Professional Documents
Culture Documents
DM001 F All MPS WPS DCC 400003 PDF
DM001 F All MPS WPS DCC 400003 PDF
Document Title:
Revision History
E
D
C
B
A1 First Issue N/A N/A
MARK DATE DESCRIPTION RAIL CIVIL
DM001/F/ALL/MPS/WPS/DCC/400003 A1
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
-i-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
4. SUBSOIL INVESTIGATION
5. TRANSFORMER COMPOUNDS
8. PILING
8.1 Standards
8.2 General Requirements
8.3 Proprietary Piling Systems
-ii-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
10. CONCRETE
10.1 Design, Materials and Workmanship
10.2 Testing
10.3 Cement
10.4 Cement Test Certificate
10.5 Cement Samples
10.6 Cement Storage
10.7 Aggregates
10.7.1 Aggregates - Physical Requirements
10.7.2 Aggregates - Chemical Requirements
10.7.3 Aggregate Storage
10.7.4 Aggregate Sampling
10.8 Approval of Materials
10.9 Water
10.10 Admixtures
10.11 Supervision
10.12 Plant
10.13 Concrete Strength Requirements
10.14 Concreting in hot weather
10.15 Concrete Mixing
10.16 Workability
10.17 Transport and Placing
10.18 Compaction of Concrete
10.19 Vibrators
10.20 Construction Joints
10.21 Construction Bays
10.22 Curing
10.23 Trial Mixes
10.24 Works Test Cubes
-iii-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
12. WATERPROOFING
12.1 Generals
12.2 Submittals
12.3 Materials
12.3.1 Roofing Membrane
12.3.2 Separation Layer
12.3.3 Insulation Board
12.3.4 Primer
12.3.5 Rainwater Outlet
12.3.6 Mortar and Tiles
12.3.7 Waterproofing of cable basement, oil/water tank, septic
tank, etc.
12.4 Workmanship
-iv-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
12.4.1 Storage
12.4.1 Installation
12.4.2 Tests
13. METALWORK
14. BLOCKWORK
14.1 Cement
14.2 Sand and Aggregates
14.3 Concrete Blocks
14.4 Mortar for Blockwork
14.5 Jointing
14.6 Block Laying
14.7 Protection Against Damage
14.8 Precautions During Inclement Weather
14.9 Damp Proof Course
-v-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
16.4 Faults
16.5 Builder's Ironmongery
17. GLAZING
17.1 General
17.2 Clear Glass
17.3 Wired Glass
17.4 Tinted Glass
18. PAINTING
18.1 Paint
18.2 Emulsion Paint
18.3 Oil Paints
18.4 Painting of External Surfaces
18.5 Wood Finishes
18.6 Bituminous Paints
18.7 Workmanship
18.7.1 Storage
18.7.2 Generally
18.7.3 Ironmongery and Fittings
18.7.4 Preparation of Surfaces
18.7.5 Preparation of Paints
18.7.6 Conditions of Applications
18.7.7 Application of Paint
18.7.8 Re-premixing
18.7.9 Undercoats
18.8 Specific Surface Coatings
18.8.1 Woodwork
18.8.2 Iron and Steel Work
18.8.3 General
-vi-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
19.4 General
19.5 Concrete Bed and Casings
19.6 Testing
19.7 Cable Ducts
19.8 Manholes
19.9 Manhole Covers
21. PLUMBING
-vii-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
-viii-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
-ix-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
INDEX
SECTION TITLE
24. CRANE
26 LIST OF REFERENCES
26.1 Civil Works
26.2 Lighting and Small Power
-x-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
-1-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
1.3 Tender Conditions, Drawings, Schedule of Rates
The General Conditions, Tender Drawings and Schedule of Rates shall be
read in conjunction with this Specification. Matters described in one
are not necessarily repeated in the others.
The tender drawings show general layouts, architectural features and
facilities to be provided. The drawings indicate the scope of the
Works and tenders must comply with this, minimum requirement, however
room
1.7 Records
The Contractor shall keep at the site accurate and up to date records
and drawings of the works, and shall provide the Engineer with copies
of these records. At the end of every week the Contractor shall submit
to the Engineer returns of labour, plant and materials employed on the
site during that week. At the conclusion of the Civil Engineering and
building construction works, the Contractor shall supply reproducible
-2-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
copies of all drawings, showing full details of the works as
constructed, including location of drains, services, foundations,
roads, etc.
-3-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor should ascertain for himself during the tender stage
that the plant he proposes to supply will be suitable for the
arrangements shown on Specification Drawings, and the Contract Price is
deemed to include the cost of any enlarged buildings or modified layout
to meet the Employer's design parameters. Failure of the Engineer or
Employer to comment on drawings submitted by the Contractor during the
tender stage which show modified arrangements not complying with
Specification Drawings and design parameters shall not be accepted as
approving such arrangements; any modifications proposed should be
clearly stated in the Schedule of Deviations.
Particular attention should be given to the positioning of doors,
windows and louvers to minimise the effects of sandstorms and salt
laden spray and winds from the sea. Cladding, flashing and the like
shall be as tightly fitting as practicable so as to exclude pollution
under all likely local weather conditions. All external doors shall
have canopy/protection and be sealed to prevent ingress of dust and
wind blown rain water, using heavy duty seals which shall have
canopy/protection and be guaranteed for a minimum period of five years
from date of commissioning. The doors and seals shall be designed so
that replacement of worn seals can be achieved easily on site.
2.5 Services
-4-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor shall be responsible for the provision of services in
accordance with the Contractual General Requirements Sections of this
Specification.
-5-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
2.9 Foundations
Foundations shall be capable of restricting settlements and other
movements in service to acceptable limits for the equipment or
superstructure to be erected thereon.
All foundations shall be in reinforced concrete. The minimum cover to
reinforcement shall be 75 mm and the cement shall be of a type
appropriate to the ground conditions. Extent of foundation for each
building/structure should, unless otherwise agreed, be restricted
within the periphery of the building/structure.
Where the ground is excavated for any reason below the underside of the
proposed foundation the void shall be filled with weak concrete.
2.11 Buildings
The general layouts of buildings are to be maintained as shown, but
minor modifications may be made to provide buildings wholly suitable
for the equipment being provided by the Contractor to satisfy the
requirements of other parts of the Specification.
All buildings shall be designed to have reinforced concrete frames,
with infill panel walls of concrete blockwork. External walls shall be
cavity concrete blockwork, each leaf being 100 mm minimum thickness,
with 50 mm insulation and approved ties between leaves.
Switchgear buildings shall be designed to withstand pressure due to
internal arcing or arragement shall be made for pressure release in
such an event by providing wall dampers. Parameters considered in the
building design shall be subject to DEWA's approval.
Particular attention must be given in the design of buildings and
layouts to fire prevention and safety of personnel at all times.
Buildings housing switchgear and control equipment shall be designed as
far as practicable to exclude pollution under all likely weather
conditions. Fire-proof or flame-retarding materials are to be used for
floor, wall and ceiling finishes. Where areas are designed as having a
fire resistance rating then materials shall be shown to have passed
approved standard tests for that class of fire resistance.
-6-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
All floor slabs shall be constructed of reinforced concrete supported
on reinforced concrete beams. Floor finishes will be designed to
provide high impact and abrasion resistance. The finishes shall be in
accordance with the schedule of finishes.
-7-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
All roofs shall be impervious to rain and provide a rapid run-off of
rain water.
Special attention shall be given to the waterproofing of all roofs;
sealing of all joints; allowance for thermal and shrinkage movements.
Roof drainage shall be constructed so that water will not enter the
building in the event of blockages. Rainwater down pipes shall be
external to the buildings.
Toilets shall be provided with , 1 No. Asiatic type WC, 1 No. wash-hand
basin, 1 No. wall mounted mirror. WC shall be provided with a hand
spray. All necessary fittings and accessories shall be provided.
Battery rooms shall be supplied with sink and drainer and eye wash
facility..
Cable basements, 2 m high clear below beams, shall be provided for the
complete width of the substation buildings, under the switch room
section. Precautions must be taken to waterproof both the walls and
the floor slab to ensure that no water can permeate into the basement
structure. The basement shall be divided with fire compartment barrier
walls and interconnecting doors. Provisions shall be made for access
from the ground floor, into various sections of the basement, via
hatches and permanent ladders.
Where cables enter the building all ducts and trenches shall be sealed;
the ends of all ducts entering trenches shall be bell-mouthed. The
-8-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
floor shall be screeded, the walls finished as per the schedule of
finishes.
-9-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor is responsible for all civil works required for the
installation of cables. Cable entries into buildings shall be through
ducts or in cable trenches. All cable runs in buildings shall be
within the cable basement or in trenches, provided with checker plate
covers. The covers for external cable trenches shall be of precast
concrete. All cable trench covers shall be of suitable weight and size
such that they may be removed or replaced by no more than two men
without the use of a crane or special lifting equipment.
The pump house shall be a single storeyed building near the fire water
tank and shall house the fire water pumps and associated
interconnecting pipework, controllers and shall have a room for the
operators. The pump house shall be of reinforced concrete construction
with blockwork infill panels. The features of the pump house shall be
generally similar to the main substation building.
Stairs to equipment rooms and loading areas shall have non slip epoxy
screed finish. Threshold to doors shall be of marble.
The Engineer shall have the right to order that any materials which do
not meet with his approval shall not be used in the works. The
Contractor shall have the right to sample, test and give an opinion on
such materials. If after this the materials are rejected by the
Engineer they shall be removed from the site by the Contractor.
Samples of materials approved shall be made available.
The Contractor shall design the civil engineering and building works
and prepare complete working drawings as necessary for the construction
of the works.
-10-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
3.2 Liability
Civil engineering and building works and services shall all be designed
and constructed in accordance with the relevant British Standard or
equivalent approved Codes of Practice for the purpose of satisfying the
Building Regulations of the Dubai Municipality and obtaining the
necessary Building Permit approval from the Local Authority as required
and provide supervision fulfilling Dubai Municipality’s requirements.
