Инструкция по монтажу 31.10.13

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 76

SILENS PRO Compact

Installation manual

Rev.: 0
SILENS PRO Compact

INDEX ................................................................................................................................................... 2

1. INTRODUCTION ................................................................................................................................. 3

2. TECHNICAL SPECIFICATIONS ........................................................................................................... 5

3. SAFETY REGULATIONS ..................................................................................................................... 7

4. SPECIFIC TOOLS AND MATERIALS FOR ASSEMBLY ...................................................................... 15 Before using the installation, the client
must read this document carefully and
5. SPECIALISED EQUIPMENT REQUIRED DURING INSTALLATION .................................................... 19 in its entirety.
This document must be kept in a safe
and accessible place. In the event of any
6. UNLOADING & UNPACKING OF MATERIAL .................................................................................... 23
doubts or incomprehension, consult the
lift installer.
7. INSTALLATION PROCEDURE ............................................................................................................ 25

7.1. CHECKING & PREPARATION OF SITE ................................................................................ 26

7.2. ORDER OF INSTALLATION ................................................................................................. 27

7.3. DESCRIPTION OF EACH PHASE OF INSTALLATION ........................................................... 28

8. ELECTRICAL DOCUMENTATION ........................................................................................................ 75

Rev.: 0 2 / 76
SILENS PRO Compact

This section describes the structure of


this installation manual and how to use
it, and sets out the terms of the limited
warranty and the waiver of liability, and
the acknowledgement of the risks
1 - INTRODUCTION inherent to the installation process.

Rev.: 0 Introduction 3 / 76
SILENS PRO Compact

This manual recommends a specific procedure to be followed for the installation of the lift system in the shaft,
for which the use of a range of characteristic tools and equipment is necessary. The said procedure does not
exclude the modification of certain aspects of the installation process on the authority of the person in charge
of installation, which could include the decision to use all the tools and equipment specified or only those
corresponding to those areas which the installer deems appropriate for incorporation into the particular
installation process in question.

The manufacturer accepts no responsibility whatsoever for the procedure followed by the installer nor for Before using the installation for the first
compliance with the particular parameters set out in the Safety Plan established to govern the work of the time, the client must read this
installation technicians. At no time does this manual have a contractual character. It is designed to act as a document carefully and in its entirety.
helpful guide to the installation process, to clear up possible confusions, to improve effectiveness and to This document must be kept in a safe
resolve any possible problems which may arise during the particular installation process. and accessible place. In the event of any
doubts or incomprehension, consult the
lift installer.
Furthermore, the manufacturer accepts no responsibility whatsoever for any changes experienced by the
product over its useful life and any changes to it which are not set out in this document. The particular
If the user detects any malfunction
procedure followed will always be adaptable to the installation of the given lift system, irrespective of the whatsoever in the lift system,
components’ details, quantity or type. immediately put the system out of
service and contact the installer.
Nor does the manufacturer accept any responsibility whatsoever for the construction of the lift shaft and of the
machine room, if applicable, nor for any problems consequent on the improper use of the lift system.

This manual sets out the installation procedure to be followed for all possible variants across the whole product
range and its associated options, and will be applicable only in such case as its application has been approved
in the particular contract in question.

Rev.: 0 Introduction 4 / 76
SILENS PRO Compact

This section sets out the lift system’s


2 – TECHNICAL SPECIFICATIONS technical specifications, applicable
throughout the product range.

Rev.: 0 Technical specifications 5 / 76


SILENS PRO Compact

TECHNICAL CHARACTERISTICS
2 300 / 4 375 / 5 450 / 6 630 / 8
Directive 95/16 CE
Compliant with Standards: UNE-EN 81-1:2001+A3
Installation: MRL Electric
Roping: 2:1
WYJ140-10-450-2 WYJ140-10-450-2 WYJ140-10-630-2
Gearless drive: XAF1 S 320 XAF1 M 480 XAF1 M 630
Load-bearing beams: Material hoisting hooks for use during installation
Entrance configurations: Simple, double or triple at 90º &/or 180º
Speed: 1 m/s
Maximun travel: 60 m
Control cabinet: A2 type at top floor landing (other options available)
Doors: Clear opening width: 600-900mm, Height: 2000 or 2100mm (EN 81:21 1800 or 1900 options)
Control: WVF
Control system: IMEM Altamira II. CAN bus communication. Direct Aproach System. Universal control system
Rescue system: Automatic
Electrical emergency operation: TORN
Nominal motor powerr: 2,2 kW 3 kW 4,3 kW
Voltage: 400 V The manufacturer accepts no
OPCIONES responsibility whatsoever for any
Installation equipment: Drive unit installation / Material hoist and guide rall installation
Car design: Series 206, 406, 410; Special cars
changes experienced by the product
Slack rope switch: Obligatory in Australia over its useful life and any changes to it
Down collective / Full collective / Call & send / Independent service / EN 81:73 / EN81:72 / Doorhold / VIP service / Lift which are not set out in this document.
attendant service / Selective opening / U36 / French firefighters standard / Lift evacuation / Advance door opening / Out of
Control system options: service display / Full car display
Conversions: EN 81:21 compliant
Accessibility: EN 81:70 compliant
Car doors: Door locking
Additional options: Voice synthesizer, EcoSAVER system, lift car fan, landing display, electronic overload monitor

Rev.: 0 Technical specifications 6 / 76


SILENS PRO Compact

This section sets out the safety


regulations to be followed during the
3 – SAFETY REGULATIONS installation process in order to avoid any
related risks and ensure that all works
are carried out under optimum safety
conditions.

Rev.: 0 Safety Regulations 7 / 76


SILENS PRO Compact

KEY SAFETY REGULATIONS

ALWAYS use the fixed scaffolding/work


platforms to comply with the
established safety requirements.
ALWAYS use fall protection when at risk
of falling from a height.
ALWAYS follow the master switch lock-
out procedure whenever the work to be
carried out does not require power.
NEVER work with any part of the body
close to moving parts or unprotected
electrical components.
ALWAYS maintain control of the lift
SAFE WORK PROCEDURE - SWP system when working on the car top
(before access, while on the top and on
exiting from it).
NEVER travel on the car top at its rated
speed.
ALWAYS maintain control of the lift
system when working in the pit (before
access, while in the pit and on exiting
from it.
ALWAYS comply with the rated load
maximums established.

