Professional Documents
Culture Documents
Fuji Elevator Installation PDF
Fuji Elevator Installation PDF
2015.A
Silver Swallow Series Passenger Elevator with
Machine Room
Elevator Installation Manual
Table of Contents
Elevator Structure ................................................................................................................................ 1
Chapter 1 Preparations before Elevator Installation ............................................................................ 2
1.1 General ..................................................................................................................................................... 2
1.2 Safety precautions .................................................................................................................................... 2
1.2.1 Inspection before installation ............................................................................................................ 2
1.2.2 Maintenance of the working environment ...................................................................................... 13
1.2.3 Safety precautions for hoistway work ............................................................................................. 13
1.2.4 Protection at the hoistway entrance................................................................................................. 14
1.2.5 Fire prevention ................................................................................................................................ 14
1.2.6 Management of gas ......................................................................................................................... 14
1.2.7 Safety protection ............................................................................................................................. 14
1.2.8 Trial run operation .......................................................................................................................... 14
1.2.9 Safety inspection ............................................................................................................................. 15
1.3 Preparatory work on the construction site.............................................................................................. 15
1.3.1 Consultation with the customer....................................................................................................... 15
1.3.2 Verification of the hoistway ............................................................................................................ 15
1.3.3 Storage of materials ........................................................................................................................ 15
1.3.4 Installation plan confirmation ......................................................................................................... 15
1.3.5 Tool preparation (list) ..................................................................................................................... 16
Chapter 2 Process Specification for Elevator Installation ................................................................... 22
2.1 Material open-package inspection ......................................................................................................... 22
2.2 Erection of scaffolding ........................................................................................................................... 22
2.3 Sample holder and suspension wire ....................................................................................................... 25
2.4 Installation of machine room equipment ............................................................................................... 27
3.4.1 Drive system installation................................................................................................................. 27
2.4.2 Control cabinet positioning and installation ................................................................................... 41
2.4.3 Machine room trunking layout ........................................................................................................ 42
2.5 Navigation system installation ............................................................................................................... 44
2.5.1 Guide rail support installation ......................................................................................................... 45
2.5.2 Guide rail installation ...................................................................................................................... 51
2.5.3 Governor positioning and installation ............................................................................................. 55
Elevator Installation Manual
2.6 Car System Installation .......................................................................................................................... 57
2.6.1 Car Frame Installation ..................................................................................................................... 58
2.6.2 Installation of Car Cab .................................................................................................................... 71
2.6.3 Installation of Door Operator and Car Door ................................................................................... 83
3.6.4 Installation of Car Roof Guardrail, Cross Flow Fan and Ceiling.................................................... 84
2.7 Installation of Counterweight System .................................................................................................... 89
2.7.1 Installation of Counterweight System ............................................................................................. 90
2.7.2 Installation of Counterweight Protection ........................................................................................ 93
2.8 Installation of Buffer .............................................................................................................................. 94
2.9 Installation of Hoistway Equipment ...................................................................................................... 96
2.9.1 Installation of Traveling Cable and Hoistway Cable ...................................................................... 97
2.9.2 Installation of Ultimate Limit Device and Leveling Device ......................................................... 102
2.9.3 Installation of Counterweight and Weighing Device .................................................................... 109
2.10 Traction Steel Wire Rope................................................................................................................... 110
2.10.1 Installation of Steel Wire Rope ................................................................................................... 110
2.11 Installation of Landing Door System ................................................................................................. 112
2.11.1 Installation of Sill ........................................................................................................................ 112
2.11.2 Installation of Door Pocket and Upper Sill ................................................................................. 114
2.11.3 Installation of Door Leaf ............................................................................................................. 117
2.11.4 Adjustment of Door Lock ........................................................................................................... 119
2.12 Installation of Compensation Device ................................................................................................. 121
2.13 .Assembly of Pit Ladder..................................................................................................................... 127
2.13.1 Installation of Pit Ladder............................................................................................................. 127
2.13.2...................................................................................................................................................... 129
Tension device ....................................................................................................................................... 129
2.13.3 Installation of Pit Electrical Equipment ...................................................................................... 129
2.14 Removal of Scaffold .......................................................................................................................... 130
Appendix: Car Decoration .................................................................................................................131
Elevator Installation Manual
Elevator Structure
Traction
machine
Control
cabinet
Traction
Machine machine rack
bearing beam
Car
Car door
component
Counterweight
guide rail support
Counterweight
device
Leveling frame
Note: 1. The installation positions of main elevator parts are as shown in the figure;
2. Any site assembly in case of a special condition can be carried out only after the
confirmation of our related personnel.
1 / 135
Elevator Installation Manual
2 / 135
Elevator Installation Manual
1 pc.
Landing door Triangulation chain of
3 per
warning sign the landing door
floor
For elevator
Label of Elevator out
5 1 pc. maintenance (ground
of Service
floor)
3 / 135
Elevator Installation Manual
1 pc.
if
there
Elevator leveling are On the wall of the
7
mark (32-62) 32-62 machine room
floors
in
total
4 / 135
Elevator Installation Manual
Label\ Electric
Outer side of the
13 Shock Danger 1 pc.
control cabinet door
\80*105
5 / 135
Elevator Installation Manual
Label\ Moving
Equipment Hazard
16 1 pc. On the car roof
in Hoistway \
80*105
Label\ Overhead
On the wall of the top
17 Crash Hazard in 1 pc.
floor
Hoistway \ 80*105
Label\
On the counterweight
18 Counterweight 1 pc.
housing
Hazard\ 80*105
6 / 135
Elevator Installation Manual
Label\ Hard-hat
21 1 pc.
Required\ 80*105
Label\ Voltage
Indication Tag for On the power box of
22 1 pc.
Machine Room\ the machine room
180*180
7 / 135
Elevator Installation Manual
Label\
Counterweight
23 1 pc. On the pit guardrail
Hazard in Pit\
180*180
1 pc.
for
Label\ emergency
elevat
rescue work
or Inner side of the door
procedure for
26 witho of control cabinet
traction machine
ut without machine room
without machine
machi
room \200*270
ne
room
8 / 135
Elevator Installation Manual
Proposed sign
No. Material description Quantity Sign
position
1 pc. for
Label\ emergency
elevator
rescue work
with
procedure for traction
machine On the wall of the
27 machine with
room machine room
machine room (gear
(gear
main engine)\
main
200*280
engine)
1 pc. for
Label\ emergency
elevator
rescue work
with
procedure for traction
machine On the wall of the
28 machine with
room machine room
machine room
(gearless
(gearless main
main
engine)\ 200*270
engine)
Elevator safety
instructions \ L*W:
30 1 pc. Inside the car
210*290 \ base color:
white
9 / 135
Elevator Installation Manual
Elevator installation
Caution label\ L*W:
32 1 pc. Ground floor
297*210 \ base
color: white
Project frame
diagram\ L*W:
33 1 pc. Machine room
297*210 \ base
color: white
Up and down
traveling label \ base Traction machine
34 1 set
color: Y07 mid hood
yellow
10 / 135
Elevator Installation Manual
Leveling mark
indication label\
36 L*W: 105*60\ base 1 pc. On the machine rack
color: Y07 mid
yellow
11 / 135
Elevator Installation Manual
Wear protective
43
gloves
12 / 135
Elevator Installation Manual
Wear safety
45
glasses
Try to avoid several works on different floors in the hoistway at the same time.
13 / 135
Elevator Installation Manual
14 / 135
Elevator Installation Manual
15 / 135
Elevator Installation Manual
1pc. for
1 Chain block 0.5T,1T,3T,5T
each
Made of steel
4 Crow bar 2 pcs.
tube
Steel wire
Y4~Y12,Y5~Y1 10 pcs. for
5 rope tying
5 each
head
16 / 135
Elevator Installation Manual
IV.
Lifting
tools
2 sticks
8 Sling 3T 5T
for each
8m
1 Multimeter 1 pc.
V. Tools
of
electricia
n
Tong-type
3 5~150A 1 pc.
ammeter
17 / 135
Elevator Installation Manual
Wire
5 1 pc.
stripper
V. Tools of
electrician 6 Test pencil 2 pcs.
Electrician’s
7 2 pcs.
knife
Rubber
1 1 pc.
hammer
VI. Special
2 Guide ruler 2 pairs
tools
1pc. for
3 Tape 30,50CM
each
18 / 135
Elevator Installation Manual
10 pcs. for
6 Plumb line 5kg,10kg
each
VI.
Special
tools
Car operation
7 1 set No scaffolding available
platform
Top operation
8 1 set No scaffolding available
platform
9 Wrench 1 set
19 / 135
Elevator Installation Manual
Electric AC
10 welding 380V/220V 1 set
machine dual purpose
VI.
1 pc. for
Special 11 Spring scale 0.5N, 30N
each
tools
Power box at
the
12 2 pcs.
construction
site
VII.