-11-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
revision following the Engineer's initial review. Design calculations
shall be in accordance with an approved method of computation and
should take account of the most unfavourable combination of dead load,
live load, wind load. Live loads shall be in accordance with BS.6399
Part 1. A basic wind speed (3 set gust 1-in-50yr return period) of 45
m/s at a height of 10 m above ground level shall be assumed. The
design of all buildings, structures and components shall resist wind
loads calculated in accordance with British Standard CP3 Chapter V,
Part 2.
The minimum design live load on all floors shall be based on the static
and dynamic loadings from the equipment to be installed with due
consideration for future addition/replacement with equipments of the
same manufacturer but also of other standard products. Floors of the
GIS room, 11kV switch gear rooms and control rooms shall be designed
for a minimum live load of 8KN/sqm or actual equipment load whichever
is greater.
The Contractor shall make any changes in the design which are necessary
to make the work conform to the provisions and intent of the Contract.
Calculations
⇒ Contractor's name
⇒ Project name
⇒ Designer's name
⇒ Checker's name
⇒ Contract number
-12-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
⇒ Name of the item
⇒ Assumption used for design purposes
⇒ Codes used
⇒ Loadings used
⇒ Date of Calculation
⇒ Calculation
⇒ Reference sources
⇒ Manufacturers' names and literature
⇒ Reference to the appropriate drawing
⇒ Technical specification section and paragraph number
⇒ Control register reference all as applicable.
Drawings
-13-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
For calculating the maximum dimensions the following definitions shall
apply :-
(a) "Area", in relation to a building, means the area calculated by
reference to its finished internal faces:
(b) "Basement" means a storey of which the floor is at any point more
than 1.2 metres below the finished surface of the ground adjacent
to it.
(c) "Floor area" means the aggregate area of every floor in a
building or extension, calculated by reference to the finished
internal faces of the walls enclosing the areas, or if at any
point there is no such wall, by reference to the outermost edge
of the floor.
(d) "Height" means the height of the building measured from the mean
level of the ground adjoining the outside of the external walls
of the building to the level of half the vertical height of the
roof of the building, or to the top of the walls or of the
parapet, if any, whichever is the higher.
To restrict the spread of fire, certain walls and floors shall be
designated as fire compartment barriers. Fire compartment barriers
shall provide complete barrier to spread of smoke heat and other
products of combustion. The barriers shall have a rating of 2 hours
minimum. All openings in walls/floors for entry/exit of cables shall
be sealed with approved fire sealant rated for minimum 2 hours.
3.10 Drainage
Drainage shall be designed in accordance with relevant Codes of
Practice published by the British Standards Institution, viz : BS 6031,
BS 6367 and BS 8301.
In the neighbourhood of embankments and cuttings surface water run-off
is to be controlled by the provision of lined drainage channels.
Provision shall be made for the disposal of surface water from roads.
-14-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Roofs 75 mm/hr
Site 15 mm/hr
Septic Tank and Soakaways for foul drainage as well as storm water
drainage shall be located giving due consideration and with
consultation/approval of the local Authorities so that in future when
main sewerage/storm water drainage net work for the area is made
available these services may be connected to the main line easily.
3.11 Foundations
4 SUB-SOIL INVESTIGATIONS
5 TRANSFORMER COMPOUNDS
-15-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
i) Where access to the transformer enclosures is from within the sub
station and front elevation is not prominently visible from out
side, the rooms shall be enclosed with removable galvanized mesh
fencing of opening size not more than 25 x 25x 3.5 mm for full
height having lockable mesh access gates.
Provision shall be made for the catchment of oil spillage and fire
deluge water from the transformers resulting from mechanical or
electrical failure. Precautions shall be provided to prevent pollution
of streams, ground water, irrigation ditches and other watercourses by
leaking or ejected oil.
are to finish at a level 150 mm below the top level of the oil
retaining wall. A sump is to be provided in one corner of the oil pit,
to facilitate removal of the oil or water by suitable pump to be
provided. A gauge to indicate the level of water inside the oil water
tank to be fixed at convenient location to the Engineers approval.
Attention should be paid to the separation of water and oil in the
sump.
The Contractor is responsible for the accuracy of all setting out and
construction as follows: -
-16-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
7.1 Backfill
The Contractor shall allow for risk of meeting and having to excavate
through any sort of material including rock.
-17-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor shall at all times keep the site free from all surplus
materials, rubbish and offensive matter.
The bottom of all excavated areas shall be trimmed, levelled and well
rammed.
7.5 Dewatering
The excavated surfaces shall be kept dry and clean by pumping or any
other method deemed necessary and approved by the Engineer. Water from
such dewatering shall be properly drained away from the site and
disposed of off site, so as not to inconvenience users of adjacent
properties or sites. Water table to be brought down to minimum 300 mm
below the foundation level.
Should any slips occur in the excavations, banks or filling during the
execution of the works or during the Defects Liability Period from any
cause whatsoever, the Contractor shall execute the necessary remedial
works in such manner and form, and with such materials as the
Engineer's Representative shall approve.
The Contractor shall make good all settlement of filling that may occur
up to the issue of the last Final Certificate.
7.8 Explosives
-18-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Contractor shall remain responsible for their use including injury to
any person or any damage to property, and for their safe storage. The
Contractor shall make his own arrangements for the safe storage, the
Two numbers of water outlets with valve control suitable for taking one
inch water connection shall be provided just outside the main
transformer cells.
8 PILING
8.1 Standards
Piling work, materials and tests shall comply with the following Codes
of Practice and Standards, together with all Statutory Regulations:
Title Subject
The piles shall be designed to carry at least twice the working load
and this shall be determined by normal design procedures.
The pile shall be adequately anchored into pile caps in accordance with
seismic design practice.
-19-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
9 ROADS AND OTHER SURFACES
9.1 General
-20-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
9.2 Materials
Broken stone and chippings for use as site surfacing shall consist of
hard crushed natural stone.
Bituminous wearing courses for approach roads shall be suitable for the
high temperatures experienced in the area and shall comply with an
authoritative and approved standard appropriate to the locality of the
Work. The details and grading of the aggregate and the binder contents
shall be submitted to the Engineer for approval. Sealing grit shall be
applied as required.
All drains, sewers, cable ducts and other necessary work below
formation level shall be completed, inspected and passed by the
Engineer before the construction of any road or path is started.
9.5 Sub-base
After the formation has been properly made, rolled and approved by the
Engineer, a sub-base consisting of well graded natural sands, gravels
or rock or mixtures thereof shall be laid and compacted to minimum 95%
of MDD, to give a finished thickness of at least 200 mm or as described
or directed.
75 mm 100
37.5 mm 85 - 100
10 mm 40 - 70
5 mm 25 - 45
0.6 mm 8 - 22
0.075 mm 0 - 10
-21-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The formation and sub-base for road areas with interlock paving blocks
shall be as described in Clauses 11.9.4 and 11.9.5 above. Interlock
paving blocks shall be placed in a herring bond pattern on a 4 cms
laying coarse of coarse sand above the sub-base.
9.9 Crossfall
In the case of roads with a straight crossfall, this fall shall be not
more that 1 in 40 and not less than 1 in 48. With roads to be cambered
the average fall of the finished surface from the crown to the road
edge shall be not more that 1 in 30 and not less than 1 in 45.
9.10 Kerbs
Where concrete covers are required for trenches crossing roads, these
shall be designed for the heavy wheel loads expected on them and shall
be specially reinforced as necessary.
10 CONCRETE
-22-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Construction practices shall conform to the recommendations given in
the CIRIA Guide to concrete construction in the Gulf Region Special
Publication 31, 1984.
10.2 Testing
10.3 Cement
The Engineer shall have the right to require the Contractor at any time
to draw samples of cement from locations to be specified by the
Engineer.
10.7 Aggregates
Before the Engineer can approve any aggregate source the contractor
shall furnish the following data:-
-23-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
v) Silt content
vi) Grading curves
vii) Specific gravity
viii) Impact value
ix) Water absorption
x) Soundness
xi) Salt content
xii) Alkali reactivity
The fine and coarse aggregates shall comply with BS.882, and the
Clauses below, unless exceptions listed by Tenderers in the attached
schedule are approved by the Engineer.
Marine aggregates may be used when their chloride content complies with
the clause on "Chemical Requirements" below and where the shell content
does not adversely affect the workability of the concrete.
ii) The weight of the clay and fine silt fraction (smaller than
A.S.T.M. sieve No.200) shall not exceed 1% by weight for coarse
aggregates or 3% by weight for fine aggregates.
iii) Absorption of fine and coarse aggregate shall not exceed 2.5%
as measured in accordance with BS.812 or similar standard.
ii) Fine and coarse aggregates shall not contain more than 0.4% by
weight of acid soluble sulphates (as S03).
-24-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Engineer shall have the right to require the Contractor at any time
to draw samples of aggregates from Stockpiles on the site or any other
locations to be indicated by the Engineer. Testing is to be carried
out at an independent laboratory approved by the Engineer.
The Engineer shall have the right to order that any materials which do
not meet with his approval shall not be used in the Works. The
Contractor shall have the right to sample, test and give an opinion on
such materials. If after this the materials are rejected by the
Engineer they shall be removed from the site by the Contractor.
Samples of materials approved shall be made available at site.
10.9 Water
The water used for making concrete, mortar and grout shall be clean,
fresh and free from injurious amounts of oil, vegetable or organic
matter or any other deleterious substance in suspension or solution.
The mix water shall be continually monitored for salt content and the
concrete mix designed accordingly to limit total salt content. The
water should comply with the requirements of BS.3148.
10.10 Admixtures
-25-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Admixtures shall not be used without the approval of the Engineer. The
self retarding and water reducing admixtures where used shall be free
of chlorides and consist of Ligno-sulphonate.
