How You Can Precommission Process Plant Systematically PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

PLANT DESIGN AND ENGINEERING

How you can precommission


process plants systematically
Follow these guidelines for the best logical sequence
for startup preparations
V. RAMNATH, Engineers India Ltd., New Delhi, India

L
eading to engineering completion, Contrary to the construction work other parts of the plant, is undertaken to
operating personnel need to convey progress, which is essentially planned by define, prepare and execute all mechanical
to the project/construction team trades and areas, the startup sequence of completion and precommissioning. This
which sections of the unit/plant are to be a new plant is driven by operational con- benefits the operation by saving time and
handed over chronologically so that the straints with safety equipment and systems optimizing resources.
entire procedure is smooth. This informa- being given the highest priority; followed The systems will be identified at an early
tion is conveyed by dividing the unit/plant by utilities, power generation and other stage so that the mechanical completion of
into sections called systems. Each operating essential services required to supporting the systems can be expedited per priority.
facility and associated units are divided into commissioning of the process equipment. This early stage of systems identification
logical process and/or piping equipment Therefore, a subdivision of an installation will also help properly sequence and inte-
systems. Normally, the precommissioning that performs a given operational func- grate mechanical completion and precom-
and commissioning of units in the chemi- tion, with little or no interference from the missioning activities.
cal process industry are carried out on a
system-by-system basis. TABLE 1. System definition database
Systems are divided into process and
utility systems. Process systems are those Subsystem code System description Subsystem description
involving process fluids (e.g., the atmo- 400 – P – 01 Reformate splitter Feed to reformate splitter
spheric distillation unit column’s over-
head system), while utility systems involve 400 – P – 02 Reformate splitter Reformate splitter column
utilities like instrument air, plant air, etc. 410 – P – 01 Clay treaters Clay treater feed
Precommissioning involves water flush- 410 – P – 02 Clay treaters Clay treater equipment, V-111 and V-112
ing, air or steam blowing of piping and
440 – P – 01 Adsorbent chambers Adsorbent chambers, V-101 and V-102
equipment, water trial of pumps, adsor-
bent loading, drying out fired heaters, etc. 810 – U – 01 Plant air Plant air header
Following these activities, hydrocarbon 820 – U – 01 Nitrogen Low pressure nitrogen
is put into designated plant areas such as 830 – U – 01 DM water DM water supply
cold circulation of crude oil, also termed
840 – U – 01 Cooling water Cooling water supply
as commissioning. Even though some
parts of the plant are in this phase, others 840 – U – 02 Cooling water Cooling water return
like the desalter, may still be in precom-
missioning mode.
Construction Precommissioning Commissioning Product out Test run
System approach advantages.
The checking and testing phases of a new Schedule
Construction advantage
plant are relatively long and complicated
processes—not all parts of the plant reach Precommissioning
the same degree of completion at the same Commissioning
time. Hence, some areas or units of a plant Product out
may be complete and ready for precom-
missioning, while others are not. It’s there- Test run
fore a waste of time to wait for the whole
plant to be complete at the same time for FIG. 1 Comparison when using “systems.”
precommissioning activities to begin.
HYDROCARBON PROCESSING APRIL 2011
I 119
PLANT DESIGN AND ENGINEERING

FI
6823
TI FQI PI
6846 6823 6850
L
TE FIT FE PIT TG PG
6846 6823 6823 6850 6891 6801
6-in.–PA–68006–H1A–N Plant air
Offsite
FI
6822
TI FQI PI
6847 6822 6849
L
TE FIT FE PIT TG PG
6843 6822 6822 6849 6815 6816
6-in.–TA–68004–H1A–N Instrument air
Offsite
FI
6842
TI FQI PI
6843 6842 6844
L
TE FIT FE PIT TG PG
6843 6842 6842 6844 6809 6810
6-in.–NG–68005–A1A–N Nitrogen
Offsite
TI H FI PI H
6837 6836 6838
L L L
FQI TG PG
TE 6836 PIT 6819 6820
6837 6838 Fuel oil
3-in.–FO–68002–B1B–LP supply
FQIT
6838 Offsite
5 5 5
3-in.–FLO–68005–A1A–N TG PG
B1B 6871 6872 Flushing oil
2-in.
AIR supply
Offsite

