Report on Tokyo Super Batching Plant visit at Bathalayaya.
With reference to the instructions given during the progress meeting of Nila Piayasa Project held on 08.10.2019 at Monaragala, Tokyo Super Batching Plant visit was done and observations and information collected are listed as below.
Observations and Data Collected:
Date: 09.10.2019 1. C35A concrete has been supplied to NWS&DB water project in Mahiyanagana by the plant and supplied quantity was around Location: 1000m3. Kivulathalawa, 2. An order has been placed to provide C35A concrete to Angunarama Rd, Girandurukotte Water treatment plant recently. Mix design has Bathalayaya, Mahiyanganaya. been completed and a copy is attached herewith for information. Attendees: 3. 4hr initial setting time can be guaranteed for the mix design which 1. Eng. D.M.L. has been already done. Wijebandara Disawe 4. To transport from Batalayaya to Monaragala, estimated travelling – Material Engineer time will be around 2hr 45min during night time. 2. Eng. J.M.G. Indunil 5. Crushed ice shall be used for concrete mixing and so concrete is – Office Engineer guaranteed with no cracks. 29 °C temperature can be maintained (Department of Buildings) at site. 6. 2 days advance order is expected by the plant to be ready with Resource Person: Mr. D.M. Lohitha – crushed ice. Assistant Plant 7. River sand is used as fine aggregate and crushed sand is not using Manager (Tokyo for C35A. Super – Bathalayaya) 8. For C35A, minimum order quantity of 8m3 is required.