1. Scope:
This Method statement describes the broad sequence and execution methodology for Waterproofing
at Terrace.
2. Activities:
The following activities will be carried out for the waterproofing of the Terrace.
Ponding Test.
Applying Spray applied PUFF Insulation on to horizontal surface.
Surface preparation:-
All surfaces shall be free from oil, grease and general curing compounds.
Concrete surfaces shall be cleaned using mechanical means by surface grinder / hand grinders
2 /planicrete SBR (polymer modified mortar) in proportion 1:5:15, and bonding slurry mix with cement
in proportion 1:5:15.
DOC NO : 01 / 19-20 / Treon Tower
Date : 08.07.2019
CONSTRUCTION SPECIALITY REV NO :00
REV DATE:
Minor cracks more than 1mm shall be filled with PU sealant depending on the size of crack. (Surface
crack not be treated).
Fill the water minimum 50mm water for minimum 72:00 hrs for leakage / ponding test.
Leakage rectification through injection grouting using cement slurry Admix with non shrink grout
Cebex 100
Injecting cement slurry admixed with Cebex 100 / Non shrink compound
sealant paste and confined between layers of repair mortar / Micro concrete.
The residual moisture content of the substrate must not exceed 4 % (check with Moisture meter).
Primer application :-
The residual moisture content of the substrate must not exceed 4 %
(Primer application over the concrete shall be done using Silcor primer BS / Smart care epoxy
primer Apply a Single coat of Silcor primer BS / Smart care epoxy primer to the prepared
substrate by spreading with a squeegee at the rate of 0.10 kg/m² and finished with brush/ roller.
Allow to cure for at least 6:00 hours.
inhibit adhesion between the membrane and concrete. Applying Silcor 560/ Smartcare PU
Magnum (waterproofing membrane) in two coat using brush / Roller over the “tack free” primer at
coverage of 2.25- 2.35 kg/m2 to achieve a uniform membrane. Allow the membrane to cure for 7
days (air cure) prior to subsequent topping / further layer.
Repair Methodology:-
Treatment to damages, bubbles formation at site if it will be happened during application, PU
membrane which will rectify by cutting PU layer, cleaning the surface under rectification using
DOC NO : 01 / 19-20 / Treon Tower
Date : 08.07.2019
CONSTRUCTION SPECIALITY REV NO :00
REV DATE:
emery paper, solvent (thinner) then have to do touch up with epoxy primer over it, then apply the
PU coating Silcor 560 / Smartcare PU Magnum with a minimum overlap of 50 mm over the old
Spraying Smartcare PU insulator ‐ Two component polyurethane resin (PUR) based foam that is
applied with a Two component spray Machine. Coverage approx 2kg per Sqm , Average
Thickness 35 mm, Thickness variation may take place depends on wind velocity & ambient
temperature.
Applying Damproof – acrylic coating of one coat to be applied on to puff insulation, Coverage @
Laying Separation layer of Geo textile 300 GSM on to waterproofing coating to prevent it from
mechanical damage.
Laying brick bat coba average thickness 110 mm in cement mortar 1:5 admixed with integral
China mosaic (mix colour broken Tile pieces) over brick bat coba.
Laying China mosaic (mix colour broken Tile pieces) over brick bat coba.
The china mosaic shall be cured by ponding for a minimum of 7 days.
Kg per sqm to received mechanical bonding to Protection Plaster . (Note: On vertical plaster
:Plaster may get crack on primed surface with quartz sand.)
Laying protective Plaster Average 10- 12mm thick to the wall in cement mortar (1:4) including
mixing integral waterproofing compound (100ml per bag of cement).
Curing