Professional Documents
Culture Documents
S4 Harvey Kirk PDF
S4 Harvey Kirk PDF
• $400 M plant
expansion &
modernization
• Double plant
production capacity
• Equipment &
technology:
quantum leap up
Safety Pre-Planned for
Construction Phase
• Early decision by
Corporate Risk Mgmt
& Insurance broker
• OCIP – Owner
Controlled Insurance
Policy
Safe by Design
Promoted at Plant Level
• No corporate
safety dept.
• Began as part of
plant input &
review process
• Champions:
Plant Mgr. &
Manufacturing VP
• Plant-level team assembled
– All engineers & technical managers
• Production, Maintenance, Environmental,
Project, Quality, Safety
– Key process & maintenance personnel
Safety woven throughout project
• Began at concept
level
• Specifications
• Design review
• Contractor pre-bid
/ qualification
• Construction phase
• Commissioning &
Start-up
Key Safety
Concepts &
Concerns
• Fire / explosion
• Preheater vessels
• Noise attenuation
• Equipment guarding
• Manual material handling
• Fall protection / Safe access
• Maintenance safety / Lockout systems
• Signage / Color coding
• Illumination
Design Specifications
• A lesson learned…
• Safety specifications written, just as for:
– Site preparation and grading
– Mechanical and electrical systems
– Structural steel, concrete, etc.
• Resources
– MSHA and corporate standards
– Best Practices
• Construction, Chemical, Europe, ASSE, Local, Personal
• All other specs reviewed for and modified to
address safety issues
• Incorporated into Purchase Orders
First of all… No explosions, please
Coal Fire & Explosion Prevention
• Modern coal mill & peripheral equipment
• Pulverization in inert atmosphere
• CO sensors for incipient
combustion
Redundant systems
• Explosion venting
• CO2 inundation
• Suppression
• Isolation
Explosion
Protection
Suppression
Venting
Isolation
CO2 Inerting
System
SA = Simple Asphyxiant,
Odorizer added
CO2 Injection
Vapor or Liquid
Noise Attenuation
• Individual equipment: spec ≤ 85 dBA
• Fans, mills, compressors & blowers
• Silencers
• Noise barrier materials
• Noise absorbing materials
• Power transmission equipment
• Vibration dampening
• Laboratory equipment included
Separation
Silencer
Insulated
housing Silencers
*
Decoupling
material on
ductwork
Silencer &
Anti-vibration
mount
Sound
absorbing
material
* *
*
Duct wrapping
Silencer;
Fan duct
insulation not
yet installed Verification:
noise levels
attenuated to
specification
Signs &
Labels
Travelways & Work Platforms
9
Work Platforms & Travelways
Air cannons
Cleaning platforms
Lockout
Systems
As-built:
Guards all around
As-received:
No motion sensor
guard
As-Built:
Guard fabricated and
installed on-site
Lifting eye & hoist provided
As-received:
Inadequate guard
As-built:
Improved guard
Manual Material
Handling
In addition to automatic
packer & palletizer…
Radioactive source