Rev.: 0 Safety Regulations 8 / 76


SILENS PRO Compact

SWP – SAFETY HELMET The safety wear and equipment


The safety helmet(s) must be used AT ALL TIMES from the point(s) at which their use is designated as obligatory on the essential for operation in the work area
corresponding workplace signage. The helmet chinstrap must ALWAYS be used by all installation operatives working within the and which all personnel must use are
shaft. the following:
Once all the shaft doors have been installed and are completely closed throughout the shaft, helmet use can ONLY be dispensed 1 - Equipment which must be used at
with once the lift car has been installed and its guard rail installed on the car top when required, and there is no risk of objects falling all times and during all operations:
during work operations. ● Safety helmets with chinstraps
● Safety footwear (with reinforced
toecaps and soles)
● Workwear
2- Equipment which must be used
occasionally, and only when required
for the particular task being performed:
SWP - FALL ARREST BLOCK the handling of loads, the use of hand
Installation operatives must always carry with them their fall arrest block, and check that it is at hand at all times. tools, the use of electric tools by hand,
In order to avoid the risk of a serious fall, installation operatives must always attach themselves to their fall arrest block before the handling of dangerous substances
entering the shaft. etc.
NEVER use it if the free space below the user is less than 3m. ● Risk of piercing
NEVER anchor it below the user. Gloves for loading and unloading
NEVER use the equipment after having suffered a fall. materials
NEVER leave the shaft with the fall arrest block still attached to the rope/webbing. Heavy-duty cut-resistant gloves
Medium-duty cut-resistant gloves
Obligatory when using tools and
handling loads.

Rev.: 0 Safety Regulations 9 / 76


SILENS PRO Compact

SWP – PREVENTION OF FALL HAZARDS AT EACH LANDING LEVEL ● Eye protection – against impact and
Ensure that all the door openings on the worksite have been fitted with fall protection. piercing.
Ensure that the fall protection consists of handrails, guard rails and skirtings. Safety glasses and goggles
Where fall protection has not been fitted or is inadequate, those in charge of works must be informed immediately. Obligatory when using hand tools and
A notice must be fixed at each landing level warning of the shaft fall hazards in the area. electrical tools by hand and when
The above inspection procedure must be carried out at the start of each working day to ensure that proper safety standards are handling dangerous substances.
maintained. Obligatory both for the technician
directly carrying out the operation and
for any other operative also exposed to
the particular risk.
● Respiratory protection
Face mask
Recommended for use when
undertaking cleaning work and working
in dusty environments.
● Hearing protection
SWP – WINCH INSTALLATION Ear plugs.
When installing a w¡nch, the following factors must always be taken into account: Recommended for use when using
● Always be aware of the maximum rated load of the winch in question, and ensure that each load to be lifted conforms with the electric hand tools.
limit. Recommended for use when in a noisy
● Ensure that the winch cable is longer than the travel distance and is in perfect working order. environment.
● Ensure that the winch hooks are in perfect condition. Obligatory when using abrasives.
● Ensure installation of the limit switch actuator at the end of the cable.
● Check that the equipment’s preventive maintenance is fully up-to-date.
● Check that the power cabling is in perfect condition.
● Check that the power plugs are in perfect condition.
● Hang the winch from the shaft roof beams with the safety chains.
● Check that the button pad is in perfect working order (test operation prior to use)

Rev.: 0 Safety Regulations 10 / 76


SILENS PRO Compact

SWP – LIFELINES ● Strain protection


The Senior Technician’s and Assistant’s lifelines must be visually distinctive and each must be able clearly to distinguish their own Lumbar support belt.
line, in order to avoid the danger of their both attaching themselves to the same line at any point in time. ● First Aid
The Senior Technician must always ensure that the lifelines are longer than the shaft height in question. First-aid kit.
Attach the anchor slings to the anchorage and then attach the lifelines to their anchor slings and drop them to extend down the pit. Must always be available in the work
The lifelines must be hung so as to be accessible from the landing door level so that operatives can attach themselves to their area and kept properly equipped.
lifelines without entering the shaft. (Never go into the shaft without first attaching your lifeline to prevent any risk of falling)
3 - When works are carried out where
there is a risk of falling from a height,
both operatives must always use:
● Anchor slings
● Fall arrest harnesses
● Lifelines
● Fall arrest blocks
SWP – ENTRY INTO THE SHAFT ● Safety billets
Every technician must ALWAYS activate their fall arrest device before entry into the shaft and must ALWAYS attach themselves to
their particular lifeline. In the event of a fall, all this fall
protection equipment must be
withdrawn immediately.

Rev.: 0 Safety Regulations 11 / 76


SILENS PRO Compact

SWP – SHAFT LIGHTING The safety equipment required by the


The portable lighting used in the shaft, should it be required, must always have a supply voltage of 24V, for which there is a power Senior Technician and Assistant must
point in the control cabinet. be supplied to them in full compliance
Consequently, it must be borne in mind that 220V halogen spotlighting is unavailable in portable form, only as fixed lighting. with the safety regulations in force on-
site.
The equipment used must always be in
good condition. The installation
technicians must monitor the condition
of their safety equipment and must
immediately report any fault or
disrepair.
SWP – HAND TOOLS & ELECTRICAL HAND TOOLS
All hand tools must be CE-marked and include all applicable protective fittings at all times. INSPECTION OF SAFETY EQUIPMENT
When using tools that are likely to propel particles or objects, remember to take precautions in the area to protect both operatives ELECTRICAL TOOLS, SLINGS, LIFTING
from flying particles and flammbale substances from flying sparks. APPARATUS & ELECTRICAL CABLING &
When using hand tools, operatives must wear gloves to prevent cuts, eye protection to prevent impact and piercing, ear protection to PLUGS
deaden high noise levels and respiratory protection when necessary. Before commencement of each
installation job, the installation
technicians must ensure that:
SAFETY EQUIPMENT – all the safety
equipment required is available for use,
is in full working order and is not past its
expiry date (if applicable).