TI H FI PI H
6853 L 6851 L 6852 L
FQI
PIT 6851 TE PG PG
6853 6852 6890 6803
2-in.–FO–59034–BLB–LP Fuel oil return
FQIT
6851 Offsite
5 5
5 TG PG
6873 6873 Flushing oil
2-in.–FLO–68006–A1A–N 2-in. B1B
AIR return
Offsite

Plant air (810-U-001) Instrument air (820-U-001) Flushing oil (570-P-001)

Fuel oil (560-P-001) Nitrogen (850-P-001)

FIG. 2 System markup at the unit battery limit.

This overall project planning will be ken down into its components indicating systems
better optimized if the mechanical test, the associated equipments, tie-ins, control EFG: Progressive numbering, two or
pre-commissioning and commissioning valves, safety valves, instrumentation and three digit number.
activities are organized. As Fig. 1 indicates, any other component in its limit. Table 1 details examples of a typical
there is a definite schedule advantage if the The system and subsystem identifica- process and utility system database. This
systematic approach is undertaken. This tion code is generated with the goal that tabulation can include more information
approach does not wait for the entire unit each system and its subsystems are uniquely as required. Fig. 2 illustrates a mark-up of
to be handed over, thus meeting the goal of defined. The coding identifies the unit, typical process and utility systems at the
early unit startup. system type (process or utility) and cor- unit battery limit. As illustrated in Fig. 3,
responding subsystem. the hydrogen system 550-P-002 consists of
Systems and subsystems coding. The coding can be similar to: ABC – the vessel, the overhead line HV-8003 to
Systems are first identified per the agreed D – EFG flare, to the isolation valve and safety valve
coding philosophy and defined on the ABC: System identification, three digit upstream piping. Downstream, the safety
unit piping and instrumentation diagrams number (e.g., 100-799 for process systems valve is the system 850-U-001, part of the
(P&IDs). These define the boundaries and 800-999 for utility systems) flare system. Fig. 3 is a typical diagram of
between systems. Each system is then bro- D: P = process systems and U = utility systems marked-up within the unit.

120
I APRIL 2011 HydrocarbonProcessing.com
Meet the Right People
for Business Success

Join colleagues and customers at


NPRA’s Reliability & Maintenance
Conference and Exhibition
May 24–27 « Colorado Convention Center « Denver, CO

In today’s slowly recovering economy, you want value for your dollar, and NPRA’s Reliability & Maintenance
Conference and Exhibition delivers it this year with a more interactive program that includes nearly 40 workshops
in six subject tracks and longer, more open discussion sessions with leading industry experts where you can drill
down into the topics that are essential to your success.

The Exhibition will again showcase the latest technologies and services for you to evaluate. More than 200
companies will exhibit their equipment, materials, and special expertise in solving problems that are critical to
your competitiveness.

The 2011 Reliability & Maintenance Conference and Exhibition is your best opportunity to keep up with industry
developments by meeting with experts and fellow practitioners who will share their proven practices in reliability,
maintenance, mechanical integrity and safety, analyzers, electrical and instrumentation,
and turnarounds.

Register today at npra.org/rmc or call us at (202) 457-0480 for more information.

. !4)/.!, ß0 %42/#(%-)#!, ßß2 %&).%23 ß! 33/#)!4)/.


Select 92 at www.HydrocarbonProcessing.com/RS
PLANT DESIGN AND ENGINEERING

1:500

Min.