Commissi Tong-type
2 1 pc.
oning ammeter
tools
Noise meter
3 1 set
(A)
20 / 135
Elevator Installation Manual
5 Stopwatch 1 pc.
1 pc. per
3 Flashlight
person
21 / 135
Elevator Installation Manual
Protective equipment
1 Site and channels Confirm that the material piling yard and channels are smooth
22 / 135
Elevator Installation Manual
Protective equipment
Tools
Scaffolding must
2 be erected by a
professional unit
(1)Plane layout requirements
23 / 135
Elevator Installation Manual
The vertical space of the scaffolding cross bar is generally less than 1.3m. It is required to meet
the bar space for each landing first in vertical layout. The other parts can be determined according to
the specific size, but not exceeding the space. The cross bar at the entrance of the landing door
should be erected according to the requirements of Fig. For the convenience of climbing, a cross
beam can be added between two adjacent cross beams on one side of the scaffolding. It is required
as below.
Two or more scaffold boards can be laid on the cross beam of each floor to form a platform with the
overall width greater than 400mm, which is able to withstand the load of 2500 N/m2. The two ends
of the scaffold boards should extrude 100~200mm beyond the cross bar and be securely fixed on the
cross bar with the Φ1.2mm or above galvanized wire. The scaffold boards of the adjacent floors
should be arranged in 90° cross form.
24 / 135
Elevator Installation Manual
Tools
List: tape, angle rule, leveling instrument, hammer, steel saw, saw, snap line, etc.
Steps Operation Remarks
Sample holder
1
diagram
B- Car depth
C- Distance of the counterweight guide rail support
D- Distance between the car frame centerline and the
counterweight housing centerline
E- Distance between the car frame centerline and the car rear wall
F- Net width of the door opening
G- Distance of the car guide rail support
1 - Plumb line 2 - Counterweight centerline
3 - Car centerline 4 - Connected nail
25 / 135
Elevator Installation Manual
Plumb line
Plumb
5 Retest
26 / 135
Elevator Installation Manual
Tools
List: chain block, wrench, level ruler, tape, welding machine, etc.
Car centerline
Actual size of door
See rope winding method of the drive system as shown on the next
page.
27 / 135
Elevator Installation Manual
Traction machine
Traction sheave
Traction machine rack
Counterweight
rope hitch plate
Car guide pulley
Car
Car door
Counterweight
guide pulley
28 / 135
Elevator Installation Manual
Traction
曳引机
machine Machine rack
机架
导向轮装置
Guide pulley device
Shock pad
减震垫
Machine
搁机大梁
Bearing beam
A
Traction
曳引机
machine
Machine
Machine 机架
rack
搁机大梁 Shock pad
减震垫
Bearing beam
Note: AH refers to hoistway width; BH refers to hoistway depth; both A and B are in counterweight postposition
structure.
29 / 135
Elevator Installation Manual
Machine
Machine Bearing beam
Landing door direction Bearing beam Landing door direction
30 / 135
Elevator Installation Manual
Center of load
bearing wall
Machine
Bearing beam
Backing plate
(5) Adjust the levelness and height difference of the machine bearing beams by spacer. After the
installation of a number of machine bearing beams, the levelness of the upper surface shall be not more
than 0.5/1000. The height difference between the upper surfaces of the machine bearing beams shall be
not more than 0.5mm, and the mutual parallelism (observed from top view) shall be not more than 2mm.
Steps Operation Remarks
31 / 135
Elevator Installation Manual
(2) Lift the traction machine and install it on the machine rack. Connect by bolt set as shown in the figure
below.
Traction machine
E
B Square taper washer 16 Square taper washer 24 Square taper washer 20 4 pcs.
E
Nut 16 Nut 24 Nut 20 8 pcs.
Adjust positions of the traction machine and the machine rack base so that the traction machine can meet
the following installation technical requirements:
a. Traction machine position deviation: on the horizontal plane, the installation error shall be not more
than 2mm in the traction sheave diameter direction and not more than 1mm in the traction sheave axial
direction; during installation and inspection, hang plumb line in the center rope groove of the traction
sheave; check whether the plumb line coincides with the reference position on the sample holder and
then adjust position of the traction machine accordingly.
b. The parallelism between the end face of the traction sheave and the plumb line shall be not more than
2mm in no-load or full-load working conditions. During installation and inspection, hang two plumbs on
the end face of the traction sheave (the side far away from motor of the traction machine). Measure the
horizontal distance from the same plumb to the two measuring points on the end face of the traction
sheave. The difference value shall be not more than 2mm.
(3) After accurate positioning of the traction machine and the machine rack, install the machine rack
components on the machine bearing beam and fasten them by M16 bolt set and rail clip, as shown in the
figure below:
32 / 135
Elevator Installation Manual
(4) Install the guide pulley components on the machine rack and fasten them by M20 bolt set. Hitching legs of the guide
pulley device shall be configured as per the order BOM.
Traction sheave
A
Machine rack
A E
C
F
D
G
E
Installation of Guide Pulley Components (installation without hitching leg (above) and installation with hitching leg
(below))
33 / 135
Elevator Installation Manual
Adjust the guide pulley components (adjusting shim may be added at the junction place) to meet the
following requirements:
a.Guide pulley position deviation: on the horizontal plane, the installation deviation shall be not more
than 2mm in the guide pulley diameter direction and not more than 1mm in the guide pulley axial
direction; the calibration method is the same as that for the traction sheave.
b.The parallelism between the end face of the guide pulley and the plumb line shall be not more than
2mm in no-load or full-load working conditions. During installation and inspection, hang two plumbs
on the end face of the guide pulley. Measure the horizontal distance from the same plumb to the two
measuring points on the end face of the guide pulley. The difference value shall be not more than
2mm.
c.After installation, the guide pulley shall rotate flexibly without abnormal sound during rotation.
Steps Operation Remarks
Rope hitch plate Confirm the rope hitch plate specification and installation direction as
4
installation below.
The existing rope hitch plate may be in 5 types of specifications with 4-8 holes in specific layout as
below: 4-hole 5-hole 6-hole 7-hole 8-hole
Car rope
hitch plate
Counterweight
rope hitch plate
Note: Serial numbers of hole sites in the figure above are corresponding to the installation positions
of steel wire ropes in the figure below.
The installation direction of rope hitch plate shall follow the principle below: car/counterweight rope
hitch plate shall have the side with more hole sites close to the car roof sheave/counterweight sheave.
Taking 5-hole for example, see the installation direction of rope hitch plate and installation position of
steel wire rope as shown in the figure below. Counterweight
sheave
Guide pulley
Counterweight
sheave
Guide pulley
Traction sheave
Traction sheave
Fig. a (Schematic Diagram 1 of Installation Direction of Counterweight Postposition Rope Hitch Plate)
Fig. b (Schematic Diagram 2 of Installation Direction of Counterweight Postposition Rope Hitch Plate)
34 / 135
Elevator Installation Manual
Counterweight
sheave
Fig. c (Schematic Diagram of Installation Direction of Counterweight Side Position Rope Hitch Plate)
I
ΙΙ
35 / 135
Elevator Installation Manual
Fastened steel
channel component
Machine bearing beam
Supporting steel channel
Fig. a Fig. b
36 / 135
Elevator Installation Manual
Added rope
hitch plate
Fig. c
b) Fasten by fastener and welding. Fasten the rope hitch plate and the rope hitch shock pad by M10 nut
as shown below.
C
Weld the car rope hitch plate base on the machine bearing beam as shown in Fig. a below, and then
fasten the assembled rope hitch plate and rope hitch shock pad on the car rope hitch plate base by M12
bolt and rail clip as shown in Fig. b below. Direct the center of rope hitch plate at the car. The assembly
diagram is as shown in Fig. a below.
Full weld
Fig. a
37 / 135
Elevator Installation Manual
D
C
Fasten the rope hitch plate and the rope hitch shock pad by M10 nut as shown below.
C
Counterweight rope
hitch plate steel
channel
Fig. a Fig. b
38 / 135
Elevator Installation Manual
b) Fasten both ends of the supporting steel channel on the solid load bearing wall of the machine room
according to technical requirements the same as that for the installation of the machine bearing beam.
Weld the counterweight rope hitch plate on the fastened steel channel component and then, weld the
fastened steel channel component on the supporting steel channel and the machine bearing beam. Align
the center of counterweight rope hitch plate with the counterweight sheave rim, as shown in the figure
below.
Full weld
Fastened steel
channel component
Counterweight rope
hitch plate
Machine bearing
Full weld Supporting beam
steel channel
39 / 135
Elevator Installation Manual
Tools
List: impact drill, wrench, plumb, etc.
Steps Operation Remarks
According to the machine room layout and actual situation on site,
Confirm control draw the trunking layout on the ground of the machine room. Ensure
1 cabinet installation being horizontally and vertically straight and having as less turning as
position possible. Pay attention that the encoder line, power line and control
line must be separately laid.
Leading to power
box trunking
Leading to trunkings of
governor, rope clip,
band-type brake switch, Leading to encoder
band-type brake device, box trunking
41 / 135
Elevator Installation Manual
Expansion bolt
M12×125
Fig. a Fig. b
Protective equipment
Tools
List: impact drill, cutting machine, polishing machine, wrench, small hammer, tape, etc.
