Professional Documents
Culture Documents
Project Execution Dilemma@MICC
Project Execution Dilemma@MICC
Project Execution Dilemma@MICC
Background
What is Refurbishing Project (RP) of NIM?
Scope: Refurbishing external and internal facade of Main Building ( 4
classroom blocks, 3 faculty blocks, 2 admin blocks)
Major activities: Stone removal, Plastering, Painting
INR 30 million contract
Time line: 8 months
Contract was awarded to MICC on Nov 17, 2012 after due tendering
process
Crucial milestone : Work in the four classroom blocks to be completed
before the commencement of new academic term i.e. June 1, 2013
1
07-12-2019
Background
EXHIBIT 4: MAJOR MILESTONES
Per cent equivalent work completion is proportionate to time required; however, the buffer time is provided for smooth
project execution.
# NIM would take 10 days to settle bills presented by MICC after achieving particular milestones.
Source: Project Tender Documents.
2
07-12-2019
Current Problems in RP
What problems did MICC face in the Refurbishing Project?
As per conditions of the tender, MICC had to complete the project within eight
months from the date of award of the contract.
However, a month after the commencement of work, Parkhi observed a very slow
pace of work due to a poor deployment of resources and ad-hoc project planning.
It was envisaged that the project could be delayed and that MICC could not even
achieve the first crucial milestone (completing work on the classroom blocks of the
main building).
The potential project delay would result in a cost overrun, a reduction in the profit
margin and a loss of reputation for MICC, which would force NIM to make alternate
arrangements for classroom blocks.
Parkhi considered how to fast-track the project execution and also contemplated the
pros and cons of the early completion of the project.
Current Problems in RP
What could the possible causes for the execution
delay be?
Ad-hoc planning approach
In-sufficient resource deployment
Lower Productivity of team
Loose monitoring and control mechanism
3
07-12-2019
Consequences of ad-hoc
project planning to various stakeholders
For MICC
Loss of goodwill or reputation
Cost overrun resulting into a reduced profit margin
Working capital issue
Opportunity loss to begin upcoming projects on time
For users (faculty, students, visitors)
More risk and inconvenience in using main building
For NIM
Non-availability of classroom blocks for next academic year
Additional efforts and costs for alternate arrangements
Loss of goodwill
4
07-12-2019
(No. of teams)
(m2/team/day)
Work content
for a typical
Predecessors
No. of days
required to
Total work
work front
resources
relationship
Work rate
Precedence
complete
Planned
content
activity
(in m )
(in m )
Activity
2
(a) (b) =a/14 fronts (c) (d) (e) = a/(c*d)
A - - 28,000 2,000 250 4 2
B A SS+1day 28,000 2,000 20.00 20 5
C B SS+1day 28,000 2,000 36.36 11 5
D C SS+1day 2,800 200 40 1 5
E D SS+1day 2,800 200 40 1 5
F E SS+1day 28,000 2,000 41.67 8 6
G F SS+1day 28,000 2,000 33.33 10 6
H G FS+0 day 28,000 2,000 500 1 4
I G SS+13days 28,000 2,000 166.67 2 6
J I SS+1day 28,000 2,000 71.43 4 7
K J SS+1day 28,000 2,000 57.14 5 7
L K SS+1day 28,000 2,000 40.82 7 7
M - - 24,400 1,743 44.69 3 13
N M SS+1day 24,400 1,743 29.05 4 15
O N SS+1day 24,400 1,743 48.42 2 18
P O SS+1day 24,400 1,743 48.42 2 18
Q P SS+1day 24,400 1,743 48.42 2 18
Activity
A 4 4
B 20 20 20 20 20
C 11 11 11 11 11
D 1 1 1 1 1
E 1 1 1 1 1
F 8 8 8 8 8 8
G 10 10 10 10 10 10
H 1 1 1 1