Rev.: 0 Safety Regulations 12 / 76


SILENS PRO Compact

SWP – SAFETY BILLET ELECTRICAL TOOLS – all the necessary


Before inserting the plumb line platform in the shaft, two safety bars must be installed: one for the senior technician and the other electrical tools are available for use, and
for his assistant. the tools and their wiring and plugs are
Before you start to move the plumb line platform into the shaft, both installation technicians must attach themselves to the safety in full working order.
bars to prevent any risk of falling to a different level when manouvering the platform.The senior installation technician must always POLYESTER SLINGS, WIRE-ROPE
carry a safety bar in his tool chest and will be provided with another one together with the lift system material. SLINGS & WIRE-ROPE HALF-SLINGS –
When the mechanical installation part has been completed, the senior installation technician must remove his safety bar and leave all the slings are in full working order,
the other one installed so that it can be used by maintenance technicians in their after-sales work. their maximum rated loads are as
required and prepare them for their
particular use.
LIFTING APPARATUS – all the lifting
apparatus is in full working order,
preventive maintenance is fully up-to-
date, their maximum rated loads are as
required and their adequacy for the
particular operation.
SWP – PLUMB LINE AND WORK PLATFORMS ELECTRICAL CABLING & PLUGS – all the
All plumb line and work platforms used must be fitted with a guard rail and kick board. electrical cabling and plugs used during
installation works must be in perfect
order, with no breaks and no splicing
and suitable for the particular power
supply to be used.

Rev.: 0 Safety Regulations 13 / 76


SILENS PRO Compact

SWP – HANDLING OF DANGEROUS SUBSTANCES FALL HAZARDS AT EACH LANDING


Whenever dangerous substances are to be handled, eye and hand protection must be worn. LEVEL ON THE WORKSITE
The containers in which dangerous substances are stored (drums, cans etc.) must always be clearly labelled with notices identifying The first task to be carried out by the
the particular substance which they contain (so as to avoid mistaken use arising from misidentification) installation technicians is to check that
the worksite is properly equipped with
anti-fall protection at every lift
entranceway at every landing served.
This protection should consist of
handrails, guard rails and kick plates.
In the event that any protective element
is missing or inadequate, the works
management team must be informed
SWP – STEPLADDER immediately.
On each job and before every use of the stepladder, the Installation Manager must check that it is in perfect condition, that the steps A safety notice must be fixed by each
are undamaged, that the front rails have larger feet, that they are fitted with non-slip shoes at their upper and lower ends and that landing door opening, warning of the
the lockable spreaders are in perfect condition. hazards associated with the shafts.
At the start of every working day, an
inspection must be carried out to ensure
compliance with all the above points.

SWP – INSTALLATION PEDAL


Before beginning to move the car up or down, always perform tests in the lower shaft area beforehand to check the system operates
reliably.

Rev.: 0 Safety Regulations 14 / 76


SILENS PRO Compact

This section details the tools which must


4 – TOOLS REQUIRED FOR INSTALLATION PROCESS be available to the installation crew in
order to carry out the tasks described in
this manual.

Rev.: 0 Tools required 15 / 76


SILENS PRO Compact

TAPE MEASURE

LEVEL

The manufacturer accepts no


responsibility whatsoever for the
incorrect use of any of the tools detailed
in this section.
PLUMB BOB & LINE
The manufacturer is in no way
responsible for supplying the tools
required for the installation process.

SET OF ALLEN KEYS

SET OF SPANNERS Herramientas necesarias…

Rev.: 0 Tools required 16 / 76


SILENS PRO Compact

SET OF RATCHET SPANNERS

POWER DRILL

SWP – HAND TOOLS & ELECTRICAL


HAND TOOLS
SET OF SCREWDRIVERS (SLOT-HEAD & PHILLIPS)

RIVETER

MALLET Herramientas necesarias…

Rev.: 0 Tools required 17 / 76


SILENS PRO Compact

SUCKER
(STRUCTURE)

SILICONE GUN
(STRUCTURE)

Herramientas necesarias…

Rev.: 0 Tools required 18 / 76


SILENS PRO Compact

This section details the specialised


equipment which must be used while
5 – SPECIFIC TOOLS FOR ASSEMBLY undertaking the installation procedure
set out in this manual.

Rev.: 0 Specialised equipment 19 / 76


SILENS PRO Compact

500KG WINCH

1000KG WINCH

The manufacturer accepts no


METAL STEPLADDER responsibility whatsoever for any misuse
of the equipment listed in this section.

CAR TOP INSPECTION STATION

GUIDE RAIL TEMPLATE


(ONE FOR CAR, OTHER FOR COUNTERWEIGHT)

Rev.: 0 Specialised equipment 20 / 76


SILENS PRO Compact

TERMINAL LANDING INSTALLATION PLATFORM

DRIVE UNIT HOIST MOUNTING FIXTURE

The equipment necessary for fulfilment


of this manual’s instructions is supplied
CAR HOIST FITTINGS only on order. In the absence of such,
the equipment will not be delivered with
the lift system components.

MATERIAL HOIST FITTINGS / UPPER PLUMB LINE BRACKETS

LOWER PLUMB LINE FIXINGS

Rev.: 0 Specialised equipment 21 / 76


SILENS PRO Compact

GUIDE SHOE ALIGNMENT FITTINGS

UPPER OVERSPEED GOVERNOR BELT TENSOR SUPPORT

Rev.: 0 Specialised equipment 22 / 76


SILENS PRO Compact

This section details the procedure for


6 – UNLOADING & UNPACKING OF MATERIAL unloading and unpacking material, and
the organisation and distribution of said
material in its packets.

Rev.: 0 Unloading & Unpacking of material 23 / 76


SILENS PRO Compact

The unloading and unpacking of material must be carried out in such a way as to avoid any denting or abrasion of the components
delivered.

Recommendations for the placement of material on-site are detailed in the Installation Procedure section of this manual.

The packing list which is sent with each delivered set of components details the exact content of each package. The packages have
been prepared according to manufacturing criteria focused on facilitating on-site installation and on avoiding the loss or non-
inclusion of material essential to the installation process.

The manufacturer accepts no


responsibility whatsoever for any
damage to the material during the
transport, unloading or unpacking of the
said material. The manufacturer accepts
no responsibility whatsoever for the loss
of any components during the
aforementioned procedures.

Rev.: 0 Unloading & Unpacking of material 24 / 76


SILENS PRO Compact

This section details the complete


7 – INSTALLATION PROCEDURE recommended installation procedure,
describing every task to be carried out in
chronological order.

