Pre-Commissioning Check:
Sta√tus
Sl. Remarks Record
Description
No N Deficiencies, If
YES
O Any
1 AVAILABILITY OF DOCUMENTATION
Erection Drawings including OGA OK
Erection/Maintenance Manual OK
Transport Packing List OK
2 RECEIPT OF TRANSFORMER
Externally Inspected Damage (if any)
Gas pressure on Receipt (Where Applicable) OK
Oil Level (In case of Oil Filled Transformer) OK
Unit Correctly Positioned OK
Core Shield Isolation & Capacitance of Core Shield to be measured OK
3 RECEIPT OF ACCESSORIES
All Materials stored correctly OK
Packing Cases inspected, damage if any OK
Marshalling Box Inspected, damage if any OK
Controls Panel, RTCC Inspected OK
Any Shortages/Wrong Supply OK
4 ERECTION
Transport Rollers Mounted OK
Conservator Mounted OK
Buchholz relay and Oil surge relay mounted (arrow mark should be
OK
towards conservator)
Breather mounted and dully charged OK
HV Bushing Mounted OK
LV Bushing Mounted OK
Tertiary Bushing Mounted OK
HV neutral Bushing Mounted N/A
Page 1 of 6
DOC NO.: D-2-01-03-01-04
STATUS REMARKS
Page 2 of 6
DOC NO.: D-2-01-03-01-04
Sr.
No. Check Points OK Not Ok
Direction & mounting angle of O.S.R & Buchholz OK
1.
relay
Dryness of silica gel, seal removal & oil Level in OK
2.
Bottom Cup
3. Oil Level in main conservator OK
4. Oil Filled in OLTC Conservator OK
5. Oil Filled in OTI/WTI Pockets OK
Earthing of main tank, cooler bank, neutral, fans, OK
6.
pumps, etc.
7. Absence of oil seepages/leakages OK
8. Bushing their oil levels & Test cap covering OK
9. Explosion vent & rupture pin settling OK
10. Touch up painting & Washing OK
11. Overall clearances OK
Atmoseal commissioned (top gauge glass show full OK
12.
oil)
13. Sagging of Radiator/pipes OK
14. Tightness of bushing top seal OK
Distortion in expansion bellows/ removal of transit OK
15.
support
A. Marshalling Box
1. W.T.I
a. Transit lock release OK
b. Switch Setting & Operation OK
c. Connections OK
d. Ambient Reading OK
e. Heater shunt shorting link OK
f. Matching with repeaters OK
g. Power Supply & current converter OK
2. O.T.I
a. Transit lock release OK
b. Switch Setting & Operation OK
c. Connections OK
d. Ambient Reading OK
e. Matching with repeaters OK
3. Space Heater & Thermostat settings OK
4. Cabling, Glanding, Termination etc. OK
5. Earthing& Touch Up Painting OK
6. Stand by supply change over operation OK
7. Timer Settings OK
8. Closure of openings & Tidiness OK
Page 3 of 6
DOC NO.: D-2-01-03-01-04
7. Megger Values OK
Page 4 of 6
DOC NO.: D-2-01-03-01-04
1U1N = 206 V
1U2n = 51.6 V
1N2n = 155.3 V
1V2v = 278 V
1W2w = 283 V
1V2w =333 V
Conditions to satisfy:
MODE APPLIED AT AT 5 KV AT 10 KV
Page 5 of 6
DOC NO.: D-2-01-03-01-04
MODE APPLIED AT 5 KV AT 10 KV
BETWEEN CAPACITANCE (F) TAN δ (%) CAPACITANCE (F) TAN δ (%)
UST HV TO LV 6786 pF 0.195 6790 pF 0.197
GST-GND LV TO E 15.94 nF 0.330 15.95 nF 0.336
GST-GND HV TO E 8580 pF 0.332 8592 pF 0.445