces in high 
corrosive and humid environment is approved under submittal 1801‐05500‐005‐R02. 

Non Commissioning Issues Page 4 of 2


Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

 
   

 
7 The plumbing above grade plastic drainage piping is about 10 foot on-center between
supports (3.05 m). 15050 3.2 F 3 requires a maximum spacing of 2.5m. It is noted that the
International Plumbing Code section 305 requires supports at 4 feet on center (1.2m) for
horizontal run of PVC piping).

BCEG’s Response. 
  BCEG has installed the hanging supports for all PVC horizontal pipes per approved 
drawing 1801‐PG‐A1‐00008. The schedule in drawing shows the support at 3 meters 
distance for pipes above 4”. 
 
 
 
 
Non Commissioning Issues Page 5 of 2
Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

8 Detail 9 on sheet 0751A-PG-A1-067 does not include a P trap for the roof drains. Traps
are installed. It appears that these traps will collect sand over time and clog.

All the P‐traps for roof drain & planter drain has been removed per IFC drawing 0751A‐
PG‐A1‐067.  
 

   
  
 

Non Commissioning Issues Page 6 of 2


Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

9 Some of the traps on the floor drains observed has a dimension from the drain outlet to the
trap weir greater than 24" (0.61 m). This violates section 1002 of the IPC.

Traps in Cooling Tower area were observed to have pipe vertical length from drain 
outlet to P‐trap more than 24”. This is per site condition. BCEG has removed the P‐Trap 
per IFC drawing 0751A‐PG‐A1‐067.  

10 Pump P-07, serving the condenser water side stream filter, was noted to not have electrical
bonding. EME noted that all other major HVAC equipment (pumps, AHUs, HRUs, etc.)
are connected via electrical bonding for lightning protection.

  The bonding for side stream filter pump P‐07 is done. 
 

 
Non Commissioning Issues Page 7 of 2
Royal Commission for Jubail and Yanbu
Headquarters, Yanbu, KSA

12. Commissioning Issues Log


The following pages summarizes the commissioning deficiencies identified during EME’s first site visit.

Commissioning Issues Page 1 of 1


RCHQ 
Yanbu, Saudi Arabia 

PlanGrid report – RCHQ 
 
Prepared by: EME Group 
Report date: Tuesday, February 19, 2019 
Items in this report: 32 tasks 
 
 
 
Contents 
 
#1 ‐ Chilled & Condenser Water Piping Supports.................................................................................. 3 
 
#2 ‐ Chilled Water Valve Insulation ...................................................................................................... 4 
 
#3 ‐ Valve Installation .......................................................................................................................... 5 
 
#4 ‐ Chilled & Condenser Water Pressure Gauge Assembly .................................................................. 6 
 
#5 ‐ Pump Lubrication.......................................................................................................................... 7 
 
#6 ‐ Pump Drain Piping ........................................................................................................................ 8 
 
#7 ‐ Piping Vibration Control ................................................................................................................ 9 
 
#9 ‐ VAV Box Support......................................................................................................................... 10 
 
#10 ‐ HRU Filter Section ..................................................................................................................... 11 
 
#11 ‐ AHU G6 Access Doors Blocked .................................................................................................. 12 
 
#12 ‐ Return Air Sensors Installed on Fresh Air Duct........................................................................... 14 
 
#13 ‐ AHU CHW Coil Sections Installed Backwards ............................................................................. 15 
 
#14 ‐ Chilled Water Coil Clearance ..................................................................................................... 17 
 
#15 ‐ Fan Guards Not Installed........................................................................................................... 18 
 
#16 ‐ Fan Coil Spring Isolated Hangers Not Installed........................................................................... 19 
 
#17 ‐ Unions Installed on System Side of Isolation Valve .................................................................... 20 
 
#18 ‐ AHU Air Flow Sensor Installation ............................................................................................... 22 
 
#19 ‐ CH‐1 Damaged Insulation.......................................................................................................... 24 
 
#20 ‐ Heat Recovery Units ‐ Damaged Heat Pipe Fins ......................................................................... 25 
 
#21 ‐ AHU‐B3 Condensate Piping ....................................................................................................... 27 
 