Rev.: 0 Installation Procedure 25 / 76


SILENS PRO Compact

7.1 CHECKING & PREPARATION OF SITE


Prior to unloading, the Installation Manager must, in consultation with the Works Manager, determine the most appropriate place at
ground level for unloading and handling materials, the best place to store the drive unit and control cabinet at the specific landing or
in the machine room, and where to keep the tools required during installation.
It must also be confirmed that:
● All shaft walls are rendered smooth.
● The slab edge finish does not exceed 2 centimetres in thickness.
● The height of the shaft is as indicated on the plans, and the shaft is damp-free and clear of debris and dirt of any kind.
The manufacturer accepts no
● The terminal landing has the height indicated on plan.
responsibility whatsoever for the
● The travel distance is as defined in the installation’s general plans.
construction of the lift shaft and of the
● The shaft cross-section (width x depth) is correctly dimensioned, and the shaft has been correctly plumbed to ensure minimum
machine room (where applicable), nor
required dimensions throughout.
for any problem resulting from the
● The upper shaft area is adequately ventilated, either directly to the exterior or through a fire-rated duct system, or directly into the
incorrect use of the lift system.
machine room, with a minimum cross-section of 2% of the shaft cross-section, 300 x 300mm².
The shaft must be capable of supporting
● At each landing, the door front is free of obstruction, and that a load-bearing beam is in place capable of bearing the added weight
the loads produced during the normal
of the landing door(s).
operation of the lift, in any case. These
● There is a horizontal load-bearing beam in place above each landing door opening on each floor at the height and in the position
loads are indicated on the General
indicated on the installation plan, and not interfering with the door front.
Drawing, and they are calculated
● There is a three-phase voltage system and an electric circuit protection box sized following the single-line diagram and in
following the Security Coefficients
accordance with the corresponding voltage.
stated in the Rule for the pit dampers
● There are hooks or beams adequate for the hoisting of material within the shaft.
and the guide rails
● There is a beam in the machine room roof (if applicable) for use during drive unit maintenance work, placed as set out in the
plans.
● The machine room (where applicable) has a minimum illuminance of 200 lux (18.58 fc).
● The machine room entranceway (if applicable) has a minimum clearance width of 900mm.
The following must be checked: works safety measures, accesses, protective elements, the closing-off of access to the shaft at each
landing and the accessibility of the material required. The existence, function and integrity of the power supply for use on-site during
works must be verified. The protective elements must be fixed in place and the warning notices set by the landing door openings.

Rev.: 0 Installation Procedure 26 / 76


SILENS PRO Compact

7.2 ORDER OF INSTALLATION


1. Unloading and distribution of material. Installation and checking of safety measures and of installation tools and equipment.
2. Setting out site layout.
3. Installation of upper car frame hoisting fixtures.
4. Installation of guide rail baseplates, upper and lower support brackets and guide rails.
5. Installation of pit damper.
6. Installation of counterweight.
7. Installation of car frame.
8. Installation of overspeed governor belt tensioners and commissioning of the governor. Removal of work platform from the top
floor.
9. Installation of car base, top and cladding. Installation of car pulleys.
10. Installation of remaining guide rail support brackets and removal of plumb lines.
The manufacturer accepts no
11. Installation of lift car’s mechanical stops and guide rail supports.
responsibility whatsoever for the
12. Installation of the machine lifting tool and the bedplate
procedure followed by the installer nor
13. Installation of hoist roping.
for their compliance with the particular
14. Putting the roping under tension.
parameters set out in the Safety Plan to
15. Installation of travelling cable and inspection box. Installation of limit switch skate.
be followed by the installation
16. Installation of landing doors.
technicians.
17. Installation of conduits, shaft lighting and external electrical system. Installation of pit access ladder.
18. Installation of safety switches and limit switches.
19. Installation of remaining car and counterweight accessories.
20. Installation of door operator. Installation of sensors, bistable relays and magnets.
21. Installation of car lighting and car operating panel. Connection of components to inspection box.
22. Check system function in normal operation.
23. Final counterweighting.
24. Lift car levelling.
25. Fitting of car aprons and counterweight protection in the pit.
26. Installation of EN 81-21 compensatory safety measures
27. Final inspection.

Rev.: 0 Installation Procedure 27 / 76


SILENS PRO Compact

7.3 DESCRIPTION OF EACH PHASE OF INSTALLATION


This section describes below the distinct phases numbered and listed in the previous section, which together make up the complete
lift installation procedure.

This manual describes the installation procedure for all the variations and optional extras across the full range on offer of this
particular product, which in each case are only applicable when they correspond to the particular contract in question.

Throughout the installation process, the following metric tightening torque table must be adhered to:

The manufacturer accepts no


responsibility whatsoever for any
changes undergone by the product over
the course of its useful life and which
are not recorded in this manual.
Procedure must always be adapted to
the installation of this lift, irrespective of
the particularities, quantity and type of
the components employed.
The information required for the assembly of the guides is indicated on the general drawing of the lift. A table shows the assembly
sequence of the guides and the distance between the brackets, from the bottom to the top of the shaft cross-section. Another table
shows the different levels, the distance between levels and the number and position of each door. For special lifts, these data are
displayed graphically.

Rev.: 0 Installation Procedure 28 / 76


SILENS PRO Compact

SWP – PREVENTION OF FALL HAZARDS AT EACH LANDING LEVEL 1. Unloading & unpacking of material.
Installation & checking of safety
measures and of installation tools and
equipment
Unload tools and equipment, tool chest,
safety equipment, winch, stepladder etc.
SWP – WINCH INSTALLATION
Check the provision of the required
safety measures on the job, accesses,
protective fittings, the shutting-off of the
shaft at each landing and the
accessibility of materials on-site.
SWP – STEPLADDER Investigate site preparation. Check the
plans and the overall shaft dimensions
– width, depth, headroom clearance, pit,
landing-to-landing distances. Check door
opening fall protection and personnel
and material access. Check provision of
worksite power supply, close to the
control cabinet. Ensure that safety
notices are fixed by the landing door
openings.

Rev.: 0 Installation Procedure 29 / 76


SILENS PRO Compact

SWP – LIFELINES Use a crane to lift the winch, extension


cables, lifelines, plumb line, 220V
spotlight board, 24V portable lighting,
power drill, the site layout setting out
plan and the overspeed governor belt.
The rest of the tools required will be
SWP – ENTRY INTO THE SHAFT
lifted by the hoist, once it has been
installed. If no crane is available, carry
the winch up by the stairway to use for
lifting material.

