PARK TERRACES TOWER 02

TECHNICAL DUE DELIGENCE AUDIT


Target ACTUAL STATUS
Floor/ Per System Target
Item No. Endorsement No. of Close Percentage
(Architectural and MEPFS) Completion
Condo Corp. No. of Punchlist Punchlist Accomplist
Open Punchlist
3th-15th Floor 460 457 99.35% 3
Tranche 1 Plumbing May 17, 2019 June 03, 2019 39 39 100.00% 0
Mechanical 21 21 100.00% 0

16th-36th Floor 944 743 78.71% 201


Tranche 2 June 28, 2019 July 15, 2019

Electrical & Power Distribution 45 42 93.33% 3


Fire Pro & FDAS 32 23 71.88% 9
37th-50th Floor 525 160 30.48% 365
Basement 1-4 82 33 40.24% 49
Fire Exits B1-Roof Deck 510 204 40.00% 306
Tranche 3 August 02, 2019 August 19, 2019
Gen Set 49 45 91.84% 4
Elevator Architectural 61 4 6.56% 57
Elevator MEPFS 12 6 50.00% 6
GF and 2F 113 61 53.98% 52
Tranche 4 Roof Deck Sept. 18, 2019 Sept. 30, 2019 35 13 37.14% 22
51st-52nd 52 7 13.46% 45
Total Accomplishment 3641 2403 66.00% 1238

Over all Accomplishment as of June 18, 2019


Total No. of Remaining
Description Percentage
Punchlist Done Punchlist
Architectural Punchlist 3443 2227 64.68% 1216
MEPFS Punchlist 198 176 88.89% 22
Total Accomplishment 3641 2403 66.00% 34.00%

PARK TERRACES TOWER 01


FACADE AUDIT