10.11 Supervision
The Contractor shall employ at the Works a competent person whose first
duty shall be to supervise all stages in the preparation, placing and
curing of concrete. All test cubes shall be made and site tests carried
out under his direct supervision.
10.12 Plant
The concreting plant shall be suitable in type, capacity and design for
its purpose. The performance of the plant and its disposition shall be
to the satisfaction of the Engineer.
Due allowance must be made for the free water contained on surface-wet
or saturated aggregates, as outlined in the above publication.
(a) data showing that the proposed mix proportions and method of
manufacture will produce concrete of the required quality with the
intended workability, or
-26-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
(c) Wherever possible all small pours should be carried out as late as
possible in the afternoon.
10.16 Workability
-27-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The concrete shall be discharged from the mixer and transported to the
Works by means that shall be approved by the Engineer and which shall
prevent adulteration, segregation or loss of ingredients, and ensure
that the concrete is of the required workability at the point and time
of placing.
Where chutes are used to convey the concrete, their slopes shall not be
such as to cause segregation and suitable spouts or baffles shall be
provided to obviate segregation during discharge. Concrete shall not
be allowed to fall freely more than 1.5 metres except with the approval
of the Engineer. Where pneumatic placers are used the velocity of
discharge shall be regulated by suitable baffles or hoppers where
necessary to prevent segregation or damage and distortion of the
reinforcement, other embedded items and formwork, caused by impact.
The kickers for RCC walls shall not be less than 150 mm high and
shall be cast monolithically with the base.
-28-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The concrete shall be fully compacted throughout the full extent of the
layer. It shall be thoroughly worked against the formwork and around
reinforcement and other embedded items, without displacing them.
Successive layers of the same lift shall be thoroughly worked together.
10.19 Vibrators
When not indicated on the drawings the following general rule shall
apply:-
When work is resumed adjacent to a surface which has set the whole
surface shall be thoroughly roughened. It shall be cleaned of all loose
and foreign matter and laitance and washed with water immediately
before placing the fresh concrete,which shall be well compacted against
the joint.
-29-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
-30-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor shall agree with the Engineer, prior to the commencement
of concreting, upon the sequence of placing concrete and the positions
of vertical and horizontal joints, whether shown or not on the
drawings.
10.22 Curing
The curing of the concrete shall be maintained for at least ten days
after which time the concrete shall remain covered for a further four
days.
The Contractor shall submit not less than 3 weeks before the
commencement of manufacture of preliminary trial design mixes the
following information to the Engineer in respect of each grade of
concrete.
-31-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The Contractor shall also confirm his proposed testing regime and
acceptance criteria for the Preliminary Trial Mixes. Should the
proposals not be approved by the Engineer, then the Contractor shall
comply with the paragraph on preliminary test cubes and the two
following paragraphs below.
At least four weeks before commencing any concreting in the Works, the
Contractor shall make trial mixes using samples of aggregates and
The current margin for each particular type of concrete mix should be
determined; it may be taken as having the smaller of the values given
by (i) or (ii).
(i) 1.64 times the standard deviation of cube tests on at least 100
separate batches of concrete of nominally similar proportions of
similar materials and produced over a period not exceeding 12
months by the same plant under similar supervision, but not less
than 1/6 of the characteristic strength for concrete of grade 7,
10 or 15, or 3.75N/mm2 for concrete of grade 20 or above.
-32-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
or ii) above. However, when the required characteristic strength
approaches the maximum possible strength of concrete made with a
particular aggregate, a smaller margin but not less than 7.5N/mm2 may
have to be permitted for the initial mix design.
At each age of test no cube strength shall fall below the appropriate
minimum specified in the Contractor's designs.
Before commencing the Works the Contractor shall submit to the Engineer
for his approval full details of the mixes he proposes to use, with
their anticipated average strength, which must be based on the
satisfactory results of these preliminary tests.
The Contractor shall inform the Engineer of his intention to carry out
such tests and the time and place of the tests at least 24 hours before
they take place.
Neither the mix proportions nor the source of supply of materials shall
be altered without the prior approval of the Engineer except that the
Contractor shall adjust the proportions of the mix as required, to take
account of permitted variations in the materials. Such approval shall
be subject to the execution, to the Engineer's satisfaction, of trial
mix procedures set out herein.
-33-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Reports of all tests made shall be supplied direct from the laboratory
to the Engineer within 24 hours of the cubes being tested. The
Engineer's Representative on site shall have the authority to stop all
further concrete work until acceptable test results are forthcoming.
Neither the mix proportions nor the source of supply of materials shall
be altered without the prior approval of the Engineer, except that the
Contractor shall adjust the proportions of the mix as required, to take
account of permitted variations in the materials. Such approval shall
be s ubject to the execution, to the Engineer's satisfaction, of trial
mix procedures set out herein.
If the specified requirements have not been met, the Contractor shall
take such remedial action as may be required. Before proceeding with
concreting, the Contractor shall submit for the Engineer's approval
details of the action proposed to ensure that the concrete to be placed
in the Works shall comply with the Specification.
10.28 Formwork
The material and position of any ties passing through the concrete
shall be approved by the Engineer. The whole or part of the tie shall
be capable of being removed so that no part remaining embedded in the
concrete shall be nearer the surface of the concrete than the specified
-34-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
thickness of cover to the reinforcement. Any holes left after the
removal of ties shall be filled, unless directed by the Engineer, with
concrete or mortar of approved composition.
All forms shall be removed without damage to the concrete. The use of
mould oil or other material to facilitate this shall be subject to the
approval of the Engineer.
Before soffit forms and props are removed the concrete shall be exposed
by removal of the side forms or otherwise as required by the Engineer,
in order to ensure that it has sufficiently hardened. The forms shall
not be struck until the concrete has reached a cube strength of at
least twice the stress to which the concrete may be subject at the time
of striking. The formwork to vertical surfaces may be removed after 24
hours in normal weather conditions (over 15°C).
All form work for pits, ducts and holding down boltholes must be so
constructed that it can be easily collapsed to facilitate withdrawal
after the initial set of the concrete.
The Contractor's proposed method for the construction and fixing of the
formwork for bolthole pockets shall be submitted to the Engineer for
approval before construction. The top of the shuttering shall be
suitably covered to prevent entry of excess grout, materials used for
curing etc.
Solid timber must not be used for forming holding down boltholes.
Bolthole formers may be made of plywood, expanded metal, polystyrene or
other method approved by the Engineer, who may require the Contractor
to carry out a test pour, using the proposed bolthole former.
Minimum Period before Striking Formwork.
-35-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
-36-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
10.30 Finishes
The Contractor shall state precisely on his plan which of the types of
finishes described hereunder he intends to use in the various
locations. Any defective concrete finish will be rejected. The
Engineer may at his discretion order the defects to be cut out and made
good.
10.31 Chamfers
Type F.2 - This finish is for surfaces which are normally exposed to
view but where the highest standard of finish is not required. Forms
to provide Type F.2 finish will be faced with wrought and thickened
boards with square edges arranged in a uniform pattern. Alternatively,
plywood or metal panels may be used if they are free from defects
likely to detract from the general appearance of the finished surface.
Joints between the boards and panels shall be horizontal and vertical
unless otherwise directed. This finish shall be such as to require no
general filling of surface pitting but fins, surface discolouration and
other minor defects shall be remedied by methods approved by the
Engineer.
-37-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Type U.2 - This is a floated finish for surfaces of beds and slabs to
receive mastic pavings or block or tile pavings where a hard smooth
steel-trowelled surface is not required. Floating shall be done only
after the concrete has hardened sufficiently and may be done by hand or
machine. Care shall be taken that the concrete is worked no more than
is necessary to produce a uniform surface free from screed marks.
10.35 Reinforcement
Mild steel and high yield steel bars and steel fabric shall comply with
relevant approved standards. Foundation and substructure reinforcement
shall be deformed bars. Test certificates for each consignment
delivered shall be supplied by the Contractor.
All reinforcement shall be free from oil, grease, paint, dirt, loose
scale or rust at the time of concreting.
-38-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Reinforcement shall be rigidly fixed in the positions shown on approved
drawings, using soft pliable annealed steel coated binding wire of 1.6
mm diameter, to prevent movement during concreting and to maintain the
specified cover to bars. Chairs and concrete spacer blocks shall be
provided as required to achieve the designed bar arrangement.
All reinforcement having surface rust, which does not reduce the size
of the bar, shall be blast cleaned with proprietary grit immediately
prior to concrerting.
The Engineer shall have the right to select at any time samples of
steel reinforcement for testing in accordance with the relevant
approved standard.
11 STRUCTURAL STEELWORK
11.2 Connections
11.3 Design
11.4 Materials
Samples of all materials shall be tested and copies of the test reports
giving physical and chemical properties issued to the Engineer for
approval. These tests shall prove the compliance of the material for
the purpose intended in accordance with the approved standard. Where
tests are carried out by an independent laboratory, the source of
origin of the material shall be stated and if different sources of
-39-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
supply are contemplated, additional tests shall be carried out. All
materials shall be offered for inspection before and after
galvanization, prior to painting.
The whole of the steelwork shall be blast cleaned to remove all rust,
grease and mill-scale, then zinc coated before despatch to site as
follows:-
11.6 Painting
11.7 Bolts
11.8 Workmanship
11.9 Welding
Where the Engineer approves site welding, this shall not be done under
weather or other conditions which might adversely affect the efficiency
of the welding and, where necessary, effective protection and other
safeguards, as shall be agreed with the Engineer, shall be provided.
-40-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Butt welds in flange plates and/or web plates shall be completed before
the flanges and webs are welded together.
Approval of the welding schedule and procedure shall not relieve the
Contractor of his responsibility for correct welding and for the
minimising of distortion in the finished structure.
All welds shall be finished full and made with the correct number of
runs, the welds being kept free from slag and other inclusions, all
adhering slag being carefully removed from the exposed faces
immediately after each run.