#22 ‐ AHU‐15 Fan Vibration Isolation ................................................................................................. 28 
 
#23 ‐ AHU‐31 VAV Access .................................................................................................................. 29 
 
#24 ‐ AH‐32 Shipping Blocks............................................................................................................... 30 
 
#25 ‐ HRU‐04 Interior Cable Severed.................................................................................................. 31 
 
#26 ‐ Core 5 Fresh Air Duct Motorized Damper Installation................................................................ 32 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
#27 ‐ AHU CHW Coil Connection Assembly ........................................................................................ 33 
 
#28 ‐ HRU‐01 Flex Connection at Fan Outlet ...................................................................................... 34 
 
#29 ‐ AHU Flex Connectors Torn ........................................................................................................ 35 
 
#30 ‐ Chilled Water Field Device Insulation ........................................................................................ 36 
 
#31 ‐ Chiller Pressure Relief Valve with Manual Ball Valve ................................................................. 37 
 
#32 ‐ Internal AHU Wiring Not Protected ........................................................................................... 38 
 
#33 ‐ Refrigerant Storage Tank .......................................................................................................... 39 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
 
 
#1 ‐ Chilled & Condenser Water Piping Supports   
  Status 
List  Open 
 
Cx Deficiency   
 
  Type 
Created  Issue 
1/9/2019 at 3:02 AM 
tjuliana@emegroup.com 
 
 
 
Location  Assignees 
Plant Room  Beijing Construction 
  Engineering 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
 
 
Description 
 
Per Specification 15050 section 3.2.F.3, hanger spacing shall in no case be less than one hanger per 
2.5m.  Pipe hangers observed in multiple locations at spacing in excess of 3m. 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 24 2019,  By:  sajjad.bceg@gmail.com 

The hanger spacing for CHW piping is as per approved shop drawing "CHW piping HVAC standard details" 1801‐HV‐
A1‐00003. 
 
The hanger spacing for drainage piping is as per approved shop drawing “Plumbing standard details” 1801‐PG‐A1‐
00008. 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

Photos: 

 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#2 ‐ Chilled Water Valve Insulation    
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 4:10 AM  Issue 
tjuliana@emegroup.com 
 
Location  Assignees 
Plant Room  Beijing Construction 
Engineering 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
Description 
Per Specification 15250 section 3.2.B, fittings and valves shall be insulated.   Triple duty valves 
throughout  the plant room were observed to be uninsulated. 
 
Photos 
 

 
 

 
BCEG’s response:         Status:  Closed,    Date:  July, 24 2019,  By:  sajjad.bceg@gmail.com 

All the TDV’s have been insulated. 
 
Photos: 
 

        

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#3 ‐ Valve Installation     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 4:39 AM  Issue 
tjuliana@emegroup.com 
 
Location  Assignees 
Basement Plant Room, AHU  Beijing Construction 
Rooms  Engineering 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
Description 
Per Specification 15080 section 3.2.1.G, all valves located 1.8 meters above finished grade shall be 
furnished with permanent ladders or operating chains.  Valves installed throughout  the basement 
(including plant room and TES connections) were observed to be above the specified height criteria 
and do not have operating chains or permanent ladders installed.   The logical compliance  method 
appears to be chain‐driven operation based on valve locations, however the existing valve handles do 
not appear to be suitable for chain installation. 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 24 2019,  By:  sajjad.bceg@gmail.com 

There are over 20 valves in plant room with a height above 1.8 meters.  
Further to the site condition and a thorough site visit, BCEG together with  
PMT reached to a suggestion to use 3 portable Aluminum ladders (hook type) 
on either side of chillers and heat exchanger side. 
 
 
             Photo:

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#4 ‐ Chilled & Condenser Water Pressure Gauge Assembly   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 5:04 AM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Plant Room  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/15/2019 at 5:42 PM 
 
Description 
Per Material Submittal 15050‐028, manufacturer  installation instructions  indicate snubbing element is 
to be placed in the line immediately  before the pressure gauge.  Siphons (pigtail) are recommended 
when a gauge is to be used in a steam application as they will become clogged with debris in a 
hydronic system.  Gauge assembly installations  were observed to include both snubbing element and 
siphon, with snubbing element installed immediately  after the line tap.  Placing the snubber after the 
isolation valve allows for maintenance  staff to clean the element in the case of clogging. 
 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,     

Date:  July, 24 2019,  By:  sajjad.bceg@gmail.com         Photo: 

This issue has been resolved by placing the snubber immediately after the pressure gauge. The said construction 
is followed for the whole building.