Steps Operation Remarks
Trunking route See detailed requirements as shown below. See the legend on Page
1
arrangement 39.
42 / 135
Elevator Installation Manual
43 / 135
Elevator Installation Manual
Self-tapping screw
Press plate
Trunking body
Trunking cover
Connection
plates
44 / 135
Elevator Installation Manual
Tools
List: tape, steel ruler, level ruler, impact drill, wrench, welding machine, etc.
Steps Operation Remarks
Confirm support
Note: the sleeve after being fastened by expansion bolt shall not
1 installation position
stretch out of the hoistway wall.
and fastening mode
45 / 135
Elevator Installation Manual
Each guide rail should have at least two gears of guide rail support. If the guide rail on the top is less
than 800mm long, it is only necessary to fasten by gear 1 guide rail support. The distance of guide rail
supports should be not more than 2500mm. The specific value will be subject to the construction layout
drawing of the project.
(1) Steel expansion bolts are suitable for cement components only and are inapplicable for brick
structure components. Moreover, cement intensity should be no less than 180kg/cm;
(2) Cement wall thickness should be no less than 120mm;
(3) Please refer to the figure for the requirements for the distance between bolt and cement edge as well
as the distance between the bolts
Fastening component
46 / 135
Elevator Installation Manual
Hoistway
wall
Full weld
c.After installation and adjustment without any problem, fully weld the connection, remove
welding slag and paint repair accordingly. See welding position as shown in the figure
above.
d.Guide rail and guide rail support will be fastened through rail clip as shown in the figure
below.
A Bolt M12x40 2 pcs.
A
B Flat washer 12 2 pcs.
Rail clip
C Spring washer 12 2 pcs.
Bottom plate
C Point weld
D
47 / 135
Elevator Installation Manual
a.Fasten the fixed support on the hoistway wall with expansion bolts and then connect
adjustable support and fixed support with bolts as shown in the figure below.
b.After installation and adjustment without any problem, fully weld the connection, remove
welding slag and paint repair accordingly. See welding position as shown in the figure
below.
B D
A C
A Bolt M12x40 2 pcs.
Supporting
a. Fasten the supporting steel angle (fixed support) with the Steel angle
Support feet Cut part
Steel hilti bolt.
b. Cut the length of the support feet according to the actual Hoistway wall
dimension on site.
c. Connect the support plate and the support feet (fixed
support and adjustable support) by bolts.
48 / 135
Elevator Installation Manual
d. After installation and adjustment without any problem, fully weld the connection, remove welding
slag and paint repair accordingly. See welding position as shown in the figure below.
Full weld
Full weld
Rail clip
f. Fasten the guide rail and the guide rail support by rail clip.
g. The structure after installation is as shown below.
Guide
rail
满焊Angle stiffener
Expansion bolt
M16x125
a.Fasten the supporting angle steel (fixed support) with the steel expansion bolts
b.Cut the length of the support feet according to the actual dimension on site.
c.Connect the support plate and the support feet (fixed support and adjustable support) by
bolts.
49 / 135
Elevator Installation Manual
d.Adjust position of the support plate and connect the support plate and support feet by bolts as
shown below.
e.After installation and adjustment without any problem, fully weld the connection and
remove welding slag. See welding position as shown in the figure above.
f.Fasten the guide rail and the guide rail support by rail clip.
g.Fasten the support plate and the car guide rail by rail clip. The structure after installation is as
shown below.
Full weld
The unevenness a of the guide rail support shall not exceed 1.5% regardless of any type or length (see
the figure below).
Guide rail
Guide rail
Horizontal line
50 / 135
Elevator Installation Manual
Tools
List: tape, ruler, plumb, guide ruler, hammer, wrench, laser parallelometer, etc.
Steps Operation Remarks
(1)Before installation, check whether the guide rail is straight without
Guide rail serious damage so as to ensure good comfort after installation.
1
inspection (2)Trim the guide rail joint and surface and clear away debris and
burr; after cleaning, apply a layer of anti-rust oil.
Guide rail Before handling to the pit, lay wooden board in the pit first to avoid
2 handling to the bump injury of the guide rail ends in handling. Note that all tongues
pit or grooves of the guide rails shall be in the same direction
Remove the base line of the guide rail support and hang the plumb
Guide rail line from the sample holder. The plumb line should be accurately and
3 base line stably fixed on the pit sample holder with the base line of 300mm of
placement the guide rail top surface, and this plumb line will be used as the base
line for the preliminary fixing of the guide rail.
Position the guide rail based on sample plumb line and fastens the
guide rail on the support by rail clip. Block up the first gear of guide
Installation of
rail by about 50mm with wood block or brick. 50mm is the part to be
4 the first guide
removed in unloading and guide rail calibration.
rail in the pit
Note: the guide rail should be placed on solid ground or the guide rail
base during guide rail calibration.
Lift the guide rails one by one through the bolt holes on the
connection plates from the bottom to the top by the hoister or
Installation of
manpower; wipe clean the joint parts with the cotton yarn and then
the second and
5 connect T114/B guide rail by super thick connecting plates (24mm
above guide
thick) (see the thickness of connecting plates used for other guide
rails in the pit
rails as shown in the table). Tighten the nuts till the spring washers are
compressed slightly; fasten them till the alignment of the guide rails.
Cut the most upper guide rails according to the actually measured
Installation of
dimensions to keep the guide rail top 50~100mm away from the
6 the top guide
machine room floor slab bottom, and then fix them on the guide rail
rail
support.
51 / 135
Elevator Installation Manual
D B
C
Guide rail
Base plate
Rail clip
C
A B
52 / 135
Elevator Installation Manual
1. The method of calibrating the guide rail by unloading is applied for the
alignment of guide rail, with the details as follows:
(1) Start the alignment from the lowest guide rail;
(2) Tighten the rail clips for the 2nd and above guide rails while calibrating the
1st guide rail. Knock the wooden blocks (50mm) under the 1st guide rail off by
the hand hammer, and loosen the connecting bolts for the 1st and 2nd guide
rails to lower down the 1st guide rail in order to separate the tongue and
groove at the connection of the guide rails;
(3) Lower down the 2nd guide rail to align it after the 1st guide rail is aligned
(4) Lower down the guide rails in turn from bottom to top for alignment.
2. The aligned position of the guide rail shall be the connection of the guide
rails and the guide rail supports.
3. Align the distance between the guide rails with the guide rail calibrator.
+1
The standard value of the guide rail distance: BG mm for main guide
0
+2
Guide rail rail and WG mm for auxiliary guide rail (BG and WG are standard rail
0
7
calibration distance).
4. When the poor verticality of the support affects the verticalness of the
guide rail, the guide rail spacers shall be used for adjustment
5. Verify that the partial gap a at the connection of the guide rails shall not
exceed 0.5mm, as shown in the following figure as shown in the figure below.
53 / 135
Elevator Installation Manual
7. For the unevenness of the plane at the connection of the guide rails, a 500mm steel ruler can be used against the
guide rail surface to check the positions a, b, c and d with a feeler. The unevenness shall not exceed those specified
in the following table (see the next page for the table).
(1) a and b gap correction: it can be adjusted by the special tool after the bolts of the connection plates are
completely tightened;
(2) c and d gap correction: it can be adjusted by inserting 0.1mm thick spacer at the position marked with “x” in
Figure b.
1—GUIDE
RAIL
2—500MM
STEEL RULER
Cut the most upper guide rails according to the actually measured dimensions
to keep the guide rail top 50~100mm away from the machine room floor slab
bottom, and then fix them on the guide rail support, as shown in the figure
below. Machine room ground
Installation of the
8 most upper
guide rail Guide rail support
Note: After installation and adjustment of the guide rail without any problem, fully weld the
connection and fasten bolt connection part by spot welding; remove welding slag and paint to
prevent rust.
54 / 135
Elevator Installation Manual
Tools
55 / 135
Elevator Installation Manual
It is required that the plumb line set in a above shall coincide with the
rope groove center of tension pulley close to the guide rail side; ensure
that the swing arm of the tension device is in horizontal position; keep a
Tension device
3 certain height between the center of the tension pulley and the pit ground
installation
to ensure that the tension pulley switch can act properly before the
tension pulley descends to the limit position. The tension device should
be installed on the car guide rail as shown in Fig. c below.
Expansion bolt
Fig. b
M12x125
Rail clip
Fig. a Fig. c
56 / 135
Elevator Installation Manual
Car roof
guardrail
Car magnetic
Car roof
induction rack
VF door
Car frame
operator
Car door
Car Enclosure
57 / 135
Elevator Installation Manual
Protective equipment
Tools
List: chain block, steel wire rope clip, rope shackle, suspender, wrench, level ruler, plumb, hammer,
electric hand drill, etc.
Steps Operation Remarks
Option 1:
Install two angle steel brackets at corresponding positions on
concrete hoistway wall on the opposite of the top landing door
(100×100 angle steel). Place a wood beam horizontally at the
bracket of the landing door. Erect two 200×200 wood beams (or
two 20# joist steels) on the angle steel bracket and the crossing
wood beam. Then fasten ends of the wood beam.
