SAURA IMPORT and EXPERT CO V CA

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

SAURA IMPORT and EXPERT CO., INC., vs DBP [G.R. No.

L-24968, April 27, 1972] MAKALINTAL,


J.

FACTS:

In July 1952, Saura, Inc., applied to Rehabilitation Finance Corp., now DBP, for an industrial loan of
P500,000 to be used for the construction of a factory building, to pay the balance of the jute mill machinery
and equipment and as additional working capital. In Resolution No.145, the loan application was approved
to be secured first by mortgage on the factory buildings, the land site, and machinery and equipment to be
installed.

The mortgage was registered and documents for the promissory note were executed. But then, later on, was
cancelled to make way for the registration of a mortgage contract over the same property in favor of
Prudential Bank and Trust Co., the latter having issued Saura letter of credit for the release of the jute
machinery. As security, Saura execute a trust receipt in favor of the Prudential. For failure of Saura to pay
said obligation, Prudential sued Saura.

After almost 9 years, Saura Inc, commenced an action against RFC, alleging failure on the latter to comply
with its obligations to release the loan applied for and approved, thereby preventing the plaintiff from
completing or paying contractual commitments it had entered into, in connection with its jute mill project.

The trial court ruled in favor of Saura, ruling that there was a perfected contract between the parties and
that the RFC was guilty of breach thereof.

ISSUE: Whether or not there was a perfected contract between the parties. YES. There was indeed a
perfected consensual contract.

HELD:

·Article 1934 provides: An accepted promise to deliver something by way of commodatum or simple loan
is binding upon the parties, but the commodatum or simple loan itself shall not be perfected until delivery
of the object of the contract.

· There was undoubtedly offer and acceptance in the case. The application of Saura, Inc. for a loan of
P500,000.00 was approved by resolution of the defendant, and the corresponding mortgage was executed
and registered. The defendant failed to fulfill its obligation and the plaintiff is therefore entitled to recover
damages.

· When an application for a loan of money was approved by resolution of the respondent corporation and
the responding mortgage was executed and registered, there arises a perfected consensual contract.

· However, it should be noted that RFC imposed two conditions (availability of raw materials and increased
production) when it restored the loan to the original amount of P500,000.00.

· Saura, Inc. obviously was in no position to comply with RFC’s conditions. So instead of doing so and
insisting that the loan be released as agreed upon, Saura, Inc. asked that the mortgage be cancelled.The
action thus taken by both parties was in the nature of mutual desistance which is a mode of extinguishing
obligations. It is a concept that derives from the principle that since mutual agreement can create a contract,
mutual disagreement by the parties can cause its extinguishment.

·WHEREFORE, the judgment appealed from is reversed and the complaint dismissed.

You might also like