SWP – SHAFT LIGHTING Use the crane to lift the control cabinet
to the top floor or the machine room (if
applicable).

Fit and fix each operative’s lifeline in the


upper shaft area or the machine room
(if applicable) and drop them down the
full length of the shaft.

Rev.: 0 Installation Procedure 30 / 76


SILENS PRO Compact

Use the crane to lift the drive unit, the


drive unit support plate and the control
cabinet to the top landing or to the
machine room (if applicable).

Set the drive unit on its support plate


with M16x40 bolts if using the WYJ140
drive unit, or with M12x40 bolts if using
the XAF1 drive unit.

Rev.: 0 Installation Procedure 31 / 76


SILENS PRO Compact

2. Setting out site layout


Set up the upper work platform at the
top landing (A).
Attach using M10 wall fixing (2 per tool)
the guide rail hoisting fixtures (B) and
the upper plumb line brackets (C) in the
upper shaft area at a height above that
of the fully assembled guide rails (see
general installation plan: guide rail
height and plumb line positioning).
Drop the plumb lines down the shaft in
the position indicated on the general
site layout plan.
Take the vertical measurements of the
pit, the travel distance and the overhead
clearance. On each floor, measure the
distance from the plumb lines to the
side and front walls so as to ensure
conformity at all times with the
minimum required shaft dimensions as
marked on the general site layout plan.
In the case of any nonconformity
whatsoever, reposition the plumb lines
so as to ensure throughout a vertical
volume consistent with the minimum
required shaft cross-section.

Rev.: 0 Installation Procedure 32 / 76


SILENS PRO Compact

3. Installation of upper car frame


hoisting fixture
Install the car frame hoisting fixture (D)
between the guide rail hoisting fixtures
(B), so that it sits 500mm below the
position of the underside of the
bedplate’s central section indicated on
the general installation plan. Fix it to the
wall using M10 fixing bolts.

Rev.: 0 Installation Procedure 33 / 76


SILENS PRO Compact

4. Installation of guide rail baseplate,


upper and lower support brackets and
guide rails
Fit the guide rail baseplate with the
lower plumb line brackets (A) in the pit,
using as a reference point the position
of the plumb lines (see general
installation plan). Fix the baseplate to
the pit using M10 anchor bolts
Fix the plumb wires in the pit to the
plumb line brackets.

Rev.: 0 Installation Procedure 34 / 76


SILENS PRO Compact

Place the first and last guide rail support


brackets in accordance with their
positions as marked on the general
installation plan and taking as a general
reference point the plumb line wires. Fix
the brackets to the wall with M10
anchor bolts (2 per bracket).

There are two bracket types, to be used


according to the distance between the
back of the guide rails and the wall in
question: the standard type (A) for fixing
to the side walls and the smaller type
(B) for the front walls. If side set-offs are
used, depending on the distance of the
guide rail from the wall, fix the wall
bracket (C) to the guide rail using either
short bend or the long bend, depending
on the requirements of the site.

Rev.: 0 Installation Procedure 35 / 76


SILENS PRO Compact

Install the guide rails, starting with one


of the counterweight guide rails. Set the
first length in the pit and hoist it with the
500kg winch fixed to the hoisting fixture
at the top of the shaft. Once this length
has been raised to a suitable height, set
another length below it and join them
together with a guide rail coupling.
Repeat this operation with the rest of
the lengths until completion.
Repeat the above procedure with the
rest of the counterweight and car frame
guide rails.
Check that the top end of all the guide
rails are at the same level. If not, fit
wedges under baseplate (A) until the
right level is obtained.

Rev.: 0 Installation Procedure 36 / 76


SILENS PRO Compact

Provisionally fix the guide rails to the top


wall set-offs.
In the pit, using the appropriate guide
rail template provided, place the guide
rails in their correct positions relative to
the plumb lines, fix them to their
brackets and fix the brackets to the
shaft wall.
Drill the lower ends of the car guide rails
so that they can be bolted to their
baseplate brackets (M12), using the
baseplate brackets as templates (M12).
Fix the baseplate brackets to the guide
rails (car frame guide rails with M12
bolts, counterweight guide rails with
ties).
Carry out the same operation with the
wall brackets at the top of the shaft, first
detaching them from the guide rails and
finally refixing them in their correct
positions.

Rev.: 0 Installation Procedure 37 / 76


SILENS PRO Compact

5. Installation of pit damper


In case of pits over 850mm, install the
car frame damper in the pit with the
pillar length specified on the general
plan, and the counterweight damper
baseplate fitting (for lifts without
reduced overhead clearance). Fix them
with the bolts and anchor bolts
provided.

Rev.: 0 Installation Procedure 38 / 76


SILENS PRO Compact

6. Installation of counterweight
All counterweight structural pieces are
joined together using M10X25 bolts. The
guide shoes and the sheave casing are
attached using M8 bolts. The cutting
seals on uprights that enable the
weights to be inserted should be fixed to
the uprights using countersunk M10
bolts. The sheave axis stud is fixed to
the lower crosspiece using M10x16
bolts. The damper is installed with M16
bolts. In the pit,
install the counterweight frame with the
damper (A) and its fittings (B), and set it
onto the baseplate in between the
counterweight guide rails. The fittings
are to be bolted with only two bolts to
the lower crosspiece assembly and to
each other, in order to allow access
during lift maintenance works for
installing and uninstalling the fittings
once the lift has been installed.
Engage the guide shoes onto the guide
rails and fix them to the counterweight.
Place half the required counterweights
into the frame.
Put half the counterweight load inside.

Rev.: 0 Installation Procedure 39 / 76


SILENS PRO Compact

7. Installation of car frame


Fix all the car frame’s structural
elements together using M10x25
bolts.The uprights, the sheave sub-
assembly and the plates are joined
together using M10x35 bolts.
The sheave axis stud is fixed to the
lower crosspiece with M10x16 bolts.
The guide shoes are fixed to the uprights
using M12x50 bolts.
The uprights, the sheave subassembly
and the plates are joined together using
M10x35 bolts.
The sheave axis key is fixed to the lower
crosspiece with M10x16 bolts.
The safety gears are connected to the
uprights using M12x25 bolts.
Assemble the car frame base in the pit.