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#5 ‐ Pump Lubrication     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 5:49 AM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Plant Room  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
Description 
Per Specification 15540 section 3.2.I, pumps shall be lubricated before start‐up.  Per BCEG, 
manufacturer  start‐up has begun but the pumps were observed to not be lubricated. 
 
 
BCEG’s response:         Status:  Closed,    Date:  July, 24 2019,     By:  sajjad.bceg@gmail.com 

The delivered pumps are factory lubricated. BCEG will further keep lubricating the pumps and motor 
bearings according to lubrication schedule, sent from supplier. 

There are two types of CHW pumps (Horizontal Split‐case – HS) & (End Suction – NK) 

  End Suction – NK
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

Horizontal Split‐case – HS 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
   
#6 ‐ Pump Drain Piping     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 5:52 AM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Plant Room  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
Description 
Per Specification 15540 section 3.2.F, drains shall be provided for pump bases and seals, piped to and 
discharging  into floor drains.  Drains were observed to be installed, however  no piping to floor drains 
were installed.  In some instances, hoses were connected and routed to the floor drains. 
 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 24 2019,     By:  sajjad.bceg@gmail.com 

Pumps drain piping is connected to nearest floor drain. The drain connection is done for all the following 
equipment. 
1. Pumps 
2. Strainers 
3. Chiller 
4. Heat exchangers 
5. Blow down. 
6. AHU’s, FCU’s & HRU’s.  

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

Photos 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Heat Exchanger drain 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
        CHW pumps drain 
 

 
 
  RCHQ – Cx Issues Log 
      Chiller drain drain
RCHQ 
Yanbu, Saudi Arabia 

   
#7 ‐ Piping Vibration Control     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/9/2019 at 6:20 AM  Issue 
tjuliana@emegroup.com 
 
Location  Assignees 
Plant Room  Beijing Construction 
Engineering
 
  Last updated 
  2/15/2019 at 2:25 PM 
Description 
Per Specification 15050 sections 3.2.1.B.1.a and 3.2.1.B.2.a,  the first three hangers away from any 
spring isolated piece of equipment shall have hangers with same static deflection as equipment 
isolators.   No spring isolated hangers were observed within the plant room associated with spring 
isolated equipment. 
 
Photos 
 

     

BCEG’s response:         Status:  OPEN,    Date:  July, 25 2019,     By:  sajjad.bceg@gmail.com 

The Hangers are installed against the details shown in approved shop drawing. HVAC standard details‐2 (Chilled 
water piping) 1801‐HV‐A1‐00003. 
 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

BCEG is working to install the first three hangers with spring isolators of same deflection as used for equipment 
base. 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#9 ‐ VAV Box Support     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  1/31/2019 at 3:05 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Various  Beijing Construction 
   
Sheet  Engineering 
 
O751A‐HV‐A1‐149  Standard Details   
 
‐ Sheet 6 
  Last updated 
  2/15/2019 at 2:25 PM 
 
Description 
Per design documents,  VAV boxes are to be supported with two hangers.  Field installation provides a 
single hanger. 
 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 25 2019,     By:  sajjad.bceg@gmail.com 

The current installation method is approved by PMT under RFI ‐1541.  
 
As the VAV has rigid connection on one side so one hanger was assumed to be enough as per site condition. 
 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#10 ‐ HRU Filter Section     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  1/31/2019 at 3:20 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Core 1 & Core 2 ‐ 21st Floor  Beijing Construction 
   
Sheet  Engineering 
 
O751A‐HV‐A1‐149  Standard Details   
 
‐ Sheet 6 
  Last updated 
  2/15/2019 at 4:35 PM 
 
Description 
Heat Recovery Units were observed to contain a single filter rack installed on the fresh air intake. 
Design documents indicate 3 filter sections are to be installed ‐ pre‐filter, bag filter, and carbon filter. 
 
