Professional Documents
Culture Documents
3 Week Ahead
3 Week Ahead
I CONSTRUCTION WORK
CIVIL WORK
A PREPARATION WORK
1 Excavation (Foot Plate 2 Unit) Tie Beam
Equipment: Excavator Excavator
Manpower: 3 Orang Tukang Batu
2 Leveling of soil
Equipment: Excavator Excavator
3 Backfill Foof Plate
Material: Tanah Existing Tanah Existing
Equipment: Excavator Excavator
Manpower: 2 Orang Tukang Batu
4 Backfill Area Building
Material: 15 Rit Pasir Sirtu 5 Rit (Setelah Pengecoran) Pasir Sirtu
Equipment: Excavator Excavator
Manpower: 3 Orang Tukang Batu
B EARTH WORK
1 Lantai Kerja Area CMC (Gravel) 20 titik Tie Beam
Material: Pasir Sirtu Pasir Sirtu
Equipment: Excavator Excavator
Manpower: 6 Orang Tukang Batu
C CONCRETE WORK
1 Foundation (120x120)
Install Setting Besi 4 Orang 4 Orang Tukang Besi
Install Setting Formwork 4 Orang 4 Orang Tukang Kayu
Pengecoran 8 Orang 15 Titik Sisa
Pabrikasi Besi Foot Plate 3 Orang Tukang Besi
Pabrikasi Formwork Foot Plate 6 Orang Tukang Kayu
Material: Material On Site Material On Site Besi Polos Diameter 10
Equipment: Vibrator 1 Unit, Pompa Listrik 4, Pompa Mesin 2, Penerangan, Terpal/ Plastik, dll Inventarisir Kebutuhan
Note: Metoda Casting in Situ dan Precast Area CMC
2 Tie beam (200X300) Area (D, 5-14)
Pengecoran 6 Orang
Pabrikasi Besi Tie Beam 6 Orang 6 Orang Tukang Besi
Material: Material On Site Material On Site Besi Polos Diameter 10
Equipment: Vibrator 1 Unit, Penerangan, Terpal/ Plastik Inventarisir Kebutuhan
Tie beam (200X300) Area (H, 5-14)
Install Setting Besi 10 Orang 6 Orang Tukang Besi
Install Setting Formwork 6 Orang 10 Orang Tukang Kayu
Pengecoran 10 Orang
Pabrikasi Besi Tie Beam 6 Orang 6 Orang 6 Orang Tukang Besi
Material: Material On Site Material On Site
Equipment: Vibrator 1 Unit, Penerangan, Terpal/ Plastik Inventarisir Kebutuhan
3 Ground Slab
Pemadatan
Gelar Plastik dan Beton Decking (Local Area) Local Area
Formwork (Local Area) Local Area
Gelar Wiremesh M6 (Local Area) Local Area
Material: Material On Site Wiremesh M6
Equipment: Siku 40x40x4, Vibrator, Gunting Besi, Stamper Inventarisir Kebutuhan
4 Kolom (250x250)
Install Setting Besi 10 Orang 10 Orang 10 Orang 10 Orang 10 Orang
Install Setting Formwork 10 Orang 10 Orang 5 Orang 5 Orang
Pengecoran (D, 5-14) 10 Orang 11 Kolom Pengecoran
Pabrikasi Besi Kolom 6 Orang 6 Orang 6 Orang Tukang Besi
Material: Material On Site Besi Polos Diameter 12
Equipment: Vibrator 2 Unit, Penerangan, Terpal/ Plastik Inventarisir Kebutuhan
5 RingBeams
Pabrikasi Besi Ring Beams
Material: Material On Site Besi D13
Equipment: Material On Site (Schafolding, dll) Inventarisir Kebutuhan
MECHANICAL and PLUMBING WORK
B BVI SITE OFFICE PLUMBING SYSTEM : Black Water and Grey Water
Instalasi Grey Water dan Black Water
Material: Material On Site Pipa 4",Keni, Lem PVC
Equipment: On Site
Weigth (%)