Rev.: 0 Installation Procedure 40 / 76


SILENS PRO Compact

Fit and fix the safety gears with their


extensions (A) onto the uprights, and
install the uprights onto the car frame
base. In the case of a pit <700mm, the
guide shoes will be placed directly on
the uprights. In this case, remove the
bolts which connect the heel plate to the
uprights below the guide shoes (B) so as
to allow the shoes to be placed into
position later.

Rev.: 0 Installation Procedure 41 / 76


SILENS PRO Compact

Place this structure between the car


guide rails onto the car frame pit
damper. Place and fix the upper guide
shoes with M12 bolts. In the case of a
pit <700 mm, place and fit the lower
guide shoes directly onto the uprights.
Place and fix the lower guide shoes with
M12 bolts. Fit and fix the bolts which
connect the frame base with the
uprights (A).

Rev.: 0 Installation Procedure 42 / 76


SILENS PRO Compact

In the case of a pit ≥ 700mm, place and


fix the lower guide shoes (A) and (B) on
their support brackets with M12 bolts
and install these support brackets under
the heel plates using M10 bolts.

Rev.: 0 Installation Procedure 43 / 76


SILENS PRO Compact

Set the crosshead assembly onto the


car frame base, with the overspeed
governor on its support bracket (A) and
the linkage mechanism’s lateral support
brackets (B). Fit the linkage rod’s lateral
locking bushes (C) and the operating
arms (D). Fit the overspeed governor so
that the switch is located horizontally in
the area closest to the counterweight
(E). Introduce the linkage rod into one of
the end bushes and feed it through the
governor and the bushing at the other
end. Fit the tension springs into position
with their support brackets (F), one on
each side, and fix the linkage rod with
the bushings’ set-screws (G). Mount and
fix the overspeed governor belt idler
wheels onto the governor support
bracket (H). Fit the safety gear switch on
the bracket closest to the governor (I).

Rev.: 0 Installation Procedure 44 / 76


SILENS PRO Compact

Mount and fix the uncontrolled car


movement protection module onto the
overspeed governor, above the linkage
rod (A), so that the coil axle is
introduced into the governor’s internal
gearing. To achieve this, first remove the
module’s casing (B), removing the bolts
of the governor which coincide with the
position of the drill holes in the coil
support bracket (C) and then replacing
them in their original position. Replace
the module casing and fix it to the
support bracket.
On the face of the module furthest away
from the overspeed governor, there is a
small plate (D) adjusted with two Allen
bolts, which prevent the coil axle from
obstructing the governor during
installation. Remove this plate once lift
installation is complete in order to put
the module into normal operation.

Rev.: 0 Installation Procedure 45 / 76


SILENS PRO Compact

Fit the crosshead assembly onto the


frame uprights and fix it to them using
the side bolts (A).
Fit the safety gear activation extensions
to the upper arms of the linkage
mechanism using the pivot bolts with
the cotter pins (B).
Pack the upper and lower guide shoes
(C) so as to ensure the correct distance
between guide rails, and leave a 1mm
gap between the liner and the back of
the guide rail so as to prevent
obstruction of the car frame during
normal operation. Install the overspeed
governor protection (D).

Rev.: 0 Installation Procedure 46 / 76


SILENS PRO Compact

Slacken the upper guide shoes and fit


them into their correct position using
the fittings supplied for that purpose (A).
Attach these fittings onto the upper part
of the uprights (B) and use their through
bolts to manoeuvre the guide shoes into
the positions compliant with the safety
gear positioning specifications indicated
in the safety gear manual. Once
correctly positioned, tighten the guide
shoes’ bolts and remove the fittings.
Install the car frame tie rods (C), using
the fixing brackets (D).

Rev.: 0 Installation Procedure 47 / 76


SILENS PRO Compact

8. Installation of overspeed governor


belt tensioners, & commissioning of
governor. Removal of work platform
from the top floor
Install the overspeed governor’s lower
tensioner on the guide rail baseplate in
the position indicated on the general
plan, according to which type of
tensioner is to be used - standard (A) or
horizontal (B).
Install the upper tensioner of the
governor belt below the shaft ceiling, or
the guide rail bracket with built-in
tensioner provided for the installation
(C), at a distance of 500mm from the
upper edge of the guide shoes in the
position indicated on the general
arrangement drawing.
Attach one end of the overspeed
governor belt to the upper tensioner so
that it hangs down the full height of the
shaft. Use two belt fixings (D).
In the pit, fit the belt around the
overspeed governor sheave, tauten it
and fix the free end to the lower
tensioner. Use two belt fixings (D).

Rev.: 0 Installation Procedure 48 / 76


SILENS PRO Compact

9. Installation of car base, top and


cladding
Attach the 1000kg winch for lifting the
car frame (previously attached to the
central hoisting fixture at the top of the
shaft) to the car frame sheave
subassembly.
Fit the dampers (or load cells, if
applicable) which support the lift car
from below onto the car frame base (A).
Then fit the car base onto them.
Suspend the car frame so as to allow
access into the pit. Fix the car base to
the car frame dampers. Install the car
door sill onto its support member.
Install the panelling and car fronts. Fix
the car top. Fix the car to the upper car
frame using the brackets designed for
that purpose (B). Install handrails on the
roof of the car.

Rev.: 0 Installation Procedure 49 / 76


SILENS PRO Compact

10. Installation of remaining guide rail


support brackets, and removal of
plumb lines
From the car top, and using the winch to
hoist the car, install the remaining set-
off brackets in the positions indicated
on the general plan, using the templates
to maintain the correct distance
between guide rails and the guide rails
correctly plumbed.
Remove the plumb lines, the guide rail
hoisting and positioning fittings and the
plumb line fixings.

Rev.: 0 Installation Procedure 50 / 76


SILENS PRO Compact

11. Installation of lift car’s mechanical


stops and guide rail mountings
Fix the mechanical stops to the car
frame crosshead assembly (A) using
M16 bolts. Fix their two guide rail
mountings (B) in the position indicated
on the general plan with M12 bolts. To
achieve this, the guide rails must be
drilled using the mounting as a
template.

Rev.: 0 Installation Procedure 51 / 76


SILENS PRO Compact

12. Installation of the machine lifting


tool and the bedplate
Position the lift car frame so that the car
top is level with the top landing.
Install the drive unit mounting fixture,
supported on the car frame so that it
runs guided between the car guide rails.

