PENTA ENGINEERING MACHINERIES, INC.

699 Jose Abad Santos Street, Little Baguio, San Juan City 1500
Trunkline: (632) 722-8260 Fax: (632) 722-8270 Email: pentaeng@pldtdsl.net

Friday, January 17, 2020

ENERGETIX ICL INDIA CONSORTIUM, INC.


Unit 1702 Atlanta Center,
#31 Annapolis St., Greenhills,
San Juan CityPhilippines
Tel. No.: 571-3809

Attention : MR. BERNARD PABILONA

Dear Sir:

We are pleased to submit our offer as follows based on the conditions indicated:

4 units EVAPCO Model AXS 12-19M22 induced draft axial fan crossflow cooling tower certified to cool
143 LPS at 37°C to 32°C at 29°C entering wet bulb temperature.

Technical data for each unit:


Capacity : 2,989 kW
Fan Motors : (1) @ 22 kW /380V /3Ph /60Hz
Air Flow : 84 m3/s
Inlet Pressure Drop : 0 kPa
Evaporated Water Rate : 1.03 LPS
Operating Weight : 17,051 kg
Dimensions LxWxH : 6,934 x 3,607 x 5,893mm

Including the following:


CTI CERTIFIED
IBC Standard Structural Design
Seismic(Sds) : up to 2.4g, z/h=0
Wind Load(P) : up to 2.85 kPa
304 Stainless Steel Construction
Internal Drive Access Platform
Perimeter Handrail with Ladder & Safety Cage
Fan Motor: VFD Duty

Origin: EVAPCO – CHINA (SHANGHAI PLANT)

@ Php 11,500,000.00 /unit

TOTAL NET PRICE Php 46,000,000.00


(VAT INCLUSIVE) ===================

NOTE: Each unit are divided in 2 sections (1-Basin section, 1- upper section) and loaded into 2 x 40’ Flat
Rack Low Bed Truck

SCOPE OF WORKS:
1. Supply and Delivery of 4 units EVAPCO cooling tower (Price based on Metro manila delivery only)
2. Supervision during lifting, positioning & assembly
3. Testing & Commissioning
4. Project turn-over
PENTA ENGINEERING MACHINERIES, INC.
699 Jose Abad Santos Street, Little Baguio, San Juan City 1500
Trunkline: (632) 722-8260 Fax: (632) 722-8270 Email: pentaeng@pldtdsl.net

Proj.: Energetix
Page 2

EXCLUSIONS:
1. Handling equipment (CRANE), tools and manpower (RIGGER) required for unloading, rigging, positioning
and assembly of cooling tower
2. Steel Beams and civil works for equipment foundation
3. Cooling tower supply and return connection and piping works
4. Make-up water piping works
5. VFD, Installation of VFD and electrical works
6. Electrical power & water requirement during installation & testing
7. Storage and warehouse keeping

Terms & Conditions:

PAYMENT : 50% downpayment, 50% upon complete delivery.

DELIVERY : 18 weeks upon receipt of Purchase Order and Downpayment.

WARRANTY : FIVE (5) YEARS against factory defects from the date of shipment.
NOTE: Wear & Tear parts (Bearings, Belts & Float Valve) – 1 year against factory defects.

VALIDITY : 30 days from the date of issue.

Thank you and we look forward to your valued order.

Yours sincerely,

PENTA ENGINEERING MACHINERIES, INC.

RANDY P. MORCO
Product Manager

Noted by:

ALFONSITO A. ENRIQUEZ
General Manager