Angle steel bracket
Wood beam (200*200) (100*100*10)
Hoistway wall
1 Platform erection
58 / 135
Elevator Installation Manual
Wall
Wood beam
Door centerline
1 Platform erection
Wall hole
Two wood beams or profile steels
Crossing skid
59 / 135
Elevator Installation Manual
Wood brick
Ground on top floor
60 / 135
Elevator Installation Manual
Crosshead
Sheave assembly
A B
61 / 135
Elevator Installation Manual
Car frame The installation steps introduced below are mainly applicable for car
4
installation frame A and C.
1.Place the lower beam on the erected wood beam or joist steel with one end of the lower beam (the
end with pull rod installed on safety gear) at the same side of the governor. Please refer to
construction layout drawing of the project for governor position, usually in the back. Adjust the gap
between the safety gear jaw and the guide rail top and then stabilize the lower beam to prevent it
from loosening. Adjust the levelness of the bottom beam to ensure horizontal and vertical levelness
to be ≤1/1000.
2.When installing the upright beam, insert M20x50 bolts into screw holes at the bottom beam and
the upright column. The verticality of the upright beam for the entire height should be ≤1.5mm.
Then, tighten connecting bolts of the car upright column and the bottom beam as shown in the figure
below. In B and D car frame structure, there will be no directional washer and 16 pcs of bolt
M16x60, flat washer 16, spring washer 16 and nut M16 respectively.
D C B
E A
A Directional washer 12 pcs.
3.Lift up the upper beam by chain block and connect with the upright beams on both sides by bolts.
Adjust horizontal and vertical levelness of the upper beam to be less than 1/2000mm. Check and
ensure the diagonal deviation of car frame to be less than 2mm and finally fasten the bolts, as shown
in the figure below. In B and D car frame structure, there will be no directional washer and 16 pcs of
bolt M16x60, flat washer 16, spring washer 16 and nut M16 respectively.
B
C A
A Directional washer 12 pcs.
D
B Bolt M20x50 12 pcs.
Upper beam assembly
E
C Flat washer 20 12 pcs.
4.To install upper and lower dust guards, fasten dust guards on upper beam assembly by 8 pcs of
M6x20 flange face bolts, as shown in the figure below. Properly adjust installation position of the
dust guard rubber plate (cable-retaining angle steel) to avoid inference with steel wire rope during
elevator operation.
62 / 135
Elevator Installation Manual
Flange face
bolt M6x20
(1)For car frame structure A, unscrew the nut first and then, insert bolt into the hole connecting to
the upper beam assembly, and tighten it by nut as shown in the figure below.
(2)For car frame structure B, unscrew the large nut M60x3 and then, insert the upright bolt of the
crosshead sheave device into the hole on the reinforced plate; tighten it by large nut M60x3 as
shown in Fig. 1.
Crosshead sheave assembly
Reinforced plate
Nut M12
Upper beam assembly
Upper beam steel channel
Upright bolt
Fig. a Fig. b
(3)For car frame structure C and D, adjust nut M12 in the figure below to ensure that the gap
between nut and the upper end face of the upper beam steel channel is 8±1mm as shown in Fig. b
above.
63 / 135
Elevator Installation Manual
b.Insert the plug pin into the hole on the lifting bar and the safety gear handle to fasten the two ends
by the cotter pin to prevent the loosening of the lifting bar in work process. See the figure below.
Lifting device
64 / 135
Elevator Installation Manual
Fig. a
65 / 135
Elevator Installation Manual
Pin
Lifting bar Pin
Lifting bar
Fig. b Fig. c
Counterweight block
Sill assembly
Car bracket
Car platform
Note: When the floor is made from PVC (3mm thick) material, PVC floorboard will leave
factory after well paved, therefore the paved floorboard should be protected in installation of the
car platform assembly. When the floorboard is marble (20mm thick) material, it should be paved
after installation so as to protect it from damage, and the pre-paving is required beforehand.
66 / 135
Elevator Installation Manual
1.Connect the sill bracket on the platform floor with bolts, but do not screw them down. Adjust the
height of sill, make it slightly higher than the platform surface by about 0.5~1.0mm, and screw the
bolts down, as shown in the figure below. Fasteners for platform structure of deep car C and D are
the same as the following figure, both are 7 pieces.
67 / 135
Elevator Installation Manual
2.Hoist the car platform assembly with chain block and put it on the lower beam, insert bolts
through the lower beam from bottom to top, but do not screw them down, as shown in the figure
below. Adjust the gap between two sides of car platform and car upright columns, ensure the car
platform at center of car frame, adjust the horizontal and longitudinal levelness of car platform when
there is no external force exerted on the car platform, and make sure the deviation of levelness shall
be not more than 1/1000mm, and screw the bolts down after adjustment. Replace bolts among
fasteners of deep car platform structure with M20x60, and add 4 pcs of washer 20 for each steel
channel.
Upright beam
D
C
A Bolt M20x50 4 pcs.
B
B Flat washer 20 4 pcs.
3.Connect the stay screw rod assembly and tiepiece lugs on the upright beam with bolts, and screw
them down, as shown in the figure below.
B A
C
4.Adjust nuts at the lower end of stay screw rods, insert the protruded studs of stay screw rods into
the plug holes on the car bracket, and tighten the nuts, as shown in the figure below.
68 / 135
Elevator Installation Manual
C
A Flat washer 16 4 pcs.
5.Insert 5 pieces of slotted countersunk bolts M6x20 into toe guard hole and corresponding slotted
holes of sill bracket, as shown in Fig. a below. Insert bolt into the hole of toe guard support
corresponding to frame plate (welded on the platform floor), and then insert the bolt into the hole
of frame plate (welded on the toe guard) corresponding to toe guard, as shown in Fig. b. Tighten
the bolts one by one finally.
C B
D A
Toe guard
Fig. a Fig. b
6.Skirting board is divided into side skirting board and rear skirting board, which are installed in the
same way. First, place the skirting board on the corresponding car platform frame, insert the bolts
into the frame from bottom to top, and tighten them one by one, as shown in the figure below.
69 / 135
Elevator Installation Manual
D
Skirting guard C
B
A
A Bolt M6x20
B Flat washer 6
C Spring washer 6
D Nut M6
Car platform
Frame
7.Install the car guide shoe on guide shoe installation plate of upper beam assembly with bolts.
There are three types of guide shoes, in which DX10A is standard; DX1 and DX2 are optional, as
shown in the figure below. The car guide shoe of lower beam assembly will be installed in the
same way. There are four car guide shoes in total.
A
A Upper beam
assembly
B
B
C
C Guide shoe
installation plate
70 / 135
Elevator Installation Manual
2.6.2 Installation of Car Cab (Generally start after installation of steel wire ropes)
Overview: Car enclosure generally consists of single-side single-face punched car wall, double-side
punched car wall, front car wall, operation panel wall, door header and upright column etc.
2
1
4
5
6
7
A1 center opening integrated A2 center opening through A3 center opening embedded
operation panel integrated operation panel operation panel
8
9
A4 center opening through A5 center opening integrated A6 side-mounted center opening
embedded operation panel operation panel side-placed Through integrated operation panel
71 / 135
Elevator Installation Manual
B1 side-mounted side opening B2 side-mounted side opening through B3 side-mounted side opening
integrated operation panel integrated operation panel embedded operation panel
Note: 1. Single-side single-face punched car wall 2. Double-side punched car wall
3. Front car wall 4. Door header 5. Right upright column
6. Integrated operation panel wall 7. Upright column 8. Left upright column
9. Embedded operation panel wall
Schematic Diagram of Car Enclosure Structure
The following installation steps mainly take A1-A4 car enclosures with front-mounted operation panel as example.
72 / 135
Elevator Installation Manual
Protective equipment
Tools
List: wrench, level ruler, plumb, hammer, rubber hammer, safety belt, etc.
Steps Operation Remarks
Installation of car The following installation steps mainly take A and B car enclosures with
1
wall front-mounted operation panel as example.
1.In accordance with the requirements of different car specifications, connect left, right and rear car
walls, as shown in the figure below. Insert bolts into two punched car walls, adjust the planeness
difference of internal car wall≤1mm and height difference of car wall ≤0.5mm, and tighten bolts
after adjustment.
Single-side Double-side
single-face (or punched car wall
double-side)
punched car wall
A Bolt M6x16
B Flat washer 6
D C Spring washer 6
D Nut M6
C
A B
2.Move the well-connected rear car wall into hoistway and place it on the rear skirting board. Adjust
perpendicularity of rear car wall, and fasten the rear skirting board and rear car wall with bolts
M6x20, as shown in the figure below. Car wall
Skirting board
Bolt M6x20
73 / 135
Elevator Installation Manual
3.Move the side car wall into hoistway and place it on the side skirting board. Adjust the
perpendicularity of side car wall, and fasten the side skirting board and side car wall with bolts
M6x20 in the same way as (2).
4.Insert bolts into corresponding holes at corner of rear car wall and side car wall, and screw them
down, as shown in the figure below.