Fusion faces, angle of bevel, root radius and the like shall be
properly prepared to give the approved weld forms. The fusion faces
shall be carefully aligned and the correct gap and alignment maintained
during the welding operation. In the preparation of the fusion faces,
shearing shall be limited to metal thicknesses not greater than 8mm.
All fusion
All main butt welds shall have complete penetration and, except on
tubes where it is impracticable, shall be welded from both sides, the
back of the first run being suitably gouged out.
The ends of the welds shall have full throat thickness. This shall be
obtained on all main welds by use of extension pieces adequately
secured on either side of the main plates. Additional metal remaining
after the removal of the extension pieces shall be removed by
machining, or by other approved means, and the ends and surfaces of the
welds shall be smoothly finished.
12 WATERPROOFING
12.1 General
-41-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Areas of suspended slabs for toilet/kitchen shall be sunken and
waterproofed with two layers of 4 mm thick SBS modified bituminous
memnrane separated with minimum 50 mm mortar to the Engineer's
approval.
12.2 Submittals
The Contractor shall make the following submittals to the Engineer for
approval:
- Format of Guarantee.
12.3 Materials
-42-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
12.3.4 Primer
The primer to be used shall comply with all respect to ASTM D 41 and
shall be applied at a minimum rate of 250-300 g/sq.m.
12.4 Workmanship
12.4.1 Storage
All materials shall be stored in dry area, out of direct sunlight and
according to manufacturer's instructions (correct rolls position,
maximum load and stacking allowed).
12.4.2 Installation
The tiles shall be laid on a bed of 4 cm thick cement sand mortar with
appropriate expansion joints.
12.5 Tests
-43-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
13 METALWORK
Metalwork articles shall have a first class finish, and be free from
scale, rust, damage or other defects.
Frame corners shall be mitred and coupled together with solid aluminium
corner blocks and sealed and secured by pressure crimping.
Welded joints shall be made in the factory and finished smooth and
flush.
-44-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
All framing, glazing and structural elements in connection with
windows, doors and screens shall be capable of withstanding the wind
loads specified.
Aluminium sections shall be polyester powder coated or in colours to be
selected. Average thickness of polyester powder coating shall be 40
microns.
Steel Doors - Steel doors shall be of standard manufacture approved by
the Engineer. The doors shall be manufactured in accordance to BS 6510
or equivalent approved standard except for fire rated doors which shall
comply with the requirements of NFPA 80.
The doors shall be insulated and protected by galvanising and
application of epoxy paint system to the approval of DEWA.
Other Materials - Materials not herein fully specified and which may be
offered for use in the Works shall be first class quality and of such
kind as is generally used in first class work. The Engineer shall have
the right to determine whether all or any of the materials offered or
delivered for use in the works are suitable for the purpose.
14 BLOCKWORK
14.1 Cement
Fine and coarse aggregates for forming blocks shall be aggregates from
neutral sources of hard durable material or other approved, free from
deleterious substances.
Cement for mortar shall comply with the requirement of BS 12 and sand
shall be naturally occurring type complying with BS 1200. Plasticisers
shall be added to mortars only after Engineer has approved its use in
writing and shall be used in accordance with the recommendations of the
manufacturer.
14.5 Jointing
-45-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
-46-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
All blocks shall be kept damp during building and shall be laid on a
full bed of mortar. All joints shall be completely filled with mortar.
Sealed movement joints shall be formed where necessary. The
installation shall be as per BS 5628.
Wall ties shall be laid sloping downwards towards the exterior. The
ties shall be spaced at 900 mm horizontally and 450 mm vertically, or
equivalent to suit the block sizes.
Weep holes shall be built into the external skin of cavity walls in the
form of sand filled vertical joints at 1 m centres and are to be raked
out on completion. Weep holes shall be placed over all lintels, dpc or
other significant obstructions to the cavity.
Where shown on the drawings and at the jambs of all openings hollow
concrete blocks shall be filled with weak concrete, well tamped down
and carried from base slab to top of such openings.
Where the blocks abutt reinforced concrete columns and where indicated
elsewhere, the blocks shall be tied to the columns every second course
by means of approved galvanised ties fixed to the columns.
Holes and chases shall be cut out or left in the walls as required and
provision shall be made for making good to the satisfaction of the
Engineer.
-47-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Newly laid blockwork shall be protected from the harmful effects of the
sunshine, rain, drying wind, running or surface water and shocks. Any
work that may be damaged shall be taken out as directed and pointed
out by the Engineer. Any costs incurred in carrying out such remedial
work shall be borne by the Contractor.
15 FLOORLAYING
15.3 Protection
15.4 Defects
-48-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Rejected floors shall be replaced at the Contractor's expense to the
satisfaction of the Engineer.
The tiles shall be cast in heavy steel moulds under pressure. The
thickness of topping (wearing layer) shall not be less than 10 mm.
PVC flooring shall be flexible 300 mm square minimum 2.5 mm thick PVC
tiles complying with the requirements of BS 3261 obtained from an
approved manufacturer. PVC vinyl asbestos tiles will not be accepted.
The tiles shall be laid by a specialist and the jointing layout is to
be approved by the Engineer. A matching PVC cove-type skirting is to
be used in conjunction with the floor tiles. The tiles and skirting
shall be laid on a flat, clean screed, in strict accordance with the
manufacturer's instructions.
Vitrified ceramic floor tiles and fittings shall comply with the
requirements of BS 6431 and have a maximum water absorption of 0.4%.
The sizes and colour of the tiles shall be to the Engineers approval.
The floor finish of the panels shall be hard print laminate to a core
material of high density processed timber protected against humidity,
rotting and fire and shall not be less than 38 mm thick. (not
including floor covering), seated in a 0.9 mm galvanised steel tray.
The panel shall be edged with a rigid PVC lipping to all four sides.
The lipping shall be planed to finish flush with the surface covering.
-49-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The under side, and all four edges of each panel shall be protected to
“class 1” surface spread of flame in accordance with the fire rating
requirements of BS476, part 7.
Fully vitrified ceramic floor tiles and fittings shall comply with
BS.6431 with a maximum water absorption of 0.3%. Sizes and colour of
tiles shall be to the Engineer’s approval.
The workmanship for tiles shall be similar to ceramic tiles except that
the tiles shall be laid on chemical resistant mortar in accordance to
ASTM-C-287-71. The pointing of tiles shall be carried out using
compatible chemical grouts applied to the recommendation of the
approved manufacture.
The screed shall be laid in panels above sound concrete substrata which
shall be free of defects and loose delaminating material. The surface
shall be acid etched to remove surface laitances and provide a rough
texture suitable for bonding of the screed.
The acid etched concrete surface shall be washed to remove all acid
residue and allowed to dry before application of primer. Screed shall
be laid on tacky primer strictly in conformity to the instructions of
the approved manufacturer.
-50-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Materials for treating the concrete surface which will not receive any
subsequent finishes shall comprise of a epoxy based sealer and
hardner.The materials which the contractor proposes to use shall be
subject to Engineers approval and the application shall be strictly in
accordance with the manufacturers instructions.
15.12 Skirtings
16.1 Timber
16.2 Preservative
16.3 Workmanship
16.4 Faults
-51-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
sets, door closers, door stops, flush bolts, panic bolts and latches,
etc., as appropriate and approved by the Engineer.
The locks shall be linked to DEWA's existing masterkey system and the
details of grand and sub masterkey shall be discussed and agreed with
the Employer.
17 GLAZING
17.1 General
The Contractor shall replace all cracked or broken glass and clean all
glazing on both sides and all mirrors prior to handing over.
Clear float sheet glass, where required, shall be 6mm thick and of an
approved make.
Wired glass shall be either wired cast glass or polished wired glass
with 12.5mm square wire mesh 0.5mm in diameter or hexagonal wired cast
glass with 23 mm hexagonal wire mesh 0.5mm in diameter.
Tinted glass shall be body tinted and solar control type. It shall be
minimum 6 mm thick and shall have the required colour and thickness
generally in conformity with BS 952. The colour of glass shall be
uniform throughout and be subject to Engineer's approval. All tinted
glass shall be tempered. Each individual glass shall have tempered
seal embossed. Glass shall be fixed with UV protected sealant.
18 PAINTING
18.1 Paint
-52-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The primers and undercoats where applicable, shall also comply with the
requirements of the manufacturer of the paint system. All paints shall
be obtained from manufacturers to be approved by the Engineer
Best quality high gloss Alkyd based enamel paint with compactible
primer resistant to corrosion, water, fungus, etc., applied strictly in
accordance with the manufacturer's recommendations. The paint shall be
sourced from Hempel, Jotun, National Paint or other equivalent to the
approval of DEWA.
Where required by the drawings these shall comply with the requirements
of BS 1070 or BS 3416 as necessary.
18.7 Workmanship
18.7.1 Storage
-53-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
Materials shall be stored to the manufacturers recommendations, but
generally in cool, dry conditions protected from direct sunlight.
-54-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
18.7.2 Generally
All surfaces shall be made sound, clean, dry and free from deleterious
materials.
When spraying, the Contractor shall ensure that overspray mist, rebound
or drift does not cause a nuisance to others or permanent damage to the
Works.
18.7.8 Re-Priming
18.7.9 Undercoats
18.8.1 Woodwork
-55-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
All woodwork required to be painted shall be knotted, primed, stopped
and painted with two undercoats and one finishing coat.
Any damaged paintwork shall be cleaned down and re-treated, to the same
state as the original before further paint coats are applied.
-56-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
abrasion, impact, chemical attacks, corrosion, etc., applied strictly
in accordance with the paint manufacturer's recommendations from
Hempels, Jotun, National Paint or other equivalent to the approval of
DEWA. The DFT remains same as specified above.
18.8.3 General
All work shall be properly cleaned and prepared in a way, and using
materials, recommended by the manufacturers of the paints concerned.