BCEG’s response:         Status:  Closed,    Date:  July, 25 2019,     By:  sajjad.bceg@gmail.com 

The HRU is approved under submittal 1801‐15656‐008 with the following construction. 
 
A pre filter and bag filters are used for the approved model TW series. 

 
 

 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

Spec 15653 
 
Cleanable (Washable) Permanent 
Panel Filters. 
 
The filter media shall be made of 
metal strips or metal strips coated 
with viscous substance. 
 
Filter: 30 – 35% efficiency 

 
 
 

Spec 15653 
 
High Efficiency Filters/Bag Filters: 
 
High efficiency, extended surface 
pocket type, consisting of galvanized 
steel holding frame and replaceable  
 
Filter: 90 – 95% efficiency  MERV15 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 
#11 ‐ AHU G6 Access Doors Blocked   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/31/2019 at 3:26 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Basement AHU Room  Beijing Construction 
   
Sheet  Engineering 
 
Bsmt Fl 1801‐HV‐A1‐BS101  2 of 2   
   
  Last updated 
  2/15/2019 at 2:25 PM 
 
Description 
CHW piping/hangers  block unit access doors from opening.  Raising the piping run approximately 
15cm would provide sufficient clearance for unit access. 
 
 
 
Photos 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
 
 
BCEG’s response:         Status:  Closed,    Date:  July, 25 2019,     By:  sajjad.bceg@gmail.com 

 
This issue has been resolved. CHW pipe has been lifted upward to provide enough passage for AHU‐G6 
access door. 
 
Photo:

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 
#12 ‐ Return Air Sensors Installed on Fresh Air Duct   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
1/31/2019 at 3:37 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Basement AHU Room  Beijing Construction 
   
Sheet  Engineering 
 
Bsmt Fl 1801‐HV‐A1‐BS101  2 of 2  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
Return Air Sensors (temp, flow, & CO2) for AHUs 15, 25, & 35 are installed on the fresh air purge duct 
rather than the return air duct. 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 25 2019,     By:  sajjad.bceg@gmail.com 

This issue is resolved the replacing the BMS field devices from Fresh air duct to return air duct. 

Photo: 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#13 ‐ AHU CHW Coil Sections Installed Backwards   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/1/2019 at 10:48 AM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Basement Plant Room, Core 3  Beijing Construction 
First Floor AHU MER  Engineering 
 
 
  Last updated 
 
2/18/2019 at 11:42 AM 
 
Description 
Chilled water coil sections in AHUs B3 & 31 were observed to be installed backwards with the drain 
pan extended in the upstream side of the coil.  The coil is located off‐center in the section to allow for 
proper absorption distance and prevent carry over from entering the fan section.  The current 
orientation will not allow condensate  to be properly collected and drain from the unit. 
 
 
 
Photos 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
BCEG’s response:         Status:  Closed,      Date:  July, 27 2019,        By:  sajjad.bceg@gmail.com 

This issue is resolved. Cooling coil section for AHU B3 and 31 has been rotated per right flow 
direction. 
 
Photos: 
 

       
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
   
#14 ‐ Chilled Water Coil Clearance    
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/1/2019 at 11:10 AM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Floor 21, Core 4 AHU Rooms  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/15/2019 at 2:26 PM 
 
Description 
AHUs 41 & 42, HRUs 01, 02, 03, & 04 chilled water coils installed with insufficient clearance to pull coil 
for maintenance/repair  as required per design documents 
 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 27 2019,     By:  sajjad.bceg@gmail.com 

Confirmed on site, Coil can be removed from connection side by twisting it along vertical axis. 

Furthermore as per Zamil confirmation during pre‐commissioning, coil can be removed from either side of AHU. 

Further, BCEG can demonstrate on site by removing the coil from other side of equipment. 
 