Single-side
single-face punched Double-side
car wall punched car wall
A Bolt M6x16
B Flat washer 6
C Spring washer 6
D Nut M6
D
A C
B
74 / 135
Elevator Installation Manual
The operation panel wall includes integrated type and embedded type
Installation of
3 according to the different types of operation panels, in which the
operation panel
integrated operational panel is standard, as shown in the figure below.
Fix the left upright column and the operation panel wall with bolts, and screw them down one by one, as
shown in the figure below, and install the right upright column in the same way as the front car wall.
Left upright
column Integrated operation panel
wall (embedded operation
panel wall)
D Nut M6 7 pcs.
A D
B C
1.The door header is classified into normal straight door header and inclined door header. The normal straight door
header, as shown below, is featured by simple and elegant design structure and easy fabrication to provide the
elevator a simple elegant and grand profile. Connect the door header in the same way as two kinds of operation
panels.
A B
Note: A - for center opening car structure B - for side opening car structure
75 / 135
Elevator Installation Manual
D Nut M6 3 pcs.
D
C
B
A Bolt M6x16 3 pcs.
A
B Flat washer 6 6 pcs.
2.Fix the operation panel and car side wall with bolts, but do not screw them down, as shown in Fig.
a, and install the front car wall and car side wall in the same way. For B1-B4 structure, the front car
wall will be replaced with upright column as shown in Fig. b. D
C
B A
C B
D A
Upright column
Integrated
Car side wall
operation panel Car side wall
Fig. a Fig. b
76 / 135
Elevator Installation Manual
D Nut M6 7 pcs.
(1) Installation of integrated operation panel (which can proceed after car is completely installed)
a.There are 6 hardy holes on the operation panel as shown in Fig. a, and 6 fastened special bolts at
the bottom case of operation panel as shown in Fig. b. During installation, align large hardy hole to
the special bolt, slowly move down the operation panel after compressing it, and clamp the special
bolts with small hardy holes. Thus complete the installation.
Special bolt
Door header
Hardy hole
Operation panel
图a 图b
b.When operation panel is disassembled, insert the handle of operation panel into the gap between
operation panel and bottom case, as shown in the figure below, and uplift the operation panel about
10mm until to thread bolts through the hardy holes, and finally take the operation panel down.
Operation panel
Bottom case of
Handle of
operation panel
operation panel Handle of operation panel
77 / 135
Elevator Installation Manual
Bottom case of
operation panel
A Special bolt M8 6 pcs.
C C Nut M8 6 pcs.
A B
b.Insert bolts into the corresponding holes of embedded operation panel wall and left upright
column, and finally screw them down, as shown in the figure below. Connect the front car wall in
the same way as the right upright column.
Left upright column
D Nut M6 7 pcs.
C
A B
c.Fix the embedded operation panel wall and car side wall with bolts, but do to screw them down, as
shown in the figure below.
C B
D
A
A Bolt M6x16 7 pcs.
d. Install the embedded operation panel in the same way as the integrated operation panel.
78 / 135
Elevator Installation Manual
3.Connect the car front wall and the operation panel to the car platform with bolts, and tighten the
bolts one by one, as shown in the figure below.
Operation panel or
front car wall
A Bolt M6x20 4 pcs.
D
B Flat washer 6 8 pcs.
C
C Spring washer 6 4 pcs.
B D Nut M6 4 pcs.
A
Car platform
4. A5、A6、B5、B6 For car enclosure structures A5, A6, B5 and B6 with side-mounted integrated
operation panel wall
(1) Fix the operation panel connecting plate and the front car wall with bolts, and tighten the
bolts one by one, as shown in the figure below.
Operation panel
connecting wall
A Bolt M6x16 7 pcs.
(2)Install the operation panel on the car side wall, fix it on two operation panel connecting plates
with bolts, and tighten the bolts one by one, as shown in the figure below.
79 / 135
Elevator Installation Manual
C A
B
D Nut M6 14 pcs.
Bottom case of
operation panel wall
Special bolt
Operation panel
connecting wall
Top view
(2) Fix the operation panel connecting wall and car side wall with bolts, and tighten the bolts one by one, as shown
in the figure below. Car side wall Operation panel
connecting wall
D Nut M6 7 pcs.
A D
C
B
5. There is no operation panel connecting wall in the car enclosures A7, A8, B7 and B8 with side-mounted
embedded operation panel wall. The other installation way is the same as step 6.
80 / 135
Elevator Installation Manual
(1)Insert bolts into car roof at three sides (rear and two sides) and car wall, but do not fasten the
bolts; insert bolts into front side of car roof, operation panel and front car wall without fastening.
Adjust the vertical deviation of car wall and operation panel ≤1.5mm, then tighten the bolts one by
one as well as the bolts in step c of (8), as shown in the figure below, and decide quantity of bolt
assembly according to the car specification.
B C
A Car roof
A Bolt M6x20
B Flat washer 6
C Spring washer 6
Operation panel or
Car enclosure front car wall
(2)Connect the door header on the car roof with bolts, but do not tighten the bolts, as shown in the
figure below.
Car roof
A A Bolt M6x20 3 pcs.
Door header
(3) Tighten the bolts connecting the door header to the front car wall, operation panel and car roof.
(4) Tighten the bolts connecting the side wall to the front car wall and operation panel.
Installation of car alignment Keep the car stable by fastening two alignment racks
5 rack, measurement and above the car roof and upright beams of car frame.
adjustment Installation and adjustment are as follows:
81 / 135
Elevator Installation Manual
(1) Fix the alignment rack on the alignment seat, make rubber ring at the other end contact with
upright beam slightly. Adjust the alignment racks at left and right sides by long waist-shaped hole as
shown in the figure below, make vertical deviation of the car in front, rear, left and right directions in
the whole height≤1.5mm, and tighten the bolts after adjustment, as shown in the figure below.
Alignment rack
Upright beam
A
A Bolt M8x25 8 pcs.
B
B Flat washer 8 8 pcs.
(2) Measure the diagonals of car body, and make the deviation smaller than 2mm. Measure the
diagonals of car door frame, and make the deviation smaller than 2mm. Measure the net door
opening width JJ of car and height HH of door header.
(3) Measure the perpendicularities of car front and side in case of no external force, and make the
deviation smaller than 1/1000mm. Measure the perpendicularities of car door frame front and side,
and make the deviation smaller than 1/1000mm.
After cleaning the hoistway and guide rails, fix the oil cup in the
Installation of oil U-groove of car guide shoe (installed on the upper beam assembly)
6
cup with bolts. The guide shoe DX2 is required for 4 pcs of flat washer
8, as shown below.
82 / 135
Elevator Installation Manual
C D
E
B
F
A
F D Bolt M8x30 2 pcs.
G E Spring washer 8 2 pcs.
Protective Equipment
Tools
83 / 135
Elevator Installation Manual
Tools
List: wrench, level ruler, hammer, screwdriver, tape, etc.
84 / 135
Elevator Installation Manual
1 Car roof guardrail According to different car structures, there are two types of car roof
guardrails as shown in Fig. A, B, C, D.
Upper beam
Side toe guard
Right guardrail
A B
85 / 135
Elevator Installation Manual
(2) Connect 2 rear brackets between 2 fixed side guardrails, and fasten a striking warning sign on the upper most
rear bracket with bolts, as shown below.
C B
D A
Left guardrail
Rear bracket
D Nut M6 8 pcs.
B Square taper
C A washer for steel 8 pcs.
A channel
D B Bolt M10x30 12 pcs.
E
C Flat washer 10 16 pcs.
86 / 135
Elevator Installation Manual
(1) Fasten a striking warning sign on the upper most rear bracket of left guardrail with bolts, as shown in the figure
below.
4.Toe guards on the car roof include a left front toe guard, a right front toe guard, rear toe guards (2 pcs.) and a rear
toe guard. Place the toe guards on the corresponding frame of car roof, insert bolts into the toe guards from top to
bottom, and screw the bolts down, as shown in the figure below.
Toe guard
A
B
A Pan head screw M4x16 16 pcs.
C
B Spring washer 4 16 pcs.
D
C Flat washer 4 16 pcs.
Frame
Install the cross flow fan on the car roof, insert one side of the fan into the long hole of car roof; adjust the
position of fan, place bolts into holes one by one and tighten them, as shown in the figure below (the quantity of
fasteners in brackets is applicable for the integrated car roof).
87 / 135
Elevator Installation Manual
▲Ceiling
The ceiling has different specifications due to different car specifications, but the installation
way is the same. Before installation, first disassemble the cross recessed pan head tapping screws of
acrylic boards or polycarbonate sheets for temporary fixing of ceiling in transportation, as shown
in Fig. a; then fix the ceiling on the car roof at four corners with bolts, as shown in Fig. b.
Lower ceiling frame
Cross recessed
pan head
tapping screw
Fig. a
C
D B
Car roof
A
A Bolt M10x75 4 pcs.
Car enclosure
Fig. b
88 / 135
Elevator Installation Manual
Sheave assembly
Guide shoe
Counterweight housing
Counterweight device
89 / 135
Elevator Installation Manual
Tools
List: tape, wrench, screwdriver, chain block, steel wire rope, shackle, etc.
