Professional Documents
Culture Documents
TOS 5 Unit 3 Design of Columns Across Multiple Floors
TOS 5 Unit 3 Design of Columns Across Multiple Floors
DESIGN
W CONTINUED
TOS 5: UNIT 2C: DESIGN OF FROM TOS IV
Concrete is good in compression however we design Compression Members like Columns and do
put steel in these columns mainly for the following reasons
1. Reduction in Size: Steel is good in compression and helps us to reduce the size of the
column members
2. Eccentricity in Loading: There is always eccentricity of Loading on a column leading to a
situation where the column is subjected to both pure compressive stresses and bending
stresses which may put part of the column under tensile stresses.
The reasons for this eccentricity are many. I am just elucidating a few
1. Beam Position: Beams may not be placed centrally on a column due to architectural
considerations in the sense that Beams are placed flush to one face of the column (Beams
width is lesser than the column width) because the wall above is to be placed on that side
4. Reduction in Size of Column as we go up: Columns as they go from top floors to bottom
floors required to carry one floor load extra at every floor (This is considering a same plan
at all floors). Thus the column size may have to be increased as we go down to the ground
floor. This increase in size may be carried out symmetrically on each side of the column or
as in most cases increase is affected on one side only as can be seen in the following
diagrams.
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
3
There are different ways of dealing with this eccentricity of loading on a column but out of scope
of our syllabus, so we shall now proceed to the main objectives of this unit.
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
4
Before we begin this exercise I would like to High Light a few of the I.S.Code points and some
points regarding the Design of Columns
1. Cover is 40mm
2. The maximum distance between two bars in a column is 300mm along the periphery
The above two points result in the conclusion that if a column is rectangular with one side
greater than 380mm, then we will have to provide at-least 3 no of bars along that face,
hence at-least 6 bars in the Column.
The Structural Engineers prefer to not use more than 3% of Steel as this would make
Concreting operations difficult
5. Each Main Bar is to be tied by a Link in Two Direction at-least top prevent buckling in those
directions
6. A Column shall be called Short if Le/b min < 12
7. Minimum number of bars in a Column is 4 in a Rectangular Column and 6 in a Circular
Column.
The above points gets us the result that minimum side of the column with a normal floor to
floor height of 3000mm (effective length of the column≈2800)will be 2800/12≈230
Hence the minimum size of a Column would be 230 x 230 and minimum reinforcement
would be 4 no 12mm bars.
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
5
2. If the % of steel in a column is 1% then the load taken by the column = 1.5w, in terms of
gross cross sectional are can be calculated as follows
Let % of steel be 1.0 % (We can assume 0.8% to 6%). Hence Asc = Ag/100, Ac = 99Ag/100
Pu = 0.4 fck x Ac + 0.67 x fy x Asc
Pu = 0.4 x 20 x 99Ag/100 + 0.67 x 500 x Ag/100
Pu = 7.92 Ag + 3.35 Ag
Pu = 1.5w = 11.27 Ag
We can also calculate the Load taken by a column for different % of steel and arrive at the
following conclusions
For Fe 500 Steel and M20 grade Concrete these then are the values for load by a Column
% of Steel Load Taken By Column
1 11.27 Ag
1.5 12.905 Ag
2 14.54 Ag
2.5 16.175 Ag
3 17.81 Ag
Problem 1: A column in a building is abutted by 3 beams. Two beams of clear span 7.2 M
carrying a load of 42 kN/M each in the same direction and one beam of 3.5M clear span
carrying a load of 32kN/M. The Building is Parking + 4 Floors Calculate the load at each Floor
considering the same configuration exists at every floor; also design the columns at every floor
given the following
1. Design Column on Fourth Floor.
2. For Column on Third Floor Take one side same as on Fourth Floor
3. For Column on Second Floor Take Size same as on Third Floor (Change % of Steel)
4. For Column on First Floor, Change the Size if you want and decide % of steel
5. Column on Parking Floor. Give Options and Choose one most suitable
The Plan for Column and Beam Configuration on fourth floor has been shown.
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
6
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
7
Explanation for Different Answers: The expression Pu = 0.4 fck Ac + 0.67 fy Asc has two variables
Ac and Asc which are interdependent i.e. changing the percentage of steel or Asc will also change
the concrete area i.e. Ac.
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
8
I am going to choose Option C and take the size of my column as 300 x 550
Asc = 3/100 x 300 x 550 = 4950mm²
Let us Provide 10no 25mm = 10 x 490 = 4900mm²
Design of Links: After Due Design Provide 8mm Links @ 300c/c
Provide Column of Size 300 x 550, 10no 25mm, 8mm links @ 300c/c
Column Schedule
8 Φ@ 4no 16 Φ, 8 Φ@ 4no 25 Φ, 8 Φ@
230 x 230 4no 12 Φ 190c/c 230 x 450 2no 12 Φ 190c/c 230 x 450 2no 20 Φ 230c/c
C2
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho
9
Main
Size Steel Links Size Main Steel Links
8 Φ@ 8 Φ@
230 x 550 8no 25 Φ 230c/c 300 x 550 10no 25 Φ 300c/c
C2
TOS 5 Unit 3 Design of Columns Across Multiple Floors Compiled by Ar. Arthur Cutinho