Planning Scheduling and Reporting Procedure
Planning Scheduling and Reporting Procedure
Approval Sheet
Name Title Date Signature
Revision Status
PT. Petronesia Benimel Owner
Rev Issue Date Issue Purpose
Prepared Checked Approved Signature
A 11-07-2019 DK DK BN Issued For Review
0 30-07-2019 DK DK BN Approved For Construction
PHE WMO
Planning, Schedule & Reporting Procedure
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 2 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 3 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
Table of Contents
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 4 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 5 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
1. PURPOSE
The scope of this procedure is to describe the process to be taken to identity, monitor and control all
project planning. The purpose is to establish planning and scheduling of the project to be followed by
CONTRACTOR’S Project Management Team for the execution of Provision of ORF Building and
Infrastructure Service Project, ensuring that the project shall be managed, monitored and controlled in a
professional and efficient manner and shall meet the requirments of the COMPANY as envisaged in the
contract.
The purpose of this procedure is to identify the processes, the roles & responsibilities of both parties
required to perform the invoicing, approvaland payment activities associated to and in accordance with
the CONTRACTOR’s scope under the Provision of ORF Building and Infrastructure Services Project.
2. REFERENCES
Contract Document 4710002759
Contract Document - Exhibit B (Scope of Work)
Contract Document – EXHIBIT C (Compensation and Payment)
Contract Document – EXHIBIT C1 (Contract Price Breakdown)
Contract Document – EXHIBIT E (Project Control and Coordination)
Progress Measurement Procedure (PHEWMO-ORF-G-PRC-0002)
3.1. Definitions
COMPANY : PT. Pertamina hulu Energi West Madura Offshore (PT. PHE WMO)
CONTRACTOR : PT. Petronesia Benimel
CONTRACT : Contract Agreement between PT PHE WMO
Between PT Petronesia Benimel.
3.2. Abbreviation
• WBS : Work Breakdown Structure
• COR : Change Order Request
• PMT : Project Management Team
• MDR : Master Document Register
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 6 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
Project Control Manager assigned to the project and supported by Project Control Team shall be
responsible for project planning, scheduling, progress monitoring and control.
Planning and Schedulling Engineers for Planning, Scheduling, Reporting and Progress Monitoring.
Document Controller for receiving, distributing, control all project document /deliverables and,
Cost Control Engineer for Cost Estimating and Control
5.1. Actvities
During development of Planning, Scheduling and Reporting Procedure for this Project, estabilished
proven methods and procedures to be used.
Experiences gained over a wide range of business areas has been incorporated within the standard
methods of operation, resulting in a system being implemented, which is sufficiently flexible to meet
different requirments for operation on the Project. To Achieve consistency throughout all phases of the
Project, a common work breakdown structure shall be utilized by all work areas
Under the direction of CONTRACTOR’S Project Manager, who will be responsible for the overall
coordination of the programmers and for management reporting project control group will develop the
detail program for approval of COMPANY.
Close coordination shall be maintained between CONTRACTOR’S Project manager and COMPANY
Project Manager for joint discussion to inform / ensure that effect of any variations are reflected in the
program.
During the initiation of the Project, a Project Control System shall be developed to be
implemented in all along the project duration. This system will be applied for CONSTRACTOR,
SUBCONTRACTOR’s, VENDORs, and all involved parties in the project.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 7 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
At the project finalization stage, the Project Control Team shall take necessary action for
preparation of Project Close-out Report and final documentation.
5.2. ProjectProcedures
Following Project Management plan & procedures are to be prepared by Project Control Team for
COMPANY approval and implement to the Project.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 8 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
6.2. Software
For preparation of schedule PROJECT MANAGEMENT, will be used. On conditional needs,
CONSTRACTOR will consider to use the said software together with other application such as MS
Project, MS Excel spreadsheets for other purposes related to planning, schedulling and control.
The copy of any electronic files and native files (if required) of schedule will be provide to COMPANY. In
the event that the software release number used by CPY and CTR are different, CTR will convert the
native file to readable release before sending to CPY.
The Planning and scheduling activities shall be broken down into successive levels of detail, each lower
level is detailing of the immediate upper level. Each unit of WBS shall have unique number to be yhe
basis of schedule integration, progress monitoring & reporting and cost.
Work Phases, Sub-Phase Unit which form Levels of the WBS are detailed in Section following. While
these levels will provide a summary of the schedule and progress, intergration of the activities to form a
CPM (Critical Path Methode) network is carried out. Critical path should be shown in time schedule.
Schedule level-1 or usually called as Contract schedule; shown project key dates and/or milestone
including Project Phases; consumption for high level management; Summary level in accordance
the project WBS, underpinned by the level 2 schedule.