1.Preparation
(1)Disassemble part of scaffold transom at the bottom until the counterweight housing can
enter the hoistway in position;
(2)Fasten wire line hitches on two opposite counterweight guide rail supports at an
appropriate height (based on convenience for lifting of counterweight housing), and
hang a chain block in the center of wire line hitch. Fasten the wire line hitches on the
guide rail supports, but not on guide rails directly to avoid displacement or deformation
of guide rail under stress;
(3)Support a piece of batten with enough strength at two sides of counterweight buffer
respectively, in which height=height of buffer base + free height of buffer+ height of 2
adjusting base (200)+ buffer distance (refer to the project construction layout drawing),
(as shown in the figure below).
Installation position of
counterweight housing
Adjusting base
Buffer
Batten
Buffer base
Buffer distance is subject to the project construction layout drawing, but not beyond the following
scope: mm
Buffer distance
Type of buffer
(mm)
Polyurethane 200-350
hydraulic 150-400
90 / 135
Elevator Installation Manual
Move the counterweight frame into the hoistway (with upper counterweight stretching into the
hoistway), and connect the counterweight guide pulleys and chain block hooks with wire line hitch;
hoist the counterweight frame slowly with chain block to the preset height, hold the counterweight
frame, and push it to the counterweight guide rails; install four counterweight guide shoes up and
down, but do not tighten bolts for the moment, in which the quantity of fasteners is always 8, as
shown in the figure below.
Counterweight Counterweig
A guide shoe ht guide shoe
B A
DXP126-02 DX1
C B
A Bolt M16x30
B Flat washer 16
C Spring washer 16
Counterweight
housing
4.Placement of counterweight frame: loosen the chain block and place the counterweight frame on
the batten.
5.Installation of oil cup: fix the oil cup on the counterweight guide shoe with bolts.
91 / 135
Elevator Installation Manual
Counterweight Counterweight
guide shoe guide shoe
DXP126-02 DX1
8.Follow-up adjustment: start adjustment after the steel wire rope is installed, add counterweight
blocks in proper quantity to meet coefficient of balance, and install spring prevention pressing plate
for counterweight block.
92 / 135
Elevator Installation Manual
1. Connect upper, middle and lower protection plates to connecting bracket with bolts.
Upper protective plate
Middle protective plate
D
C B A
D Nut M6 12 pcs.
2. Install counterweight protection plate: connect pit protection device on the counterweight guide
rail with rail clips, as shown in the figure below.
93 / 135
Elevator Installation Manual
Tools
List: tape, plumb, wrench, screwdriver, level ruler, impact drill, etc.
94 / 135
Elevator Installation Manual
The buffer is normally installed on the buffer seat in the pit. If the pit is an accessible space for
people, the counterweight buffer bracket shall be extended to the solid ground in the pit if the
counterweight is not provided with safety gear.
The car buffer base is poured with concrete, and concrete height should guarantee the car buffer
distance indicated in the project construction layout drawing after installation of the buffer.
After installation of the buffer, make sure that hydraulic oil is filled into the buffer, with oil
brand and quantity as shown below.
Reference Table of Buffer Oil Quantity
YH1/17 YH1A/17 YH68/21 YH13/23 YH2/42
Type of Buffer YH4/270
5 5 0 0 0
Brand of hydraulic oil N68 N68 N68 N68 N68 N68
Oil Theoretica 1.40
quantity l oil 2.20 1.20 0.63 3.10 4.70
required quantity
to add Current oil 1.52
2.28 1.25 0.65 3.19 4.81
(L) quantity
Buffer C
95 / 135
Elevator Installation Manual
A B
C D
Note: A hoistway equipment layout type shall be selected from Methods A, B, C, D according
to the structure of drive system and the position of calling board.
Code description:
1. Governor steel wire rope 2. Fixing rack of traveling cable
3. Fixing rack of hoistway cable 4. Leveling device 5. Ultimate limit device
Layout of Counterweight Postposition Hoistway Equipment
A B C
Note: A hoistway equipment layout type shall be selected from Methods A and B according to
the positions of calling board and counterweight. Method C is applicable to the structure
of 2.5m/s counterweight side position.
Code description:
1. Governor steel wire rope 2. Leveling device 3. Ultimate limit device
4. Fixing rack of traveling cable 5. Fixing rack of hoistway cable
Layout of Counterweight Side Position Hoistway Equipment
96 / 135
Elevator Installation Manual
Protective Equipment
Tools
List: wrench, level ruler, hammer, screwdriver, tape, etc.
Steps Operation Remarks
The traveling cable includes two types - with steel core or without steel core. Use the traveling
cable without steel core when lifting height TH≤80m; Use the traveling cable with steel core when
lifting height TH>80m. The traveling cable is fixed on the circular steel tube of lower beam.
Move the cable round the cable rack circular pipe, and press the lower end with cable clamp
plate rack, as shown in the figure below:
Car platform
cable fixing rack
Binder
Traveling cable
Cable clamp
Video cable
plate rack
97 / 135
Elevator Installation Manual
When the video cable is provided, the video cable shall be laid beside the traveling cable and
bound with the binder properly. The distance between every two binders in the upper part of the
hoistway shall not exceed 3,000mm. As the video cables in the middle and lower part of the
hoistway move together with the traveling cable, the distance between every two binders shall not
exceed 500mm, as shown in the figure above.
(2)Fixing method of car platform cable with steel core in case of lifting height 80m<TH≤120m:
Rope cramp 6
Traveling cable
Pull out the steel wire rope of traveling cable, connect head and tail of another steel wire rope,
and fix it with steel wire rope of traveling cable by rope cramp; sleeve it on the steel tube of cable
rack, and finally press the cable with cable clamp plate rack.
(3)Fixing method of car platform cable with steel core in case of lifting height 120m<TH≤150m:
98 / 135
Elevator Installation Manual
Fix the support rod on the lower beam with square steel pressing plate, cover the sleeve on the
square steel and fix it with pins. Pull out the steel wire rope of traveling cable, connect the head and
the tail of another steel wire rope, and fix it with steel wire rope of traveling cable by rope cramp;
sleeve it on the hanger shaft of cable rack, and finally press the cable with cable clamp plate rack.
Support rod
Rope cramp 6
(1) When lifting height TH≤80m, the hoistway traveling cable is fixed on the guide rail by cable
fixing rack; when TH≤30m, there are 2 sets of cables; when 30<TH≤80m, there are 3 sets of
cables (the third gear added);
Installation position (as shown in the figure below): the first gear: at 1m below the top floor;
the second gear: at 3/4TH (lifting height); the third gear: 1/2TH (lifting height) +1m.
(2) When lifting height TH>80m, the upper traveling cable in the hoistway should be installed on
the steel-core cable fixing rack. The steel-core cable fixing rack is fixed to the concrete wall by 4
pieces of M16 expansion bolts through the holes of the installation support. The middle and lower
cable rack are still installed on the common cable fixing rack (same as above). The rope clamp shall
have spring washer, and the fixing nut shall back to the cable side.
99 / 135
Elevator Installation Manual
Upper cable
fixing rack
Middle cable
fixing rack
100 / 135
Elevator Installation Manual
The installation method of hoistway traveling cable rack is as follows, the fixing method of
hoistway cable is the same as that of car platform cable.
A
Traveling
cable
A Bolt M12x40 4 pcs.
Rail clip
B Flat washer 12 4 pcs.
Cable clamp
plate rack C Spring washer 12 4 pcs.
B
D C D Nut M12 4 pcs.
Hoistway
traveling
cable rack
Split the traveling cable located at the lower cable fixing rack, pull out and shear the steel wire
rope, and hang it on the hanger shaft of cable fixing rack, as shown in the figure below.
Expansion
bolt
M16x125
Hanger shaft
Steel core
Rope cramp
Traveling cable
Precautions:
a.The traveling cable shall not be knotted or curved, and shall not scratch or touch the
hoistway and car articles during the running;
b.The cables shall not touch the pit ground and car bottom frame after the car has
compressed the buffers;
If there is a pit maintenance platform, its distance with the bottom surface of the pit maintenance
platform shall be ≥150mm; if there is not, its distance with the buffer base shall be ≥50mm.
101 / 135
Elevator Installation Manual
Car
Traveling cable
Suspending diameter of traveling cable 700±50
Buffer
Buffer base
Pit ground
Install the hoistway cable fixing rack on the top hoistway with expansion bolts, and insert the
hoistway cable between the bottom plate base and the pressing plate base, and finally tighten bolts
M12x60, as shown in the figure below.
Hoistway cable
Expansion bolt
Bolt M12x60
Protective Equipment
Tools
102 / 135
Elevator Installation Manual
The ultimate limit device comprises limit collision bow rack and travel switch bracket, and the
switch includes speed reducing switch and ultimate limit switch. The limit collision bow rack is
installed on the upright beam and runs along with the car up and down; the limit collision bow rack
is a structure of double connectors, so it has enough strength.
1.When the speed is 1.0~2.0m/s, the ultimate limit device adopts the structure in the figure below.