No coat shall be commenced until the Engineer has passed the previous
coat as dry, hard and satisfactory. Each coat shall be of a distinct
colour from the preceding one and all colours shall be approved by the
19.2 Pipes
19.3 Ducts
19.4 General
All drains and cable ducts shall be laid in straight lines and regular
gradients as described or directed. Great care shall be exercised in
setting out and determining the level of the drains. All drains shall
be kept clear from earth, debris, superfluous cement and other
obstructions during and after laying.
Concrete beds and casings to drain pipes and cable ducts under roads
shall be of weak concrete and of 150 mm minimum thickness. Elsewhere
the pipes and ducts shall be laid on and surrounded with approved
granular material.
19.6 Testing
-57-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
a period of five minutes without dropping below 125 mm head. Any
defects revealed shall be made good at the Contractor's expense. The
tests shall be conducted as per BS 5572.
After the cable ducts have been completed, a cleaning rod shall be
drawn through each duct and a No. 8 gauge galvanised iron fishing-wire
drawn in after the rod. The ends of the ducts shall be plugged with a
wooden plug and the fishing-wires left in the ducts.
19.8 Manholes
Galvanised malleable cast iron step irons are to be provided and built
in as work proceeds.
Manhole covers shall comply with BS 497 all manhole covers shall be
double seal heavy duty.
20.1.1 Cement
20.1.2 Sand
20.1.3 Plaster
Internal plaster in basement, pump house and IBT areas only shall be
with cement mortar 1:4 with a water proofing agent added to the mix to
the Engineer's approval.
20.1.4 Water
-58-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
20.1.5 Lathing
20.2 Workmanship
20.2.1 General
20.2.2 Storage
20.2.3 Mixing
All undercoats shall be scored to provide a key for the finish coats.
20.2.4 Lathing
-59-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
In no circumstances shall cement be used in the same mix as gypsum
plaster, nor shall the two materials be allowed to contaminate each
other. Any materials inadvertently contaminated shall be rejected from
the site.
20.2.8 Inspection
Any and all defects shall be made good to the satisfaction of the
Engineer.
20.2.9 Curing
20.3.1 Materials
The tiles shall be true to shape, flat and free from flaws, cracks and
crazing.
The tiles and the fittings shall be obtained from the same
manufacturer.
20.3.2 Workmanship
-60-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
time for complete drying shrinkage shall be allowed to elapse between
the completion of the floated coat and the start of tiling.
The work shall be properly set out to the Engineer's satisfaction. The
height of tile courses shall be set out properly by means of a tiling
rod; all tiles and joints shall be accurately aligned, both vertically
and horizontally. Joints between the tiles shall be 2mm wide or as
recommended by the tile manufacturer. Continuous expansion joints
shall be made at all internal wall angles.
All tiles shall be dipped in water to ensure that they are completely
clean prior to the application of the ceramic tile fix. All tiles
shall be immersed in water in clean containers for at least half an
hour before use. Tiles shall then be stacked lightly together on a
clean surface to drain with the end tiles turned glaze outwards. They
shall be fixed as soon as all surface water has gone - they must not be
allowed to dry out more than this.
The rendered backing for tiling shall be clean and will be wetted (just
enough to prevent it from absorbing water from the fixing bed)
immediately prior to tiling. The tiling shall be bedded in Ceramic
Tile fix or similar tile adhesive which shall be trowelled on to the
wall with a plasterer's trowel having 6mm x 6 mm notches at 25 mm
centres; the tiles shall be tapped or pressed into position to a true
plane.
Approximately two days after the fixing of the tiles, all joints shall
be pointed with approved tile grout; the finish shall be flush and free
from all voids and irregularities.
All wall faces shall be finished plumb and flush throughout, free from
unevenness and irregularities of plane; all angles shall be straight
and true. The finished work shall be left clean and free from all
materials; cleaning down must not be carried out with materials which
will scratch or in any way impair the finished work. Final polishing
shall be done with a dry cloth. The Contractor shall be responsible
for the adequate protection of the tiling from all damage until the
handing over. Any damage which does occur shall be made good by the
Contractor at his own expense. The whole of the work shall be left in
a state satisfactory to the Engineer.
The workmanship for tiles shall be similar to the ceramic wall and
floor tiles except that the tiles shall be laid on chemical resistant
mortar which shall comprised of sulphur mortar in accordance to ASTM-C
287-71. The pointing of tiles shall be carried out using compatible
chemical grouts applied to the recommendations of the approved
manufacturer.
20.4 Plasterwork
-61-
1.5.3.1.0.01-Rev.9
CIVIL WORKS
The panels shall be secured with locking clips to the grid. The visible
face of the panels shall have a self-finished surface.
At perimeter walls and columns the grid shall be neatly trimmed with
angle trimmers.
In other areas where required and shown on the drawings, the ceiling
shall be made airtight at individual panel supports and at junction of
ceilings and walls.
Other equal and approved insulating material and methods of fixings may
be used subject to the Engineer's prior approval.
The Tenderer shall specify the type and manufacture of his proposals
for the above ceilings, in the Schedule included in the document.
All finishes are to be of high quality and all proprietary finishes and
treatments are to be to the approval of the Engineer and applied
accordance with the manufacturers instructions.
The following table lists the required building finishes to the various
areas:-
-62-
CIVIL WORKS
1.5.3.1.0.01-Rev.9
Finishing Schedule
Room Floor Skirting Walls Ceiling
MAIN SUB/STN
BUILDINGS:
Entrance, hall & Terrazzo tiles 100 mm high Plastered sealed, & Suspended ceiling.
terrazzo to match painted with washable
corridor
floor with quadrant emulsion paint. Colour
coving. to the approval of
DEWA.
Toilet Non-slip ceramic ------ Plastered and finished Suspended ceiling with 60
tiles with glazed ceramic x 60 cm aluminium tiles
tiles to top of door compatible with lighting.
height. Seal,
undercoat & washable
emulsion paint above.
Battery/Charger Non-slip ceramic 100 mm high Plastered, sealed and Fair faced concrete,
tiles laid to falls Ceramic to match painted with washable prepared, sealed and
floor with quadrant emulsion paint. Colour painted in textured
coving to the approval of finish to approval.
DEWA.
Workshop stores & Hardened solvent 100 mm high epoxy Plastered, sealed & Suspended ceiling.
free epoxy resin screed skirting. painted with washable
records
mortar screed emulsion paint. Colour
minimum 4 mm thick, to the approval of
sealed. DEWA.
-63-
CIVIL WORKS
1.5.3.1.0.01-Rev.9
Finishing Schedule
Room Floor Skirting Walls Ceiling
* High quality PVC PVC 100 mm high to Plastered sealed, & Suspended ceiling.
Telecom Room painted with washable
tiles.300 x 300 x match floor
2.5mm. emulsion paint. Colour
to the approval of
DEWA.
* High quality PVC PVC 100 mm high to Plastered sealed, & Suspended ceiling.
Control Room painted with washable
tiles.300 x 300 x match floor
2.5mm. emulsion paint. Colour
to the approval of
DEWA.
*High quality PVC PVC 100 mm high to Plastered sealed, & Suspended ceiling.
Relay Room painted with washable
tiles. 300 x 300 x match floor
2.5 mm. emulsion paint. Colour
to the approval of
DEWA.
LVAC *Hardened solvent 100 mm high epoxy Plastered sealed, & Suspended ceiling
free epoxy resin screed skirting painted with washable
mortar screed emulsion paint. Colour
minimum 4 mm thick to the approval of
sealed. DEWA.
-64-
CIVIL WORKS
1.5.3.1.0.01-Rev.9
Finishing Schedule
Room Floor Skirting Walls Ceiling
Hardened solvent Epoxy screed Plastered, sealed & Fair faced concrete,
PUMP HOUSE prepared, sealed and
free epoxy resin skirting 100 mm painted with washable
mortar screed high. emulsion paint. Colour painted in textured
minimum 4 mm thick, to the approval of finish to approval.
sealed. DEWA
-65-
CIVIL WORKS
1.5.3.1.0.01-Rev.9
Finishing Schedule
Room Floor Skirting Walls Ceiling
GATE HOUSE:
Guard Room Terrazzo tiles. 100 mm high Plastered, sealed & Plastered (with sand
terrazzo to match painted with washable cement mortar) sealed and
floor with quadrant emulsion paint. Colour painted with washable
coving. to the approval of emulsion paint. Colour
DEWA to the approval of DEWA.
Toilet Non-slip ceramic ----- Plastered with glazed Suspended ceiling, with
tiles. ceramic tiles to top 60 x 60 cm. aluminium
of door height. Sealed tiles compatible with
& painted with lighting.
washable emulsion
above. Colour to the
approval of DEWA.
WATCHMAN
ACCOMMODATION:
Bedrooms and Lobby Terrazzo tiles 100 mm high Plastered sealed & Plastered (with sand
terrazzo to match painted with washable cement mortar) sealed and
with quadrant emulsion paint. Colour painted with washable
coring. to the approval of emulsion paint. Colour
DEWA. to the approval of DEWA.
Kitchen Non-slip ceramic ---- Plastered with glazed Plastered (with sand
tiles ceramic tiles to top cement mortar) sealed and
of door, sealed & painted with washable
painted with washable emulsion paint. Colour
emulsion paint above. to the approval of DEWA.
Colour to the approval
of DEWA.
-66-
CIVIL WORKS
1.5.3.1.0.01-Rev.9
Finishing Schedule
Room Floor Skirting Walls Ceiling
Bath Non-slip ceramic ----- Plastered with glazed Plastered (with sand
tiles ceramic tiles to top cement mortar) sealed and
of door. Sealed & painted with washable
painted with washable emulsion paint. Colour to
emulsion above. the approval of DEWA.
Note :
A high quality water resistant paint in black colour shall be applied to all concrete surfaces above
suspended ceiling.
Floor along all fire escape routes shall be marked with reflective paint as per relevant standard and to
DEWA’s approval.