16-in.NF–80002–A28A–N
Tube Tube

6-in. NF–80006–E28A–N
A28A ½-in. OD ½-in. OD
A1A P P
FO

½-in. HG–80015–E25A–N

½-in.HG–80016–E25A–N
8001
Set: 145 Kg/CW2G Set: 145 Kg/CW2G
Size: 3J4 16-in.NF–80003– Size: 3J4
1-in. x 2-in.
PSV A28A–N PSV
Nipple 8001A 16-in. x 4-in. 8001B Nipple
2-in. NG–80009–AIA–N

2
½-in. (Plxth.) 2 ½-in.
4-in. x 3-in. CSO

2-in.HG–80008–E25A–N
CSO ½-in. SW LO A28A 4-in. x 3-in. ½-in. SW

A28A
E25A
¾-in. E25A ¾-in.
Distance 2 Distance
by vendor CSO 2 by vendor
A28A CSO
3-in. x 6-in. CSO CSO
E25A
FO
8002 HS
8003A
31-1183
4-in.HG–80010–E25A–N
4-in. HG–80011–E25A–N
Open

HY Close
8003 HS
ZLC ZLO S

Close
8003B
8003 8003
AS ATM Close SDY
HS 8002
ZSC ZSO S ZLO ZLC ATM
8003 8003 Note–8,9 8002
R 8002 8002
ATM AS
TSO
ZSO ZSO
3-in. HG–80008–E25A–N HV
FC CSO CSO 8002 8002
8003 ¾-in. TSO
PI H FC
Readable 8003 SDV
from grade L 8002 ¾-in.
PG
8004
PIT
8003 High-pressure
HC–80012–E25A–N

Flare (900-U-001) close valve


H TI 2-in. I
8001
Close

L
Hydrogen (550-P-002) Close SDY
HS 8001 ZLC
S
TIT 8001 8001
R
8001
ATM AS

FIG. 3 System mark-up within the unit.

System dossiers. All documentation • Functional test sheets—a spreadsheet • Vendor reports—documentation on
pertaining to the precommissioning opera- showing the various stages of equipment vendor’s acceptance of installation
tions are compiled into a specific dossier. installation from setting to sign-off. • Design-change notes/modifica-
All the facilities—including the equipment, • Operational test sheets—a spread- tions—site modification, as required or sug-
instrument activities and all the subsystems sheet showing the completion status of gested by licensor, should be well documented
pertaining to a particular system—should miscellaneous mechanical components • As-built drawings—while it may not
be grouped in the same system. The draw- (e.g., PSV’s, orifice plates, check valves, be entirely possible to issue as-built docu-
ings, reports and all other related docu- spring supports) mentation during the precommissioning
ments of the system may be maintained • Specific procedures/reports—an stage, all of it should be ready before com-
and retained as part of the same system. example may include catalyst-loading pletion of commissioning
Dossiers should include, as a minimum: procedures • Precommissioning punchlists—
• System description and marked- • Mechanical/electrical/instrumen- internal equipment inspection, e.g., vessel,
up drawings. The systems are defined tation maintenance-related reports—an column, tanks, etc.
by P&ID markups and have a detailed example may consist of a mechanical seal • Leak test all defined systems as
description, such that the systems are nei- replacement on a process pump or replacing required or recommended from the
ther too broad or too narrow. a faulty pressure transmitter punchlist