When the speed is 1.0~1.75m/s, the lower speed reducing switch 1 is canceled. If a 2nd generation
all-in-one is available, the limit switch is cancelled.
Upper ultimate
limit switch
Upper limit switch
Upper speed
reducing switch 2
Upper speed
reducing switch 1
Lower speed
reducing switch 2
Lower speed
reducing switch 1
Lower ultimate
limit switch
103 / 135
Elevator Installation Manual
(1) Fix the limit collision bow rack on the upright beam of car with bolts, as shown in the figure
below.
D
A
C
B
(2) Fix the travel switch bracket on the guide rail with rail clip, as shown in the figure below.
A
B
Rail clip
C
D Upper ultimate
limit switch
(3) After installation, check the installation position correctness and working reliability of each
switch by overtravel tests to the top and the bottom.
104 / 135
Elevator Installation Manual
2.When the speed is 2.5m/s, the ultimate limit device adopts the structure in the following figure.
The limit switch should be canceled when the 2nd generation all-in-one is available.
Upper ultimate
limit switch
Upper speed
reducing switch 2
Upper speed
reducing switch 1
Lower speed
reducing switch 2
Lower speed
reducing switch 1
Lower ultimate
limit switch
105 / 135
Elevator Installation Manual
(1) Fix the limit collision bow rack on the upright beam of car with bolts, as shown in the figure
below.
Limit collision
bow rack
Upright beam
D A
C
B
(2) Fix the travel switch bracket on the guide rail with rail clip, as shown in the figure below.
B
Rail clip
C
D Upper ultimate
limit switch
(3) After installation, check the installation position correctness and working reliability of each
switch by overtravel tests to the top and the bottom.
106 / 135
Elevator Installation Manual
The leveling device consists of the leveling frame and car magnetic induction frame. The car
magnetic induction frame shall be fixed on the upright beam. The switch fixing plate with the long
waist-shaped hole is used for easy adjustment during the installation.
1.When the speed is 1.0~2.0m/s, the leveling device should be a structure as the figure below.
a.Fix the relay on the inductive switch bracket with bolts, as shown in the figure below.
A
A Bolt M12x40 6 pcs.
b.Fix the inductive switch bracket on the upright beam of car with bolts, as shown in the figure
below.
B A
C B
D C
(2)Installation of leveling frame: leveling frame is fixed on the car guide rail with rail clip, as shown
in the right figure above, only one leveling frame at each floor.
107 / 135
Elevator Installation Manual
2.When the speed is 2.5m/s, the leveling device should be a structure as the figure below.
(1)Installation of car magnetic induction frame
a.Fix the relay on the inductive switch bracket with bolts, as shown in the figure below.
Photoelectric switch
D
A Bolt M5x25 8 pcs.
C B Flat washer 5 8 pcs.
D Nut M5 8 pcs.
A
b.Fix the inductive switch bracket on the upright beam of car with bolts, as shown in the figure
below. B C D
A
Upright beam
Car magnetic
induction frame
A Bolt M10x30 3 pcs.
(2)Installation of leveling frame: leveling frame is fixed on the car guide rail with rail clip, as shown
in the figure below, only one leveling frame at each floor.
Rail clip of guide rail A
Guide rail Bolt M12x45 2 pcs.
A
B Flat washer 12 2 pcs.
B C Spring washer 12 2 pcs.
Leveling frame
D D
C Nut M12 2 pcs.
108 / 135
Elevator Installation Manual
Tools
List: wrench, level ruler, hammer, screwdriver, etc.
▲Counterweight Block
After the installation of car part and other accessories is finished, install the counterweight block.
Hang counterweight block on the rear beam or front beam to keep the car balanced, make sure all
counterweight blocks are installed without missing. Then sleeve the flat bars and nuts on the
double-screw bolts protruded from the counterweight blocks, and tighten the bolts one by one, as
shown in the figure below. Each counterweight block shall have two sets of fasteners, and the
specific number depends on the quantity of counterweight blocks.
C
B
Flat 40x4 A
Rear beam
(front beam) of
car bracket
A Nut M6
B Spring washer 6
C Flat washer 6
Counterweight block
Installation plate
D Nut M8 4 pcs.
A
B C D
109 / 135
Elevator Installation Manual
2.Make magnet absorbed at the car platform and the mark directly face the inductive points of
device. There are 2 pcs of ECW-P1 overload detection devices, which are installed at the
mounting holes of overload detection device as shown in the figure above. Each hole is
provided with one overload detection device, make the car platform magnet directly face the
center of upper end face, and ensure upper end face of overload device and end face of magnet
parallel mutually, adjust the detection gap to be 8-15mm, as shown in the figure below.
3.When the elevator is overloaded, adjust the device up and down make the indicator light shine
gradually (or vibrate), then fasten the device, and the commissioning is over.
2.10 Traction Steel Wire Rope
2.10.1 Installation of Steel Wire Rope
Protective Equipment
Tools
110 / 135
Elevator Installation Manual
Reel-off
2
requirement
错误的解法
Wrong
正确的解法
Right
First insert from rope head of car - car roof (platform) diversion
sheave - traction sheave - guide pulley - counterweight diversion
3 Order of setup sheave - counterweight rope head (This way mainly depends on
the friction of traction groove, saves manpower, and can avoid
falling of steel wire rope once release grip in reel-off process).
Insert the head end of steel wire rope into the taper sleeve from the
bottom up, then bend it and insert the head end back, put a taper
wedge into the taper sleeve, uplift the steel wire rope at the stress
side, and then tighten the head end.
Installation of taper
4
sleeve
Each end of steel wire rope should be fixed with 3 rope clips that
are arranged in order, two adjacent rope clips should be staggered
in order not to make noise in operation due to shaking of steel wire
rope; U opening of rope clip should be at the rope head, and then
Installation of rope fasten the rope clip.
5
clip
111 / 135
Elevator Installation Manual
Insert the taper rod of rope head from the bottom of rope hitch
plate to the top, and sleeve with a spring ring, and screw the nut
Installation of rope down preliminarily. Adjust the tension of steel wire rope to make
6
head the tension difference of steel wire rope not more than 5% of
average value, otherwise readjust it. Then screw the nut down after
adjustment, and insert the cotter pin.
It requires secondary protection from twist of steel wire rope after
installation.
Secondary
7
protection
Steel rope
Rope clip
Rope hitch
After installation of steel wire rope, adjust the gap of guard rods of
main engine, guide pulley, car diversion sheave, counterweight
8 Anti-bouncer
diversion sheave. Make sure the gap is not more than 1/3 of rope
diameter.
Setting of vacant
9 It is subject to technical drawings.
rope slot
2.11 Installation of Landing Door System (Note: Details in Copy of Landing Door Manual)
2.11.1 Installation of Sill
During installation of landing door, first install the top landing door of elevator. Close all gaps to
make sure nothing can fall into the hoistway. Do not install the landing door for transporting 5m
guide rails into the hoistway until all guide rails are placed into the hoistway. If the landing door and
guide rails are installed at the same time, installers shall keep them at the same height.
112 / 135
Elevator Installation Manual
Protective Equipment
Tools
List: tape, level ruler, plumb, hammer, impact drill, socket head wrench, wrench, screwdriver,
welding machine, etc.
Steps Operation Remarks
The adjusting range of center opening landing door sill support
channel is: X (based on real object) the gap from car sill to landing
Civil engineering door sill is 30mm, so the vertical line of car door sill sample to
1 confirmation hoistway wall of landing door D=X+30mm.
before installation Note: A fixed support is required if the distance exceeds the
adjusting range, or part of civil engineering should be
reconstructed if the distance is too small.
(1) Mark lines in accordance with the line of elevation provided by
Confirmation of building contractor in written form and door opening width of
installation position landing door in civil engineering layout drawing.
2
for bracket and (2) At the parallel line of 210±25mm below the line of elevation of
fixed support hoistway landing door, the vertical position is line of net opening
dimension at two sides and line of middle dimension.
Drill 2 (Ø14*100mm) expansion bolt holes, insert M12*110mm
expansion bolts, and install two expansion bolts for each sill
Installation of fixed
3 support channel.
support of bracket
Note: After adjusting the position, install washers by spot welding
at slot hole of bracket, in order to avoid position variation.
Installation of
4 Cover the sill fender into the bottom of sill.
fender
Connect sill and fender on sill bracket with M8 bolts, and tighten
Installation of sill the bolts. Adjust the horizontal and longitudinal levelness of sill,
5 and height then adjust the sill height (by which the sill should be higher about
adjustment 2-5mm than the sill facing to prevent water seepage to the
hoistway), and tighten the bracket bolts after adjustment.
113 / 135
Elevator Installation Manual
Protective Equipment
Tools
List: tape, level ruler, plumb, hammer, impact drill, socket head wrench, wrench, screwdriver,
welding machine, etc.
114 / 135
Elevator Installation Manual
Back of bracket
Place the upper sill on the crossbeam of door pocket, insert the bottom edge of upper sill into the
notch of bracket, match screw holes at two ends of upper sill with the screw holes of bracket, and fix
the upper sill and the bracket with two M8 bolts. Adjust the upper sill center and sill center to be on
the same vertical line, and fasten the connecting bolts of bracket and door pocket.