Schedule Level-2 or Project Coordination Schedule; apply EPCI element. This is a summary of level
3 schedule, activities are depictingthe integrated schedule of the entire project including a cleary
identified critical part can be attached to Monthly Report.
Schedule Level-3 or Project Master Schedule; shown detail working schedule with CPM (Critical
Path method). In common pratice of schedule controling, level-3 schedule is usually the result of
schedule breakdown as deep as discipline level on each phase.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 9 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
Schedule Level-4 or Detailed Work Schedule, shown detailed main work Activities level or Detail
deliverables planning, engineering drawing, major item procurement, fabrication or installation by
sub element, this is guidance for site fabrication & offshore installation also.
Following the schedules completion & approval by the COMPANY, the schedule shall be used for
progress measurement, reporting, monitoring, updating and will be used as the baseline for S-Curves.
Critical path to be provided in activity level.
Different Schedule layout using Activity Code may develop by CONTRACTOR to view / read schedule
in other way. Assignment of Activity Code for each Activity will align with Site Workk sequences and
layout can be shorted out as per needed.
a) Basic elements information which considers productivity, site condition, resources, risk factor,
budget allocation, and activity execution method.
b) Variables consists of specific Key Dates and / or Milestones, Long Lead Items (LLI), Work
sequence, project type;
c) Activity ID, whichh should be unique and can be set to multi fuction like tag name or address of
works;
d) Correct relationship assigned between activities, it will show how an activity relates to the start or
finish of another activity or assignment;
e) Correct constraint to be applied wen te activities must start or finish on a specific date, however it
will be applied minimally in the schedule.
Activity ID
WBS Number
Activity duration
Early start and finish date
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 10 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
The Project Master Schedule will be reviewed and approved by CONTRACTOR’S Project Manager &
Management before submission to COMPANY.
6.5.4. S-Curves
For progress measurement of units of WBS, S-Curves will be used. The weigtage for each activity will
be distributed based on the activity duration. Weightage should be be applied during the S-Curves
development. Thereafter, the total weight of all activities will be plotted periodically. The planned S-
Curves shall be then developed for each Project phase, and Overall Project. These S-Curves will be
consisted of Early Start (ES) dates of Project Master Schedule and used ad a reference. Actual S-
Curves will be calculated based on actual work performed by periodical pysical progress
measurement. The actual progress curve calculation will be in accordance with Progress
Measurement Procedure. S-curves shall also be plotted based on grouping such as work areas or
phases when required.
Project Master Schedule will be updated using a split bar display where the lower section of the bar
represents the planned dates and the upper section shows the actual & forecast completion dates.
Controlling/monitoring of schedule means monitoring progress against the baseline time scale, hence it
can be done by comparing actual progress achieved against the planned proggress which is ussualy
delineated by S-Curves.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 11 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
If the actual progress falls below the planned progress, it is indicated that the project is running behind
target timeline. In case there are no extenuating circumstances such as performance is not in line with
planned, unrecorded changes of Contract and force major forcing the actual progress curve below its
plan, then a failure analysis shall be performed by the Project Management Team. Necessary and
appropriate actions shall be formulized to further be implemented to rectify the problems.
Speeding up the activities that are predicted to finish late is the way to improve the rate of progress
whenever a project is behind schedule. In doing so, few actions to be undertaken:
a) Improving productivity
b) Increasing resources (Man Power & Equipment)
c) Increasing Work time by applying overtime and
d) Subcontracting possible part of the project.
Among those, Improving productivity is the best and cheapest way to increase the speed of the work,
either by using better-qualified manpower or by improving work methods.
The Project Master Schedule is to be updated periodically in weekly basis on the current information
provided by the all related project team members.
Progress S-curves shall be re-drawn accordingly. Revised plan S-Curves shall be started with actual
current progress at the revision date. Baseline S-Curves shall be shown as reference. All revisions shall
be referenced (title and revision number) and dated.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 12 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
However, CONTRACTOR will monitor closely critical path and any variation in plan & actual progress,
corrective action shall be taken accordingly.
8. COST CONTROL
Cost control principle is continually monitor actual and forecast cost against project budget/cost estimation.
Comparisons are to be made at the detail level of each element defined by dedicated cost code. Cost
control functions is also involved in controlling change order, trending, predicting and recommending
corrective actions wherever necessary to ensure that execution proceeds according to the established
budget.
Deviations are to be reviewed and alternates schemes are to be implemented wherever necessary
accordingly for the objective of maintaining budget and schedule, without impacting the quality and safety.