Rev.: 0 Installation Procedure 52 / 76


SILENS PRO Compact

With the running fully carriage retracted,


install the bedplate on the securing
bracket (A), and bolt the bottom and
back sections to it using four M12 bolts
(B).

Rev.: 0 Installation Procedure 53 / 76


SILENS PRO Compact

"All the structural components of the


bedplate are joined together using 12
metric bolts and self-locking nuts. The
radial dampers will be fixed with
M14x70 bolts (the bolt on the back
must be installed upwards so it can be
uninstalled once the drive unit has been
installed). The slack rope actuator
will be fixed sideways with M6 bolts.
Install the fixed section of the bedplate:
central section, fixing brackets, radial
dampers without upper safety ends (A)
(only with the M14 bolts so that they
serve as a guide when positioning the
drive unit on the bedplate) and guide rail
supports (B). Install the bolts of the
guide rail brackets so that their heads
are facing the lift car (C).
Fix the guide plate on the bedplate to
install the dampers (D).
Fit the dampers used to support the
drive unit onto the bedplate (E).

Rev.: 0 Installation Procedure 54 / 76


SILENS PRO Compact

Using the hook installed by the builder


at the top of the shaft, fit the drive unit
with the plate on the bedplate. Fit the
front bedplate safety casing (A) and the
back safety washer (B). Hoist the car
frame until the bedplate is higher than
the upper end of the guide rails. Push
the running carriage so that the guide
rails are positioned between the side
support brackets of the bedplate.

Rev.: 0 Installation Procedure 55 / 76


SILENS PRO Compact

Fix these support brackets to the upper


drill holes of the car frame guide rails
with M12 bolts and to the counterweight
guide rails with M8 bolts (A). Release
the bedplate of the tool support bracket
and collect the carriage. Place and fix
the set-off brackets to wall (B) with M10
wall fixings. Install the rope anchorage.
Fit the wedge socket damper of the car
frame side (C), with its upper plate (D).
Install slack rope if applicable (E).

Rev.: 0 Installation Procedure 56 / 76


SILENS PRO Compact

Fix the upper support bracket of the


overspeed governor tensioner (A) to the
bedplate. If the tensioner is horizontal,
fit the special securing bracket (B) on
the support bracket. Use M8 bolts.
Fix the tensioner (C) to the support
bracket. If the tensioner is horizontal
and the distance between the guide rails
is 650mm, remove the sheave
protection from the drive unit.
Release the belt from the guide rail
support bracket used during the
installation and fix it to the bedplate
tensioner. Uninstall the guide rail
support bracket.
Lower the car until the car top is level
with the top landing and uninstall the
entire hoist mounting assembly.
Install the control cabinet in the position
indicated on the general plan.
Power up the drive unit from the control
cabinet and check that it operates
correctly.

Rev.: 0 Installation Procedure 57 / 76


SILENS PRO Compact

13. Installation of hoist roping


Set the lift car frame onto the pit
damper.
Using the winch, hoist the counterweight
until its lower crosspiece assembly is at
800mm from the pit damper’s lower
support (950mm in the case of
restricted overhead clearance). Use a
sling around the crosshead of the
counterweight frame, taking special
care in placing it in the sheave assembly
area where there is no lower flange so
as to avoid any flange deformation. Fit a
sling over a bracket to hold the
counterweight in the position indicated,
or place a prop below the
counterweight.
Fit the ropes around the car frame
sheave and place the free ends onto the
car top, with the roping carefully coiled
so as to avoid any damage as the car
moves through the shaft. Fit and fix the
sheave rope guards of the car frame
sheave crosspiece (A), and the sheave
safety guard (B).

Rev.: 0 Installation Procedure 58 / 76


SILENS PRO Compact

Attach the winch back onto the car


frame sheave crosspiece and hoist it to
the top of the shaft, in such a way as to
leave comfortable space for working on
the bedplate.
Install the anchorage wedge sockets on
the car frame side (A) and fix one end of
each rope to one, using the rope grips
(one per socket) (B).
Pass the other end of each rope through
the drive unit sheave and then hang the
ropes down the full height of the shaft.
Pass the ropes around the
counterweight sheave and then hoist
the ropes up again to the top of the
shaft.
Set the car so that its floor is 600mm
below the top landing.
Install the wedge sockets on the
anchorage on the counterweight side (C)
and fix the ropes to them using the rope
grips (one per socket) (B). Attach and fit
the slack rope activation rings, if
applicable (D).

Rev.: 0 Installation Procedure 59 / 76


SILENS PRO Compact

14. Tensing the roping


Check that when the car frame is flush
with the lower level there is a distance
of 60mm between the pit damper and
the support bracket on which it collides
(25mm in the case of a pit no deeper
than 400mm). Also check these
distances in the counterweight, when
the lift car is at the top landing level.
Place the remaining weights in the
counterweight frame and fit the
restraint brackets which ensure that
they are kept in place (A).
If appropriate, place the special weights
on the standard weights (B). Fix them
using the special rods and nuts provided
for this purpose (C).
Disconnect the winches and uninstall
the car hoist mounting at the top of the
shaft. Release the counterweight or
remove the prop, whichever is
applicable. From this moment on, use
the lift drive unit to move the car
through the shaft during the remainder
of the installation process.

Rev.: 0 Installation Procedure 60 / 76


SILENS PRO Compact

15. Installation of travelling cable and


inspection box. Installation of limit
switch skate.
Install the inspection box on the car top
guard rail (A) or on the car top itself.
Install the travelling cable between the
inspection box and the control cabinet.
Fix it to the underside of the car frame
using one of the wedge clamps supplied
for that purpose, fixing the wedge clamp
to the side of the car’s lower support
member (B). Attach the cable to the
shaft using the rest of the plastic wedge
clamps.

Rev.: 0 Installation Procedure 61 / 76


SILENS PRO Compact

Install the limit switch skate (A) on the


upright of the car frame, according to
the position indicated on the general
installation drawing. If the limit switch
skate collides with the bedplate or any
of the brackets, refit the skate at a
height using the pre-drilled holes in the
uprights for this purpose.

Rev.: 0 Installation Procedure 62 / 76


SILENS PRO Compact

16. Installation of landing doors


Install the landing doors, starting from
the top landing and using the sill of the
lift car base as a reference point (see
the general installation plan and the
door installation manual).