Photo: 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 

 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#15 ‐ Fan Guards Not Installed     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  2/1/2019 at 11:21 AM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Core 1 & Core 2 ‐ 22nd Floor  Beijing Construction 
   
Sheet  Engineering 
 
22nd Fl 1801‐HV‐A1‐22001   
   
  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
Stair and elevator shaft pressurization  fans on Core 1 & 2 roof MER do not have screens/guards 
installed at fan inlet.  Fans were observed to be spinning freely. 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 27 2019,     By:  sajjad.bceg@gmail.com 

Mesh screen installed  for fans protection from birds and insects.. 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#16 ‐ Fan Coil Spring Isolated Hangers Not Installed   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/1/2019 at 12:16 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Various  Beijing Construction 
   
Sheet  Engineering 
 
O751A‐HV‐A1‐148  Standard Details   
‐ Sheet 5   
  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
Spring isolated hangers required for FCU installations  per design documents.   FCUs were observed to 
be rigidly mounted. 
 
 
 
Photos 
 

BCEG’s response:         Status:  Closed,    Date:  July, 27 2019,     By:  sajjad.bceg@gmail.com 

The FCUs are installed based on approved method statement described in RFI 1606. 
 
BCEG prepared a mockup before proceeding towards FCUs installation. All the installation is based on that 
approved method statement described in RFI‐1606. 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#17 ‐ Unions Installed on System Side of Isolation Valve   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/1/2019 at 12:26 PM  Issue 
tjuliana@emegroup.com 
 
Location  Assignees 
Various  Beijing Construction 
Engineering 
 
  Last updated 
 
2/18/2019 at 12:08 PM 
 
Description 
Dielectric unions at several locations were observed to be installed on the system side of isolation 
valves.  Sample locations include the potable water tanks and fan coil units.  The current installation 
does not allow for isolating the unit and disconnecting  it from the system piping.  The isolation valve 
should be located on the system side of the union. 
 
 
Photos 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

BCEG has solved this issue by installing di‐electric unions on both side of isolation valve for Potable water 
transfer pumps and Cooling Tower water transfer pumps. 
 
For FCUs, the system side unions are kept as it is because the machines can be isolated from flange type, double 
bowl, rubber flexible connections. 
 
Photos: 

                        

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
 
 
 
#18 ‐ AHU Air Flow Sensor Installation   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/1/2019 at 12:50 PM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Various  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/15/2019 at 2:26 PM 
 
Description 
AHU flow sensor (supply & return) installation locations do not have laminar flow and violate 
manufacturer  installation requirements  for upstream/downstream  straight duct runs. 
 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

These devices are installed under the supervision of Honeywell engineer as per site condition. Further to the 
discussion with Honeywell, the location of devices will be changed where required during the testing & 
commissioning phase.

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
   
#19 ‐ CH‐1 Damaged Insulation     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  2/13/2019 at 2:54 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Basement Plant Room  Beijing Construction 
   
Sheet  Engineering 
 
1801‐HV‐A0‐BS111  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
CH‐01 insulation was observed to have minor damage 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

The damaged insulation is rectified. 
Photos: 

      

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#20 ‐ Heat Recovery Units ‐ Damaged Heat Pipe Fins   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/13/2019 at 2:59 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
21st Floor HRU Rooms  Beijing Construction 
   
Sheet  Engineering 
 
21st Fl 1801‐HV‐A1‐21002   
   
  Last updated 
  2/15/2019 at 2:26 PM 
Description 
HRUs 01 through 04 were observed to have minor damage to the aluminum fins in the heat pipe 
section 
 
Photos 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 
 
 

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

All known damaged fins have been rectified as of today. 

     

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
   
#21 ‐ AHU‐B3 Condensate Piping     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  2/13/2019 at 3:05 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Basement Plant Room  Beijing Construction 
   
Sheet  Engineering 
 
1801‐HV‐A0‐BS111  Last updated 
  2/15/2019 at 2:26 PM 
Description 
Condensate  drain pipe was observed to be back pitched from unit to p‐trap 
 
Photos 
 

                                               

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

Condensate drain piping is done for AHU B3. 

 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#22 ‐ AHU‐15 Fan Vibration Isolation   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/13/2019 at 3:35 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Basement AHU Room  Beijing Construction 
   
Sheet  Engineering 
 
Bsmt Fl 1801‐HV‐A1‐BS101  2 of 2   
  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
One of the mounting bolts on the fan vibration isolator was observed to be cockeyed, impeding free 
movement of the isolator. 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

All the crooked, uneven spring vibration isolators have been adjusted for all the AHUs.  
 