-67-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
21 PLUMBING
21.1 Extent of Work and General
This section describes the services to be provided in general and addresses
the general requirements in respect of sanitary plumbing, drainage, rainwater
and domestic water services.
All aspects of plumbing work shall comply with government/local authority
regulations and codes of practice and work shall be subject to their approval
at various stages as required by law. The Contractor shall be responsible for
ensuring that all aspects of materials, workmanship and testing have
appropriate government approval.
All domestic water services pipework shall be sized to provide the necessary
flow rates to sanitary fittings on the basis of probable simultaneous demands.
The method of calculating the size of pipework shall be in accordance with
the British Standards Code of Practice CP.310 using demand units to assess the
probable simultaneous demand for water at any point in the system. Velocity
of water in the system shall be limited to 1.5 metres per second as a maximum
and the demand units and flow rates for sanitary fittings are in accordance
with the following table:
All sanitary plumbing and drainage installations shall comply with BS.8301
and the regulations and by-laws of the Local Authorities. The Contractor
shall arrange for a permanent water supply facility from the local authority
network. The charge for permanent water connection (payable to DEWA) will
be borne by DEWA.
Foul water drains shall be installed in accordance with BS.8301.
Easy bends of either long radius type or two 135 deg. bends shall be used at
the base of all plumbing stacks. Access points shall be provided on all
draining runs by manholes of an appropriate size.
All drains shall be accurately laid, true to line and gradient from point to
point. Manholes shall be provided at changes of direction or gradient and
at points of connection. Drain pipe runs between manholes shall be
absolutely straight. Lines and falls shall be accurately set out.
The Contractor shall provide all materials, labour, equipment, plant and
incidentals to execute, complete and maintain the works. The Contractor
shall carry out the tests required under supervision and shall make good and
replace any defective work. The Contractor shall be responsible for
protection of all plumbing from any damage whether due to the concurrent
work of the other trades or otherwise and he shall clean up upon completion
leaving all works in perfect working order and to the satisfaction of the
Engineer.
The entire works shall be robust and designed for a long service life with
minimum maintenance. Special care shall be taken in designing drainage
works to ensure the least chance of blockage.
-68-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
11.21.2.2 below.
-69-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
21.2.2 NOT USED
21.2.3 Sanitary Plumbing and Drainage
uPVC soil and waste water pipes and fittings shall comply with BS 4514 and
be protected against misuse or attack by vermin. Fittings shall be of the
push-fit or solvent welded type.
-70-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
Valves and cocks for use on hot and cold water services shall comply with
the regulations and requirements of the appropriate Water Authority
concerned and arrangements shall be made with that Authority and no extras
shall be allowed for any charges for testing and stamping of valves and
cocks which may be required.
Valves up to and including 50 mm bore shall, unless otherwise specified, be
screwed in accordance with BS 21 : 1973 "Pipe threads for tubes and fittings
where pressure tight joints are made on the threads" and subsequent
amendments.
On open circuit high pressure systems such as domestic water and irrigation
water services, all isolating valves shall generally be stopcocks.
Bends, swan necks, outlets and other fittings shall as far as possible be of
materials matching the main pipe. Where dissimilar materials are formed
together, approved adaptors and methods shall be used.
Jointing shall be in accordance with Codes of Practice relevant to the
materials concerned.
Metal surfaces in contact with asphalt shall be scored, wire brushed, and
treated with suitable bitumen based primer, before installation. Where the
rainwater pipes discharge above ground, they shall be fitted with a 45
degree elbow directing rainwater away from the building.
21.6 Sanitary Fittings, Materials and Equipment
21.6.1 General
All sanitary fittings shall be Ideal Standard, Twyfords, Armitage Shanks or
equivalent make. Sanitary fittings and their connections, services, wastes,
etc. shall be located, designed and installed to the satisfaction of the
Engineer.
21.6.2 Quality and Colour
Unless otherwise approved by the Engineer, the quality and sizes of the
fittings shall be according to British Standards and as listed below.
Unless specifically shown on the drawings, the sanitary appliances shall be
in white.
21.6.3 Wash Basins
Wash basins shall be enamelled glazed fireclay complying with BS 1188 size
55 x 40 cm weighing approximately 20 kg fitted with 13 mm diameter chromium
plated pillar taps, combined overflow and 32 mm diameter trapped waste with
plug.
-71-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
Ball valves shall comply with BS 1212 and marked with the manufacturer's
name or trade mark. Floats shall comply with BS 2456 and shall be marked
with the manufacturer's name or trade mark. A manufacturer's certificate
testifying that the flushing cisterns comply with BS 1125 shall be submitted
to the Engineer.
21.6.7 Urinals
Bowl urinals shall be vitreous china bowl urinal, overall size approximately
41 cm by 61 cm complete with 1 1/4 inch chromium plated outlet and all
necessary concealed hangers and supports. The urinals shall be fixed in
single or in ranges of two, three, four or more urinals and as shown on the
drawings with vitreous china divisions of 67 cm/150 cm height approximately.
Flushing cisterns shall be enamelled fireclay automatic flushing cistern
with copper syphon and 1/2 inch inch drip tap with loose key. The cistern
shall be of a capacity of nine litres for each single urinal or for a range
of two urinals, fifteen litres capacity for a range of three urinals served,
and complete with pair cast iron cantilever brackets for each, built in to
wall. The flush pipes, reduced size sparge pipes, pipe fittings and
spreaders (of suitable diameters as recommended by the manufacturer) between
cistern and bowls shall be chromium plated with necessary 1 1/4 inch traps
(one for each bowl) and all necessary chromium plated connection to supply
and waste water piping.
-72-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
and the necessary raising pieces with the necessary side inlet opening (or
openings), covers to be of chromium plated cast brass.
21.6.11 Waste Water Gully Traps
Unless otherwise directed, waste water gully traps or P-traps shall be of
UPVC as per relevant British Standard.
Each gully trap shall be equipped with a conical gully inlet and a raising
piece with the necessary side inlets. The gully inlet and the raising
piece shall be of the same material as the gully.
The gully trap together with the gully inlet and the raising piece shall be
fixed and surrounded with not less than 10cm thick plain concrete from
bottom and sides of the same and as directed by the Engineer.
In areas subject to use of excessive water, the floor drains shall be in the
form of channels of adequate size fitted with removable grilled covers
suitable for heavy traffic and connected to separate drainage system.
Detailed design and information shall be submitted to the Engineer to obtain
his approval on the system and materials prior to commencement of the work.
The outer jacket shall be mild steel with a baked enamel finish, and shall
have removable access covers for maintenance purposes.
The insulation shall be high density fibreglass matting of at least 25 mm
thickness or injected polyurethane foam.
Heating elements shall be screw-in type incaloy sheathed suitable for 220
volts supply with an integral thermostatic control adjustable through the
range of 49oC to 82oC with a high temperature cut out.
A factory fitted combination valve assembly on the water inlet shall
incorporate an isolating valve, a non-return valve, and a thermal and
pressure relief valve set at 99oC and 700 kPa (7.0 Bar) which shall be piped
to safe discharge.
The type, storage capacity and element rating of the heaters shall be as
described in the schedule.
Immersion electric heaters shall further comply with BS 3456, Section 2.21.
Thermostats shall comply with BS 3955, Section 2B. Notwithstanding the
stipulations of these standard specifications, thermal storage electric
water heaters and their installation shall be in accordance with the
prevailing government regulations.
The contractor must obtain the Engineer's approval on the capacity, number,
type and manufacaturer of the water heaters prior to ordering them.
-73-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
-74-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
- Indicator lamps for mains on, pump run and pump trip for each pump.
- Anti-condensation heater.
The control circuitry shall provide for the connnection of float switch
controls for the protection of the pump set against dry running.
21.8 Testing
When the installation has been completed to the satisfaction of the
Engineer, it shall be tested for water tightness and leakage. Rate of flow
and correct operation shall also be checked.
The Contractor shall provide all facilities for the testing and making good
of any defects to the satisfaction of the Engineer.
21.9 Cleaning
The Contractor shall carefully clean out all cold water and hot water
tanks. Service pipes, sanitary fittings throughout, traps and wastes. The
Contractor shall also overhaul and make good all flushing valves, check
regulating valves, check taps including rewashering as necessary and leave
all works in perfect clean working condition.
21.10 Disinfection
After completion of all tests, the replacement and repairs, all water
supply systems shall be thoroughly flushed with water to remove sediment.
Disinfectant shall be applied to all piping systems of potable cold and hot
water supplied.
The disinfectant shall be chlorine, in the form of a hypochlorite solution.
During chlorination, all valves and equipment shall be operated, to ensure
that chlorine reaches all parts of the system. Water and chlorination
agent shall be fed into the system at rates that will provide a residual
chlorine content of not less than 10ppm after a retention period of 24
hours. (An initial application of 30 ppm will generally be required).
-75-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
22.2 Fence
Fence shall be chain link type designed to resist wind load at 160 km per
hour.
The fence shall comprise of 50 x 50 chain link mesh, galvanised wire not
less than 2.65 mm core diameter and with PVC coating not less than 3.75 mm
diameter. It shall be at least 2.4 m above ground and buried at least 0.3
m below ground level. The tension lines shall be not less than 4 lines of
3.5 mm core diameter and PVC coating not less than 4.1 m diameter.
The supporting posts shall be hot dip galvanised to BS 729 after
fabrication and polyester powder coated to a minimum thickness of 80
micron. The posts shall have extension arms beyond chain link mesh to
accommodate 3 lines of barbed wire. The posts shall be at least 60 mm
diameter 2.9 mm thick for intermediates and 76 mm diameter and 4.5 mm
thick for end straining posts.
The barbed wire shall have a core diameter of 1.6 mm and the diameter with
PVC coating shall be a minimum of 1.95 mm.
The material shall be installed generally as per the requirements of BS
1722.
22.3 Gate
The gate for substation shall be of structural steel construction using
rolled hollow steel sections of grade 43C generally in conformity with BS
4848. The gates shall be to the height of compound wall generally in
conformity to BS 1722 part 10.