Rev.: 0 Installation Procedure 63 / 76


SILENS PRO Compact

17. Installation of conduits, shaft


lighting and external electrical system.
Installation of pit access ladder
Install the conduits through the full shaft
height. Install the shaft lighting system
(see the general plan).
Install the electrical wiring and connect
the door switching to the control
cabinet. Install the landing push-button
panels.
Install the pit access ladder in the
position marked on the general
installation plan.

Rev.: 0 Installation Procedure 64 / 76


SILENS PRO Compact

18. Installation of safety connections


and limit switchs.
Install and wire up (if applicable) all the
electrical connections in the upper part
of the shaft: overspeed governor
tensioner (A)/(B), slack rope (if
applicable) (C). Install the emergency
stop device next to the drive unit. Fit the
upper limit switch (D) with its guide rail
bracket onto the car frame guide rail on
the side on which the limit switch skate
is installed, in the position indicated on
the general plan. Install and wire up
(where applicable) all the electrical
connections in the pit: the overspeed
governor tensioner (A)/(B), ladder switch
(if applicable). Install the emergency
stop device, and the shaft lighting
socket and switch, accessible from the
entranceway.
Fit the lower limit switch (D) with its
guide rail bracket onto the car frame
guide rail on the side on which the limit
switch skate is installed, in the position
indicated on the general plan.

Rev.: 0 Installation Procedure 65 / 76


SILENS PRO Compact

19. Installation of remaining car and


counterweight accessories
Install the overload monitor onto the
lower car frame crosspiece and set the
switch (A).
Fix the grease fittings onto the upper
guide shoes of the car frame (B) and the
counterweight (C).
Install the car frame rope protection
fittings (D).
Install the compensation chain (if
applicable) on the side of the car frame
(E)with the U-bolt and on the
counterweight side (F) with M16 bolts
fixing the chain directly onto the
crosspiece (without the U-bolt). Install
the oil drip trays (if applicable) on the
baseplates.
Clean the shaft and clear out all surplus
material.
Check lift operation at its rated speed.

Rev.: 0 Installation Procedure 66 / 76


SILENS PRO Compact

20. Installation of door operator.


Installation of sensors, bistable relays
and magnets
Install the car door(s) and operator(s).
Connect the operators to the inspection
box.
Install the door area’s magnetic sensor
on its bracket onto the car frame upright
(A) with M6 bolts and the speed-change
bistables on their brackets (B) onto the
sling upright with a M10 bolt. Fit the
stop magnets directly onto the car
frame guide rail onto which the sensor
was installed. Attach the magnets of the
bistables to their brackets (C) and fix
them to guide, in the positions indicated
on the general installation plan and in
the electrical documentation.
Where advance door opening is
specified, fit the two magnetic sensors
over the door area sensor(D).

Rev.: 0 Installation Procedure 67 / 76


SILENS PRO Compact

21. Installation of car lighting and car


operating panel. Connection of
components to inspection box
Fit the car operating panel. Establish all
the electrical connections between the
lift car and the control cabinet: the coil
of the overspeed governor, the safety
gear switch, the overload monitoring
device, the car operating panel, the
mechanical stops’ switches, the lighting,
the guard rail and hatchway switches (if
applicable), the magnetic sensors and
bistables.
Correct door settings.

Rev.: 0 Installation Procedure 68 / 76


SILENS PRO Compact

22. Check system function in normal


operation

23. Final counterweighting (see Lift


Counterweighting Manual)

24. Lift car levelling


Level the lift car: start from the bottom
landing, travelling upwards floor by
floor, fixing the stop magnets in the
positions making the car stop level with
each landing. Once levelled in upward
travel, repeat the same operation
travelling downwards, but without
changing the positions of the magnets:
in each case, shorten or add to their
length as required so as to ensure that
the car stops perfectly level with each
landing.

Rev.: 0 Installation Procedure 69 / 76


SILENS PRO Compact

25. Fitting of car aprons and


counterweight protection in the pit
Install the car skirtings.
Install the counterweight protection,
connecting all the components with M6
bolts. Remove the curled edges from the
sides of the safety casing (A) where it
rubs against brackets.

Rev.: 0 Installation Procedure 70 / 76


SILENS PRO Compact

26. Installation of EN 81-21


compensatory safety measures
Where there is a reduced pit of a depth
of over 850mm, attach the push-in
skirtings and install the electrical safety
switches on them.
Where there is a reduced pit with a
depth of less than 850mm, as well as
the push-in skirtings, fit the
maintenance pillar (A) below the car
frame base and install the control
switches (B). At the same time, fit the
inspection switch with its guide rail
bracket (C) on the side the limit switch is
positioned at the height indicated on the
general installation drawing.

Rev.: 0 Installation Procedure 71 / 76


SILENS PRO Compact

When the depth of a reduced pit is less


than 850mm, also install the accessory
(A) with the damper (B) under the car
frame base.

Rev.: 0 Installation Procedure 72 / 76


SILENS PRO Compact

In the event of reduced overhead


clearance, fit the maintenance pillar (A)
below the counterweight and install the
control switches (B). At the same time,
fit the inspection switch with its guide
rail bracket (C) on the side where the
limit switch is positioned at the height
indicated on the general installation
drawing.
Where both pit depth and overhead
clearance are restricted, implement the
compensatory measures already
described for both conditions.

Rev.: 0 Installation Procedure 73 / 76


SILENS PRO Compact

27. Final inspection


Carry out all the checks indicated in the
Final Inspection protocol and required in
order to put the lift system into
operation.

Rev.: 0 Installation Procedure 74 / 76


SILENS PRO Compact

This section includes all the


documentation related to the
8 – ELECTRICAL DOCUMENTATION installation of the electrical aspect of
the lift system and to the distinct
operational options specific to the
design of the particular lift system
ordered.

Rev.: 0 Electrical documentation 75 / 76


SILENS PRO Compact

The documentation supplied with each lift system includes all the specific electrical documentation required for the correct
installation of the said system.

The manufacturer accepts no


responsibility whatsoever for the
incorrect application of the instructions
included in the electrical documentation
or for any unilateral modification of any
component without the said
manufacturer’s previous approval.

Rev.: 0 Electrical documentation 76 / 76

You might also like