Photos: 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#23 ‐ AHU‐31 VAV Access     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  2/13/2019 at 3:46 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Floor 3, Core 1 AHU Room  Beijing Construction 
   
Sheet  Engineering 
 
3rd Fl 1801‐HV‐A1‐03100   
  Last updated 
  2/15/2019 at 2:26 PM 
Description 
Placement  of fire protection piping & sprinkler head is in conflict with VAV access/maintenance 
 
Photos 
 

                   

BCEG’s response:      Status:  Closed ,        Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

This issue has been solved. NAFFCO pipe blocking the VAV has been adjusted. 
Photo: 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#24 ‐ AH‐32 Shipping Blocks     
 
  List  Status 
  Cx Deficiency  Open 
   
 
  Created  Type 
  2/13/2019 at 3:55 PM  Issue 
  tjuliana@emegroup.com   
   
   
 
     
  Location  Assignees 
  Floor 3, Core 2 AHU Room  Beijing Construction 
   
Sheet  Engineering 
 
3rd Fl 1801‐HV‐A1‐03100   
   
  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
Shipping blocks observed to remain installed on fan vibration insulator 
 
 
BCEG’s response:      Status:  Closed,         Date:  July, 27 2019,            By:  sajjad.bceg@gmail.com 

 
 
Shipping blocks are removed.

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 
#25 ‐ HRU‐04 Interior Cable Severed   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/13/2019 at 4:11 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
21st Floor, Core 2 HRU Room  Beijing Construction 
   
Sheet  Engineering 
 
21st Fl 1801‐HV‐A1‐21002   
   
  Last updated 
  2/15/2019 at 2:26 PM 
 
Description 
Liquid tight flexible cable serving interior lights was observed to be severed and repaired with 
electrical tape.  No grommets  observed on cable pass‐through  between unit sections. 
 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

BCEG electrical team has repaired all the severed cables wherever found. The cable is running through 
flexible hose in above picture. Flexible hose is repaired with electrical tape. 
 
Photo: 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

    

    

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#26 ‐ Core 5 Fresh Air Duct Motorized Damper Installation   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/14/2019 at 4:03 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Core 5 AHU Rooms  Beijing Construction 
   
Sheet  Engineering 
 
7th Fl 1801‐HV‐A1‐07102   
   
  Last updated 
  2/18/2019 at 12:10 PM 
 
Description 
Fresh air duct motorized damper is located above the supply duct and is not readily accessible. 
Witnessed installation on floors 7 and 5, appears to be consistent on all Core 5 AHUs per the 
drawings.  The contractor should verify the installation location (upstream  of the CO2 VAV takeoff 
branch) is appropriate  for unit operation. 
 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

BCEG observed FAD take‐off branch and MVD wrong installation at 5th, 6th and 7th floor of core 05. The 
installation was based on wrong drawing sent by PUSA. However, BCEG has rectified these issues. 
 
Photo: 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
 

 
 

 
 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#27 ‐ AHU CHW Coil Connection Assembly   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/15/2019 at 12:21 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Various  Beijing Construction 
   
Sheet  Engineering 
 
2nd Fl 1801‐HV‐A1‐02103   
   
  Last updated 
  2/15/2019 at 2:27 PM 
 
Description 
AHU/FCU chilled water coil connection assembly detail indicates a drain cock is to be installed at the 
unit outlet.  Assembly installation was noted to be in progress during the time of EME's inspections, 
however drain cocks were not observed.   BCEG to confirm intent to install based on approved 
connection drawing detail. 
 
 
Photos 
 
 

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

The installation is done per IFC‐Rev00 which doesn’t show drain cock in valve package. The said valve was included 
later in IFC‐Rev01. However, BCEG has started installation of drain cock at the supply line lower level. 
 