The gate for the Substation shall have steel spikes and shall be
galvanised and painted as the structural steel items.
-76-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
rendered and painted on both sides, and capped with a precast concrete
coping. Pointed steel spikes - galvanised and painted as per
specifications for steel work shall be fixed above the wall.
Gates of RHS steel construction complete with all fittings shall be
provided where indicated on the drawings.
All lamps, fittings, plugs, sockets and general accessories of the same
size and types shall be similar and interchangeable throughout the
installation.
23.3 Defects Liability Period
The Contractor shall be responsible for the efficient and good working of
the installations comprising this section of the Specification for the
agreed period as set out in the Specification document.
23.4 Approvals
The Contractor shall submit to the Engineer for approval copies of all his
calculations forming the basis for the designs of the specified systems
which shall be shown on the working drawings also to be submitted for
approval.
-77-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
Infrared movement sensors to be provided in all areas to control automatic
switching on and off of at least 50% lights in a room.
The installations shall also meet the limiting glare index requirements as
set out in the specified codes of practice. This schedule gives proposals
for the types of lighting fittings to be used in the area, type of control
to be employed, number of socket outlets and the types of mounting
expected to be suitable for the respective areas. Where discharge and
fluorescent light sources are to be used in areas containing rotating or
reciprocating machinery, the fittings shall be allocated between the 3
phase and neutral in such a manner as to avoid stroboscopic effects. When
3 phase lighting installations are to be used contactor switching
controlled by pushbuttons located in the area to be illuminated are
preferred.
In all rooms and corridors having two entrances the lighting installation
shall have two way switching, the switches being located in appropriate
positions adjacent to the entrances.
Emergency lighting shall be arranged to illuminate all stairways, exits
and entrances and provide some illumination in operational areas.
Key to Abbreviations:
L Local switches
S1, S2 etc. Socket outlets or fused spur circuits
P.B Pushbutton for remote control
T.S Time switch control
C Ceiling mounted
W Wall mounted
P Pole or earth mast mounted
M Recessed modular mounting
D Suspended
F Flush installation
S Surface installation
A Automatic on mains failure.
BH Behind ceiling diffuser.
-78-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
All busbars, neutral bars and primary conductors are to be PVC sleeved in
respective phase and neutral colours.
Distribution boards for exterior use shall be galvanised and weatherproof.
Neutral bars shall have an appropriate number of ways relative to the size
of the board. They shall have a rating not less than that of the
associated phase busbars.
The metal surface adjacent to any live part and all spaces between phases
shall be protected by barriers of fireproof insulation material.
The distribution boards shall be either single pole or triple pole and
neutral types and shall be equipped with means to provide overcurrent
protection to each circuit. This protection may comprise an HRC fuse or a
miniature circuit breaker, both of which shall be removable without
exposing live connections.
Fuse bases and bridges where used shall be of an approved non- hydroscopic
insulation suitable for the receipt of HRC fuses.
Residual current circuit breakers shall be incorporated to protect all
lighting circuits, socket outlets and supplies to appliances, etc. These
shall comply with the requirements of the main electrical part of this
Specification.
-79-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
list, the list and cover to be easily removable to permit circuit
modifications.
The cables feeding the distribution boards will be connected directly to
the incoming isolator or neutral bar as appropriate unless otherwise
indicated by the Specification.
Mixed capacity boards shall be employed and all contactors and time
switches associated with the respective outgoing circuits shall be
accommodated within the distribution board.
23.8 Miniature Circuit Breakers
Miniature circuit breakers shall comply with the requirements of the main
electrical part of this Specification.
23.9 Cables
Armoured cables shall be XLPE insulated, single wire armoured and
polyvinyl chloride sheathed overall and be manufactured and tested in
accordance with the requirements of BS.5467, 600/1000V grade or
equivalent. The outer sheath shall be coloured black and incorporate
flame retardant characteristics to meet the requirements of BS.4066 and
IEC.332. Jute fillings will not be permitted. Cables shall comply with
the requirements of the cable section of this Specification.
Each armoured cable shall be provided with separate Earth Continuity
Conductor (ECC) of minimum half size of the phase conductor, coloured
yellow/green.
Flexible type cables for pendant cords and final connections to fixed
apparatus are to be butyl or silicone rubber insulated and sheathed
manufactured and tested in accordance with the requirements of BS.6500,
300/500V or 300/300V grade as applicable.
The conductor is to comprise multi-strands of 0.25 mm wire. The number of
strands are to be not less than 30 and in all cases of a number suitable
for the protection rating of the respective circuits.
All cables used for lighting and small power shall have copper conductors.
(b) That the size is to be adequate for the current to be carried as set
out in the cable manufacturers Specification.
(c) That the size is sufficient to keep the voltage drop in the phase and
neutral conductor to the farthest lighting or power point, under
normal full load conditions to within the final circuit limit
specified in BS7671. Diversity will not be allowed.
-80-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
23.12 Conduit
The whole of the various installations described shall be carried out in
screwed heavy gauge welded steel conduit or heavy gauge PVC conduit, at
the discretion of the Engineer. No conduit less than 20 mm diameter will
be permitted.
-81-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
conduit work inside the flame-proof area shall be carried out with solid
drawn galvanised conduit and all conduit fittings, sockets and accessories
shall be galvanised and certified suitable for Group 1 hazard. At the
completion of the wiring all machine faces on accessories shall be
thoroughly cleaned and greased, prior to the screwing or bolting of all
accessory cover plates into their final flame-proof secure position.
The ends of all steel conduits shall be reamered to remove all burrs or
sharp edges after the screw threads have been cut. All dirt, paint or oil
on the screw threads, the conduit, sockets and accessories must be removed
prior to erection. All conduits shall be swabbed through prior to
installation of cables.
The ends of the conduit shall butt solidly in all couplings. Where they
terminate in fuse-switches, distribution boards, adaptable boxes, non-
spouted switch boxes, they shall be connected thereto by means of smooth
bore male brass bushes, compression washers and sockets. All exposed
threads and all bends shall be painted with an aluminium spirit paint
after erection.
All conduit and accessories, after being installed, shall be examined and
all parts where the surface has been chipped or scratched shall be
painted.
All conduits shall be kept 80 mm clear of water, gas and other services.
Should this prove impracticable, then they shall be properly bonded by
means of pipe clamps or other device ensuring mechanically sound,
electrically continuous connection.
The method of installing PVC conduit and fittings shall conform strictly
to the manufacturer's recommendation. These recommendations shall be
submitted when seeking approval to the system proposed. In general the
clauses dealing with steel conduit shall apply.
PVC tube not exceeding 25 mm in diameter shall be bent cold by means of
the appropriate spring and the tube shall be saddled as quickly as
possible after bending. When bending larger sizes of tube, the tube must
be heated in an approved manner until it is pliable. A 90o bend shall have
a radius of not less than five times the outside diameter of the tube.
Joints between conduits and conduit fittings shall be watertight and shall
be made by means of a solvent adhesive as recommended by the manufacturer.
Care should be taken to ensure that the tube is clean and free from damp
and grease and in particular dust, mould and oil.
The Contractor shall provide PVC tube ends and flexible covers to prevent
ingress of concrete grout into the tubing and boxes.
All bends are to be made on Site to suit conditions and not more than two
right angle bends will be permitted without the interposition of a draw
box. No tees, elbows, sleeves, either of inspection or solid type will be
permitted. Generally long straight conduit runs from point to point shall
have draw boxes installed at maximum intervals of 10 metres.
Deep boxes or extension rings on standard circular conduit boxes shall be
used where necessary in order to bring the front of each box flush with
the surface of the ceiling or wall. Where conduits are laid direct on the
shuttering of the reinforced slab construction conduit extension rings or
deep boxes shall be used to raise the run of conduit to between the top
and bottom reinforcing. Galvanised draw wires or other approved types
shall be provided where conduits are not be wired on completion or are to
be wired by others.
All draw boxes and junction boxes shall be of ample size to permit the
cables being drawn in and out. They shall be made of galvanised iron and
the jointing surface machined to ensure a dust tight joint. All circular
boxes shall be provided with long spouts internally threaded incorporating
-82-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
a shoulder for the proper butting of the conduit and a solid copper earth
terminal tapped and screwed into the base of the box.
All conduit boxes shall be screwed on or in walls, ceilings etc. by
countersunk wood screws of appropriate size. Holes in boxes shall be
adequately countersunk to ensure the complete recession of the fixing
screws. All inspection and draw-in boxes shall be provided with covers
fixed by round head galvanised iron screws.
Where surface conduit is specified, it shall be fixed by means of distance
saddles and shall terminate in raised back pattern conduit
boxes. Surface conduits shall be bent or set to enter accessories, and
where they turn through walls back outlet boxes shall be provided.
Conduits shall be fixed at 1200 mm centres on vertical runs and 900 mm
apart on horizontal runs.
Vertical conduit runs shall have saddles at 300 mm maximum from their
points of emergence from floors or ceilings and the remaining saddles
shall be fixed consistent with the requirements of spacing and appearance.
Saddles shall be fixed on each side of every bend at 300 mm maximum from
the point of intersection of the centre line conduit.
-83-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
shall be fixed to the structure of the building independently of the
conduit.
Where a conduit is exposed to different temperatures (either by
surrounding air conditions or by virtue of the surrounding medium with
which it is in contact) at any particular time, the section of the conduit
at the higher temperature shall be isolated from the section at the lower
temperature by means of a conduit box filled with an approved permanently
plastic compound, after completion and testing of all wiring. Such a
condition would arise if a conduit running in a warmed building is run to
exterior points.
-84-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
Cable trays where required as part of the Contract supply are to be the
perforated galvanised sheet type.
Trays are to have upturned edges and be of a width suitable for the number
of cables to be supported and are to be supplied with purpose- made
galvanised steel brackets suitable for mounting from the building
structure. External cable trays shall be provided with covers.