122
I APRIL 2011 HydrocarbonProcessing.com
PLANT DESIGN AND ENGINEERING

• Ready for commissioning certifica- groups of the engineering, procurement be links to the equipment tag numbers
tion—signed off by all stakeholders and construction contractor along with that are fundamental to the requirements
• System-related milestones—all the client can work out the initial action— of inspection, testing and commission-
major activities, as decided, should be focusing on the systems most critical for ing at each stage of the project. Tools for
planned and monitored. a timely precommissioning. This sched- preservation and maintenance, as well as
ule will identify, by system, the preferred management and control on punch listing
Categorize your punchlists. Punch sequence where each construction group throughout the mechanical completion,
list categories should be segregated criti- should prepare and complete the scoped precommissioning and commissioning
cally—a minimum of three categories are project systems. It will also identify walk- phases, are to be provided.
suggested. Category PINK are those issues down dates for each system and specific Ideally, there are many desired func-
that prevent the subsystem/system from precommissioning activities to precommis- tions, only limited examples are cited for
being precommissioned. Category RED sion individual systems (i.e., reactor catalyst each of these functions and include:
are those issues that prevent the subsystem/ reduction, regeneration of water removal • Employee wise departmental and
system from being commissioned or started driers, etc.). functional access control—the commis-
up. Category GREEN are those issues that sioning group leader can restrict the dele-
are not in Category PINK or RED. Systems record management. As tion of records, thus controlling the modi-
the time required to hand over projects fication of documents.
Define your milestones. The key decreases, real-time monitoring and trou- • Client/contractor/licensor access con-
milestones associated with transferring the ble-shooting assumes paramount impor- trol has real-time access to punch lists and
responsibility from the precommission- tance. Software packages, i.e., structured enables client/contractor/licensor to log in.
ing phase to the operation phase includes database management systems, which are Access should be controlled while certain
a subsystem ready to hand over when all customized to be completion management groups don’t need access, i.e., a pump ven-
precommissioning operations on that sub- systems are preferred for real-time informa- dor doesn’t need access to items not in their
system are complete. Another milestone is tion agents. scope of work.
when a system is ready for commissioning/ This enables a structured approach to • A standard checklist for construction
startup when all checks are complete for manage, control and improve the abil- phases includes checklists for activities that
introducing feedstock. ity to safely and successfully execute and are not limited to pump alignment, com-
integrate construction and commissioning pressor alignment, hydrostatic tests and
Be precise with your schedules. activities. Within these packages should equipment installation.
Three schedule levels are recommended
to control the mechanical completion Asset Longevity
and precommissioning activities. These
are levels A, B and C. Level A schedule Plant & Pipeline Performance
indicates the key dates for the entire plant
with the overall period of precommis-
sioning. Level B schedule highlights the
key phases and milestones for a particular
unit, and also highlights the expected con-
struction completion dates, duration and
timeframes for precommissioning phases
per unit, etc. Level C schedule illustrates,
per system, the various precommission-
ing main activities sorted per discipline/ Quest Integrity Group is a dynamic company built on a founda-
trade (i.e., electrical, piping and process tion of leading edge science and technology that has innovated
inspection activities, instrumentation and and shaped industries for nearly 40 years.
rotating equipment).
Our asset integrity and reliability management solutions are
Before you begin. In breaking down
comprised of technology-enabled advanced inspection and
the facility by systems, the following is par-
amount: hydrostatic test packages normally engineering assessment services and products that help com-
do not cross subsystem boundaries. This panies in the refining and chemical, pipeline, syngas and power
will ensure no rework of hydrostatic pack- industries increase profitability, reduce operational and safety
ages by counterparts in construction. Also, risks and improve operational planning.
subsystems shall not cross system bound-
aries and process systems shall not cross (888) 557-3363
existing facilities boundaries. (888) 893-7030

Developing a schedule. A detailed www.QuestIntegrity.com


precommissioning schedule of sequen- Sales@QuestIntegrity.com
tial activities for each system should be
developed. The planning and scheduling
Select 178 at www.HydrocarbonProcessing.com/RS
123
PLANT DESIGN AND ENGINEERING