Photos 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#28 ‐ HRU‐01 Flex Connection at Fan Outlet   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/15/2019 at 2:05 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Core 1, 21st Floor HRU Room  Beijing Construction 
   
Sheet  Engineering 
 
21st Fl 1801‐HV‐A1‐21001   
   
  Last updated 
  2/15/2019 at 2:27 PM 
Description 
Flexible connection at fan outlet is installed improperly.   Flex connection is squished, and will not 
provide the intended sound attenuation and vibration isolation. 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

BCEG has taken all measures to possibly identify and fix such issues by either repairing or replacing the defected 
parts. 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#29 ‐ AHU Flex Connectors Torn     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/15/2019 at 2:09 PM  Issue
tjuliana@emegroup.com 

Location  Assignees 
Various  Beijing Construction 
Engineering 
 
  Last updated 
 
2/15/2019 at 2:27 PM 
 
Description 
Flex connectors on return and supply duct connections  to AHUs were observed to be torn/damaged  in 
multiple locations.  Flex connectors should be reviewed and repaired as necessary during unit start ups. 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 29 2019,            By:  sajjad.bceg@gmail.com 

BCEG Has rectified all the similar flex connector issues known as of today, perhaps, this may occur somewhere 
again with passage of time. BCEG will continue repairing all such issues, whenever occur. 
 
Photo: 

            
 
RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

    
 

  

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#30 ‐ Chilled Water Field Device Insulation   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/15/2019 at 2:20 PM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Basement Plant Room  Beijing Construction 
Engineering 
 
  Last updated 
 
2/15/2019 at 2:25 PM 
 
Description 
Insulation around CHW field devices (gauges, sensors, etc.) was observed to not be filled in and sealed 
after device installation.   Insulation should be sealed to prevent excess heat loss and condensation. 
 
 
Photos 
 

                                                        

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

BCEG has rectified this issue. Most of the field devices have insulation around them. The remaining ones are 
being insulated. 
 
Photo: 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

       
 
 
 
 
 

     

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#31 ‐ Chiller Pressure Relief Valve with Manual Ball Valve   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/19/2019 at 12:14 PM  Issue 
tjuliana@emegroup.com 
 
 
  Location  Assignees 
 
Basement Plant Room  Beijing Construction 
   
Sheet  Engineering 
 
1801‐HV‐A0‐BS111   
   
  Last updated 
  2/19/2019 at 12:16 PM 
 
Description 
The chiller's (CH‐1 through 3) pressure relief valve assembly includes an additional manual isolation 
ball valve between the unit and the PRV, which is noted as a safety concern.  Should the PRV open to 
relieve pressure during an event and the manual valve is mistakenly left closed, the chiller may suffer 
significant  damage. 
 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

The ball valve is there for Chiller’s evaporator and condenser vessel’s pressure and vacuum testing with ranges 
above the PRV rating. Now the testing is done and piping is installed, we will keep the valve open and remove 
the handle. 
 
Photos:  
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

          

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

 
#32 ‐ Internal AHU Wiring Not Protected   
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/19/2019 at 4:15 PM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
AHU/HRU  Rooms  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/19/2019 at 4:17 PM 
 
Description 
Internal wiring in AHUs/HRUs were observed to be unprotected.   Wires are run through openings 
between unit sections without proper grommets, sleeves, or other protection.  Over time, wires will 
rub against the metal, potentially leading to shorting out.  Observed in every AHU/HRU. 
 
 
 
Photos 
 

BCEG’s response:      Status:  Closed,         Date:  July, 29 2019,            By:  sajjad.bceg@gmail.com 

BCEG’s electrical team has installed grommet kind of protection for all the internal electrical wiring passing 
through sharp edges. 
 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

RCHQ – Cx Issues Log 
RCHQ 
Yanbu, Saudi Arabia 

   
#33 ‐ Refrigerant Storage Tank     
List  Status 
Cx Deficiency  Open 
   
Created  Type 
2/19/2019 at 4:31 PM  Issue 
tjuliana@emegroup.com 
 
 
Location  Assignees 
Basement Plant Room  Beijing Construction 
Engineering 
 
 
  Last updated 
 
2/19/2019 at 4:32 PM 
 
Description 
Per Specification 15680 Section 2.3.K.4 a free‐standing refrigerant storage tank and pump out unit 
shall be provided.  No storage tank is currently installed. 
 
BCEG’s response:      Status:  Closed,         Date:  July, 28 2019,            By:  sajjad.bceg@gmail.com 

A free standing refrigerant storage tank is placed at its designated location in plant room.  
 