23.15 Cable Jointing
The Contractor shall be responsible for the sealing and jointing of all
cables supplied and installed as part of this Section of the Contract.
-85-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
Lighting fittings for interior and exterior use are to be manufactured and
tested in accordance with the appropriate sections of BS.4533, IEC 162 or
equivalent and together with all components are to be suitable for service
and operation in the tropical climate stated.
Each fitting is to be complete with all lampholders, control gear,
internal wiring, fused terminal block, earth terminal and reflectors or
diffusers as specified. The design of each fitting is to be such as to
minimise the effect of glare and such that the ingress of dust, flies and
insects is prevented, where open type fittings are used it is to be
impossible for insects to become lodged therein.
The control gear for use with fluorescent lamps and is to be quick or
resonant start type without starters. Chokes are to be impregnated and
solidly filled with polyester resin or other approved high melting
compound and are to be manufactured to restrict the third harmonic content
to less than 17% of the uncorrected current value and are to be silent in
operation.
The built-in ballast units shall comply with IEC Publication No. 82 and
shall include radio interference suppressors and capacitors to correct the
fitting power factor to a minimum of 0.95 lagging as per DEWA's wiring
regulations. Control gear noise levels shall be minimal.
23.19 Lamps
The Contract includes the supply and erection of all lamps and tubes
necessary to complete the installation.
-86-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
Each fused spur outlet shall be equipped with double pole isolator, a fuse
to British Standard 1362 or equivalent and where required front entry for
flexible connection.
Each socket outlet and fused spur outlet shall be equipped with a
galvanised metal box with earth terminal.
Each group of five socket outlets is to be provided with a matching fused
plug top. 3 nos. of 63A sockets shall be provided in the GIS room at
suitable location for the gas handling plant. There shall be a separate
heavy duty industrial type socket outlet of 200 Amps rating with plug to
be provided in the 132Kv GIS Room for HV testing of GIS.
All socket outlets for exterior use shall be galvanised and weather-proof
and be equipped with screwed dustproofed cap attached to the socket by
means of a chain.
23.21 Time Switches
Time switches for use with lighting systems shall be the synchronous motor
wound types protected by a suitably rated fuse for 220 volts operation
with a nine hour reserve spring and are to be fitted with a twenty-four
hour hand set dial two "off" and two "on" levers and manual operation
pushbutton. The main contacts shall be rated for 20 Amps on a 220 Volt 50
Hz A.C. supply.
Time switches shall be suitable for mounting in the distribution boards
supplying the circuits to be controlled.
23.22 Poles
Lighting poles shall be tapered of hot dipped galvanised steel with
bituminous preservative inside and outside at the base and shall be
approved by the Engineer.
Each pole shall be equipped with a base section compartment of 470 mm by
150 mm to house an inspection trap, lockable door, fused cutout, cable
entry and terminations for both the incoming and outgoing power cables and
secondary cables feeding the light sources.
Poles for substation lighting shall support the floodlights at minimum
4.5m above ground level, and poles for access roadway lights shall support
the lanterns at 10 m above ground level.
The Contractor shall ensure each pole is provided with foundations
suitable for the ground conditions occurring at each Site.
-87-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
All cables not contained within conduit for their whole route shall be
terminated with a cable gland.
Where lighting fittings are mounted direct on walls or ceilings the main
circuit cables may be connected into the fitting terminal block. Where
terminal blocks do not exist within the lighting fitting flexible heat
resistant cable shall be used connected to a separate junction box.
Each and every trunking route shall be bonded across all joints with
external copper bonding links supplied for the purpose.
-88-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
(a) The battery in the portable emergency wall mounted light should be
housed in a vertical position and should not be in horizontal
position.
(b) In addition to the lamp control switch, there shall be an isolation
switch, which when kept in “off” position shall prevent its working
(discharging of battery) even in case of AC supply failure.
-89-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
(c) Portable emergency lighting shall be provided in the following areas
but not limited to :-
(i) GIS Room – 2 nos. (one at each end)
(ii) 11kV Switchgear rooms – 2 nos. each room (one at each
end)
(iii) Control room - 2 nos.
(iv) Battery, LVAC, DC Charger,
Cap. Bank Room, Security Room, - 1 no. each room
Telecommunication/Scada Room
Fire Pump Control Room
(v) 132kV & 11kV basements,
Control Building Corridor - 2 nos. in each area.
-90-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
TYPE F1 Shall indicate a basic channel complete with control gear and
lampholders for one 1500 mm long fluorescent lamp, equipped with an
open ended metal reflector having upward light slots.
TYPE F2 Shall indicate a fitting which shall comply generally with the
description for Type F1 but be equipped for use with two 1500 mm
lamps.
TYPE F3 Shall indicate a recessed modular fitting louvre type approximately
1200 mm long 600 mm Wide suitable for mounting in a suspended
ceiling. The metalwork and trim are to comprise a rigid welded unit
so arranged as to be invisible when erected complete with
controller. The fitting is to be equipped with a pre-wired
removable gear tray and adjusting facilities to enable leveling
relative to the ceiling to be carried out after erection. The
assembly is to be complete with control gear and lampholders for
two nos. 1200 mm long fluorescent lamp.
TYPE F4 Shall indicate a fitting which shall generally comply with the
description F3 but with three nos.1200 m long fluorescent lamps.
-91-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
TYPE E4 Shall indicate a 60 or 40 watt 110V DC wall or ceiling mounted
emergency fluoresent lighting unit which shall be manually switched
and be similar to type E3.
TYPE S4 shall indicate a 16 amp 3 phase 4 wire switched socket outlet with
plug flush mounted.
The 300A, TP & N, 5 pin, heavy duty interlocked, metal enclosed socket
outlet shall have stainless steel enclosure tested to IP 55.
3 Nos. 63 Amps, 3 Phase, 5 Pin, 400V, Sockets shall be provided in the GIS
room (one at each end and one at middle) as specified in 132kV
switchgear specification, document no.1.5.1.2.2.01.
1 no. 13 Amps, 1 Phase, 3 Pin, 230V socket shall be provided in each IDT &
ET rooms for tapping supply for testing equipments and blower.
Sockets shall be as per clause 23.20 for exterior use.
-92-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
Control/
Relay Room 300 16 F3 E1/E2 M L/A S1-4 F
Behind Panels 100 - E3/E4 S4-1
Offices 300 16 F3 E3 M L/A S1-2 F
SCADA
PLC Rooms 300 25 F3 E3/E4 M L/A S1-2 F
For key see Lighting Requirements and Schedule of Lighting Fittings and Socket
Outlet Clauses.
*The 300A, TP & N, 5 pin, heavy duty interlocked, metal enclosed socket outlet
shall have stainless steel enclosure tested to IP 55.
24 CRANES
Travelling crane(s) shall be provided for the 132kV GIS switchgear
building. The crane(s) shall be capable of lifting and accurately
positioning all loads ranging from full crane rated capacity to at
-93-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
least 10% rated capacity. The cranes shall be furnished with one
hoist.
The Contractor shall provide crane(s) of approved capacity to handle
the heaviest load to be encountered during normal maintenance and
repairs and the heaviest indivisible load during initial erection or
when carrying out extensions. It shall be capable of lifting at least
5 tonnes.
The crane shall have speeds under full load of :
Speed
(a) Hoisting 2 metres/minute
(b) Cross Travel 10 metres/minute
(c) Long Travel 20 metres/minute
(d) Creep speed of 25% of operating speed.
The bridge of gantry trolley and hoist movements shall be controlled
by suitable reversible controllers. The bridge or gantry trolley and
hoist control schemes shall permit variable speeds in both directions
of travel. Limit switches shall be provided at end limits of bridge,
trolley and hoist travel. The Control station shall be of the pendant
type. If the switchgear design and trunking make the use of a pendant
suspended from the trolley impractical, a pendant which can be plugged
into stations at selected points around the switchroom should be
provided with an adequate lead length. These stations shall be
located such that safe control of the crane for all functions can be
carried out at the front, rear or top of the switchroom as required by
the design.
The electrical equipment shall consist of one motor for each crane
motion, all of them provided with brakes; controllers, resistors,
magnetic contactors, overload protection and limit switches; all
complete with hardware, insulators and any other equipment necessary
for proper operation of the crane. The crane shall be so designed so
as to guarantee fall-safe and satisfactory operation. Brakes shall be
able to arrest the heaviest load carried at any position and hold it.
A factor of safety of 1.5 times the maximum working load is to be
taken into account for all stress calculations and also shock loading.
The bridge, trolley and hoist controllers of the crane shall each have
five positions as follows : two in the forward or raising direction,
two in the backward or lowering direction and one off position.
Bridges and trolleys shall be fed from current collectors or by means
of cables adequately supported and provided with self-winding reels.
Stepless control will be accepted.
-94-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
25 DATA SHEET
For convenience certain basic design principles and dimensions are
listed below. This is not an exhaustive list and reference should
also be made to the Technical Specification and other Schedules as
appropriate. The Contractor is required to adhere strictly to the
principles/dimensions listed, unless agreed otherwise in writing by
the Engineer. Should alternative greater dimensions be indicated on
tender drawings, these shall take precedence.
(e) Allowance to included for access to plant front and rear for fire
appliances.
(f) Safety clearances according to B.S. 7354.
Minimum number of doors and means of access
(a) Control and relay rooms - one set of double doors plus one single door
at opposite ends of room.
(b) HV Switchrooms as for (a). Doors to open outwards with handle.
(c) Corridors running complete length of building - double doors one end,
single door other end.
(d) Cable tunnels - two access hatches at opposite ends of tunnel.
-95-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
26 LIST OF REFERENCES
26.1 Civil Works
BS12 Portland Cement
-96-
CIVIL WORKS 1.5.3.1.0.01-Rev.9
-97-
1.5.3.1.0.01-Rev.9 CIVIL WORKS
-98-