I 2 2 2 2 2 2
J 4 4 4 4 4 4 4
K 5 5 5 5 5 5 5
L 7 7 7 7 7 7 7
M 3 3 3 3 3 3 3 3 3 3 3 3 3
N 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
O 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
P 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Q 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Day--> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
5
07-12-2019
Activity
A 1000 1000
B 400 400 400 400 400
C 400 400 400 400 400
D 40 40 40 40 40
E 40 40 40 40 40
F 333 333 333 333 333 333
G 333 333 333 333 333 333
H 500 500 500 500
I 333 333 333 333 333 333
J 286 286 286 286 286 286 286
K 286 286 286 286 286 286 286
L 286 286 286 286 286 286 286
M 134 134 134 134 134 134 134 134 134 134 134 134 134
N 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116
O 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
P 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
Q 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
Day--> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
6
07-12-2019
Payment Schedule
7
07-12-2019
receipts from
Interest cost
requirement
requirement
receipt from
requirement
Scaffolding
Cumulative
Cumulative
Cumulative
standalone
Direct L+M
overhead
Payment
payment
net fund
Indirect
Setup
Fund
fund
cost
cost
cost
cost
Day
NIM
NIM
0 2,500,000 0 0 0 2,500,000 25,00,000 0 2,500,000 0
30 1,407,583 67,500 1,475,083 39,75,083 0 4,012,583 37,500
60 3,907,583 67,500 3,975,083 79,50,166 0 8,010,355 60,189
90 3,907,583 67,500 3,975,083 11,925,249 9,000,000 9,000,000 3,045,404 120,155
120 3,907,583 67,500 3,975,083 15,900,332 9,000,000 6,946,013 45,681
129 15,900,332 6,000,000 15,000,000 931,589 31,257
150 3,907,583 67,500 3,975,083 19,875,415 15,000,000 4,885,196 9,782
169 19,875,415 6,000,000 21,000,000 -1,078,176 46,409
180 3,907,583 67,500 3,975,083 23,850,497 21,000,000 2,850,497 0
185 0 0 23,850,497 21,000,000 2,857,624 7,126
199 2,474,803 42,750 2,517,553 26,368,050 21,000,000 5,388,053 20,003
209 26,368,050 9,000,000 30,000,000 -3,611,947 26,940
Total 2,500,000 0 23,420,300 447,750 26,368,050 52,736,100 30,000,000 405,043
Particulars Amount
Additional scaffolding cost 0
Direct labour + material cost 25,920,300
Indirect overhead cost 447,750
Interest 405,043
Total cost 26,773,093
Total revenue 30,000,000
Margin 3,226,907
Margin % 10.76
8
07-12-2019
Project completion
Number of parallel
scaffolding sets
Requirement of
Profit Margin*
time (in days)
(of 2000 m )
work-fronts
Alternative
additional
Remarks
2
Not viable in comparison
1 0 0 199 10.76%
with Alternative 2
2 2 1 108 10.86% Best Project Return
3 3 2 82 10.09%
4 4 3 69 9.18%
5 5 4 56 8.38%
6 6 5 56 7.26%
7 7 6 43 6.46% Not viable in comparison
8 8 7 43 with Alternative 2; higher
9 9 8 43 losses due to additional
10 10 9 43 scaffolding cost
11 11 10 43
12 12 11 43
13 13 12 43
14 14 13 30 -0.46%
Activity
A 1000 1000
B 400 400 400 400 400
C 400 400 400 400 400
D 40 40 40 40 40
E 40 40 40 40 40
F 333 333 333 333 333 333
G 333 333 333 333 333 333
H 500 500 500 500
I 333 333 333 333 333 333
J 286 286 286 286 286 286 286
K 286 286 286 286 286 286 286
L 286 286 286 286 286 286 286
M 134 134 134 134 134 134 134 134 134 134 134 134 134
N 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116
O 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
P 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
Q 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97 97
Day--> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
9
07-12-2019
Thank You
10