Cost Controller will be responsible to manage and prepare Cost Control reports complete with cost s-curve
and issue it on monthly basis.
9. REPORTING
9.1. General
CONTRACTOR shall provide COMPANY with accurate and complete information with respect to the
Work already performed, to the Work in progress, to the Work scheduled and to any events affecting or
expected to affect the performance of the Work. Such information is to be provided to the COMPANY
regularly and consolidated in the Weekly and Monthly Status Reports (Daily Status Report during
Operation).
CONTRACTOR shall make available to COMPANY all relevant planning and reporting documents.
Reports of achievements shall contain facts only. Reports shall also mention scheduled works.
CONTRACTOR is to report promptly and specifically all and any matter significantly affecting the Work
progress and/or quality to COMPANY.
ltems of Work that have suffered some delay and need particular attention for Recovery;
ltems of Work, which are forecast to suffer delays even though they do not affect the critical path of
the Project Master Schedule;
Work relevant to items that are on the critical path of the Project Master Schedule.
CONTRACTOR shall include in narative, detailed information such as newly started or outstanding tasks
performance and detailed execution of Work items when progress of the activity measurement is not
always clearly representative of an on going action, i.e at. Early stage and at completion stage of an
activity.
Project status reports are to be given clear idea about where project is standing currently and give an
idea of project trend to COMPANY and CONTRACTOR's management.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 13 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
Any reporting document (weekly and monthly) is to be issued in accordance with the cut-off dates.
The Actual Progress will be measured in accordance with the Progress MeasurementProcedure
(PHEWMO-ORF-G-PRC-002).
The elements of progress / scheduling will be reported in daily /weekly /monthly and other reports.
CONTRACTOR will issue the following reports to COMPANY:
a) Safety issues/Observations;
b) The weather and loss of time, if any;
c) Description of major activities for today and plan for tomorrow
d) The Physical Progress of Construction activities;
e) The Direct manpower deployment;
f) The supervisory personnel and indirect manpower deployment;
g) The Construction equipment deployment;
h) Chronological recording of important activities accomplished
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 14 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
First of all required latest information/ data to be collected for HSSE, QA/QC, Engineering,
Procurement, Installation from concerned department and subcontractor(s) on the cut-off day or
maximum early next day about the following :
All collected information/ data to be compiled and prepare Weekly Report. In weekly report narrative
statement to be written about the status of various Works of different project phases during the week.
HSSE highlights and statistics, progress statistics will be in the report. Updated Master Document
Register, Progress Analysis Sheets and Progress planned vs. actual progress S-curves will be attached
to the report to reflect the progress trend. Information about resources will also be part of weekly report.
Technical query status, material status to be attached in the report.
4.2.Engineering
4.3.Procurement
4.4.Construction (Fabrication) and Testing
4.5.Pre-Comissioning and Commissioning
4.6.Other
4.7.QA/QC
7. ATTACHMENTS
7.1.Updated S-Curves
7.2.Weeks look ahead plan for detailed Engineering
7.3.Procurement Monitoring Schedule
7.4.Photo
The cut-off date of the weekly report is every Friday, report shall be submitted on following Tuesday.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 16 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
3.2.2 Procurement
3.2.3 Construction
3.2.4 Installation
3.2.5 Pre-commissioning and Commissioning
3.2.6 Other
3.2.7 QA/QC
4. CONCERN / ISSUES
5. OVERALL PROJECT STATISTICS
5.1 Overall Progress Summary
5.2 Schedule Performance including Key Milestones
6 RECOVERY PLAN
7 INTERFACE ISSUED
8 ATTACHMENT
8.1 Updated S-Curves
8.2 Manpower Loading
8.3 Progress Calculation Sheets (Level-5)
8.4 Updated Master Document Register
8.5 Updated Procurement Monitoring Schedule
8.6 Work Statement
8.7 TKDN Status
8.8 3 Month Look Ahead Invoicing
8.9 Progress Photographs
Additional latest information / data required Monthly Report to be collected from concerned
department and subcontractor(s).All collected information / data to be compiled and prepare
Monthly Report.The cut-off-date of the monthly report is the last Tuesday of each month. The
report shall be covering the activities in between two successive monthly cut-off dates. It shall be
submitted to COMPANY within seven (7) calendar days from monthly cut-off.
PHEWMO-ORF-G-PRC-0001-Rev.0
Page 17 of 18
PHE WMO
Planning, Schedule & Reporting Procedure
k. Project photographs
10. MEETINGS
Following regular meetings will be held between CONTRACTOR and COMPANY during execution of project:
PHEWMO-ORF-G-PRC-0001-Rev.0