• A standard checklist for the precom- “inbox messages” or “notifications” for a narios and experience. As known, for a
missioning phase includes system flush- particular user. successful startup, the plant and equip-
ing, air-blowing, steam blowing, chemi- • Historization includes generating ment should be put through a thorough
cal cleaning and inertizing. The checklists milestone completions records—w.r.t pre- mechanical completion and inspection.
should include creating/using standard defined or maybe redefined components. Commissioning procedures should be
reports and creating/using a predefined • Maintenance management is the closely monitored with the availability of
blind list. database integration with the company’s adequate spare parts and maintenance sup-
• Real-time monitoring includes inte- maintenance management system, while port and response. The company’s profit-
gration with the planning department mon- claims management is capable of managing ability, reputation, project success, plant
itoring system to report real-time progress and sending inputs to the company’s insur- effectiveness and pay are all at stake. With
(punch list status, system’s “movement sta- ance’s claim system. what was previously discussed, adequate
tus,” etc.). • The inspection test plan creates and overall planning, detailed long-term prepa-
• The checklist needs to be operation manages the construction’s inspection test ration and effective resource planning are
friendly, allowing multiple views into the plan. This includes relating NDT records, required. All field equipment are subject
same organized data, by system or sub- action on hydrotest packs, etc. to a full scope of work, as defined in bids,
systems. • Stores integration will integrate proj- except for packaged equipment that have
• Engineering database integration ect stores with the maintenance stores man- undergone rigorous factory acceptance
should be capable of importing engineer- agement system. A shortfall in material can testing (FAT) by the original equipment
ing data sets from various engineering data- be related to the bill of materials identifica- manufacturer (OEM). For these pack-
bases. These should provide a list of the add, tion and appear as part of the exception list ages (packaged equipment are compres-
delete, revise for review and optionally inte- when a checklist is generated. sors, pressure swing adsorber units, etc.),
grate with the systems defined. • Managing contractual manpower typically a single checklist is handed out.
• The “work anywhere” defines con- includes the labor/supervisor reported to Commissioning engineers should ensure
cepts that are able to handle multiple job- site, millwright fitters that work on rotating that every piece of equipment is subjected
sites/geographic work locations in a collab- equipment and manage contractual work to the appropriate checks and tests during
orative environment. passes, etc. precommissioning.
• Be the “alarm clock” by prompting The list isn’t exhaustive and should During the mechanical completion
the next action in a workflow by way of be expanded with time, business sce- checks and system tests, all discrepancies,
damaged or missing equipment, malfunc-
tions, missing documents, etc., should be
categorized and recorded in the subsystem
HIGH ACCURACY punchlists. Lists are kept updated through-
out the mechanical completion operations,
FLOW METERS so a precise status of each subsystem is
available at the “ready for precommission-
ing stage.” Additionally, arrival of startup
staff can be scheduled when construction is
nearly mechanically complete, saving time
and money. By the systematic approach,
these are all achievable. These summarize
the basic skeleton of a structured approach
to precommissioning a process unit. HP

Vinod Ramnath is employed at


Engineers India Ltd., New Delhi, India,
FOR HIGH TEMPERATURES in the process plant design, safety/loss
AND HIGH PRESSURES prevention and operations depart-
ment. He has experience with design of
– non-intrusive ultrasonic clamp-on technology www.flexim.com offsites (FEED), HAZOP/Quantitive Risk Assesment (QRA),
– for temperatures up to 750 °F usinfo@flexim.com safety integrity level (SIL), process plant commisioning,
– independent of process pressure preparing in-house precommisioning/commissioning
FLEXIM AMERICAS completion software systems. Mr. Ramnath started his
– multi-beam for high accuracy Corporation
– wide turn down career with Reliance Industries, Hazira, Gujarat, India,
Phone: (631) 492-2300
and was involved with commissioning of the naphtha
– installation without process shut down Toll Free: 1-888-852-7473
cracker unit (ethylene plant). He jointly implemented
– no maintenance and operated APC and real-time optimizer (RTO) models
– no pressure loss across the naphtha cracker units, and was involved with
– standard volume calculation debottlenecking studies and microplanning during normal
operation and shutdown. Prior to working at the naphtha
TYPICAL APPLICATIONS: cracker plant, Mr. Ramnath operated a solution polym-
HEAT TRANSFER OILS | BITUMEN | PITCH/TAR | COKER FEED | CRUDE OILS/SYNTHETIC erization-type polyethylene plant at the same location.
CRUDE | GAS OILS | REFINED PETROLEUM PRODUCTS | HOT OR TOXIC CHEMICALS He earned a degree in chemical engineering from Anna
University, Chennai, India, and graduated with honors.
Select 179 at www.HydrocarbonProcessing.com/RS
124

You might also like