115 / 135
Elevator Installation Manual
Positioning of
4
upper sill bracket
First connect two upper sill brackets on upper sill with M8 bolts,
and slightly tighten the bolts. Hang the plumb to adjust the
perpendicularity of door pocket, mark the positions of expansion
bolt holes of upper sill bracket and hoistway wall with a marking
pen.
116 / 135
Elevator Installation Manual
Adjustment of door
Left and right
6 pocket and landing deflection:
door device Front and back
deflection:
Upper levelness:
Protective Equipment
Tools
Installation of Install sliding blocks at the lower edge of landing door, meshing
1
sliding block over 10mm.
117 / 135
Elevator Installation Manual
Installation of
2 Install connecting bolts of landing door and door strap.
landing door
门 门 之 间
Between doors Between upper and lower ends
Door gap
上 下 端 100m m 间 上 端
Upper end
A100mm
=5 1 其 它 parts
Other 部 分
其 他 A =B 5±1
=4~ 6 下 端
Lower end
隙 Door门and
和decoration
装 饰 框frame Others B = 4~6
重
Between doors when full
全 闭 时 门 之 间
Overlap
amount
叠 closed L 12
门 和 装 饰 框frame
Door and decoration
量
一 般
Generally A-B 3.0
安
In installation
全 full
When 开 时 opened L2 A-B 2.0
装
When
全 闭 full时
closed CO C 1.0
时
门
Lifting height
吊
of door
起 门 和
Door and地sill坎ground
面 h =4~ 6
高
度
偏
Eccentric
clearance
钢 制 型
心 Steel type g =0.1~ 0.3
间 g =0~ 0.1
树Tree
制 type
型
隙
Plane Inclinatio
倾 门 上 door
Between 坎 架 和 sill
upper
a -b = 1
n
平 Between center
面 中 分 门 之 间 A 1.0
e
差 opening doors
118 / 135
Elevator Installation Manual
Protective Equipment
Tools
119 / 135
Elevator Installation Manual
Adjustment of door
1
lock
Check and
adjustment of gap
2
between door
holder and car sill
5—10mm
After the installation of car, adjust the snap-in of door holder and
door vane to 8mm at least, keep the door holder in the middle of
main and secondary door vane (adjusting floor by floor)
Check and Left and right gaps
adjustment of gap are consistent, and
3 the effective size
between door vane
and door holder between door vane
and door holder shall
be 8mm at least.
120 / 135
Elevator Installation Manual
121 / 135
Elevator Installation Manual
Protective Equipment
Tools
Fix the upper support (steel channel) of car compensation chain hanger on the upper portion of
car lower beam with M16 bolts, and fix the lower support (angle steel) at the bottom of car lower
beam with M16 bolts, connect the upper and lower supports with pull rods, as shown in the figure
below.
D
Lower beam assembly
C
Upper support
A
Lower support
D
A Bolt M16x60 8 pcs.
C
B Flat washer 16 20 pcs.
122 / 135
Elevator Installation Manual
Connect the crossbeam with the lower support with M12 bolts (which can be finished during
assembly of car frame). Install U bolts on the crossbeam, connect the compensation chain on the U
bolts, and reserve two rings to connect secondary protective steel wire rope which is connected with
the compensation chain bypassing another U bolt, as shown in the figure below.
D
Lower beam assembly Rubber pad
C
Big washer
Crossbeam
D
U bolt
Secondary protective
steel wire rope
D Compensation chain
C
A Bolt M12x50 2 pcs.
Lower support
D
A Bolt M16x60 8 pcs.
123 / 135
Elevator Installation Manual
Connect the crossbeam with the lower support with M12 bolts (which can be finished during
assembly of car frame). Install U bolts on the crossbeam, connect the compensation chain on the U
bolts, and reserve two rings to connect secondary protective steel wire rope which is connected with
the compensation chain bypassing another U bolt, as shown in the figure below.
D
Rubber pad
Lower beam assembly C
Crossbeam
Big washer
U bolt
Compensation chain
D Secondary protective
steel wire rope
C
A Bolt M12x50 2 pcs.
The spirals and windings of the balance compensation chain caused during the reeling shall be
removed during the installation to prevent cracking or stripping of the externally wrapped rubber and
plastic layers due to the twisting.
The method of removing the spirals and windings: when one end of the compensation chain at
the car platform is hung properly, run the elevator slowly to the top and measure the necessary length
of the compensation chain. Cut off the chain, wind and bind the compensation chain properly that
trails on the bottom. Keep it 1m above the ground and suspend it statically for 24 hours. Hang the
other end after the windings are all removed. Double check if the compensation chain has any spiral
or winding during its running several days after the elevator runs. Repeat the operation if there is still
any.
124 / 135
Elevator Installation Manual
Counterweight housing
B
C
A
Compensation chain
After installation, the bending radius shall be close to the required value in the table as much as
possible.
125 / 135
Elevator Installation Manual
Counterweight housing
Compensation
chain guide device
126 / 135
Elevator Installation Manual
Tools
List: wrench, impact drill, hammer, etc.
The hoistway ladder comprises ladder and handrail.
1.Assembly of ladder frame is shown as the figure below.
D
Expansion bolt
2.During site installation, set up steel expansion bolts at proper positions according to the drawing,
then install ladder and handrail, and make sure they are in place with reliable firmness.
Handrail(2PC)
Handrail Ladder
Ladder
When the distance between door opening boundary and side wall of hoistway L1 is less than
475, the ladder and handrail are installed at the side of hoistway. The specific installation layout
refers to the Installation Layout Diagram (right), the installation dimension of steel expansion bolts
refers to the Schematic Diagram for Installation Dimension of Steel Expansion Bolts (right).
Handrail (2pc)
Handrail (1pc)
Ladder
Ladder
Door pocket
upright
column
Note: (1) Pay attention to the installation position of handrail during installation, so as to prevent
handrail from interference with sill;
(2) If both installation ways above are unavailable on the site, the handrail can be cancelled, and
the ladder frame can be fixed on the back of landing door toe guard, as shown in the figure (for
special situation).
After final installation, the ladder and the handrail are as shown in the figure below.
Handrail
Handrail
Ladder
Ladder
Ladder
128 / 135
Elevator Installation Manual
Protective Equipment
Tools
Emergency One emergency stop device easy to touch must be arranged outside the
1
stop device bottom hoistway in the pit and on the pit ground respectively.
2 Repair case It is required to install it at 200mm from the entrance of landing door.
Buffer Adjust the position of switch when buffer switch is installed, so that the
3
switch buffer switch can be triggered during compression of buffer.
Tension First observe the movement direction of tension sheave before installation,
4 sheave ensure the tension sheave switch can be triggered after the governor steel
switch wire rope is broken.
Laying of
5 Refer to the drawing.
circuits
129 / 135
Elevator Installation Manual
Tools
Safety Before removal, safety officer of the Project Department shall give a safety
1
disclosure disclosure to the operators.
Removal
2 From the top down
sequence
(1) The removal work must proceed layer by layer from the top down, and
simultaneous operation is strictly prohibited.
(2) The stay bars must be removed layer by layer along with the scaffold; it
is prohibited removing the scaffold after the whole layer or several layers
Precautions of stay bars are removed.
3
on removal (3) It is prohibited throwing all components to the floor during unloading.
(4) Never change operators during removal of scaffold, or if have to, first
inform new operator of the current situation.
(5) The components transported to the floor must be checked, repaired and
maintained, and stored in no time by type and specification.
130 / 135
Elevator Installation Manual
Protective Equipment
Tools
List: screwdriver, wrench, tape, square master, plumb, electric drill, etc. (depending on site
decoration)
Steps Operation Remarks
Level ruler
Flooring
Installation of car
1
platform
Car platform
131 / 135
Elevator Installation Manual
Skirting board 2
Skirting board 3
Installation of car
2
skirting board
Skirting board 1
Connect the skirting boards 1, 2, 3 and the car platform with bolts.
Note: Go to Step③ if there is no skirting board.
Installation of
3
corner wall panel
(1) Remove the protective films at the joints of wall panels before
installation;
(2) Put the corner wall panels ① ② on the skirting boards of car
platform, and insert bolts.
Or fix it directly on the surface of car platform if there is no skirting
board.
Note: Install angle R first if the corner is arc type.
132 / 135
Elevator Installation Manual
Door
header
Right
front
Operation wall
wall
Trim strip
Fig. I
133 / 135
Elevator Installation Manual
Car roof
Installation of car
5
roof
(1) Move the car roof above the car wall panels, align each
connecting hole, and insert all bolts of connecting hole.
(2) Measure the diagonals of door opening with a tape measure; the
difference is not more than 5MM.
(3) Check the gaps at joints of all wall panels and levelness, and
adjust to make it flat and attractive.
Tighten all bolts finally.
Ceiling
Handrail
Installation of
6
ceiling and handrail
Installation of
7 special decorative
parts
Installation of car
8 secondary
decoration
135 / 135